Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
CASE NO.:
Appeal (civil) 8418 of 2002
PETITIONER:
Ghaziabad Development Authority
RESPONDENT:
Rajesh Chandra
DATE OF JUDGMENT: 27/09/2004
BENCH:
S. N. VARIAVA & B. P. SINGH
JUDGMENT:
J U D G M E N T
S. N. VARIAVA, J.
Before this Court a large number of Appeals have been filed by
the Haryana Urban Development Authority and/or the Ghaziabad
Development Authority challenging Orders of the National Consumer
Disputes Redressal Commission, granting to Complainants, interest at
the rate of 18% per annum irrespective of the fact of each case. This
Court has, in the case of Ghaziabad Development Authority vs. Balbir
Singh reported in (2004) 5 SCC 65, deprecated this practice. This
Court has held that interest at the rate of 18% cannot be granted in all
cases irrespective of the facts of the case. This Court has held that
the Consumer Forums could grant damages/compensation for mental
agony/harassment where it finds misfeasance in public office. This
Court has held that such compensation is a recompense for the loss or
injury and it necessarily has to be based on a finding of loss or injury
and must co-relate with the amount of loss or injury. This Court has
held that the Forum or the Commission thus had to determine that
there was deficiency in service and/or misfeasance in public office and
that it has resulted in loss or injury. This Court has also laid down
certain other guidelines which the Forum or the Commission has to
follow in future cases.
This Court is now taking up the cases before it for disposal as
per principles set out in earlier judgment. On taking the cases we find
that the copies of the Claim/Petitions made by the
Respondent/Complainant and the evidence, if any, led before the
District Forum are not in the paper book. This Court has before it the
Order of the District Forum. The facts are thus taken from that Order.
In this case, the Respondent applied for a Shop on 30.10.1995 in
Commercial Scheme Kaushambi, 1994 of the Appellants and the value
of the shop was Rs.1,20,000/-. The Respondent deposited the entire
amount with the Appellants, but the possession of the shop was not
delivered, while the possession has been given to other allottees. The
Respondent filed a Complaint before the District Forum. On these
facts, the District Forum directed the Appellants to handover the
physical possession of the shop within three months from the date of
order after constructing the shop along with interest at the rate of
18% p.a. from 1.1.1997 till the date of possession and awarded a sum
of Rs.2,000/- as cost and damages. It further directed that if the Order
is not complied with within the said period, the Appellants shall pay
interest at the rate of 21% p.a.
Aggrieved by this Order, the Appellants filed an Appeal before
the State Forum challenging the Order of the District Forum. The
State Forum partly allowed the Appeal modifying the order of the
District Forum to the extent that it directed that the interest, at the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
rate of 18% p.a., only shall be payable from 13.8.1997 till the date of
delivery of possession and imposed a cost of Rs.2,000/- on the
Appellants. The Appellants went in Revision before the National
Commission. The National Commission dismissed the Revision relying
upon its own decision in the case of Haryana Urban Development
Authority v. Darsh Kumar and observing that interest @ 18% p.a. has
been allowed by them under similar circumstances.
As has been stated in so many matters, the Order of the
National Commission cannot be sustained. It cannot dispose of the
matters by confirming award of interest in all matters irrespective of
the facts of that case. It must, on facts of a case, award
compensation/damage under appropriate heads if it comes to the
conclusion that such award is justified/necessary. Accordingly, the
Order of the National Commission is set aside.
We are informed that now possession of a shop is offered to the
Respondent but a higher rate is being claimed. We find that before
the State Forum a claim was made that Respondent must pay a higher
rate. The State Forum did not direct Respondent to pay a higher
amount. The State Forum instead confirmed the Order of the District
Forum. Neither before the National Commission nor in the Appeal
before us, is there any challenge or ground that the State Forum erred
in not directing payment of higher amount. As there is no challenge
we cannot permit oral submissions to the contrary.
We therefore direct that Respondent shall be given possession of
the shop within two weeks from today without claiming any further or
other amounts. As Respondent is getting the shop at the old rate, in
our view, interest at the rate of 12% would be sufficient. The interest
amount shall also be paid within two weeks from today, if not already
paid. If however interest at a higher rate is already paid, then on
principles set out by us in the case of Ghaziabad Development
Authority vs. Balbir Singh (supra), no refund will be claimed.
We clarify that this Order shall not be taken as a precedent in
any other matter as the order is being passed taking into account
special features of the case. The Forum/Commission will follow the
principles laid down by this Court in the case of Ghaziabad
Development Authority vs. Balbir Singh (supra) in future cases.
With these observations, the Appeal stands disposed of with no
order as to costs.