Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
K.N. KARTHIKEYAN (DEAD)
Vs.
RESPONDENT:
M.N. SREENIVASAN & ORS.
DATE OF JUDGMENT: 20/02/1998
BENCH:
G.T. NANAVATI, SYED SHAH MOHAMMED QUADRI
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
NANAVATI,J.
Delay condoned.
Substitution allowed.
Leave granted. Heard learned counsel.
The appellant is questioning the correctness of the
order passed by the High Court of Kerala in O.P. No. 14665
of 1995-U. He is the landlord and in the suit filed by him
for eviction a decree was passed in his favour. The appeal
filed by the tenant was dismissed by the Appellate authority
and the Revision Petition filed in the High Court also met
with the same fate. The appellant thereafter applied for
execution of the decree. At that stage the respondent tenant
raised an objection that the landlord did not have valid
permit and permission to reconstruct the suit premises. The
objection was overruled by the executing court. So the
tenant filed a revision application before the Appellate
Authority. it held that the building plans submitted by the
landlord were not consistent with the provisions of the
Kerala Building Rules and, therefore, the landlord cannot be
said to be in possession of valid permit and permission from
the concerned authorities. Aggrieved by that order the
appellant filed O.P. No. 14665 of 1995-U in the High Court.
The tenant also filed O.P. No. 14213/95 for obtaining a
direction that the municipality should give a hearing to him
before sanctioning the building plans of the landlord. the
High Court allowed the petition filed by the tenant and
dismissed the petition of the landlord.
The learned counsel for the appellant submitted that
whether Municipality had given the required permission and
licence to the landlord and whether the Area Development
Authority had granted the necessary permit was already
considered while deciding the Eviction Petition and,
therefore, it was not open to the tenant in execution
proceedings to raise those objection. The Appellate
Authority, therefore, went beyond its jurisdiction in
holding that the landlord did not have validly approved plan
and permission to reconstruct the building. He also
submitted that the direction given by the High Court, by its
earlier order dated 29.6.1994, that the executing court
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
should satisfy itself before putting the landlord in
possession, that he possesses valid permit and licence from
the Municipality was not correctly construed by the
Appellate Authority and the High Court. According to the
learned counsel what the executing court was required to do
under that order was to verify whether the landlord was in
possession of a valid permit and permission for
reconstruction. It could not have been the intention of the
High Court that the executing court should scrutinise the
plans and decide legality of the permit and permission.
It is not in dispute that the question of bonafide
requirement of the landlord to reconstruct the building was
decided in his favour. It is also not in dispute that the
Rent Controller had considered whether the landlord was in
possession of the requisite permission from the Municipality
before passing the eviction order. Obviously, the executing
court could not have, therefore, gone behind those findings.
What the High Court, while dismissing the earlier revision
application against the order of eviction had directed was
to verify whether in fact the landlord possessed the
requisite permit/permission or not. The High Court had not
directed the executing court to consider if the Municipality
had validly granted the permission to reconstruct. Merely
because, the landlord in order to prove that he possessed
such permission had produced documents Exhibits A1 to A4
that did not entitle the Appellate Authority to go into that
question. The fact that a permit for development was granted
by the Area Development Authority and permission to
construct was granted by the Municipality was proved by
those documents.
The contention that was raised on behalf of the tenant
was that, as the permit granted by the Area Development
Authority was not submitted to the Municipal Authority for
its approval, the landlord did not have a valid permit. This
contention was accepted in view of the evidence of the
officer of the Area Development Authority that after
granting permit and approving the plan they are sent to the
Municipal Authority and the Municipality grants approval
thereafter. No such approval was obtained in case of the
appellant. What was overlooked by the Appellate Authority
and the High Court was that the landlord had already
obtained permission of the Municipality to reconstruct his
building on 14.8.1990 and this time he had applied for
renewal of that permission. It was, therefore, not required
to submit fresh plans to the Area Development Authority for
getting a fresh permit. The landlord did possess a permit
granted by the Area Development Authority and it was not
required to be approved again by the Municipality. He
possessed sanctioned plans and the required permission of
the Municipality. It was therefore, not proper to hold that
landlord was not in possession of a valid permit and
permission as required by law.
It was contended by the learned counsel for the
respondent that as the High Court has directed the executing
court to go into the question of validity of permit and
licence/permission it was open to it to find out whether the
permit and permission granted by the respective authorities
were lawful or not. As stated earlier what the High Court
had really intended was that the executing court should
verify before handing over possession of the suit premises
whether the landlord was in possession of valid permit and
permission or not. The High Court had not directed that
validity of the permit and permission should be examined in
the light of the building rules and regulation of the bye-
laws of the Area Development Authority and Municipality.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
The Appellate Authority, therefore, committed a grave
error in dismissing the execution application and the High
Court has also committed the same error by dismissing the
writ application. We, therefore, allow this appeal, set
aside the order passed by the High Court in O.P. No. 14665
of 1995-U and restore the order passed by the executing
court. In view of the facts and circumstances of the case
there shall be no order as to costs.