Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Appeal (civil) 2880-2881 of 2005
PETITIONER:
TAMIL NADU WATER SUPPLY & DRAINAGE BOARD
RESPONDENT:
M/S. SATYANARAYANA BROTHERS PVT. LTD
DATE OF JUDGMENT: 07/02/2007
BENCH:
Dr.AR.LAKSHMANAN & ALTAMAS KABIR
JUDGMENT:
J U D G M E N T
Dr.AR.LAKSHMANAN, J.
1. Heard Mr.Mohan Parasaran, learned Additional Solicitor General
for the appellant and Mr.Dipanker P.Gupta and Mr.T.L.V.Iyer, learned
senior counsel for the respondent.
2. Aggrieved against the order passed by the Division Bench of the
High Court of Madras dt.24.03.2004 in OSA Nos.248 of 1989 and 59 of
1993, the above two appeals were filed.
3. The case on hand has a chequered history .
The Government of Tamil Nadu formulated a scheme known as
"Veeranam Project" to provide drinking water to the city of Chennai and
thereby overcome the problem of acute water scarcity in the city of
Chennai. In order to implement the aforesaid scheme, the Government
invited tenders for manufacturing, supplying and delivering 1676 mm
pre-stressed concrete pipes and fittings including transporting to site,
laying, jointing and testing for raw water and clear water conveying,
from Veeranam Tank to Chennai City. The Secretary to Government,
Public Works Department requested for clearance of foreign exchange
from the Government of India. This was done with a view to avoid delay
in the project. The respondent herein submitted their tender. The
tender submitted by the respondent was the lowest tender and on
negotiation the same was accepted by the Government and the
Government issued G.O.Ms.No.1607 Public (Twad) Department
accepting the tender of the respondent. Subsequently, the Government
suggested that the respondent should approach ICICI Ltd. for foreign
exchange loan. The Government accepted the request of the
respondent for a hike in the tender amount in view of the reduction on
foreign exchange component. An agreement was entered into between
the respondent and the Chief Engineer, Public Works Department. The
Government of India also approved the foreign collaboration
arrangements. The import license for the gasket manufacturing unit
was also cleared and a factory at Thirukalikundram was commenced
and the equipment for manufacturing pipes was also received. The
factory at Panrutti also commenced the operation and the equipment
for manufacturing rubber gaskets was received in two shipments. The
respondent sought extension of time till 31.12.1975 in order to complete
the work. On considering the prevailing circumstances, the time for
completion of work was extended till 30.06.1975. Again the
respondent wrote to the appellant informing it that the work will not be
completed even by 30.06.1976 and that it is impossible for them to
carry out the work as per the original agreement, unless the rates are
revised and on 30.06.1975, the work was abandoned by the
respondent. Again a request was made for further extension of time
and the time was also extended for completion of the work till
31.12.1975. The respondent stated that they were prepared to
continue the work only if the rates are revised. The appellant further
extended the time for completion of the work till 31.03.1976.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
4 Since disputes arose between the parties, the respondent
invoked the arbitration clause in the agreement and appointed
Sri.P.S.Subramaniam as their Arbitrator. The appellant appointed
Sri.C.K. Sreenivasan as their Arbitrator. Both the Arbitrators
appointed Hon’ble Mr.Justice K.S.Palaniswamy, a retired Judge of
the High Court as their umpire. The arbitrators entered upon the
reference on 18.03.1978. The statement of claim of
Rs.13,92,00,478.17 was also filed by the respondent before the
Arbitrators. The appellant Board also made a claim of
Rs.50,29,63,320/- filed before the Arbitrators.
5 The learned Arbitrator Sri.P.S.Subramaniam gave an award in
favour of the contractor for a sum of Rs.6,98,54,780/-. However, the
other Arbitrator, namely, Sri.C.K.Sreenivasan gave notice of his
disagreement to the award. Therefore, on 02.04.1979, the Umpire
entered upon the reference. The Umpire passed his award, inter
alia, holding that the respondent-contractor is entitled to
Rs.40,02,591/- from the appellant and that after allowing deduction
for the same the respondent is liable to pay to the appellant a sum
of Rs.2,69,93,674/- with interest at 9% p.a. from the date of the
Award. Out of the said Award only a sum of Rs.5,000/- was awarded
as damages for breach of contract.
6 The Umpire filed the Award in the High Court of Madras
and the same was numbered as O.P.No.428 of 1979. The appellant
filed Application No.560 of 1980 in O.P.No.428 of 1979 praying for a
decree to be passed in terms of the Award. Aggrieved by the Award,
the respondent filed O.P.No.122 of 1980 before the High Court for
setting aside the aforesaid Award dated 10.09.1979. The learned
Single Judge allowed O.P.No.122 of 1980 filed by the respondent
and set aside the award passed by the Umpire and consequently
application No.560 of 1980 in O.P.No.428 of 1979 and O.P.No.428 of
1979 were dismissed. On the same day, C.S.No.176 of 1978 was
also dismissed. Aggrieved by the order allowing O.P.No.122 of
1980, the appellant preferred an appeal in O.S.A.No.248 of 1989 and
aggrieved by the order dismissing Application No.560 of 1980 in
O.P.No.428 of 1979, the appellant herein preferred an appeal in
O.S.A.No.59 of 1993. Aggrieved by the order dismissing C.S.No.176
of 1978, the appellant herein preferred an appeal in O.S.A.No.211 of
1990.
7. The Division Bench allowed O.S.A.Nos.248 of 1989 and 59 of
1993, preferred by the appellant, inter alia, holding that the
respondent had stopped work without any cause, that the respondent
had abandoned the work, that the award amount arrived at by the
Umpire is correct and, therefore, passed a decree in terms of the
Award dated 10.09.1979 passed by the Umpire. It was further held
that the appellant is entitled to costs throughout and to interest at 9%
p.a. from the date of Award.
8. Aggrieved by the aforesaid order, the respondent herein
preferred Special Leave Petition (Civil) Nos.2096-2097 of 2002. The
Division Bench dismissed O.S.A.No.211 of 1990. The Special Leave
Petition (Civil) Nos.2096-2097 of 2002 were filed which were re-
numbered as Civil Appeal Nos.9136-9137 of 2003 and this Court
remitted the matter to the Division Bench of the High Court to be
considered in the light of the observation made in the paragraph 16
of the Judgment. [Sathyanarayana Brothers (P) Ltd. vs. T.N.Water
Supply & Drainage Baord, reported in (2004) 5 SCC 314]. On
remission, the Division Bench dismissed the appeals holding that
foreign exchange was to be obtained by the joint efforts of the
appellant and the respondent, that the Government was not extending
the time reasonably but in piecemeal, that the respondent had not
committed breach of contract.
9. Aggrieved by the order dt.24.03.2004, the appellant preferred
the above appeals.
10. It is also pertinent to notice that the SLP filed by the
respondent-contractor against the very same judgment was also
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
dismissed by this Court at the admission stage.
11. Before dealing with the matter on merits, it is beneficial to
refer to the order passed by this Court in Sathyanarayana Brothers
(P) Ltd. vs. T.N.Water Supply & Drainage Baord, reported in (2004) 5
SCC 314. This Court after an elaborate consideration of the
entire materials placed before it held that the learned Single Judge
has given it as one of the reasons to hold that it vitiated the award.
The Division Bench was of the view that the
learned Single Judge was right in inferring that such an infirmity
would vitiate the award. However, this Court held that the order of the
Division Bench, reversing the decision of the Single Judge was not
sustainable and the matter be required to be remitted to be
considered in the light of the "handing over note" of the Chief
Engineer in respect whereof an application was moved by the
appellant before the Arbitrator as well as before the Umpire which
remained unattended to by the forum and which later did not accede
to the request. Considering the fact that it is an old matter and it
being a speaking award, the matter having also been considered by
the learned Single Judge, this Court felt that it would better serve the
ends of justice to ensure expeditious disposal of the matter and,
therefore, the Division Bench of the High Court was requested to
consider the matter afresh taking into account the "handing over
note" of the Chief Engineer of the project and other relevant
documents. In the result, this Court allowed the appeals filed by the
contractor-Sathyanarayana Brothers (P) Ltd.- and set aside the order
of the Division Bench of the High Court and remitted the matter to the
High Court for being decided afresh by the Division Bench in the light
of the observations made in the Judgment.
12 We have carefully perused the order passed by the Division
Bench in O.S.A.Nos.248 of 1989 and 59 of 1993 after remittance.
After hearing extensive arguments advanced by Mr.Mohan
Parasaran, learned ASG and countered by two learned senior
counsel appearing on behalf of the respondent, we are of the view
that on remand, the learned Judges of the Division Bench have
considered the entire matter afresh and came to the conclusion that
the reasons recorded in the said Judgment and that the
sustainability of the claims of the contractor need not be
considered in these appeals and equally the Board is also not
entitled to any decree on the basis of the Award for the reasons
given in the said Judgment. It was also further observed that the
Bench was not dealing with the respective claims of the contractor
and the Board against each other on different headings and they
were inclined to set aside the award passed by the Umpire.
13 In the instant case, the appellant is still proceeding under a false
premises that the contractor is solely responsible for the delay in
the execution of the work and the breach of contract which have
been conclusively found against the appellant by the learned Single
Judge as well as the Division Bench of the High Court while setting
aside the award passed by the Umpire in the present case. The
appellant has not raised any substantial question of law that needs
to be considered by this Court. The questions raised are only
question of fact and in view of the concurrent findings by both the
learned Single Judge and the Division Bench, no interference by
this Court is called for particularly when a matter was fully heard in
the earlier round by the Supreme Court. The matter was remitted to
the Division Bench of the High Court by this Court only after
considering all aspects and the questions involved in the case.
Now, it has been conclusively found that the respondent-contractor
was not responsible for any breach of contract. According to the
contractor, all the advances were granted only for the mobilization
of the work with specific condition that pro-rata deductions will be
made in the bills for the work carried out by the contractor and now
the completion of the contract the advances will be adjusted from
the bills for the dues to be paid to the contractor.
14 As already noticed, the appellant has not raised any ground
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
that warrants interference with the impugned judgment. The High
Court, in our opinion, has decided the matter strictly in accordance
with the remand order made by this Court in the judgment in Civil
Appeal Nos.9136-9137 of 2003 reported in [(2004) 5 SCC 314]. The
High Court also has not entered into any finding regarding the
respective claims of the parties but set aside the award of the
Umpire only on the ground of legal mala fides.
15 In our opinion, the well-considered judgment rendered by the
High Court on remission from this Court does not call for any
interference. We, therefore, affirm the order passed by the Division
Bench and dismiss the Civil Appeal Nos.2880-2881 of 2005 filed by
the appellant.
16 We also make it clear that if any claim survives with reference
to this particular contract, the parties will be free to agitate the same
before the sole Arbitrator in terms of the Arbitration Clause. For the
said purpose, we, by consent of both parties, appoint Hon’ble
Mr.Justice S.Mohan, a retired Judge of this Court as the sole
arbitrator. The parties are at liberty to file any claim if it survives
and also documents, records etc. The sole arbitrator is requested
to dispose of the arbitration proceedings within six months from the
date of entering upon the reference.
17 The Arbitrator is at liberty to fix his remuneration and
other expenses to be equally shared by both the appellant and the
respondent.
18 The Arbitrator should file his Award in this Court.
19 The Civil Appeals stand dismissed. No costs.