Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 11
CASE NO.:
Appeal (civil) 5647-48 of 1997
PETITIONER:
Bharat Coking Coal Ltd.
RESPONDENT:
Vs.
M/s Annapurna Construction
DATE OF JUDGMENT: 29/08/2003
BENCH:
CJI. & S.B. Sinha.
JUDGMENT:
J U D G M E N T
S.B. SINHA, J :
These appeals are directed against the judgment and order dated
29.4.1997 passed by the High Court of Patna, Ranchi Bench, Ranchi in
Appeal from Original Order No.169 of 1995 (R) whereby and whereunder
the appeal preferred by the appellant herein from a judgment and order
dated 3.6.1995 passed by the Subordinate Judge, 4th Court, Dhanbad in
Title (Arbitration) Suit No.109 of 1994 was dismissed.
FACTS:
The basic fact of the matter is not in dispute. The parties
hereto entered into a contract for construction of 140 numbers of
temporary hutments, the estimated cost of which was Rs.49,45,447.81.
A formal work order was issued to the respondent herein. Entire work
in terms of the agreement was to be completed within a period of four
months.
A formal contract was entered into for the aforementioned work by
and between the parties. The said contract contained an arbitration
agreement. The said contractual job was not allegedly completed by the
respondent within the stipulated period wherefor a request was made for
extension of time till 31.12.1986 to complete the work. Further
extensions of time were sought for and granted from time to time.
Disputes and differences having arisen between the parties, the
arbitration agreement was invoked. The Chief Engineer of the
appellant-Company was appointed as the sole arbitrator. He was to give
a reasoned award. Before the arbitrator the respondent raised a claim
of Rs.55,01,640.66. The appellant herein also raised a counter claim
for a sum of Rs.28,47,860.57. By reason of an award dated 13.7.1994,
the sole arbitrator awarded a sum of Rs.18,97,729.37 with interest @
18% per annum in favour of the respondent. The counter claim of the
appellant, however, was rejected.
The said award was filed before the learned Subordinate Judge,
Dhanbad for being made a rule of court in terms of Section 14 of the
Arbitration Act, 1940 (for short ’the Act’). The appellant herein in
the said proceedings filed an objection under Sections 15, 16, 30 and
33 of the Act. The learned trial Judge by reason of a judgment dated
3.6.1995 rejected the said objection of the appellant and made the
award as rule of court, where-against an appeal was preferred which by
reason of the impugned judgment was dismissed.
However, it may be noticed at this stage that the learned
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 11
Subordinate Judge did not grant any interest from the date of decree in
favour of the respondent wherefor an application purported to be under
Section 152 of the Code of Civil Procedure was filed. The said
application was rejected on 12.12.1995 where-against the respondent
preferred a civil revision application before the High Court. Both the
appeal being M.A. No.169 of 1995 (R) filed by the appellant herein and
Civil Revision being C.R. No.12 of 1996 (R) filed by the respondent
herein were heard together. While disposing the appeal, the revison
petition was allowed by the High Court by reason of the impugned
judgment.
SUBMISSIONS:
Mr. Ajit Kumar Sinha, learned counsel appearing on behalf of the
appellant, inter alia, submitted that the respondent having accepted
the final bill, a further claim by it was inadmissible. The learned
counsel pointed out that as a special case the appellant granted 95%
advance wherefor no interest was to be charged. The said advance was
to be adjusted from the running bills. In that view of the matter, the
learned counsel would contend that the arbitrator committed an
illegality in entertaining Claim Item Nos. 3 and 7. The learned
counsel would urge that the respondent having been granted extension,
it was obligatory on the part of the learned arbitrator to consider as
to whether the respondent was entitled to any compensation for the
alleged loss occurred on the ground of delay in completion of work,
particularly when it was agreed that the extension of time was granted
subject to payment of penalty. The learned counsel would further
submit that in terms of the contract the appellant had been supplied
with all the essential raw materials, namely, cement, steel etc. which
would cover about 95% of the total cost to be incurred for the
construction of the hutments and in that view of the matter the
respondent could not be held to be entitled to any amount by way of
escalation in the price.
Mr. S.B. Upadhyay, learned counsel appearing on behalf of the
respondent, per contra would submit that the objections filed by the
appellant herein have been thoroughly considered by the learned
Subordinate Judge and the High Court and as such it is not a fit case
wherein this Court should interfere. The learned counsel would urge
that it is not the case of the appellant that the learned sole
arbitrator did not pass a reasoned award and, thus, this court in
exercise of its jurisdiction under Section 30 of the Act would not
interfere when two views are possible. The learned counsel would submit
that while exercising its jurisdiction under Section 30 of the Act, the
court does not reappraise evidences brought on record. Strong
reliance, in this connection, has been placed on Ispat Engineering &
Foundry Works, B.S. City, Bokaro vs. Steel Authority of India Ltd.,
B.S. City, Bokaro [(2001) 6 SCC 347].
FINDINGS:
Only because the respondent has accepted the final bill, the same
would not mean that it was not entitled to raise any claim. It is not
the case of the appellant that while accepting the final bill, the
respondent had unequivocally stated that he would not raise any further
claim. In absence of such a declaration, the respondent cannot be held
to be estopped or precluded from raising any claim. We, therefore, do
not find any merit in the said submission of Mr. Sinha.
The submission of Mr. Sinha to the effect that the High Court
committed an error in granting interest from the date of the decree
purported to be in terms of Section 29 of the Arbitration Act appears
to be correct. The learned Subordinate Judge did not grant any
interest in terms of Section 29 of the Act. The same was not by way of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 11
a clerical or arithmetical mistake which could be corrected by the
court in exercise of its power under Section 152 of the Code of Civil
Procedure. The remedy of the respondent, therefore, was either to
prefer an appeal thereagaint or file a review petition. As the court
could not have exercised its jurisdiction under Section 152 of the Code
of Civil Procedure, the High Court in exercise of its revisional
jurisdiction could not have interfered therewith.
So far as the question of late payment of the bills is concerned,
the arbitrator has arrived at a finding of fact that there had been an
inordinate delay in respect of 10th R/A bill for Rs.4,85,403.31 which
was paid after a lapse of one year from the date of completion of work
on 15.1.1988 and a sum of Rs.54,737.53 was awarded as damages @ 12% on
the said amount for the period of 343 days to the appellant.
So far as Claim Item No.3 is concerned, the question which arose
for consideration before the arbitrator was as to whether any extra
work had been done or not. The case of the appellant was that the
respondent had not done any extra work. The arbitrator had considered
the materials on record for the purpose of arriving at a finding of
fact that certain extra work had been done by the respondent wherefor
only a sum of Rs.84,942.02 was awarded in place and instead of
Rs.1,58,862.26.
However, Mr. Sinha is correct in his submission that the learned
arbitrator has not taken into consideration the effect and purport of
the following clause in the contract:
"Provided always that :
(a) Contractor/Contractors shall not be entitled to
any payment for any additional work done unless
he/they have received an order in writing from
the Superintending Engineer/Sr. Executive
Engineer/Executive Engineer for such additional
work;
(b) The contractor/contractors shall be bound to
submit his/their claim for any such additional
work done during any month on or before the 15th
day of the following month accompanied by the
additional work; and
(c) The contractor/contractors shall not be
entitled to any payment in respect of such
additional work if he/they fail to submit
his/their claim within the aforesaid period."
The question is as to whether the claim of the contractor is de
hors the rules or not was a matter which fell for consideration before
the arbitrator. He was bound to consider the same. The jurisdiction
of the arbitrator in such a matter must be held to be confined to the
four-corners of the contract. He could not have ignored an important
clause in the agreement; although it may be open to the arbitrator to
arrive at a finding on the materials on records that the claimant’s
claim for additional work was otherwise justified.
Claim Item No.4 was rejected.
The award in respect of Claim Item No.5 is not in question.
Claim Item No.6 was in relation to penalty amount of Rs.10,000/- which
was deducted by way of penalty and was not found to be justifiable, and
as such the appellant was directed to refund the said amount.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 11
We are furthermore concerned with Claim Item Nos.7 and 11 which
are under the headings of ’Losses due to prolongation of work’ and
’Material Escalation’. It is not in dispute that a secured advance of
95% of the cost of materials was given in terms of the contract which
is to the following effect :
"Secured Advance will be paid @ 95% of the cost
of materials as a special case to get the work
completed within 4(four) months as per latest
price list of BCCL (copy enclosed), subject to
submissions of Indemnity Bond on non-Judicial
stamp paper of required value in the approved
proforma of BCCL and also Insurance against
fire, theft and damages etc. The secured
advance will be paid only on the items on which
it was payable in BCCL. The secured advance
thus paid, will be recovered in five equal
instalments from the subsequent running account
bills or on the consumption of materials
whichever is earlier."
The appellant does not dispute the same. It is also not in
dispute that the appellant has not charged any interest in respect of
the said advance. It is further not in dispute that cement @ Rs.51/-
per bag, mild steel rounds @ Rs.5460/- per metric tonne and tor steel @
Rs.5810/-per metric tonne were supplied by the appellant. However, the
claim relating to material escalation was confined to six articles
which were allegedly not supplied by the appellant, namely, bricks, AC
sheets, angles, doors, frames and shutters etc.
So far as these items are concerned, in our opinion, the learned
sole arbitrator should have taken into consideration the relevant
provisions contained in the agreement as also the correspondences
passed between the parties. The question as to whether the work could
not be completed within the period of four months or the extension was
sought for on one condition or the other was justifiable or not, which
are relevant facts which were required to be taken into consideration
by the arbitrator.
It is now well settled that the Arbitrator cannot act
arbitrarily, irrationally, capriciously or independent of the contract.
In Associated Engineering vs. Govt. of A.P. [(1991) 4 SCC 93],
this Court clearly held that the arbitrators cannot travel beyond the
parameters of the contract. In M/s. Sudarsan Trading Co. v. The Govt.
of Kerala [(1989) 2 SCC 38], this Court has observed that an award may
be remitted or set aside on the ground that the arbitrator in making it
had exceeded his jurisdiction and evidence of matters not appearing on
the face of it, will be admitted in order to establish whether the
jurisdiction had been exceeded or not, because the nature of the
dispute is something which has been determined outside the award,
whatever might be said about it in the award by the Arbitrator. This
Court further observed that an arbitrator acting beyond his
jurisdiction is a different ground from the error apparent on the face
of the award.
There lies a clear distinction between an error within the
jurisdiction and error in excess of jurisdiction. Thus, the role of the
arbitrator is to arbitrate within the terms of the contract. He has no
power apart from what the parties have given him under the contract. If
he has travelled beyond the contract, he would be acting without
jurisdiction, whereas if he has remained inside the parameter of the
contract, his award cannot be questioned on the ground that it contains
an error apparent on the face of the records.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 11
In paragraph 577 of Halsbury’s laws of England 4th Edition Vol 2,
the law has been stated in the following terms:
"As an arbitrator (and subsequently any umpire)
obtains his jurisdiction solely from the
agreement for his appointment it is never open
to him to reject any part of that agreement, or
to disregard any limitations placed on his
authority, as, for example, a limitation on his
right to appoint an umpire. Nor can he confer
jurisdiction upon himself by deciding in his
own favour some preliminary point upon which
his jurisdiction depends. Nevertheless he is
entitled to consider the question whether or
not he has jurisdiction to act in order to
satisfy himself that it is worth while to
proceed, and an award which expressly or
impliedly refers to such a finding is not
thereby invalidated."
In ’Commercial Arbitration’ by Mustill and Boyd at page 598 it is
stated :
"in the first place, it could be argued that an
arbitrator who is appointed in respect of a
dispute arising under a contract expressly or
impliedly governed by English law is authorised
by the parties to pronounce upon the issues in
accordance with that law, and in no other way.
Any decision which proceeds, on a different
basis lies outside the scope of the
arbitrator’s mandate to bind the parties. The
award is accordingly void for want of
jurisdiction, since the arbitrator has done
something which the parties never authorised
him to do. Secondly, it would be possible to
draw support from a line of authority
culminating in three important decisions during
the past decade which approach the question
whether a tribunal can effectively decide
contrary to law by using the word ’jursdiction’
in the first of the three senses indicated
above. Whilst a reconciliation of this decision
is a matter for a treatise on administrative
law, there is no doubt that in relation to
certain kinds of tribunal the law has
recognised a distinction between errors of law
which go to jurisdiction and those which do
not, and that there is a difference between
tribunal which has arrived at a decision by
asking itself the wrong question, and one which
has correctly identified the question, but has
supplied the wrong answer in terms of law.
Following up this line of authority, it could
be said that an arbitrator empowered to decide
the rights of the parties under a contract
governed by English law, who asks himself not
what England law has to say about those right,
but what the rights ought to be if assessed in
accordance with his own ideas of an extra-legal
concept of justice, is either asking himself
the wrong question, or not really asking a
question at all."
In Alopi Parshad & Sons Ltd. v. Union of India [(1960) 2 SCR
793], this Court clearly held that if damages are awarded ignoring the
expressed terms of the contract, the arbitrator would commit misconduct
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 11
of the proceedings. Reference in this connection may also be made to
Naihati Jute Mills Ltd. Vs. Khyaliram Jagannath [(1968) 1 SCR 821].
In Heyman v. Darwin [1942 (1) All ER 327], it was held that
arbitrator as a rule cannot clothe himself with the jurisdiction when
it has none.
In paragraph 622 at pages 330-331 Halsbury’s Laws of England (4th
Edn) Vol2 it has been stated but misconduct occurs, for example;
(1) If the arbitrator or umpire fails to decide
all the matters which were referred to him.
(2) If by his award the arbitrator or umpire
purports to decide matters which have not in
fact been included in the agreement of
reference, for example, where the arbitrator
construed the lease (wrongly), instead of
determining the rental and the value of
buildings to be maintained on the land; or
where the award contains unauthorised
directions to the parties, or where the
arbitrator, has power to direct what shall be
done but his directions affect the interest of
third persons; or where he decided to the
parties rights, not under the contract upon
which the arbitration had proceeded but under
another contract;
(3) If the award is inconsistent, or is
uncertain or ambiguous, or even if there is
some mistake of fact, although in that case the
mistake must be either admitted or at least
clear beyond any reasonable doubt;"
In Associated Engineering (supra), it has been held:
"If the arbitrator commits an error in the
construction of the contract, that is an error
within his jurisdiction. But if he wanders
outside the contract and deals with matters not
allotted to him, he commits a jurisdiction
error. Such error going to his jurisdiction can
be established by looking into material outside
the award. Extrinsic evidence is admissible in
such cases because the dispute is not something
which arises under or in relation to the
contract or dependent on the construction of
the contract or to be determined within the
award. The dispute as to jurisdiction is a
matter which is outside the award or outside
whatever may be said about it in the award. The
ambiguity of the award can, in such cases, be
resolved by admitting extrinsic evidence. The
rationale of this rule is that the nature of
the dispute is something which has to be
determined outside and independent of what
appears in the award. Such jurisdictional error
needs to be proved by evidence extrinsic to the
award.
In the instant case, the umpire decided matters
strikingly outside his jurisdiction. He
outstepped the confines of the contract. He
wandered far outside the designated area. He
digressed far away from the allotted task. His
error arose not by misreading or misconstruing
or misunderstanding the contract, but by acting
in excess of what was agreed. It was an error
going to the root of his jurisdiction because
he asked himself the wrong question,
disregarded the contract and awarded in excess
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 11
of his authority. In many respects, the award
flew in the face of provisions of the contract
to the contrary.
The umpire, in our view, acted unreasonably,
irrationally and capriciously in ignoring the
limits and the clear provisions of the
contract. In awarding claims which are totally
opposed to the provisions of the contract to
which he made specific reference in allowing
them, he has misdirected and misconducted
himself by manifestly disregarding the limits
of his jurisdiction and the bounds of the
contract from which he derived his authority
thereby acting ultra fines compromissi."
In State of Orissa v. Dandasi Sahu [1988 (4) SCC 12], this Court
observed:
"In our opinion, the evidence of such state of
affairs should make this Court scrutinise the
award carefully in each particular case but
that does not make the court declare that all
high amounts of award would be bad per se."
In K.P. Poulose v. State of Kerala [(1975) 2 SCC 236], this
Court observed that the case of legal misconduct would be complete if
the arbitrator on the face of the award arrives at an inconsistent
conclusion even on his own finding or arrives at a decision by ignoring
the very material documents which throw abundant light on the
controversy to help a just and fair decision.
In K.V. George v. The Secretary to Government, Water and Power
Dept, Tri-vendrum [1989 (4) SCC 595], this Court held :-
"In the instant case, the contract was
terminated by the respondents on April 26,
1980, and as such all the issues arose out of
the termination of the contract and they could
have been raised in the first claim petition
filed before the Arbitrator by the Appellant.
This having not been done the second claim
petition before the Arbitrator raising the
remaining disputes is clearly barred. With
regard to the submission as to the
applicability of the principles of res judicata
as provided in Section 11 of the Code of Civil
Procedure to arbitration case, it is to be
noted that Section 41 of the Arbitration Act
provides that the provisions of the Code of
Civil Procedure will apply to the Arbitration
proceedings. The provisions of res judicata are
based on the principles that there shall be no
multiplicity of proceedings and there shall be
finality of proceedings. This is applicable to
the arbitration proceedings as well."
This Court referred to the decision in Satish Kumar v. Surinder
Kumar [AIR 1970 SC 833] and held:
"The true legal position in regard to the
effect of an award is not in dispute. It is
well settled that as a general rule, all claims
which are the subject-matter of a reference to
arbitration merge in the award which is
pronounced in the proceedings before the
arbitrator and that after an award has been
pronounced, the rights and liabilities of the
parties in respect of the said claims can be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 11
determined only on the basis of the said award.
After an award is pronounced, no action can be
started on the original claim which had been
the subject-matter of the reference....... This
conclusion, according to the learned Judge, is
based upon the elementary principle that, as
between the parties and their privies, an award
is entitled to that respect which is due to
judgment of a court of last resort. Therefore,
if the award which has been pronounced-between
the parties has in fact, or can in law, be
deemed to have dealt with the present dispute,
the second reference would be incompetent. This
position also has not been and cannot be
seriously disputed."
In Union of India vs. Jain Associates and Another [(1994) 4 SCC
665], this Court upon following K.P. Poulose (supra) and Dandasi Sahu
(supra) held :
"8. The question, therefore, is whether the
umpire had committed misconduct in making the award.
It is seen that claims 11 and 12 for damages and loss
of profit are founded on the breach of contract and
Section 73 encompasses both the claims as damages.
The umpire, it is held by the High Court, awarded
mechanically, different amounts on each claim. He
also totally failed to consider the counter-claim on
the specious plea that it is belated counter-
statement. These facts would show, not only the state
of mind of the umpire but also non-application of the
mind, as is demonstrable from the above facts. It
would also show that he did not act in a judicious
manner objectively and dispassionately which would go
to the root of the competence of the arbitrator to
decide the disputes."
In Sikkim Subba Associates Vs. State of Sikkim [(2001) 5 SCC
629], this Court held:
"It would be difficult for the courts to either
exhaustively define the word "misconduct" or
likewise enumerate the line of cases in which
alone interference either could or could not be
made. Courts of law have a duty and obligation
in order to maintain purity of standards and
preserve full faith and credit as well as to
inspire confidence in alternate dispute
redressal method of arbitration, when on the
face of the award it is shown to be based upon
a proposition of law which is unsound or
findings recorded which are absurd or so
unreasonable and irrational that no reasonable
or right-thinking person or authority could
have reasonably come to such a conclusion on
the basis of the materials on record or the
governing position of law to interfere."
In Maharashtra State Electricity Board Vs. Sterilite Industries
(India) and Another [(2001) 8 SCC 482], it was observed:
"In the light of this enunciation of law, we
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 11
are of the view that unless the error of law
sought to be pointed out by the learned counsel
for the petitioners in the instant case is
patent on the face of the award, neither the
High Court nor this Court can interfere with
the award. The exercise to be done by examining
clause 14(ii) of the contract entered into
between the parties, construing the same
properly and thereafter applying the law to it
to come to a conclusion one way or the other,
is too involved a process and it cannot be
stated that such an error is apparent or patent
on the face of the award. Whether under the
context of the terms and conditions of a
contract, a stipulation in the form and nature
of clause 14(ii) operates as a special
provision to the exclusion of Section 73 of the
Indian Contract Act is a matter of appreciation
of facts in a case, and when the decision
thereon is not patently absurd or wholly
unreasonable, there is no scope for
interference by courts dealing with a challenge
to the award."
In W.B. State Warehousing Corporation and Another Vs. Sushil
Kumar Kayan and Others [(2002) 5 SCC 679], this Court opined:
"In order to determine whether the arbitrator
has acted in excess of his jurisdiction what
has to be seen is whether the claimant can
raise a particular claim before the arbitrator.
If there is a specific term in the contract or
the law which does not permit the parties to
raise a point before the arbitrator and if
there is a specific bar in the contract to the
raising of the point, then the award passed by
the arbitrator in respect thereof would be in
excess of his jurisdiction."
The High Court was, therefore, required to consider, the
objections filed by the Appellant herein from the aforementioned points
of view.
Bharat Coking Coal Ltd. Vs. L.K. Ahuja & Co. [(2001) 4 SCC 86],
whereupon Mr. Sinha has placed strong reliance cannot be held to be
applicable in this case as therein the court was concerned with hybrid
award. The court was not in a position to ascertain as to whether
escalation charges had been made against the materials supplied by the
principal or also other materials.
It is no doubt true that the jurisdiction of this Court while
considering the validity of an award is limited as has been stated by
this Court in Ispat Engineering & Foundry Works (supra):
"4. Needless to record that there exists a long
catena of cases through which the law seems to
be rather well settled that the reappraisal of
evidence by the court is not permissible. This
Court in one of its latest decisions (Arosan
Enterprises Ltd. v. Union of India ((1999) 9
SCC 449)) upon consideration of decisions in
Champsey Bhara & Co. v. Jivraj Balloo Spg. &
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 11
Wvg. Co. Ltd. (AIR 1923 PC 66 : 1923 AC 480),
Union of India v. Bungo Steel Furniture (P)
Ltd. (AIR 1967 SC 1032 : (1967) 1 SCR 324), N.
Chellappan v. Secy., Kerala SEB ((1975) 1 SCC
289), Sudarsan Trading Co. v. Govt. of Kerala
((1989) 2 SCC 38), State of Rajasthan v. Puri
Construction Co. Ltd. ((1994) 6 SCC 485) as
also in Olympus Superstructures (P) Ltd. v.
Meena Vijay Khetan ((1999) 5 SCC 651) has
stated that reappraisal of evidence by the
court is not permissible and as a matter of
fact, exercise of power to reappraise the
evidence is unknown to a proceeding under
Section 30 of the Arbitration Act. This Court
in Arosan Enterprises ((1999) 9 SCC 449)
categorically stated that in the event of there
being no reason in the award, question of
interference of the court would not arise at
all. In the event, however, there are reasons,
interference would still be not available
unless of course, there exist a total
perversity in the award or the judgment is
based on a wrong proposition of law. This Court
went on to record that in the event, however,
two views are possible on a question of law,
the court would not be justified in interfering
with the award of the arbitrator if the view
taken recourse to is a possible view. The
observations of Lord Dunedin in Champsey Bhara
(AIR 1923 PC 66 : 1923 AC 480) stand accepted
and adopted by this Court in Bungo Steel
Furniture (AIR 1967 SC 1032 : (1967) 1 SCR 324)
to the effect that the court had no
jurisdiction to investigate into the merits of
the case or to examine the documentary and oral
evidence in the record for the purposes of
finding out whether or not the arbitrator has
committed an error of law. The court as a
matter of fact, cannot substitute its own
evaluation and come to the conclusion that the
arbitrator had acted contrary to the bargain
between the parties."
However, as noticed hereinbefore, this case stands on a different
footing, namely, that the arbitrator while passing the award in
relation to some items failed and/or neglected to take into
consideration the relevant clauses of the contract, nor did he take
into consideration the relevant materials for the purpose of arriving
at a correct fact. Such an order would amount to misdirection in law.
We are, therefore, of the opinion that the matter requires
reconsideration. Having regard to the facts and circumstances of this
case and particularly keeping in view the fact that the matter relates
to pure interpretation of document which gives rise to question of law
and instead and in place of remitting the matter to the named
arbitrator, we would direct that the disputes in relation to Claim item
Nos.3, 7 and 11 be referred to Hon’ble Mr. Justice D.N. Prasad, a
retired Judge of the Jharkhand High Court on such terms and conditions
as may be mutually agreed upon by the parties. The learned arbitrator
is requested to consider the desirability of making his award as
expeditiously as possible keeping in view the fact that the matter has
been pending for a long time.
These appeals are allowed to the aforementioned extent. No
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 11
costs.