Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3615 OF 2023
(ARISING OUT OF SLP(C) NO. 8493 OF 2021)
RELIANCE INFRASTRUCTURE LTD. ….APPELLANT(S)
VERSUS
STATE OF GOA ….RESPONDENT(S)
WITH
CIVIL APPEAL NO.______ OF 2023
(ARISING OUT OF SLP(C) NO. 16778 OF 2021)
JUDGMENT
DINESH MAHESHWARI, J.
Table of Contents
Preliminary ................................................................................................................. 2
Relevant factual aspects and background .................................................................. 3
Arbitration proceedings and award ............................................................................. 7
Challenge to the award under Section 34 of the Act .................................................. 9
The appeal under Section 37 of the Act ................................................................... 11
Rival Submissions .................................................................................................... 15
Relevant Statutory provisions ................................................................................... 29
The scope of challenge to an arbitral award under Section 34 and the scope of appeal
under Section 37 of the Act ...................................................................................... 33
Questions relating to proceedings and procedure .................................................... 41
The award relating to variable charges on use of alternate fuel ............................... 44
The award relating to downrating of the plant .......................................................... 58
The award relating to variable charges on 4 MW power .......................................... 65
The award relating to netting-out principle ............................................................... 67
Signature Not Verified
Digitally signed by
Neetu Khajuria
Date: 2023.05.10
13:54:01 IST
Reason:
Interest in award ....................................................................................................... 68
Final comments, observations, and conclusion ........................................................ 71
1
Preliminary
Leave granted.
2. These two appeals, preferred against the judgment and order dated
08.03.2021, as passed by the High Court of Judicature at Bombay, Goa
Bench in Commercial Appeal No. 12 of 2019, one by Reliance
1
Infrastructure Limited , being the appeal arising out of SLP (Civil) No.8493
2
of 2021; and another by the State of Goa , being the appeal arising out of
SLP (Civil) No.16778 of 2021, have been considered together and are
taken up for disposal by this common judgment.
3. By way of the impugned judgment and order dated 08.03.2021,
while dealing with an appeal under Section 37 of the Arbitration and
3
Conciliation Act, 1996 read with Section 13 of the Commercial Courts,
Commercial Division and Commercial Appellate Divisions of High Courts
Act, 2015, the High Court has proceeded to upset the order dated
12.09.2019, as passed by the Principal District & Sessions Judge, North
4
Goa, Panjim in dismissing the application filed under Section 34 of the Act;
and has partially set aside the award dated 16.02.2018, as made by the
Arbitral Tribunal comprising of the Sole Arbitrator, a former Judge of this
Court.
1
Hereinafter also referred to as ‘the claimant’.
2
Hereinafter also referred to as ‘the State’ or ‘the Government of Goa’.
3
Hereinafter also referred to as ‘the Act of 1996’ or simply ‘the Act’.
4
Hereinafter also referred to as ‘the Commercial Court’.
2
Relevant factual aspects and background
4. Shorn of unnecessary details, the relevant factual aspects could be
usefully summarised as follows:
4.1. On 10.01.1997, the claimant entered into a Power Purchase
5
Agreement with the Government of Goa to commission and operate a
power generation station of 39.8 MW capacity for the period 14.08.1999 to
13.08.2014. The power station was to use ‘Naphtha’ as fuel to generate
electricity along with a provision for using ‘Alternate Fuel’. The claimant
commenced commercial operation on 14.08.1999.
4.2. Various supplementary agreements were entered into between the
parties from September 1997 to November 2001. By the First
Supplementary Power Purchase Agreement dated 10.09.1997, it was
mutually agreed to convert the generating station from Open Cycle
Generating Station into a Combined Cycle Generating Station with a
capacity of 48 MW. The Contracted Capacity was increased from 39402
KW to 46560 KW. Furthermore, the claimant was authorized to sell power
in excess of 39.8 MW to consumers due to the combined cycle operation.
On 20.09.2000, the Second Supplementary Agreement was executed
between the parties, which enabled the claimant to conduct certain direct
sales of power to consumers with permission. The computation of tariff was
based on the 'New Rated Capacity,' which was deemed to be the
Contracted Capacity. The agreement also mandated the provision of
5
‘PPA’, for short.
3
backup power by the Government of Goa to the claimant for distribution to
its consumers in case of scheduled or unscheduled outages, as specified
in the agreement. On 05.11.2001, the parties entered into the Third
Supplementary Agreement, which specified a reduction in supply of power
by the claimant to the extent of 19.8 MW from March 2004 until the end of
the PPA term, i.e., 13.08.2014 This 19.8 MW quantum was designated as
‘New Rated Capacity’.
4.3. It appears that in view of power being costly, the Government of
Goa intended to stop the purchase from the claimant and addressed a letter
to that effect on 20.03.2013. However, in view of a provision in the PPA for
use of alternate fuel, by its communication dated 21.03.2013, the claimant
gave its proposal to the Government of Goa to supply power by using
6
Regassified Liquefied Natural Gas , which was being brought up to Goa by
GAIL by its pipeline. The claimant gave a formula by which the per unit
cost of power would be billed by it to the Government of Goa. This particular
aspect relating to the claimant’s proposal to switch over to the alternate fuel
and charges payable in that regard has formed a major part of contentions
in this case. Hence, a little elaboration shall be apposite.
4.3.1. On 26.04.2013, the Government of Goa replied to the claimant’s
letter dated 21.03.2013, inter alia , in the following terms: -
“In view of your offer under reference, the Government has decided
to continue to purchase power @ Rs. 8.58 per unit
w.e.f. 01/04/2013 as per your formula proposed in the letter
dated 21/03/2013 considering the present rates of fuel and dollar.
6
‘RLNG’, for short.
4
The same may be noted for records and incorporated in your power
st
bills. The revised fixed rate shall be applicable from 1 April 2013.”
4.3.2. On 30.04.2013, the claimant, however, sought a clarification from
the Government regarding the formula-based tariff payable for the supply
of electricity, inter alia , in the following words: -
“1. With regard to the price mentioned in our proposal dated
21.03.2013, the tariff of Rs.8.58/unit is based on the
prevailing RLNG price ($17.2/mmbtu) and INR/USD exchange rate
(1 $ = Rs 54) and is therefore not fixed. The same shall vary
depending upon the fuel price in the market and the INR/USD
exchange rate.”
4.3.3. It has been the case of the claimant that initially, the Government
of Goa agreed to a fixed per unit price but, when it was clarified that the
price would not be fixed, the Government agreed to purchase the same
considering the prevailing rates of fuel and dollar upto the expiry of the PPA
while requiring that for this purpose, documentation showing the price of
fuel and dollar be incorporated in the bills raised by the claimant. In this
regard, a communication received by the claimant from the Chief Electrical
Engineer dated 23.05.2013 has been relied upon. For its relevance, this
communication dated 23.05.2013 is reproduced, in extenso, as under : -
“GOVERNMENT OF GOA
ELECTRICTY DEPARTMENT
OFFICE OF THE CHIEF ELECTRICAL ENGINEER
No . 20 / 3 / CEE / Tech / 13 - 14 / 824
Date : 23 . 05 . 2013
To,
M / s . Reliance Infrastructure Limited,
Goa Power Station,
.
Opp Sancoale Industrial Estate,
Zurinagar, Goa - 403 726
Sub : Proposal for supply of power on RLNG
5
Ref : 1 . RINFRA / GPS / GOG / 2013 / 16 dt . 21 . 03 . 2013 addressed to
this office and a copy enclosed to the Hon ’ ble Chief Minister, State
of Goa and others .
Sir,
…..
In view of your offer under reference, the Government has decided
to continue to purchase power as per your formulae proposed in the
letter dated 21 . 03 . 2013 considering the prevailing rates of fuel and
dollar up to the expiry of the existing PPA . The same may be noted
for records and incorporated in your power bills with due
documentations of prices of fuel and dollar
…
Yours faithfully
Sd /-
( S . Lekshminath )
Chief Electrical Engineer ”
4.3.4. It has also been the case of the claimant that in fact, the decision to
purchase power at fluctuating price was approved by a decision taken by
the Cabinet Committee headed by the Chief Minister of the State of Goa.
4.4. The claimant’s grievance has been that its monthly invoices were
paid upto March 2013 and monthly invoice for April 2013 was paid partly;
but, from May 2013 onwards, its invoices were not paid. In regard to the
unpaid invoices of the claimant, partly for April 2013 and thereafter from
May 2013 till April 2014 (after which the plant was shut down), several
communications were exchanged between the parties and the claimant
submitted revised invoices but the grievance of the claimant remained
unredressed.
4.5. On 19.05.2015, the claimant filed a petition before the Joint
7
Electricity Regulatory Commission for recovery of its dues. The State
7
‘JERC’, for short.
6
submitted before JERC that an Arbitrator be appointed in terms of PPA to
adjudicate upon the disputes. On 11.12.2015, JERC, based on agreement
of both the parties, referred the disputes to the Sole Arbitrator Mr. Justice
B. P. Singh (Former Judge of this Court) in pursuance of its powers under
Section 86(1)(f) of the Electricity Act, 2003. The arbitration proceedings
under this reference have led to the present appeals.
Arbitration proceedings and award
5. After long-drawn proceedings of arbitration with filing of claim, reply
and counter claim, rejoinder, sur-rejoinder, amendment of counter claim,
filing of various applications and written submissions, the Arbitral Tribunal
ultimately passed the award dated 16.02.2018 whereby it directed the
State to pay to the claimant a sum of Rs. 278.29 crore (principal amount)
together with interest for the period up to 31.10.2017; to pay further interest
from 31.10.2017 at the rate of 15% per annum from the date of award until
the date of full payment of the amount including interest as on the date of
the award until effective payment/realization; and further clarified that in
case the non-claimant would pay the entire amount together with interest
within two months from the date of the award, it shall not be liable for
payment of interest after the date of the award.
5.1. We shall refer to the findings of the Arbitral Tribunal, to the extent
relevant, at the appropriate juncture hereafter. However, to take into
comprehension as to what was presented to the Arbitral Tribunal by way
of dispute and as to what material points called for determination, it may
7
be noticed that the parties jointly formulated the issues on which the Arbitral
Tribunal was required to give its ruling; and the same were duly taken note
of by the Arbitral Tribunal in the following words:-
“34. The parties in the joint statement submitted by them on
computation of the claim amount payable by the Respondent to the
claimant have themselves succinctly formulated the issues on
which this Tribunal is required to give its ruling, which are as follows:
a) Contention of the Respondent that Rated Capacity is required to
be downrated from September 2000 till the expiry of the PPA, i.e.
13th August, 2014, relying on the draft Notification issued by the
Ministry of Power, Government of India referred to by the
Respondent during its arguments.
b) Respondent’s claim for credit to be given to it of 4 MW for 12
hours on daily basis for weekdays in computing the Tariff Heat Rate
for arriving at the Fuel Cost (Variable Charges) from January, 2009
till 13th August 2014. The Respondent has made this claim by
referring to letters dated 2nd January, 2009 and 19th January,
2009.
c) Contention of the respondent that the claimant had agreed to
supply power based on a fixed rate of Fuel price and a fixed rate of
exchange in terms of US Dollar to INR for supply of power using
RLNG as fuel from June, 2013 onwards;
d) Claim of the Claimant that it is entitled to Fuel Facilitation
Charges for supply of power by using RLNG from June 2013, and
e) Contention of the respondent that back-up power supplied by it
from May, 2014 till 13th August, 2014 was 1.25 times of Rs.
3.78/kWh, being the rate specified by the respondent in its letter
dated 18th September, 2014.”
5.2. Out of the five issues aforementioned, four were decided by the
Arbitral Tribunal in favour of the claimant (except that relating to fuel
facilitation charges). The parties also presented various alternatives of
calculation for arriving at the amount payable in terms of findings. Having
examined these alternatives and with reference to its findings, the Tribunal
made the award in the following terms: -
“77. This Tribunal after considering all aspects of the matter has
decided four of the issues in favour of the Claimant, and one in
8
favour of the Respondent. The scenario attracted in view of the
above findings is Scenario 22. Accordingly, the Claimant will be
entitled to a sum of Rs.119.32 Crores by way of principal amount
and a sum of Rs 158.98 Crores by way of interest for the period up
to 31.10.2017 totaling Rs. 278.29 Crores. For the period
st
subsequent to 31 October 2017, the Claimant shall be entitled to
interest calculated at the same rate as for the period prior to that
date, till the date of the award. The Claimant shall also be entitled
to payment of interest at the rate of 15% per annum on the above
amount from the date of the award till the actual payment of the full
amount awarded together with interest. If the full payment of the
amount awarded together with interest is made within the period of
two months from the date of the award, the Respondent shall not
be liable to pay interest for any period subsequent to the date of the
award, otherwise, it shall be liable to pay interest at the rate of 15%
per annum from the date of the award till the date of
payment/realisation in full. In this view of the matter the Tribunal
makes the following.
AWARD
1. The Respondent shall pay to the Claimant a sum of Rs.278.29
Crores by way of payment of the principal amount together with
interest for the period up to October 31, 2017.
2. The Respondent shall pay to the Claimant interest on the above
amount, for the period from October 31, 2017 till the date of the
award, calculated at the same rate as for the period prior to October,
31,2017.
3. The Respondent shall pay to the Claimant interest on the total
amount awarded together with interest payable on October 31,
2017, at the rate of 15% per annum from the date of the Award till
full payment of the amount, including interest as on the date of the
Award is paid/realised.
4. Provided that, in case the Respondent pays to the Claimant the
entire amount together with interest awarded within two months of
the date of the Award, it shall not be liable to pay interest for the
period subsequent to the date of the Award.
5. The parties shall bear their own respective costs of this
proceeding.”
Challenge to the award under Section 34 of the Act
6. The award so made by the Arbitral Tribunal was challenged by the
State under Section 34 of the Act before the Commercial Court. A vast
variety of contentions urged on behalf of the parties were duly considered
9
by the Court and the relevant points were answered in favour of the
claimant and thereby, the award was upheld while rejecting the application
under Section 34.
6.1. The relevant observations and findings of the Commercial Court, to
the extent necessary, shall be referred hereafter at the appropriate stage.
However, we may extract the points for determination formulated by the
Commercial Court and their answers, as indicated in the impugned
judgment and order dated 12.09.2019, as follows: -
“27. Following points arise for my determination:
| Sr. No. | Points | Findings |
|---|---|---|
| 1 | Whether the GOG had agreed<br>to the fluctuating dollar rate? | In the Affirmative |
| 2 | Whether the GOG was aware<br>of the negotiations between<br>the claimant and the fuel<br>supplier? | In the Affirmative |
| 3 | Whether in the absence of tariff<br>petition filed by the claimant,<br>the claimant could claim<br>amount from GOG? | In the Affirmative |
| 4 | Whether the Ld. Arbitrator<br>ought to have appointed an<br>expert to ascertain the<br>correctness and veracity of the<br>invoices raised by the claimant<br>from 14.08.1999 and calling<br>upon the expert to submit his<br>report? | In the Negative |
| 5 | Whether the arbitration<br>proceedings are bad since<br>there is no any order passed | In the Negative |
10
| on the application filed by GOG<br>on 30.03.2016 calling upon the<br>claimant to produce<br>documents. | ||
|---|---|---|
| 6 | Whether the interest awarded<br>by the Ld. Arbitrator is<br>exorbitant and against the<br>PPA? | In the Negative |
| 7 | Whether the findings of the Ld.<br>Arbitrator that 3.78 per unit<br>was a fixed amount for supply<br>of backup power by GOG to<br>the claimant is illegal and<br>contrary to the terms of PPA? | In the Negative |
| 8 | Whether the claimant could not<br>levy variable charges on 4 MW<br>deducted from rated capacity<br>of 19 MW? | In the Negative |
| 9 | Whether the claim ought to<br>have been rejected on the<br>ground that the claimant did<br>not consider downrating? | In the Negative |
| 10 | Whether the arbitral award is<br>arbitrary and perverse and<br>passed contrary to principles<br>of natural justice and hence<br>against the public policy? | In the Negative” |
The appeal under Section 37 of the Act
7. In challenge to the aforesaid order dated 12.09.2019 as passed by
the Commercial Court, the State preferred Commercial Appeal No. 12 of
2019 under Section 37 of the Act before the High Court of Judicature at
Bombay, Goa Bench that has been partly allowed by the High Court by the
impugned judgment and order dated 08.03.2021 and thereby, substantial
11
and material parts of the findings in the award in question have been
reversed.
7.1. Again, we shall refer to the relevant findings of the High Court at the
appropriate stage but, in order to indicate the points taken up for
determination by the High Court with reference to the rival contentions, the
following extraction shall be apposite: -
“ 39. We have considered the rival submissions made by the learned
Counsel for the parties. We have also considered the material on
record, which includes the impugned Award, as well as the
impugned Judgment and Order made by the Commercial Court.
Based on the rival contentions, the following points now arise for
our determination:
(A) The scope of the provisions of Section 34 of the Arbitration
Act (as amended in 2017).
(B) Whether the Appellant has made out a case of breach of
natural justice in the course of the arbitral proceedings warranting
interference with the impugned Award?
(C) Whether the Appellant has made out a case that the
impugned Award on the aspect of variable charges for Rs. 24.66
crores is required to be set aside?
(D) Whether the Appellant has made out a case that the
impugned Award on the aspect of downrating for Rs. 18.53 crores
is required to be set aside?
(E) Whether the Appellant has made out a case that the
impugned Award on the aspect of variable charges on 4 MW power
which was permitted to be traded for Rs. 3.94 crores is required to
be set aside?
(F) Whether the Appellant has made out a case that the
impugned Award on the aspect of netting out for Rs. 2.36 crores is
required to be set aside?
(G) Whether the award of interest for the period up to the making
of the impugned Award as well as the post Award period, warrants
interference?
(H) Whether the computations at Schedules 2 and 3 to the
impugned Award are ex facie incorrect and were made without
affording sufficient opportunity to the Appellant?
12
(I) Whether the impugned Judgment and Order made by the
Commercial Court upholding the impugned Award is ex
facie erroneous and warrants interference?”
7.2. As regards point (A) aforesaid, the High Court, though mentioned a
decision of this Court in the case of Ssangyong Engineering and
Construction Co. Ltd. v. NHAI: (2019) 15 SCC 131 , wherein principles
have been laid down for dealing with challenge to an award under Section
34 of the Act of 1996 but, thereafter, considered it appropriate to refer to
the analysis by a learned Single Judge of the High Court and, after
reproducing a few passages from that decision of the learned Single Judge,
observed that the submissions would be evaluated with reference to the
principles so stated. Be that as it may, thereafter, the High Court dealt with
the questions raised by the State as regards the alleged breach of
principles of natural justice in point (B) and rejected all such contentions
with reference to the record of proceedings as also the pleadings and
evidence of the parties. However, the High Court proceeded to disapprove
the award in relation to the claims covered by the aforementioned points
(C), (D), (E) and (F). Of course, on point (G), in relation to the award of
interest for the pre-reference period and the period during which
proceedings were pending before Arbitrator, the High Court found no
reason to interfere but then, with reference to the decision of this Court in
Vedanta Ltd. v. Shenzhen Shandong Nuclear Power Construction Co.
Ltd: (2019) 11 SCC 465 , considered it appropriate to reduce the rate of
interest to 10% from 15% p.a. In point (H), the High Court found no fault in
the computations attached to the award as Schedules 2 and 3 but, in point
13
(I) observed that the Commercial Court only summarised the submissions
of the parties and made a brief reference to the award without independent
application of mind to the contentions raised. This, according to the High
Court, had not been a satisfactory way of disposing of an application under
Section 34 of the Act of 1996.
7.3. The High Court concluded on the matter with the following
observations and directions: -
“ 195. For all the aforesaid reasons, we partly allow this appeal and
set aside both the impugned judgment and order as well as the
impugned award on the issues of variable charges (Rs. 24.66
crores approx), downrating (Rs. 18.53 crores approx.), variable
charges on 4MW power (Rs. 3.94 crores approx.), and netting out
(Rs. 2.36 crores approx.). We reduce the interest rate from 15% to
10% per annum, payable from the date of Award till the date of
payment of the determined amount. The rest of the impugned
Award is however not interfered with.
196. Since we have rejected the challenge to the summary of
computations in Schedule 2 of the impugned Award, even after
holding the issues of downrating, 4 MW power, fuel formula,
facilitation fuel charges, and netting out in favour of the Appellant,
the Appellant is still due and payable principal amount of Rs. 70.58
crores together with interest component with which we have not
interfered with. This amount comes to Rs. 151.97 crores as of
31.10.2017. On this amount of Rs. 151.97 crores, the Appellant will
have to pay interest at the approved rate for the period from
31.10.2017 till the date of the Award i.e. 16.2.2018. Thereafter,
however, the Appellant will have to pay interest at the rate of 10%
per annum from the date of Award till the payment of the amount to
the Respondent.
197. The Appellant had already deposited an amount of Rs. 25
crores before the Commercial Court as a condition for a stay on the
execution of the impugned Award. Thereafter, the Appellant
deposited a further amount of Rs. 94 crores in this Court in terms of
our order dated 8.11.2019. The Respondent was permitted to
withdraw both these amounts by furnishing bank guarantees of a
Nationalized Bank. The Respondent was directed to keep alive
14
such bank guarantees until the disposal of this Commercial Appeal
and for 15 days thereafter.
198. Though we have partly allowed this appeal, it is unlikely that
the Respondent might have to bring back any portion of the
amounts withdrawn by it. The Respondent to, therefore, assess this
position and deposit such amount, if any, in this Court within 14 days
from today. Only if no amount is to be brought back, the Respondent
need not keep the bank guarantees alive beyond 15 days from
today.
199. Further, if despite our order partly allowing this appeal, the
Appellant is still due and payable to the Respondent the amounts
over and above those which the Respondent has already withdrawn
against bank guarantees, then, obviously, the Respondent need not
keep the bank guarantees alive for more than 15 days from today.
The Appellant to then deposit the balance amount in this Court
within four weeks from today. The Respondent will have the liberty
to withdraw such amount, once the same is deposited.
200. The appeal is partly allowed in the aforesaid terms. There shall
be no order for costs.”
Rival Submissions
8. In view of the above, the claimant has approached this Court
challenging the judgment and order of the High Court to the extent it sets
aside the award partially. The State of Goa, on the other hand, has laid a
limited challenge to the judgment of the High Court. We may briefly
summarise the principal contentions urged on behalf of the parties.
9. Mr. Parag P. Tripathi, learned senior counsel appearing on behalf
of the claimant, has made a variety of submissions in challenge to the part
of the impugned judgment and order dated 08.03.2021 whereby,
substantial part of the award in question has been upturned by the High
Court.
15
9.1. At the outset, learned senior counsel has submitted that the scope
of interference under Section 37 of the Act of 1996 is limited and is
restricted to the grounds mentioned in Section 34 thereof; and if the view
of the Arbitrator is a plausible view, the Court will not interfere or substitute
its own view with that of the Arbitrator. Further, re-appreciation of evidence
or review on merits is not permissible under the provisions of the Act unless
the award is shown to be in conflict with the ‘public policy of India’ or vitiated
by ‘patent illegality appearing on the face of the award’.
9.2. With respect to the submission that the application of the State for
appointment of expert under Section 26 of the Arbitration Act had not been
decided by the Arbitral Tribunal, learned senior counsel has submitted that
the High Court had noted in paragraphs 51 and 52 of the impugned
judgment that the prayer seeking appointment of expert was deleted by the
State itself. Further, the State never challenged rejection of its counter
claim and the amounts were calculated jointly by both the parties.
9.3. As regards variable charges to the tune of about Rs. 24.66 crore,
learned senior counsel for the claimant has submitted that the Arbitral
Tribunal came to a categorical finding of fact that the parties had agreed
that sale of electricity by using alternate fuel RLNG would not be at fixed
price and would be based on the fluctuating price of US dollar and fuel. It
has also been submitted that although the State had argued before the
High Court that certain clauses of PPA had not been considered by the
Arbitral Tribunal, and the High Court held that the Arbitral Tribunal did not
16
consider the issue raised regarding non-compliance with clauses 12.1.4. to
12.1.7. of the PPA but, the said clauses related only to Fuel Supply
8
Contract for Naphtha, and not the alternate fuel. There was a separate
clause i.e., clause 12.1.9. relating to change in fuel in terms of use of
alternate fuel and hence, clauses 12.1.4. to 12.1.7 were inapplicable. In
fact, the Arbitral Tribunal had observed that the Government of Goa had
even agreed to the formula on the basis of which the tariff would be
computed for alternate fuel. According to learned senior counsel, the High
Court applied an inapplicable clause, while ignoring the fact that all the
relevant documents including the price certificate and dollar rate received
from PSUs were forwarded along with invoices. Further, the Government
of Goa continued to take power from the claimant without dispute or demur.
Even otherwise, no issues were raised contemporaneously by the
Government of Goa, and the supposed non-compliance of clauses 12.1.4.
to 12.1.7 was raised for the first time in the sur-rejoinder before the Arbitral
Tribunal.
9.4. As regards downrating amount of about Rs. 18.53 crore, learned
senior counsel has recapitulated the contention of the Government of Goa
before the Arbitral Tribunal that the Rated Capacity was required to be
downrated from September 2000 until 13.08.2014 (date of expiry of PPA),
on the basis of a draft notification issued by the Ministry of Power,
Government of India. Learned counsel has countered this by relying on
8
‘FSC’, for short.
17
the observations of the Arbitral Tribunal that the issue of downrating was
irrelevant given the subsequent amendment to the PPA, restricting the
assured supply to 19.8 MW as the New Rated Capacity, without referring
to downrating of such capacity. Hence, the State was not justified in
contending that there was an annual downrating of the Rated Capacity. It
has been argued that the Arbitral Tribunal had considered the definition of
‘contracted capacity’ and other contractual provisions as well as various
provisions of the PPA and supplementary PPAs by which, there was a
reduction to Rated Capacity of 19.8 MW to hold that the parties were bound
by the contractual provisions. These findings of the Arbitral Tribunal were
9
supported by the Original Equipment Manufacturer’s Certificate dated
08.11.2005 and Minutes of Meeting dated 05.04.2007, based on which, all
the invoices were reconciled and it was agreed that future invoices would
be calculated in the same manner. The Arbitral Tribunal found that this
agreement was the basis of all the future invoices and the said invoices
were both approved and paid by the Government of Goa up to March 2013
and a part of April 2013. It was also held that this issue of downrating
capacity should not be reagitated having already been settled by the
parties. Learned counsel would submit that the High Court has erroneously
proceeded to draw an adverse inference against the claimant owing to its
failure to produce the OEM’s recommendation and has erroneously
entered into the process of interpretation of the Minutes of Meeting dated
9
‘OEM’, for short.
18
05.04.2007. Learned senior counsel, while relying on the decisions of this
Court in Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail
Corporation Ltd .: (2022) 1 SCC 131 and Haryana Tourism Ltd. v.
Kandhari Beverages Ltd .: (2022) 3 SCC 237 , has submitted that in the
appeal under Section 37 of the Act, re-appreciation of evidence was not
permissible at all.
9.5. In regard to the question of variable charges on 4 MW power, it has
been argued that the issue before the Arbitral Tribunal was as to whether
the Government of Goa was justified in claiming credits for 4 MW in
computing tariff heat rate for arriving at the fuel cost variable charges from
January, 2009 to 30.08.2014. This claim was made by the Government in
reference to the letters dated 02.01.2009 and 19.01.2009. It has been
contented that the Arbitral Tribunal, after appreciating the evidence
including the said letters, concluded that Government of Goa was
exempted from payment of only fixed cost with regard to this 4 MW power
permitted to be supplied to the other consumers; and the said letter dated
19.01.2009, in no way, affected the committed power supply by the
claimant to the Government. Moreover, the Government had maintained
its right to revert to take the said 4 MW power in future with all the terms
and conditions of PPA remaining the same; and variable charges billed to
the Government for supply to them were as per PPA. According to the
learned counsel, the High Court erroneously re-appreciated the letters to
substitute its own view with that of the Arbitral Tribunal.
19
9.6. With respect to the issue related to supply of backup power by the
Government to the claimant in case of a scheduled outage (when the plant
was shut between May and August, 2014), the Government claimed its
entitlement to 1.25 times the approved rate of Rs. 3.78 per unit which was
agreed to in the letter dated 18.09.2014. Learned senior counsel has
submitted that the Arbitral Tribunal rightly came to the finding that the rate
per unit was a fixed amount since determination of average cost of energy
had become irrelevant, by relying on office memorandums dated
13.08.2014 and 18.09.2014. According to the learned counsel, this again
has only been a matter of re-appreciation of evidence by the High Court.
9.7. In respect of reduction of interest post-award from 15% to 10% p.a.
based on the principles of proportionality and reasonableness with reliance
on the decision in Vedanta Ltd . (supra), learned senior counsel has
submitted that post-award interest was awarded under Section 31(7)(b) of
the Act of 1996 and the claimant had handed over the statement indicating
that prime lending rate was approximately 13% p.a. and above and,
therefore, award of interest @ 15% p.a. was justified.
10. Mr. R. Venkataramani, the learned Attorney General for India,
appearing on behalf of the State has countered the submissions made on
behalf of the claimant and has argued that the High Court has rightly
interfered with the award in question that suffered from patent illegalities.
The learned Attorney General has also questioned the observations and
20
findings in the impugned judgment and order dated 08.03.2021 to the
extent the submissions of the State have been rejected or overruled.
10.1. Learned Attorney General has referred to various decisions of this
Court on the scope of interference under Sections 34 and 37 of the Act of
1996 including those in Ssangyong Engineering (supra); MMTC Limited
v. Vedanta Limited: (2019) 4 SCC 163 ; and PSA SICAL Terminals (P)
Ltd. v. Board of Trustees of V.O. Chidambranar Port Trust Tuticorin
and Ors. : (2021) SCC Online SC 508 . It has been submitted that this is
not a case of two plausible views by the Arbitral Tribunal but a case of non-
advertence to, and non-consideration of, the relevant contractual clauses
leading to patent illegalities. According to the learned Attorney General, the
Arbitral Tribunal had approached the entire case from an altogether wrong
angle; and when the Arbitrator adverted to wrong questions, the result has
been of wrong answers. Learned Attorney General would submit that the
High Court rightly interfered with the order under Section 34 of the Act of
1996 considering the fact that the Commercial Court did not adjudicate
upon the arbitral award and rather framed separate issues like a regular
Appellate Court.
10.2. It has been strenuously argued by the learned Attorney General that
in the award in question, the Arbitral Tribunal proceeded to rely upon
certain correspondence between the parties but, failed to examine the root
question as to whether such correspondence had the effect of variation of
terms of contract and as to whether such correspondence changed the
21
fundamentals of contract. The learned Attorney General has
re-emphasised that the Arbitral Tribunal has not considered the relevant
clauses of the contract and this had been a matter of patent illegality. Two
decisions of this Court have been relied on in this regard, namely State of
Chhattisgarh and Ors. v. Sal Udyog Pvt. Ltd. : (2022) 2 SCC 275 and
Associate Builders v. Delhi Development Authority : (2015) 3 SCC 49 .
Hence, it has been contended that the award would be liable to be set aside
on the ground of patent illegality under Section 34(2A) of the Act of 1996
because an Arbitral Tribunal cannot rewrite the contract between parties
and the award was made in ignorance of vital evidence.
10.3. As regards procedural aspects, it has been argued on behalf of the
State that there had been clear violation of the principles of natural justice
since the application seeking appointment of an expert in terms of Section
26 of the Act was not disposed of by the Arbitral Tribunal, although an order
was passed by the Tribunal that it would be decided at an appropriate time.
It has been contended that failure of the Tribunal to consider the application
for appointment of expert had resulted in denial of equal opportunity to the
State to the present its case, in violation of Section 18 of the Act. It has also
been submitted that the High Court overlooked the purpose and intent
behind appointment of an expert under Section 26 of the Act of 1996.
10.3.1. Another application was filed by the State seeking production of 13
documents by the claimant, including drafts of progress and developments
in negotiations of each Fuel Supply Contract, minutes of meetings with fuel
22
suppliers as well as the OEM recommendations with respect to downrating
of net generating capacity. It has been submitted that this application was
also not disposed of by the Arbitral Tribunal. Learned Attorney General
would submit that non-production of documents has seriously prejudiced
the State because certain documents like the OEM manual were crucial for
its defence; and it was incumbent upon the claimant to produce the
documents in its exclusive possession; and an adverse inference ought to
have been drawn against the claimant for want of production of these
documents.
10.3.2. It has further been submitted that the request of the State to file
additional written submissions was not granted by the Arbitral Tribunal
even after additional written submissions were placed on record by the
claimant. Merely because a joint exercise was done and 24 permutations
of calculation were submitted by the parties, at no point did the State give
up its claims regarding interest or the quantum thereof.
10.4. In regard to variable charges, learned Attorney General has
submitted that applicability of clauses 12.4 to 12.7 of the PPA was not
considered or discussed in the award. These clauses had a material
bearing on the question of liability of the Government of Goa to pay Rs.
24.66 crore on account of variable charges relatable to change in fuel from
Naphtha to RLNG; and there had not been any finding by the Arbitral
Tribunal that the aforesaid clauses were not applicable when there was
change to RNLG from Naphtha. It has further been contended that the
23
claimant was obligated to keep the Government updated about its
negotiations with fuel suppliers and provide the correspondence with
potential suppliers and other drafts. The letter dated 23.05.2013 stated that
all the terms and conditions of the PPA were to remain unaffected and the
non-production of FSCs and detailed invoices took the opportunity to object
to the same away from the Government. In light of the terms of the PPA,
the submission of the claimant that the Government could not have frozen
dollar rate and RLNG rate, would be unsustainable. Moreover, it would be
wrong to assert that if fuel facilitation charges had not been given to the
claimant by the Arbitral Tribunal, the requirement of providing FSCs would
be waived off.
10.5. As regards downrating amounting to Rs. 18.53 crore, learned
Attorney General has submitted that the Arbitral Tribunal wrongly held that
the issue of downrating was resolved between parties on 05.04.2007 and
failed to appreciate the relevant contractual provisions concerning
downrating. The definition of ‘contractual capacity’ as defined under the
PPA required that downrating be taken into account, and this definition was
not amended by the Supplementary PPAs. Therefore, it was not open for
the Tribunal to hold that downrating had been given a go-by. Given that the
claimant did not produce the OEM recommendations, the State had to rely
upon a draft notification issued by the Ministry of Power to calculate
downrating. It has been submitted that this failure to produce the OEM
recommendations would necessitate an adverse inference being drawn
24
against the claimant and the claimant could not have subsequently relied
on the certificate dated 08.11.2005 to argue that no degradation had taken
place, vitiating the applicability of downrating. It has been submitted that
the certificate dated 08.11.2005 cannot be held to be conclusive as to the
degradation of the plant beyond the date of issuance of the aforesaid
certificate and, therefore, the contractual stipulation could not have been
ignored. Downrating would have to be applied in terms of the contract
irrespective of changes in contracted capacity because, if the concept of
downrating had become redundant, the claimant would have pointed it out
in the year 2007 itself.
10.6. Insofar as the award of Rs. 3.94 crore towards variable charges on
4 MW power is concerned, learned Attorney General has submitted that
variable charges were only to be paid in respect of power actually
purchased, whereas fixed charges were payable regardless of actual
purchase since there was no connection with infrastructure costs. The
contention on this score has been that they are not liable to pay variable
charges for electricity which had not been supplied to them, particularly
when the parties had also agreed to waive fixed charges in that respect.
Therefore, the Arbitral Tribunal erred in directing payment towards variable
charges for 4 MW electricity, which was never supplied to the Government
of Goa. The contracted capacity for the duration when the claimant was
permitted to sell to third parties was reduced by 4 MW and; hence, while
billing the variable charges for that period, contracted capacity also had to
25
be reduced. It has been submitted that the failure to do so has resulted in
a situation where the Government was charged by the claimant for variable
charges on units sold to third parties. This has resulted in a dual profit to
the claimant, for having been held entitled to recover variable costs for 4
MW electricity from the State despite not supplying electricity to it; and also
being compensated for both fixed charges and variable charges for 4 MW
electricity by such third parties. It has further been submitted that the
Arbitral Tribunal relied on the letter dated 19.01.2009 which permitted the
claimant to trade 4 MW of electricity to third parties but, failed to observe
that this was in response to a previous communication by the claimant in
which, the issue of fixed charges was specifically raised. Thus, the letter
dated 19.01.2009 cannot be viewed as acquiescence to payment of
variable charges on 4MW power; and the finding of the Arbitral Tribunal in
this regard had been perverse.
10.7. Learned Attorney General has also submitted that the Arbitral
Tribunal has again ignored the contractual clauses mandating netting-out
while making an award in the sum of Rs. 2.36 crore. It has been argued
that clause 15 of the Second Supplementary PPA provided that all the
backup energy supplied by the Government during an unscheduled or
forced outage would be netted-out against energy supplied by the power
station to the Government in the subsequent billing period in the ratio of
one unit of backup power equal to one and quarter of unit of energy
supplied. Both parties had construed this to mean that the claimant would
26
be liable to pay charges for the netted-out energy at the prevailing rate in
the proximate billing period. The Arbitral Tribunal has failed to take note of
the mandatory nature of netting-out for unscheduled power outages under
clause 15 and solely focused on the interpretation of the document dated
18.09.2014. It has been submitted that the determination of rate at Rs. 3.78
per unit was the base rate for calculation of netting-out and could not be
construed as waiver of the said provisions of the contract. Further, the
claimant had failed to supply electricity during the relevant billing period
which led to a need to determine the base rate. The claimant was liable to
pay for 1.25 times the units supplied to consumer by the Government,
although the claimant contended that they would only be liable to return 1
unit. In fact, the base rate of Rs. 3.78 was much lower than the last paid
rate, which was Rs. 12.57 per unit. In any event, there was no amendment
to exclude netting from the calculation of the rate in terms of clause 23.1 of
the PPA and no waiver on the part of the Government.
10.8. Finally, as regards the question of interest, it has been argued that
there was no reason for the Arbitral Tribunal to award any interest before
the date of award as the invoices were not paid being in dispute because
the claimant was charging inflated bills; and the amount that was payable
could not be crystallized for the claimant having failed to provide the
Government of Goa with the necessary details and documents. Such
documents were provided only during the arbitration proceedings and thus,
if at all any amount towards interest was considered due and payable; the
27
same could start only from the date when the final amount was crystallized.
It has also been suggested that the contractual provisions for interest were
in terrorem and liable to be discarded having regard to Section 74 of the
Contract Act, 1872. Although the High Court rightly reduced the post-award
interest but only modified the amount. It has been further submitted, by
relying on NHAI v. M. Hakeem: (2021) 9 SCC 1 , that such course of action
was not permissible as modification of an award would not be possible
under Section 34 of the Act of 1996. Thus, the award of interest of the
Tribunal was liable to be set aside as being patently illegal.
10.9. A few other submissions have also been made by the learned
Attorney General with reference to the calculation of the awarded amount.
It has been contended that as per the PPA, the claimant was required to
submit its bills according to the forecast period and thereafter for each
subsequent financial year; however, the claimant submitted bills for the
tariff period which resulted in inflated bills. Further, the Arbitral Tribunal
calculated the amount to be awarded based on the supposed mutually
agreed upon table of calculations; however, the set of calculations provided
by the claimant was disputed by the State. The Tribunal did not advert to
the submission that the principal amount to be paid would be Rs. 60.76
crore as opposed to Rs. 70.58 crore claimed by claimant. According to the
de
learned Attorney General, the claimant has resorted to exorbitant billing
hors the contract and the amount payable could not be crystallized on
account of the fact that the claimant did not provide details of the electricity
28
sold to third parties so as to ascertain liability, and this documentation was
only provided during arbitration proceedings.
11. We have given anxious consideration to the rival submissions and
have examined the record with reference to the law applicable.
Relevant Statutory provisions
12. Since the present appeals relate to an arbitral award, which was
carried in challenge under Section 34 and in appeal under Section 37 of
the Act of 1996; and looking to the variety of submissions made, we may
usefully take note of the relevant statutory provisions contained in Sections
26, 28, 34 and 37 of the Act of 1996 as follows:
“ 26. Expert appointment by arbitral tribunal.- (1) Unless
otherwise agreed by the parties, the arbitral tribunal may—
(a) appoint one or more experts to report to it on specific issues
to be determined by the arbitral tribunal, and
(b) require a party to give the expert any relevant information or
to produce, or to provide access to, any relevant documents,
goods or other property for his inspection.
(2) Unless otherwise agreed by the parties, if a party so requests or
if the arbitral tribunal considers it necessary, the expert shall, after
delivery of his written or oral report, participate in an oral hearing
where the parties have the opportunity to put questions to him and
to present expert witnesses in order to testify on the points at issue.
(3) Unless otherwise agreed by the parties, the expert shall, on the
request of a party, make available to that party for examination all
documents, goods or other property in the possession of the expert
with which he was provided in order to prepare his report.
28. Rules applicable to substance of dispute. -(1) Where
the place of arbitration is situate in India,—
(a) in an arbitration other than an international commercial
arbitration, the arbitral tribunal shall decide the dispute
submitted to arbitration in accordance with the substantive
law for the time being in force in India;
(b) in international commercial arbitration,—
(i) the arbitral tribunal shall decide the dispute in accordance
with the rules of law designated by the parties as
applicable to the substance of the dispute;
29
| (ii) any designation by the parties of the law or legal system of | |||
|---|---|---|---|
| a given country shall be construed, unless otherwise | |||
| expressed, as directly referring to the substantive law of | |||
| that country and not to its conflict of laws rules; | |||
| (iii) failing any designation of the law under clause (a) by the | |||
| parties, the arbitral tribunal shall apply the rules of law it | |||
| considers to be appropriate given all the circumstances | |||
| surrounding the dispute. | |||
| (2) The arbitral tribunal shall decide ex aequo et bono or as amiable | |||
| compositeur only if the parties have expressly authorised it to do so. | |||
| 10[(3) While deciding and making an award, the arbitral tribunal | |||
| shall, in all cases, take into account the terms of the contract and | |||
| trade usages applicable to the transaction.] | |||
| **** **** **** | |||
| 34. Application for setting aside arbitral award.-(1) Recourse to | |||
| a Court against an arbitral award may be made only by an | |||
| application for setting aside such award in accordance with sub- | |||
| section (2) and sub-section (3). | |||
| (2) An arbitral award may be set aside by the Court only if-- | |||
| (a) the party making the application 11[establishes on the basis of<br>the record of the arbitral tribunal that] --<br>(i) a party was under some incapacity, or<br>(ii) the arbitration agreement is not valid under the law to which<br>the parties have subjected it or, failing any indication<br>thereon, under the law for the time being in force; or<br>(iii) the party making the application was not given proper<br>notice of the appointment of an arbitrator or of the arbitral<br>proceedings or was otherwise unable to present his case;<br>or<br>(iv) the arbitral award deals with a dispute not contemplated<br>by or not falling within the terms of the submission to<br>arbitration, or it contains decisions on matters beyond the<br>scope of the submission to arbitration:<br>Provided that, if the decisions on matters submitted<br>to arbitration can be separated from those not so<br>submitted, only that part of the arbitral award which<br>contains decisions on matters not submitted to arbitration<br>may be set aside; or<br>(v) the composition of the arbitral tribunal or the arbitral<br>procedure was not in accordance with the agreement of<br>the parties, unless such agreement was in conflict with a | (a) the party making the application 11[establishes on the basis of | ||
| the record of the arbitral tribunal that] -- | |||
| (i) a party was under some incapacity, or | |||
| (ii) the arbitration agreement is not valid under the law to which | |||
| the parties have subjected it or, failing any indication | |||
| thereon, under the law for the time being in force; or | |||
| (iii) the party making the application was not given proper | |||
| notice of the appointment of an arbitrator or of the arbitral | |||
| proceedings or was otherwise unable to present his case; | |||
| or | |||
| (iv) the arbitral award deals with a dispute not contemplated | |||
| by or not falling within the terms of the submission to | |||
| arbitration, or it contains decisions on matters beyond the | |||
| scope of the submission to arbitration: | |||
| Provided that, if the decisions on matters submitted | |||
| to arbitration can be separated from those not so | |||
| submitted, only that part of the arbitral award which | |||
| contains decisions on matters not submitted to arbitration | |||
| may be set aside; or | |||
| (v) the composition of the arbitral tribunal or the arbitral | |||
| procedure was not in accordance with the agreement of | |||
| the parties, unless such agreement was in conflict with a |
10
Subs. by Act 3 of 2016, sec. 14, for sub-section (3) (w.r.e.f. 23-10-2015). Sub-section (3), before
substitution, stood as under:
“(3) In all cases, the arbitral tribunal shall decide in accordance with the terms of the
contract and shall take into account the usages of the trade applicable to the
transaction.”.
11
Subs. by Act 33 of 2019, sec 7, for “furnishes proof that” [w.e.f. 30-8-2019, vide S.O.
th
3154(E), dated 30 August, 2019].
30
| provision of this Part from which the parties cannot | |
|---|---|
| derogate, or, failing such agreement, was not in | |
| accordance with this Part; or | |
| (b) the Court finds that-- | |
| (i) the subject-matter of the dispute is not capable of | |
| settlement by arbitration under the law for the time being | |
| in force, or | |
| (ii) the arbitral award is in conflict with the public policy of India. | |
| 12[Explanation 1.--For the avoidance of any doubt, it is clarified that | |
| an award is in conflict with the public policy of India, only if,-- | |
| (i) the making of the award was induced or affected by fraud | |
| or corruption or was in violation of section 75 or section | |
| 81; or | |
| (ii) it is in contravention with the fundamental policy of Indian | |
| law; or | |
| (iii) it is in conflict with the most basic notions of morality or | |
| justice. | |
| Explanation 2.--For the avoidance of doubt, the test as to whether | |
| there is a contravention with the fundamental policy of Indian law | |
| shall not entail a review on the merits of the dispute.] | |
| 13[(2A) An arbitral award arising out of arbitrations other than | |
| international commercial arbitrations, may also be set aside by the | |
| Court, if the Court finds that the award is vitiated by patent illegality | |
| appearing on the face of the award: | |
| Provided that an award shall not be set aside merely on the ground | |
| of an erroneous application of the law or by reappreciation of | |
| evidence.] | |
| (3) An application for setting aside may not be made after three | |
| months have elapsed from the date on which the party making that | |
| application had received the arbitral award or, if a request had been | |
| made under section 33, from the date on which that request had | |
| been disposed of by the arbitral tribunal: | |
| Provided that if the Court is satisfied that the applicant was | |
| prevented by sufficient cause from making the application within the | |
| said period of three months it may entertain the application within a | |
| further period of thirty days, but not thereafter. | |
| (4) On receipt of an application under sub-section (1), the Court | |
| may, where it is appropriate and it is so requested by a party, | |
| adjourn the proceedings for a period of time determined by it in | |
| order to give the arbitral tribunal an opportunity to resume the | |
| arbitral proceedings or to take such other action as in the opinion of |
12
Subs. by Act 3 of 2016, sec. 18(I), for the Explanation (w.r.e.f. 23-10-2015). The Explanation,
before substitution, stood as under:
“Explanation. -Without prejudice to the generality of sub-clause (ii) it is hereby
declared, for the avoidance of any doubt, that an award is in conflict with the public
policy of India if the making of the award was induced or affected by fraud or
corruption or was in violation of section 75 or section 81.”
13
Ins. by Act 3 of 2016, sec. 18(II) (w.r.e.f. 23-10-2015).
31
arbitral tribunal will eliminate the grounds for setting aside the
arbitral award.
14
[(5) An application under this section shall be filed by a party only
after issuing a prior notice to the other party and such application
shall be accompanied by an affidavit by the applicant endorsing
compliance with the said requirement.
(6) An application under this section shall be disposed of
expeditiously, and in any event, within a period of one year from the
date on which the notice referred to in sub-section (5) is served
upon the other party.]
15
37. Appealable orders.- (1) [Notwithstanding anything
contained in any other law for the time being in force, an appeal]
shall lie from the following orders (and from no others) to the Court
authorised by law to hear appeals from original decrees of the Court
passing the order, namely:--
16
[(a) refusing to refer the parties to arbitration under section 8;
(b) granting or refusing to grant any measure under section 9;
(c) setting aside or refusing to set aside an arbitral award under
section 34.]
(2) An Appeal shall also lie to a court from an order of the arbitral
tribunal.-
(a) accepting the plea referred to in sub-section (2) or sub-section
(3) of section 16; or
(b) granting or refusing to grant an interim measure under section
17.
(3) No second appeal shall lie from an order passed in appeal under
this section, but nothing in this section shall affect or take away any
right to appeal to the Supreme Court.”
12.1. Section 31(7) of the Act of 1996 as regards interest in award may
also be usefully noticed which reads as under:-
“ 31. Form and contents of arbitral award.-
xxx xxx xxx
(7) (a) Unless otherwise agreed by the parties, where and in so far
as an arbitral award is for the payment of money, the arbitral tribunal
may include in the sum for which the award is made interest, at such
rate as it deems reasonable, on the whole or any part of the money,
14
Ins. by Act 3 of 2016, sec. 18(III) (w.r.e.f. 23-10-2015).
15 th
Subs. by Act 33 of 2019, sec 8, for “An appeal” [w.e.f. 30-8-2019, vide S.O. 3154(E), dated 30
August, 2019].
16
Subs. by Act 3 of 2016, sec. 20, for clauses (a) and (b) (w.r.e.f. 23-10-2015). Clauses (a) and
(b), before substitution stood as under:
“(a) granting or refusing to grant any measure under section 9;
(b) setting aside or refusing to set aside an arbitral award under section 34.”
32
for the whole or any part of the period between the date on which
the cause of action arose and the date on which the award is made.
17
[(b) A sum directed to be paid by an arbitral award shall, unless
the award otherwise directs, carry interest at the rate of two per
cent. higher than the current rate of interest prevalent on the date
of award, from the date of award to the date of payment.
Explanation.- The expression “current rate of interest” shall have the
same meaning as assigned to it under clause (b) of section 2 of the
Interest Act, 1978 (14 of 1978)]
xxx xxx xxx”
The scope of challenge to an arbitral award under Section 34 and the
scope of appeal under Section 37 of the Act
13. Having regard to the contentions urged and the issues raised, it
shall also be apposite to take note of the principles enunciated by this Court
in some of the relevant decisions cited by the parties on the scope of
challenge to an arbitral award under Section 34 and the scope of appeal
under Section 37 of the Act of 1996.
13.1. In MMTC Limited (supra), this Court took note of various decisions
including that in the case of Associate Builders (supra) and exposited on
the limited scope of interference under Section 34 and further narrower
scope of appeal under Section 37 of the Act of 1996, particularly when
dealing with the concurrent findings (of the Arbitrator and then of the Court).
This Court, inter alia, held as under: -
“ 11 . As far as Section 34 is concerned, the position is well -
settled by now that the Court does not sit in appeal over the arbitral
award and may interfere on merits on the limited ground provided
under Section 34 ( 2 )( b )( ii ) i . e . if the award is against the public policy
of India . As per the legal position clarified through decisions of this
17
Subs. by Act 3 of 2016, sec. 16(i), for clause (b) (w.r.e.f. 23-10-2015). Clause (b), before
substitution, stood as under:
“(b) A sum directed to be paid by an arbitral award shall, unless the award
otherwise directs, carry interest at the rate of eighteen per centum per annum
from the date of the award to the date of payment.”
33
Court prior to the amendments to the 1996 Act in 2015, a violation
of Indian public policy, in turn, includes a violation of the
fundamental policy of Indian law, a violation of the interest of India,
conflict with justice or morality, and the existence of patent illegality
. “
in the arbitral award Additionally, the concept of the fundamental
policy of Indian law ” would cover compliance with statutes and
judicial precedents, adopting a judicial approach, compliance with
the principles of natural justice, and Wednesbury [ Associated
Provincial Picture Houses v . Wednesbury Corpn . , ( 1948 ) 1 KB 223
( CA )] reasonableness . Furthermore, “ patent illegality ” itself has
been held to mean contravention of the substantive law of India,
contravention of the 1996 Act, and contravention of the terms of the
contract .
12 . It is only if one of these conditions is met that the Court may
interfere with an arbitral award in terms of Section 34 ( 2 )( b )( ii ) , but
such interference does not entail a review of the merits of the
dispute, and is limited to situations where the findings of the
arbitrator are arbitrary, capricious or perverse, or when the
conscience of the Court is shocked, or when the illegality is not
trivial but goes to the root of the matter . An arbitral award may not
be interfered with if the view taken by the arbitrator is a possible
view based on facts . ( See Associate Builders v . DDA [ Associate
Builders v . DDA, ( 2015 ) 3 SCC 49 : ( 2015 ) 2 SCC ( Civ ) 204 ]. Also
see ONGC Ltd . v . Saw Pipes Ltd . [ ONGC Ltd . v . Saw Pipes Ltd . ,
( 2003 ) 5 SCC 705 ] ; Hindustan Zinc Ltd . v . Friends Coal
Carbonisation [ Hindustan Zinc Ltd . v . Friends Coal Carbonisation,
( 2006 ) 4 SCC 445 ] ; and McDermott International Inc . v . Burn
Standard Co . Ltd . [ McDermott International Inc . v . Burn Standard
Co . Ltd . , ( 2006 ) 11 SCC 181 ] )
13 . It is relevant to note that after the 2015 Amendment to
Section 34, the above position stands somewhat modified . Pursuant
to the insertion of Explanation 1 to Section 34 ( 2 ) , the scope of
contravention of Indian public policy has been modified to the extent
that it now means fraud or corruption in the making of the award,
violation of Section 75 or Section 81 of the Act, contravention of the
fundamental policy of Indian law, and conflict with the most basic
notions of justice or morality . Additionally, sub - section ( 2 - A ) has
been inserted in Section 34, which provides that in case of domestic
arbitrations, violation of Indian public policy also includes patent
illegality appearing on the face of the award . The proviso to the
same states that an award shall not be set aside merely on the
ground of an erroneous application of the law or by reappreciation
of evidence .
14 . As far as interference with an order made under Section 34,
as per Section 37, is concerned, it cannot be disputed that such
interference under Section 37 cannot travel beyond the restrictions
laid down under Section 34 . In other words, the court cannot
undertake an independent assessment of the merits of the award,
and must only ascertain that the exercise of power by the court
under Section 34 has not exceeded the scope of the provision .
34
Thus, it is evident that in case an arbitral award has been confirmed
by the court under Section 34 and by the court in an appeal under
Section 37, this Court must be extremely cautious and slow to
disturb such concurrent findings .”
13.2. In the case of Ssangyong Engineering (supra), this Court has set
out the scope of challenge under Section 34 of the Act of 1996 in further
details in the following words: -
“ 37 . Insofar as domestic awards made in India are concerned,
an additional ground is now available under sub - section ( 2 - A ) ,
added by the Amendment Act, 2015, to Section 34 . Here, there
must be patent illegality appearing on the face of the award, which
refers to such illegality as goes to the root of the matter but which
does not amount to mere erroneous application of the law . In short,
what is not subsumed within “ the fundamental policy of Indian law ” ,
namely, the contravention of a statute not linked to public policy or
public interest, cannot be brought in by the backdoor when it comes
to setting aside an award on the ground of patent illegality .
38 . Secondly, it is also made clear that reappreciation of
evidence, which is what an appellate court is permitted to do, cannot
be permitted under the ground of patent illegality appearing on the
face of the award .
39 . To elucidate, para 42 . 1 of Associate Builders [ Associate
Builders v . DDA, ( 2015 ) 3 SCC 49 : ( 2015 ) 2 SCC ( Civ ) 204 ] ,
namely, a mere contravention of the substantive law of India, by
itself, is no longer a ground available to set aside an arbitral award .
Para 42 . 2 of Associate Builders [ Associate Builders v . DDA, ( 2015 )
3 SCC 49 : ( 2015 ) 2 SCC ( Civ ) 204 ] , however, would remain, for if
an arbitrator gives no reasons for an award and contravenes
Section 31 ( 3 ) of the 1996 Act, that would certainly amount to a
patent illegality on the face of the award .
40 . The change made in Section 28 ( 3 ) by the Amendment Act
really follows what is stated in paras 42 . 3 to 45 in Associate
Builders [ Associate Builders v . DDA, ( 2015 ) 3 SCC 49 : ( 2015 ) 2
SCC ( Civ ) 204 ] , namely, that the construction of the terms of a
contract is primarily for an arbitrator to decide, unless the arbitrator
construes the contract in a manner that no fair - minded or
reasonable person would; in short, that the arbitrator's view is not
even a possible view to take . Also, if the arbitrator wanders outside
the contract and deals with matters not allotted to him, he commits
an error of jurisdiction . This ground of challenge will now fall within
the new ground added under Section 34 ( 2 - A ).
41 . What is important to note is that a decision which is perverse,
as understood in paras 31 and 32 of Associate Builders [ Associate
Builders v . DDA, ( 2015 ) 3 SCC 49 : ( 2015 ) 2 SCC ( Civ ) 204 ] , while
no longer being a ground for challenge under “ public policy of India ” ,
35
would certainly amount to a patent illegality appearing on the face
of the award . Thus, a finding based on no evidence at all or an
award which ignores vital evidence in arriving at its decision would
be perverse and liable to be set aside on the ground of patent
.
illegality Additionally, a finding based on documents taken behind
the back of the parties by the arbitrator would also qualify as a
decision based on no evidence inasmuch as such decision is not
based on evidence led by the parties, and therefore, would also
have to be characterised as perverse . ”
13.3. The limited scope of challenge under Section 34 of the Act was
once again highlighted by this Court in the case of PSA SICAL Terminals
(supra) and this Court particularly explained the relevant tests as under :-
“ 43 . It will thus appear to be a more than settled legal position, that
in an application under Section 34, the court is not expected to act
as an appellate court and reappreciate the evidence . The scope of
interference would be limited to grounds provided under Section 34
of the Arbitration Act . The interference would be so warranted when
the award is in violation of “ public policy of India ” , which has been
held to mean “ the fundamental policy of Indian law ”. A judicial
intervention on account of interfering on the merits of the award
would not be permissible . However, the principles of natural justice
as contained in Section 18 and 34 ( 2 )( a )( iii ) of the Arbitration Act
would continue to be the grounds of challenge of an award . The
ground for interference on the basis that the award is in conflict with
justice or morality is now to be understood as a conflict with the
“ most basic notions of morality or justice ”. It is only such arbitral
awards that shock the conscience of the court, that can be set aside
on the said ground . An award would be set aside on the ground of
patent illegality appearing on the face of the award and as such,
which goes to the roots of the matter . However, an illegality with
regard to a mere erroneous application of law would not be a ground
for interference . Equally, reappreciation of evidence would not be
permissible on the ground of patent illegality appearing on the face
of the award .
44 . A decision which is perverse, though would not be a ground for
challenge under “ public policy of India ” , would certainly amount to a
patent illegality appearing on the face of the award . However, a
finding based on no evidence at all or an award which ignores vital
evidence in arriving at its decision would be perverse and liable to
be set aside on the ground of patent illegality .
45 . To understand the test of perversity, it will also be appropriate
to refer to paragraph 31 and 32 from the judgment of this Court in
Associate Builders ( supra ) , which read thus :
36
“ 31 . The third juristic principle is that a decision which is
perverse or so irrational that no reasonable person would
have arrived at the same is important and requires some
degree of explanation . It is settled law that where :
( i ) a finding is based on no evidence, or ( ii ) an Arbitral
Tribunal takes into account something irrelevant to the
decision which it arrives at; or ( iii ) ignores vital evidence in
arriving at its decision, such decision would necessarily be
perverse .
32 . A good working test of perversity is contained in two
judgments . In Excise and Taxation Officer - cum - Assessing
Authority v . Gopi Nath & Sons [ 1992 Supp ( 2 ) SCC 312 ] , it
was held : ( SCC p . 317, para 7 )
“ 7 . ... It is, no doubt, true that if a finding of fact is
arrived at by ignoring or excluding relevant material or
by taking into consideration irrelevant material or if the
finding so outrageously defies logic as to suffer from
the vice of irrationality incurring the blame of being
perverse, then, the finding is rendered infirm in law .” ”
13.4. In Delhi Airport Metro Express (supra), this Court again surveyed
the case-law and explained the contours of the Courts’ power to review the
arbitral awards. Therein, this Court not only re-affirmed the principles
aforesaid but also highlighted an area of serious concern while pointing out
“a disturbing tendency” of the Courts in setting aside arbitral awards after
dissecting and re-assessing factual aspects. This Court also underscored
the pertinent features and scope of the expression “patent illegality” while
reiterating that the Courts do not sit in appeal over the arbitral award. The
relevant and significant passages of this judgment could be usefully
extracted as under: -
NCITRAL
“ 26 . A cumulative reading of the U Model Law and Rules,
the legislative intent with which the 1996 Act is made, Section 5 and
Section 34 of the 1996 Act would make it clear that judicial
interference with the arbitral awards is limited to the grounds in
Section 34 . While deciding applications filed under Section 34 of the
37
Act, Courts are mandated to strictly act in accordance with and
within the confines of Section 34, refraining from appreciation or
reappreciation of matters of fact as well as law . ( See Uttarakhand
PurvSainikKalyan Nigam Ltd . v . Northern Coal Field
. [ . .
Ltd Uttarakhand PurvSainik Kalyan Nigam Ltd v Northern Coal
Field Ltd . , ( 2020 ) 2 SCC 455 : ( 2020 ) 1 SCC ( Civ ) 570 ] , Bhaven
Construction v . Sardar Sarovar Narmada Nigam Ltd . [ Bhaven
Construction v . Sardar Sarovar Narmada Nigam Ltd . , ( 2022 ) 1 SCC
75 ] and Rashtriya Ispat Nigam Ltd . v . Dewan Chand Ram
Saran [ Rashtriya Ispat Nigam Ltd . v . Dewan Chand Ram Saran,
( 2012 ) 5 SCC 306 ] .)
28 . This Court has in several other judgments interpreted Section
34 of the 1996 Act to stress on the restraint to be shown by Courts
.
while examining the validity of the arbitral awards The limited
grounds available to Courts for annulment of arbitral awards are
well known to legally trained minds . However, the difficulty arises
in applying the well - established principles for interference to
the facts of each case that come up before the Courts . There is
a disturbing tendency of Courts setting aside arbitral awards,
after dissecting and reassessing factual aspects of the cases
to come to a conclusion that the award needs intervention and
thereafter, dubbing the award to be vitiated by either perversity
or patent illegality, apart from the other grounds available for
annulment of the award . This approach would lead to
corrosion of the object of the 1996 Act and the endeavours
made to preserve this object, which is minimal judicial
interference with arbitral awards . That apart, several judicial
pronouncements of this Court would become a dead letter if
arbitral awards are set aside by categorising them as perverse
or patently illegal without appreciating the contours of the said
expressions .
29 . Patent illegality should be illegality which goes to the root of the
matter . In other words, every error of law committed by the Arbitral
Tribunal would not fall within the expression “ patent illegality ”.
Likewise, erroneous application of law cannot be categorised as
patent illegality . In addition, contravention of law not linked to public
policy or public interest is beyond the scope of the expression
“ patent illegality ”. What is prohibited is for Courts to
reappreciate evidence to conclude that the award suffers from
patent illegality appearing on the face of the award , as Courts
do not sit in appeal against the arbitral award . The permissible
grounds for interference with a domestic award under Section 34 ( 2 -
A ) on the ground of patent illegality is when the arbitrator takes a
view which is not even a possible one, or interprets a clause in the
contract in such a manner which no fair - minded or reasonable
person would, or if the arbitrator commits an error of jurisdiction by
wandering outside the contract and dealing with matters not allotted
to them . An arbitral award stating no reasons for its findings would
make itself susceptible to challenge on this account . The
38
conclusions of the arbitrator which are based on no evidence or
have been arrived at by ignoring vital evidence are perverse and
can be set aside on the ground of patent illegality . Also,
consideration of documents which are not supplied to the other
“
party is a facet of perversity falling within the expression patent
illegality ”.
30 . Section 34 ( 2 )( b ) refers to the other grounds on which a court
can set aside an arbitral award . If a dispute which is not capable of
settlement by arbitration is the subject - matter of the award or if the
award is in conflict with public policy of India, the award is liable to
be set aside . Explanation ( 1 ) , amended by the 2015 Amendment
Act, clarified the expression “ public policy of India ” and its
connotations for the purposes of reviewing arbitral awards . It has
been made clear that an award would be in conflict with public policy
of India only when it is induced or affected by fraud or corruption or
is in violation of Section 75 or Section 81 of the 1996 Act, if it is in
contravention with the fundamental policy of Indian law or if it is in
conflict with the most basic notions of morality or justice .
42 . The Division Bench referred to various factors leading to the
termination notice, to conclude that the award shocks the
conscience of the court . The discussion in SCC OnLine Del para
103 of the impugned judgment [ DMRC v . Delhi Airport Metro
Express ( P ) Ltd . , 2019 SCC OnLine Del 6562 ] amounts to
appreciation or reappreciation of the facts which is not permissible
under Section 34 of the 1996 Act . The Division Bench further held
[ DMRC v . Delhi Airport Metro Express ( P ) Ltd . , 2019 SCC OnLine
Del 6562 ] that the fact of AMEL being operated without any adverse
event for a period of more than four years since the date of issuance
of the CMRS certificate, was not given due importance by the
Arbitral Tribunal . As the arbitrator is the sole Judge of the quality as
well as the quantity of the evidence, the task of being a Judge on
the evidence before the Tribunal does not fall upon the Court in
exercise of its jurisdiction under Section 34 . [ State of
Rajasthan v . Puri Construction Co . Ltd . , ( 1994 ) 6 SCC 485 ] On the
basis of the issues submitted by the parties, the Arbitral Tribunal
framed issues for consideration and answered the said issues .
Subsequent events need not be taken into account .”
(emphasis supplied)
13.5. In the case of Haryana Tourism Ltd. (supra), this Court yet again
pointed out the limited scope of interference under Sections 34 and 37 of
the Act; and disapproved interference by the High Court under Section 37
of the Act while entering into merits of the claim in the following words: -
39
“ 8 . So far as the impugned judgment and order passed by the High
Court quashing and setting aside the award and the order passed
by the Additional District Judge under Section 34 of the Arbitration
Act are concerned, it is required to be noted that in an appeal under
Section 37 of the Arbitration Act, the High Court has entered into
the merits of the claim, which is not permissible in exercise of
powers under Section 37 of the Arbitration Act .
9 . As per settled position of law laid down by this Court in a catena
of decisions, an award can be set aside only if the award is against
the public policy of India . The award can be set aside under
Sections 34 / 37 of the Arbitration Act, if the award is found to be
contrary to: ( a ) fundamental policy of Indian Law; or ( b ) the interest
of India; or ( c ) justice or morality; or ( d ) if it is patently illegal . None
of the aforesaid exceptions shall be applicable to the facts of the
case on hand . The High Court has entered into the merits of the
claim and has decided the appeal under Section 37 of the
Arbitration Act as if the High Court was deciding the appeal against
the judgment and decree passed by the learned trial Court . Thus,
the High Court has exercised the jurisdiction not vested in it under
Section 37 of the Arbitration Act . The impugned judgment and order
passed by the High Court is hence not sustainable .”
13.6. As regards the limited scope of interference under Sections 34/37
of the Act, we may also usefully refer to the following observations of a
3-Judge Bench of this Court in the case of UHL Power Company Limited
v. State of Himachal Pradesh: (2022 ) 4 SCC 116 : -
“ 15. This Court also accepts as correct, the view expressed by the
appellate court that the learned Single Judge committed a gross error
in reappreciating the findings returned by the Arbitral Tribunal and
taking an entirely different view in respect of the interpretation of the
relevant clauses of the implementation agreement governing the
parties inasmuch as it was not open to the said court to do so in
proceedings under Section 34 of the Arbitration Act, by virtually acting
as a court of appeal.
16 . As it is, the jurisdiction conferred on courts under Section 34 of
the Arbitration Act is fairly narrow, when it comes to the scope of an
appeal under Section 37 of the Arbitration Act, the jurisdiction of an
appellate court in examining an order, setting aside or refusing to
set aside an award, is all the more circumscribed .”
13.7. The learned Attorney General has referred to another 3-Judge
Bench decision of this Court in the case of Sal Udyog Private Limited
40
(supra), wherein this Court indeed interfered with the award in question
when the same was found suffering from non-consideration of a relevant
contractual clause. In the said decision too, the principles aforesaid in Delhi
Airport Metro Express , Ssangyong Engineering and other cases were
referred to and thereafter, this Court applied the principles to the facts of
that case. We shall refer to the said decision later at an appropriate
juncture.
13.8. Keeping in view the aforementioned principles enunciated by this
Court with regard to the limited scope of interference in an arbitral award
by a Court in the exercise of its jurisdiction under Section 34 of the Act,
which is all the more circumscribed in an appeal under Section 37, we may
examine the rival submissions of the parties in relation to the matters dealt
with by the High Court.
Questions relating to proceedings and procedure
14. It has been argued on behalf of the State that in the arbitration
proceedings, it had made an application for appointment of an expert under
Section 26 of the Act but the same was not decided by the Arbitral Tribunal.
In our view, the High Court has dealt with this issue in its proper perspective
and this baseless objection has rightly been rejected. We find it rather
strange that such an objection standing at contradiction to its own stand
before the Arbitral Tribunal and against its own amended pleading has at
all been projected by the State as a ground of challenge to the award in
question. It appears that in the counter claim filed by Government of Goa
41
before the Arbitral Tribunal, initially it was prayed that all transactions and
invoices raised by the claimant need to be re-examined through a technical
cum financial expert so as to ascertain the correctness of the bills in terms
of Section 26 of the Act but, thereafter, the Government itself amended its
counter claim, as permitted under Section 23 of the Act by the Arbitral
Tribunal, and dropped this prayer. It was then pleaded by the Government
that it had engaged the services of an expert and with his assistance, had
reworked the amount which was payable by the claimant to it. The High
Court has held that after such deletion of the prayer, it was reasonable for
the Arbitral Tribunal to proceed on the basis that the application under
Section 26 of the Act was either rendered infructuous or was abandoned
by Government of Goa; and that it had not been able to show any prejudice
on account of non-disposal of the application. We are in agreement with
the High Court on this score. It is also noticeable that in challenge to the
award, the Government of Goa has not agitated the rejection of its counter
claim. In fact, there remains no ambiguity as regards the Arbitral Tribunal
attending on all the relevant aspects of the matter. In this regard, we may
usefully reproduce paragraph 31 of the award where the Arbitral Tribunal
specifically noticed the submissions made on behalf of the Government of
Goa about exercise having been undertaken to workout the details
pertaining to the counter claim and permitted the Government to specify
the amount with reference to different heads and with necessary
particulars. Paragraph 31 of the award reads as under:-
42
“31. In the course of hearing of the matter, on 18.10.2016, learned
counsel appearing on behalf of the Respondent stated that his client
has undertaken an exercise to work out the details pertaining to the
counter claim, since no specified amount had been claimed by the
Respondent in its counter claim. He submitted that he would like
that the figures be placed before this Tribunal by way of amendment
of the pleadings, if necessary. The Tribunal permitted the
Respondent to convey to the Claimant in writing the amount which
the Respondent claimed by way of counter claim in the instant
proceedings under different heads and with necessary particulars.
The Claimant was given liberty to file its objections.”
14.1. Another submission on behalf of the Government has been that for
non-production of certain documents by the claimant, an adverse inference
ought to have been drawn against them by the Arbitral Tribunal. It is again
a rule of evidence as to whether adverse inference is to be drawn or not;
and to what effect. The High Court has dealt with this issue and has held
that most of the documents were made available to the Government of
Goa. High Court has further held that the other documents sought for by
Government of Goa were not made available to it because the claimant
had clearly stated that such documents were not available with it at the
relevant time or did not exist at the relevant time. It has further been held
that in absence of Government of Goa establishing any serious prejudice,
there was no breach of principles of natural justice merely because the
Arbitral Tribunal had failed to make a formal order on the application
seeking production of documents. We are in agreement with the said
observations and findings of the High Court.
14.2. Government of Goa’s contention that opportunity was not granted
by the Arbitral Tribunal to file additional written submission has also been
dealt with by the High Court with the finding that sufficient opportunity was
43
given by the Arbitral Tribunal since there were at least two
meetings/hearings before the learned Arbitrator where the Government of
Goa did neither file nor seek leave to file written submissions in response
to the claimant’s written clarifications/submissions. We are in agreement
with these findings too.
14.3. In fact, the submissions of the aforesaid nature, attempting to find
fault with the proceedings of arbitration on such hyper-technical but
baseless grounds only show an attempt on the part of the State to
somehow question the award and seek interference, irrespective of the
principles laid down by this Court.
14.4. In regard to the aforesaid procedural aspects of the matter, the High
Court has cautiously taken note of the record of proceedings and has
proceeded only within the confines of its jurisdiction to reject these
contentions.
15. The question, however, is as to whether the High Court remained
within those confines while dealing with the other points of challenge
pertaining to the items of claim and consideration of the Arbitral Tribunal in
that regard. We may examine the point-wise consideration of the High
Court with reference to the applicable principles.
The award relating to variable charges on use of alternate fuel
16. The claimant has assailed the judgment of the High Court by which
it has set aside the award towards variable charges of Rs. 24.66 crore. It
is the case of the claimant that the ground on which the High Court has set
44
aside the award was not at all an issue before the Arbitral Tribunal; that in
any case, the State has referred to such clauses of the PPA which were
not applicable to supply of electricity by using RLNG as alternate fuel; and
that these clauses were applicable only for supply of electricity using
‘Naphtha’ as fuel. Per contra, it has been argued on behalf of the State that
the Arbitral Tribunal has approached the entire case from an altogether
wrong angle; and when the Tribunal adverted to wrong questions, the result
has been of wrong answers. This, according to the learned Attorney
General, has been a gross illegality and perversity on the part of the Arbitral
Tribunal.
16.1. We find it difficult to accept the submission of the learned Attorney
General. In our view, on the issue of entitlement to raise invoices based on
fluctuating price of fuel and rate of dollar, the Arbitral Tribunal has held in
favour of the claimant after thorough examination of the documentary
evidence before it and while focusing on core issue raised before it.
16.2. After taking note of relevant submissions and after having
examined the entire documentary evidence, the Arbitral Tribunal returned
a clear finding on facts in the following terms: -
“41. The facts noticed above which are based entirely on the
documentary record placed before the Tribunal clearly establish
that the proposal made by the Claimant under its letter dated 21st
of March 2013 was an offer for supply of energy at a rate based on
the formula contained in the aforesaid communication. It was clearly
mentioned that the entire PPA and all other terms and conditions
shall remain unchanged except for change in calculation of Variable
charges in Monthly Tariff. The formula for working out the costs was
also described as “Proposed Monthly Variable Charge Formula” A
Monthly Sample Calculation based on assumed values of landed
cost of oil, and dollar rate, was appended to the proposal to show
45
that the cost would be less than what was being paid by the
Respondent. When the Respondent accepted the proposal and
responded by its letter of 26th of April 2012 which referred to the
cost at the rate of Rs. 8.58 per unit, which was described as the
“ revised fixed rate”, the Claimant clarified the position immediately
by stating in its letter of 30th of April 2013 to the Respondent that
the price mentioned in the proposal dated 21st of March 2013, was
not for a fixed cost of power supplied, and that the same shall vary
depending upon the fuel price in the market and the exchange rate.
They therefore requested the Respondent to confirm that the tariff
was formula based and shall vary with changes in the fuel price in
the market and dollar variation. Thereafter it appears that the parties
were not able to resolve the differences that surfaced,, and
ultimately the matter was placed before the Cabinet of the
Government of Goa on May 22, 2013. After having considered the
matter, the Cabinet took a very clear and categoric decision to
purchase power from the Claimant at the rate given in the proposal
of the Claimant, which would vary, based on the international price
of gas and exchange rate fluctuations. The decision was
communicated to all offices concerned with a request to report
compliance. On the very next day, the Respondent by its letter
dated 23rd of May 2013 confirmed that the Government had
decided to continue to purchase power as per the formula proposed
by the Claimant in their letter dated 21st of March 2013 considering
the prevailing rates of fuel and dollar up to the expiry of the existing
PPA. The same communication also directed that the power bills
must be submitted with due documentation of prices of fuel and
dollar.
42. These facts clearly establish that the price of power to be
supplied by the Claimant was not based on fixed dollar rate or
landing cost of fuel. The proposal clearly made these charges
variable, and clarified the position further when the Respondent
wrongly understood it to mean a fixed rate formula. Ultimately, the
Cabinet of the Government of Goa took a decision clearly in favour
of the stand of the Claimant. It was faintly argued that the Cabinet
decision was not binding because, pursuant to it no order was
drawn up by the State Government. Relying on the decision of the
Hon’ble Supreme Court (AIR 1963 S.C 395) in Bachhittar Singh Vs
State of Punjab, it was contended that unless the Cabinet decision
is followed by a formal order drawn up by the State Government, it
does not have any binding effect. The submission is wholly
untenable. On facts, in the decision referred to the Court was
concerned with the note of the Revenue Minister in the file,, and
was not a decision taken by the Cabinet at its meeting. Secondly, in
the instant case the decision of the Cabinet was communicated to
all concerned officers directing them to act in accordance with the
order and report compliance. Pursuant to the said decision, a letter
was written by the Respondent to the Claimant accepting the
proposal based on variable charge in accordance with the prevailing
46
cost of fuel and dollar. This clearly shows that the Government
acted upon the said decision of the Cabinet.
43. For all these reasons, the Tribunal finds that the plea of the
Claimant that the Respondent was obliged to pay for the power
purchased by it pursuant to the proposal accepted by it, on the basis
of invoices prepared and submitted by the Claimant taking into
account the variable cost of oil and dollar, must be accepted, and
the plea of the Respondent to the contrary, must be rejected.”
16.3. Insofar as the contention of State with regard to non-consideration
of clauses 12.1.4 to 12.1.7 of PPA is concerned, in our view, the claimant
is right in its submission that the main issue raised before the Arbitral
Tribunal was only as to whether the agreement was to supply power on a
fixed rate of fuel price and fixed rate of exchange in terms of US dollar to
Indian rupee.
16.4. It might appear that in the latter part of the pleadings, the
Government of Goa referred to the aforesaid clauses 12.1.4 to 12.1.7 of
PPA but, fact of the matter remains that they were not as such considered
by the parties to be forming material propositions of law or facts so as to
form the part of the issue before the Arbitral Tribunal. Even on the first
principles pertaining to settlement of issues, like those in Order XIV Rule 1
18
of the Code of Civil Procedure, 1908 , the Court, while dealing with regular
18
Order XIV Rule 1 CPC reads as under: -
“ 1. Framing of issues .—(1) Issues arise when a material proposition of fact or law is
affirmed by the one party and denied by the other.
(2) Material propositions are those propositions of law or fact which a plaintiff must allege
in order to show a right to sue or a defendant must allege in order to constitute his defence.
(3) Each material proposition affirmed by one party and denied by the other shall form
the subject of a distinct issue.
(4) Issues are of two kinds:
( a ) issues of fact,
( b ) issues of law.
(5) At the first hearing of the suit the Court shall, after reading the plaint and the written
statements, if any, and after examination under rule 2 of Order X and after hearing the
parties or their pleaders, ascertain upon what material propositions of fact or of law the
47
civil suit, would be ascertaining as to upon what material proposition of fact
or law the parties are at variance, and thereupon would frame and record
the issues on which the right decision of the case appears to depend. The
present case had been that of arbitration and, obviously, the Arbitral
Tribunal was not obliged to frame issues on each and every fact pleaded
or disputed. The Arbitral Tribunal was only expected to arbitrate on the
dispute presented to it. Significantly, in the present case, the parties
themselves succinctly formulated the issues on which the Arbitral Tribunal
was required to give its ruling and therein, as regards this matter of variable
charges, the question posed was with reference to assertion of the
Government of Goa that the claimant had agreed to supply power based
on fixed rate of fuel price and a fixed rate of exchange in terms of price of
US dollar to INR for supply of power using RLNG as fuel from June, 2013
onwards (vide point C in paragraph 34 of the award-reproduced
hereinabove). The Tribunal, therefore, rightly indicated that the real issue
was as to whether the invoices prepared by the claimant were in
accordance with the terms and conditions of the proposal made by the
claimant and accepted by the Government; and the core of dispute was as
to whether price of energy to be supplied was based upon a fixed dollar
rate and a fixed import price irrespective of actual fluctuations. The Tribunal
parties are at variance, and shall thereupon proceed to frame and record the issues on
which the right decision of the case appears to depend.
(6) Nothing in this rule requires the Court to frame and record issues where the defendant
at the first hearing of the suit makes no defence.”
48
indeed adverted to all the relevant facts and evidence in that regard and
determined this issue in favour of the claimant.
16.5. In view of the real issue projected and agitated before the Arbitral
Tribunal, reference to clauses 12.1.4 to 12.1.7 of PPA had obviously been
unnecessary. This is coupled with the submissions of the claimant that the
definition of “Fuel Supply Contract” in PPA was restricted to a contract
entered into between the claimant and a fuel supplier for supply of
“Naphtha”, and not pertaining to alternate fuel also. For ready reference,
we may reproduce the definitions of “Fuel” as also “Fuel Supply Contract”
in the PPA which read as under: -
“ ‘Fuel’ means Naphtha or any Alternate Fuel;
*
‘Fuel Supply Contract’ shall mean any contract entered into
between RSPCL and any Fuel Supplier for the supply of Naphtha
pursuant to clause 12;”
16.5.1. If “Alternate Fuel” is also to be read alongwith “Naphtha” in the
aforesaid definition, that would be either re-writing the contract or at least
reading something into the contract by stretching the principles of
construction of document. This would, in our view, be travelling into the
area of such construction of the terms of contract which were not forming
the part of the material propositions of fact on which the parties were at
variance. As noticed, the core of variance of the parties had only been as
to whether the claimant was to supply energy on a fixed rate of fuel and
fixed rate of foreign currency after the parties had agreed to the use of
alternate fuel.
49
16.6. We have only broadly referred to the salient features of the dealings
between the parties. In fact, not much dilation and dissection of the record
is required because the Arbitral Tribunal has indeed examined all the
relevant aspects of the matter in necessary details.
16.7. In any case, all documents which showed the cost at which
alternate fuel was procured and the prevailing dollar rate were supported
by price certificates forwarded to Government of Goa with each and every
invoice, and such certificates had been from Public Sector Undertakings.
There is nothing on record to show nor has Government of Goa
demonstrated that it had either contemporaneously asked for any
documents or had disputed or denied the correctness of such certificates.
16.8. The Arbitral Tribunal has noticed that the decision of the cabinet
was produced before it by Government of Goa itself. There is also a finding
of fact in the award that the communication dated 23.05.2013 to purchase
power at a fluctuating rate of fuel and exchange rate of dollar, conveyed to
the claimant by Government of Goa, was pursuant to the cabinet decision
taken on 22.05.2013. This has been a particular view taken by the Arbitral
Tribunal of the evidence on record. We are unable to appreciate as to how
such a view on evidence could have been substituted by another view on
the same evidence by the High Court. In an overall view of the record, we
are unable to agree that the Arbitral Tribunal had approached the case from
an altogether wrong angle or it had asked wrong questions. In our view,
50
the Arbitral Tribunal had squarely answered the issue, which was raised
jointly by the parties before it.
17. True it is that consideration of any adjudicatory forum would be
vitiated by asking wrong questions but then, in our view, this flaw operates
against the consideration of the High Court rather than against the
consideration of the Arbitral Tribunal.
17.1. As noticed, the High Court has reproduced all the said clauses of
the contract under the heading “Fuel Supply” and then, elaborately
discussed the features related with their operation, particularly clauses
12.1.4 to 12.1.7. The High Court has found this aspect to be a vital issue
and non-consideration thereof has been taken to be a patent illegality. It
was observed and held , inter alia , as under:
“ 88. According to us, the issue about the applicability and the non-
compliance of contractual clauses 12.1.4 to 12.1.7 was one of the
most relevant and vital issues which arose before the learned
Arbitrator. A substantial claim was made by the Respondent
towards variable charges, of which, the fuel component was the
most dominant. Ultimately, the learned Arbitrator has made an
Award in an amount of Rs. 24.66 crores (approximately) towards
variable charges post the switch of the fuel from Naphtha to RLNG.
Such a substantial award has been made without even adverting to,
much less considering or evaluating the issue raised by the
Appellant about applicability and non-compliance with the
contractual clauses 12.1.4 to 12.1.7. This amounts to patent
illegality because the Award to that extent can be said to have been
made ignoring or even disregarding contractual provisions to be
found in clauses 12.1.4 to 12.1.7 of the PPA. The Award to this
extent will have to be held as vitiated by patent illegality because
Award ignores vital evidence on the issue of applicability and non-
compliance with the contractual provisions in clauses 12.1.4 to
12.1.7.”
51
17.2. The High Court has also proceeded to observe and reiterate that
interference was being made not because of the Court disagreeing with
any interpretation of the contractual clauses by the Arbitrator but because
the Arbitrator failed to look into the relevant contractual provisions. The
High Court justified its interference while observing as under: -
“ 98. According to us, all these predicates are attracted when it
comes to impugned Award concerning the variable charges. The
interference is by no means, merit-based. Interference is because
the Arbitrator in the present case has failed to even advert to much
less go into the merits of one of the most vital and relevant issues
concerning the applicability and non-compliance with the
contractual provisions. The interference is not because the
interpretation of the contractual clauses by the learned Arbitrator is
wrong or because we disagree with such interpretation. The
interference is because the learned Arbitrator failed to even look
into the contractual provisions to find out if the same were given a
go by post the switch of fuel from Naphtha to RLNG. The
interference is because the learned Arbitrator failed to take note of
and interpret the contractual clauses to find out whether they were
breached as alleged by the Appellant though denied by the
Respondent. Without even adverting to much less taking into
consideration the contractual provisions which governed the
relationship between the parties, the learned Arbitrator was not
justified in making an Award of Rs. 24.66 crores in favour of the
Respondent. Accordingly, we set aside the impugned Award to the
extent it awards Rs. 24.66 crores to the Respondent towards the
variable charges.”
18. As noticed, arbitral award is not an ordinary adjudicatory order so as
to be lightly interfered with by the Courts under Sections 34 or 37 of the Act
of 1996 as if dealing with an appeal or revision against a decision of any
subordinate Court. The expression “patent illegality” has been exposited by
this Court in the cases referred hereinbefore. The significant aspect to be
reiterated is that it is not a mere illegality which would call for interference,
52
but it has to be “a patent illegality”, which obviously signifies that it ought to
be apparent on the face of the award and not the one which is culled out by
way of a long-drawn analysis of the pleadings and evidence. Of course, when
the terms and conditions of the agreement governing the parties are
completely ignored, the matter would be different and an award carrying such
a shortcoming shall be directly hit by Section 28(3) of the Act, which enjoins
upon an Arbitral Tribunal to decide in accordance with the terms of contract
while taking into account the usage of trade applicable to the transaction. As
said by this Court in Associate Builders (supra), if an Arbitrator construes
the term of contract in a reasonable manner, the award cannot be set aside
with reference to the deduction drawn from construction. The possibility of
interference would arise only if the construction of the Arbitrator is such which
could not be made by any fairminded and reasonable person.
19. The case of SAL Udyog Private Limited (supra) cited by learned
Attorney General is an apposite example as to when the principles governing
“patent illegality” come into operation. In that case, in the contract concerning
supply of Sal seeds, the respondent-contractor had continued to operate until
21.12.1998, when the contract was terminated in accordance with the
change in legislation. The respondent thereafter levied a claim for refund of
a sum of about 1.72 crore, allegedly paid in excess to the State. The dispute
ultimately led to arbitration and an arbitral award was made in favour of the
respondent which was not interfered with under Sections 34 and 37 of the
Act.
53
19.1. Therein, the specific ground of challenge by the appellant-State had
been that the Arbitrator ignored the binding term of contract governing the
parties relating to recovery of “supervision charges”. Such a binding term
was brushed aside by the Arbitrator while observing that there was no basis
to admit any such “indirect expenses”. This Court found that the supervision
charges were levied by the State and paid by the respondent without any
demur right from the date parties entered into agreement and it was only after
termination of the contract that the respondent raised a dispute towards
supervision charges. It had been a classic case of the Arbitrator ignoring and
rather overriding the terms of contract, as would appear from the following
observations of this Court with reference to the facts of the case:
“ 23. On a conspectus of the facts of the case, it remains undisputed
that though the appellant State did raise an objection before the
Arbitral Tribunal on the claim of the respondent Company seeking
deduction of supervision charges, for which it relied on Clause 6( b )
of the agreement and the Circular dated 27-7-1987 to assert that
recovery of supervision charges along with expenses was a part
and parcel of the contract executed with the respondent Company,
the said objection was turned down by the learned sole arbitrator by
giving a complete go-by to the terms and conditions of the
agreement governing the parties and observing that there is no
basis to admit any such “indirect expenses”. The Circular dated 27-
7-1987 issued by the Government of Madhya Pradesh that provides
for imposition of 10% supervision charges on the amounts
calculated towards the cost of the Sal seeds in the expenditure
incurred, was also ignored. Pertinently, the respondent Company
has not denied the fact that supervision charges were being levied
by the appellant State and being paid by it without any demur as a
part of the advance payment made on an annual basis, right from
the date the parties had entered into the first agreement i.e. from
30-8-1979. This fact is also borne out from the specimen copies of
the orders filed by the appellant State with the appeal that amply
demonstrate that the cost of the Sal seeds required to be paid by
the respondent Company included “supervision charges” described
as “ Paryavekshan vyay ” in vernacular language. It was only after
the appellant State had terminated the second contract on 21-12-
1998, that the respondent Company raised a dispute and for the
54
first time, claimed refund of the excess amount purportedly paid by
it to the appellant State towards supervision charges incurred for
supply of Sal seeds. In our opinion, this is the patent illegality that
is manifest on the face of the arbitral award inasmuch as the
express terms and conditions of the agreement governing the
parties as also the Circular dated 27-7-1987 issued by the
Government of Madhya Pradesh have been completely ignored.”
19.2. In view of such an error apparent on the face of the record, this Court
found the matter to be of patent illegality which was going to the root of the
matter and the impugned award, insofar permitting deduction of the
supervision charges recovered from the respondent, was quashed and set
aside being in direct conflict with the terms of the contract and the relevant
circular. This Court held thus:
| “26. To sum up, existence of Clause 6(b) in the agreement | |
|---|---|
| governing the parties, has not been disputed, nor has the | |
| application of the Circular dated 27-7-1987 issued by the | |
| Government of Madhya Pradesh regarding imposition of 10% | |
| supervision charges and adding the same to cost of the Sal seeds, | |
| after deducting the actual expenditure been questioned by the | |
| respondent Company. We are, therefore, of the view that failure on | |
| the part of the learned sole arbitrator to decide in accordance with | |
| the terms of the contract governing the parties, would certainly | |
| attract the “patent illegality ground”, as the said oversight amounts | |
| to gross contravention of Section 28(3) of the 1996 Act, that enjoins | |
| the Arbitral Tribunal to take into account the terms of the contract | |
| while making an award. The said “patent illegality” is not only | |
| apparent on the face of the award, it goes to the very root of the | |
| matter and deserves interference. Accordingly, the present appeal | |
| is partly allowed and the impugned award, insofar as it has | |
| permitted deduction of “supervision charges” recovered from the | |
| respondent Company by the appellant State as a part of the | |
| expenditure incurred by it while calculating the price of the Sal | |
| seeds, is quashed and set aside, being in direct conflict with the | |
| terms of the contract governing the parties and the relevant circular. | |
| The impugned judgment dated 21-10-2009 is modified to the | |
| aforesaid extent.” |
the terms of contract during the currency of contract and for that matter, the
parties having definitely exchanged communication and having brought into
55
existence an agreement which, even if construed as supplemental to original
one, had been of material difference in regard to the use of particular fuel and
then raising of invoices on that basis with reference to fluctuating price of fuel
as also the exchange rate of foreign currency (US dollar).
20. The matter can be examined from yet another angle. If the terms
agreed to by the parties with exchange of communications commencing from
20.03.2013 were to be ignored, the result would be of ignoring such terms of
contract of the parties which had come into existence and which were binding
on both. Viewed thus, coupled with the fact that only the limited dispute was
presented for arbitration (i.e., as to whether power was to be supplied on the
basis of fixed rate of fuel and fixed rate of currency or on variable charges),
the Arbitral Tribunal, in our view, has been justified in focusing on the core
issue raised, rather than going astray and entering into such an analysis
which was not germane to the issue at hand.
21. For the reasons aforesaid, in our view, no ground for challenge
under Sections 34 or 37 of the Act was made out in relation to the award
pertaining to variable charges. Hence, the High Court has not been right in
setting aside the award relating to variable charges on the ground of so-
called non-consideration of clauses 12.1.4 to 12.1.7 of PPA.
21.1. Putting it in other words, the High Court, even while reminding itself
of the limitation of jurisdiction, has committed the same error by extensively
dissecting the evidence while assuming that clauses 12.1.4 to 12.1.7 were
decisive of the matter without taking a close look at the material
56
propositions which formed the dispute and which were presented by the
parties before the Arbitral Tribunal. As regards variable charges, the core
question before the Tribunal had been as to whether the claimant agreed
to supply electricity on fixed charges with fixed rate of foreign currency
while using the alternate fuel. This question was essentially to be
determined with reference to the new contract that came into existence
with exchange of communications between the parties. The Arbitrator
precisely decided the matter with reference to, and after analysis of, that
evidence. It had neither been a case of the Arbitrator not taking into
consideration the terms of contract applicable to the issue at hand nor of
any such finding which no fair-minded or reasonable person could have
possibly rendered ever. Viewed in the light of core dispute presented to the
Arbitral Tribunal by the parties, the submissions of the learned Attorney
General, that the Arbitral Tribunal has not examined the question as to
whether the correspondence in question resulted in change of
fundamentals of contract, do not make out a case for interference because
novation of the terms of contract as regards fuel had not been a matter of
dispute at all. The core question was as to how the new terms were to
operate. The Arbitral Tribunal has precisely dealt with the same in
accordance with law.
22. What has been observed hereinabove and held in disapproval of
interference by the High Court in the item of award pertaining to variable
charges more or less apply to the other items too, where the High Court
57
has interfered and has upturned the award. In view of the detailed
discussion foregoing, we need not elaborate on all other items. Suffice it
would be to deal briefly with the same as we find that on every such score,
the High Court has rather entered into merits of the matter as if dealing with
a regular appeal. It has been a clear case of the High Court travelling
beyond the periphery of Section 34 as also Section 37 of the Act of 1996.
The award relating to downrating of the plant
23. As regards downrating, the issue before the Arbitral Tribunal was
as to whether the plant was required to be downrated till the expiry of PPA
as contended by Government of Goa relying on a draft notification issued
by Ministry of Power, Government of India.
23.1. The Arbitral Tribunal considered the contractual terms of the parties
and came to a specific finding on interpretation of such terms and
conditions that various Supplementary PPAs executed between the parties
show that the Rated Capacity of the plant was reduced to 19.8 MW and the
obligation of the claimant was restricted to assuring supply upto 19.8 MW
without any reference to degradation of such capacity. On considering the
material on record, the Arbitral Tribunal held that Government of Goa was
not justified in contending that there was any downrating annually of Rated
Capacity. In regard to this issue, it is more than apparent that the Arbitral
Tribunal had considered the provisions of the contract and had taken a
particular view thereupon. The Tribunal said, inter alia , as under:-
“ 48 . An issue was raised at the stage of arguments relating to
the down rating the generating capacity of the plant annually
commencing from the first year after Commercial Operation of the
58
plant . Such a plea does not appear to have been raised in the
Statement of Defence by the Respondent even though it is
contended that down rating a small fraction of generating capacity
will have a huge impact on the monthly invoices . Learned counsel
for the Claimant brought to the notice of the Tribunal that it was in
paragraph 12 of the sur rejoinder that the Respondent sought
documents relating to Original Equipment Manufacturer ’ s ( OEM )
recommendations towards down rating of generating capacity as
envisaged in the definition of “ Contracted Capacity " which was
required to ascertain the implementation of the down rating of the
generating capacity in accordance with the recommendations of the
Original Equipment Manufacturer .
49 . According to the Respondent in terms of the PPA, the
contracted capacity was defined to be 39 . 402 KW in the first year
of commercial operation and down rated annually as per original
equipment manufacturer ’ s recommendation in successive years .
However, the Claimant did not take into account the down rating
factor in any of the bills which it submitted to the Respondent . After
the dispute arose, the Respondent observed that the down rating
factor ought to have been applied from the year 2000 onwards,
which was the second year of commercial operation, in terms of
OEM recommendations . It was therefore that the Respondent
sought necessary documents from the Claimant as regards the
recommendations of the OEM, but the same were not provided,
contending that the said documents were not available with the
Claimant . In the circumstances, the Respondent had to go by other
material to calculate the down rating factor . The Respondent has
relied upon a draft notification issued by the Government to
calculate the down rating . The said notification provides that the
down rating would start from the second year of operation and
would proceed till the fifth year, after which the plant had to be
overhauled as a result of which in the sixth year, the down rating
would be negligible . Based upon the draft notification issued by the
Ministry for Power, the Respondent has made calculations taking
into account the down rating right from the year 2000 .
50 . The Claimant responded by contending that a draft
notification issued by the Ministry for Power has no value unless the
same is duly notified in the Gazette . The Respondent has not relied
upon any final notification duly notified . The Government may have
thought of not issuing the notification for good reasons . Being only
a draft notification which was never finally issued, it has no value
in law and the Respondent cannot derive any benefit from such a
draft notification .
51 . It is the case of the Claimant that the contracted capacity
under the PPA dated 10th of January 1997 was equal to 39,402
kilowatts in the first year of commercial operation and down rated
annually thereafter as per original equipment manufacturer ’ s
59
recommendation in the subsequent years . Later, the parties agreed
to convert the generating station from Open Cycle into a Combined
Cycle generating station of 48 MW capacity . On 10th September
1997, a supplementary PPA was entered into which permitted the
.
Claimant to sell power directly in excess of 39 8 MW to consumers
in Goa . After the Claimant commenced commercial operation of the
power station on 14th of August 1999, on completion of one year
thereafter, a second supplementary agreement was entered into on
20 September 2000 whereunder the Respondent agreed to consent
to sale of electricity in full or in part, to the extent of 2000 KW
generated at the power station directly to any consumer in Goa .
Referring to such other supplementary agreements it was submitted
that the earlier definition of the contracted capacity was given a go
by, and completely changed . The issue with regard to down rating
thus became irrelevant, and in any event by subsequent written
agreement, inter alia, amending the earlier agreement, there was
no question of any further down rating as alleged . The parties are
bound by the contractual provisions . The various supplementary
PPAs executed between the parties clearly show that the rated
capacity was subsequently reduced to 19 . 8 MW and the obligation
of the Claimant was restricted to assuring supply up to 19 . 8 MW
without any reference to degradation of such capacity . The
Respondent is therefore not justified in contending that there was
an alleged down rating annually of the rated capacity .”
23.2. The Arbitral Tribunal then considered the documentary evidence
produced before it, including a certificate issued by OEM dated 08.11.2005
and Minutes of Meeting dated 05.04.2007, where the issue was settled and
all bills till that date were reconciled and future bills were raised on the basis
that there was no downrating. This is clear from the following findings in the
award in question: -
“52. What is even more significant is the reliance placed upon
the certificate issued by the OEM namely BHEL-GE Gas Turbine
Services, Private Limited dated November 8, 2005. It is certified by
the OEM that subsequent to the commissioning of the Goa plant of
the Claimant recommended inspections of Gas Turbine were
carried out and Turbine was found to be generating the Rated
Output without any degradation. Similarly, BGGTS had carried out
the Hot Gas Path Inspection of GT during Annual Inspection in
September 2005. All operating parameters were checked and the
Turbine was found to be generating its Rated Output without any
degradation.
60
53. The Respondent submitted that the certificate refers to
there being no degradation of the plant. The degradation and down
rating are two different and distinct concepts which cannot be
confused with one another. It is not possible to accept this
contention because down rating becomes necessary only if there is
degradation of the plant.
54. The Claimant has also referred to the meetings held
between the parties, on 5th April 2007, when the Respondent was
duly satisfied on the issue relating to down rating of contracted
capacity as per OEM's recommendation which were discussed in
the said committee. The Claimant explained that the plant was
maintained as per OEM's recommendation and there had been no
down rating of contracted capacity. The Claimant had already
submitted OEMs letter in this regard, which is dated 8th November
2005. The parties agreed at the said meeting that the invoices were
to be reconciled as per what was stated in the said meeting and all
future invoices were to be calculated in the same manner. The
minutes of the said meeting dated 5th April 2007 have been placed
on record. Thus, the question of down rating of contracted capacity
is completely irrelevant. It is not disputed that, based on the minutes
of the said meeting and the agreement arrived there at, the invoices
for the period April 2004 to April 2007 were reconciled and the
reconsideration was duly approved by the Respondent and the
payment was made on the basis thereof by the Respondent to the
Claimant. All future invoices were raised on the basis of the said
agreement arrived at the meeting and the invoices were duly
approved by the Respondent and have been paid by the
Respondent for the period up to March 2013 and a part of April
2013. In the circumstances, therefore, the issue relating to the down
rating of capacity of the plant appears to have been settled between
the parties, and should not be allowed to be re-agitated in this
proceeding. This claim is accordingly, rejected.”
23.3. The Arbitral Tribunal thus held that the issue relating to downrating
of capacity was settled between the parties and the parties should not be
allowed to reagitate the same.
24. As regards this issue of downrating, again, we find that the High
Court has found shortcomings in the discussions of the Arbitral Tribunal as
regards the meaning and effect of the certificate dated 08.11.2005 and as
to whether the claimant could have made any claim on that basis or not.
The High Court even proceeded to analyse the minutes of the meeting. It
61
has clearly been a case of value and worth attached to a particular
evidence by Arbitral Tribunal, which was considered not satisfactory by the
High Court; and rejection of the contention of the Government by the
Arbitral Tribunal was found to be erroneous. However, thereafter, the High
Court again observed that it was not a case of re-appreciation of evidence
but being a case of no evidence, there had been patent illegality. The High
Court observed as under: -
“ 124. The impugned Award has recorded a finding based on the
th
bald statement in the certificate dated 8 November 2005 and there
was no degradation of the plant and further, in the absence of
degradation of the plant, the concept of downrating will not apply,
Again, this is, with respect, patent illegality. The certificate could
hardly have been regarded as a recommendation of OEM. In any
case, the certificate referred to the absence of degradation in the
year 2005, and based on such a certificate, there was no question
of inferring that there was no degradation of the plant even
thereafter. Therefore, the contractual stipulation regards
downrating, which was never amended or deleted by any
subsequent agreements, could not have been ignored or bypassed
th
based on the certificate dated 8 November 2005 or the minutes of
th
the meeting dated 5 April 2007.
125. The impugned award to the extent it rejects the Appellant's
contention based on the downrating, will, therefore, have to be set
aside on the ground that the same is vitiated by patent illegality on
the face of the record. The findings recorded in the impugned
th
Award are based only on the certificate dated 8 November 2005
th
and the minutes of the meeting dated 5 April 2007. None of the
documents suggests that the contractual term of the downrating
was either done away with or complied with. This is not a case of
either reappreciation of the evidence on record or a case of
insufficiency of evidence. This is a case of no evidence. This is a
case of ignoring the contractual provision by incorrectly assuming
that such provision was amended or deleted. The tentative findings
to the contrary are, therefore, ex facie perverse and suffer from
patent illegality on the face of the record. The impugned Award, to
the extent it rejects the defence of the Appellant on the issue of
62
downrating and proceeds to make an award of Rs. 18.53 crores in
favour of the Respondent is liable to be set aside on the ground of
perversity and patent illegality.”
24.1. In regard to this issue, in our view, the High Court has again
travelled beyond its jurisdiction under Section 37 and rather than remaining
within the confines of consideration under Section 34 of the Act, has
entered into the arena which is exclusively within the Arbitrator’s domain.
What the Arbitral Tribunal has held in regard to this item had exclusively
been its view on the evidence on record and the relevant surrounding
facts/factors. The view so taken by the Arbitral Tribunal cannot be said to
be wholly perverse or suffering from patent illegality so as to be interfered
with. Needless to observe that even if two views are possible, the Court
cannot substitute its own view with that of the Arbitral Tribunal.
25. The questions raised by the learned Attorney General, in relation to
the issue concerning downrating, that adverse inference ought to be drawn
against the claimant for failure to produce OEM recommendations, are only
pertaining to the principles of appreciation of evidence. Of course, in the
regular adjudicatory process, the Court may presume existence of certain
facts under Section 114 of the Indian Evidence Act, 1872; and in terms of
Illustration (g) thereof, the Court is entitled to draw an inference that the
evidence which could be but not produced would, if produced, be
unfavourable to the person who withholds it. However, in a given case,
while determining the dispute by way of arbitration, whether the Arbitrator
draws such adverse inference or not, is essentially a matter of appreciation
63
of evidence; and if not drawing of adverse inference is also permitted to be
raised as a ground of challenge under Section 34, it would open the
confines of limited interference in an award; and would carry the propensity
of converting the proceedings under Section 34 and under Section 37 into
the proceedings of regular appeal/revision against the award and thereby,
again violating the principles that re-appreciation of evidence is not
envisaged in the proceedings under Section 34 of the Act of 1996. It gets
per force reiterated that an award could be said to be suffering from “patent
illegality” only if it is an illegality apparent on the face of the award and not
to be searched out by way of re-appreciation of evidence. The submissions
as regards drawing of adverse inference are themselves adverse to the
ethos of Sections 34 and 37 of the Act of 1996 and are required to be
rejected.
25.1. In other words, as regards the question of downrating, the questions
relating to the value of certificate dated 08.11.2005 and the effect of the
claimant not taking up this issue earlier would again fall directly within the
arena of appreciation of evidence and reach to the extent of rendering the
finding on preponderance of probabilities. The Arbitral Tribunal has taken
a particular view of the evidence before it. If it were an appeal against the
award, the approach of the Court could have been different but, not so
while examining the award within the confines of Section 34 of the Act. We
would hasten to observe in this regard too that even in a regular appeal
against a decree of the Trial Court, the Appellate Court would not substitute
64
its own views without specifically recording a finding as to the error in the
decision under challenge. In any case, if the approach of the High Court in
the present case is countenanced, the result would only be of making every
award susceptible to challenge before the Court on those very grounds
which are, otherwise, of appeal or revision and which are not permitted by
the legislature to be taken under Section 34 of the Act of 1996.
26. Having found the two major issues dealt with by the High Court not
standing within the confines of limited jurisdiction under Section 34 of the
Act of 1996, we may again observe that the approach of the High Court in
relation to the other two comparatively minor issues relating to variable
charges on 4MW power and netting-out principles is also suffering from
the same error, where the High Court has deeply analysed the evidence
on record to hold that the Arbitral Tribunal has not been correct in its
propositions or inferences.
The award relating to variable charges on 4 MW power
27. The Arbitral Tribunal examined the documentary evidence, viz.
letters exchanged between the parties dated 02.01.2009 and 19.01.2009
and came to a finding that State was not justified in its submission that the
available capacity of the plant stood reduced.
28. In this item too, the High Court has reinterpreted the said
communications dated 02.01.2009 and 19.01.2009 by which parties
agreed to the manner of billing for supply of 15.8 MW power out of 19.8
MW capacity of the power station reserved for Government of Goa by
65
permitting the balance 4 MW to be sold to third parties; and the High Court
arrived at a different finding of fact on the evidence on record. We may
usefully reproduce the summation of the findings by the High Court as
regards variable charges on 4 MW power as follows:-
“ 137. The circumstance that there was a specific clause excluding
the payment of fixed costs, could not lead to the inference that the
Appellant had agreed to bear the variable costs in respect of this 4
MW power, which variable costs were even otherwise not payable
by the Appellant to the Respondent in terms of the original PPA or
PSA and the supplementary PPAs. If there was any proposal for
encumbering the Appellant with any charges over and above the
charges undertaken by it under the contract, then surely this ought
to have been specified. Such an additional burden cannot be
imposed by implication. Therefore, the reasoning that because
there was no reference to variable charges in the communication
dated 19.1.2009, the same was agreed to be paid by the Appellant
is quite perverse and constitutes patent illegality on the face of the
record. According to us, the impugned Award to the extent it so
unjustly enriches the Respondent to the extent of Rs. 3.94 crores
conflicts with the most basic notions of morality and justice. The
impugned Award, to this extent, is also vitiated by
unreasonableness, perversity, and patent illegality apparent on the
face of the record.”
29. The High Court has once again stepped into the arena which is
reserved for the Arbitral Tribunal. It is noticed that the parties had agreed
to a particular methodology of billing for supply of 15.8 MW power but, at
the same time, retained with them the right to revert back to 19.8 MW
supply at any future point of time. With reference to the dealings of the
parties, the Arbitral Tribunal has taken a particular view of the matter. It
cannot be said that the view as taken by the Arbitral Tribunal was entirely
impermissible or implausible. There was no scope for interference by the
Court.
66
The award relating to netting-out principle
30. The aspect of netting-out, again, depended on the terms of contract
of the parties and the deductions to be drawn from the evidence on record.
The Arbitral Tribunal had drawn the particular conclusion on the basis of
notes dated 13.09.2014 and 18.09.2014. The Arbitral Tribunal considered
the documentary evidence before it, as well as the provisions of the
contract relating to supply of backup power by Government of Goa to the
claimant when the power station was under shutdown for the period May
2014 to August 2014. The Arbitral Tribunal further referred to the
communications which also include the decision of the Government of Goa
as to the rate at which power during the shut down period was to be
supplied to the claimant and on this basis, came to the finding that a fixed
rate which was not to be multiplied as per the provisions of the PPA was
agreed between the parties. The award also gave reasons for such finding.
Even if it be assumed that another view is possible, it cannot be said that
the Arbitral Tribunal has taken such a view which no fair-minded and
reasonable person could have ever taken.
31. The High Court has again justified its interference in this item in the
following terms: -
“ 148. According to us, the impugned Award on the aspect of netting
out is again vitiated by perversity and patent illegality. The note
dated 13/8/2014, as well as the communication dated 18/9/2014 on
its plain terms, refers only to the determination of a rate of Rs. 3.78
P. KWh. for applying the contractual provisions concerning netting.
This note or this communication was necessitated because for the
relevant proximate billing period there were no supplies made by
67
the Respondent to the Appellant and therefore there was no ready
rate available based on which the contractual provisions could be
worked for netting out. Therefore, the Appellant determined the rate
of Rs. 3.78 P. KWh. as the base rate for purposes of netting out.
There is nothing either in the noting or in the communication dated
18/9/2014 to even remotely suggest that by determining such base
rate, the parties intended to give a complete go-by to the clear and
specific contractual provisions for the multiplication of this base rate
into 1.25 for purposes of netting out in the eventuality of an
unscheduled shut down of the power plant by the Respondent.
Therefore, based on the noting and the communication dated
18/9/2014, the finding or the conclusion that the parties had agreed
to do away with the clear and specific contractual provisions, is not
even a plausible finding or conclusion. Such a finding or a
conclusion is vitiated by perversity and patent illegality on the face
of the record. The Award of an amount of Rs. 2.36 crores
(approximately) to the Respondent on this score is, therefore, liable
to be set aside on the grounds of perversity and patent illegality on
the face of the record.”
31.1. On this item too, the High Court has substituted its own view and
has reinterpreted the documentary evidence before it for setting aside the
award. Such a substitution of view is not permissible for the Court under
Section 34 of Act. There arise no question of it being permissible under
Section 37 of the Act.
Interest in award
32. It has been argued on behalf of the State that the High Court ought
not to have rejected its contention with regard to the interest for pre-
reference period since the liability to pay interest would arise only once the
amount to be paid has been determined.
32.1. In regard to the question of interest, the High Court has rightly held
that the Arbitral Tribunal was justified in following the contractual provisions
and the provisions of Section 31(7) of the Act; and has rightly not interfered
68
with the award of interest for the pre-reference period and the period during
which the proceedings were pending before the Arbitral Tribunal. In our
view, the State is not right in contending that the interest could not have
been awarded during the period of reference to the Arbitrator. In regard to
this aspect, the submissions to the effect that pre-reference period interest
was not based on any compelling reasons and contractual provisions for
interest were in terrorem are liable to be discarded, could only be rejected
for being not even standing within the periphery of Section 34 of the Act of
1996.
33. However, insofar as post-award period is concerned, the High
Court has reduced the rate of interest from 15% to 10% by following the
decision of this Court in the case of Vedanta Ltd. (supra). The High Court
has relied on the principles of proportionality and has scaled down the rate
of interest to 10% p.a. while observing as under:-
“ 175. Mr. Bhat handed in a statement indicating the interest rates
(Benchmark Prime Lending Rates) of the State Bank of India. For
the period 2017-18, the rates indicated range around 13 to 14% per
annum. This is no doubt one of the factors to be taken into
consideration for determining the prevailing economic conditions
when the impugned Award was made. Again, reference is also
necessary to the principle of proportionality of the amount awarded
as an interest to the principal sums awarded. Having cumulative
regard to all the factors referred to above, we feel that in the facts
and circumstances of the present case, the award of interest at the
rate of 15% per annum is excessive and contrary to the principle of
proportionality and reasonableness and the same will have to be
scaled down to 10% per annum. In Vedanta Ltd. (supra), the Award
was dated 9/11/2017 and the Court awarded interest at the rate of
9% per annum for the INR component. The impugned Award, in
our case, was made on 16/2/2018.”
69
34. We are of the view that the aforesaid reduction of rate of interest by
the High Court is also unjustified. We have noticed the provisions of Section
31(7)(b) that unless the award otherwise directs, the sum payable under
the arbitral award shall carry interest at the rate of 2% higher than the
current rate of interest prevalent on the date of the award, from the date of
the award to the date of payment. The expression “current rate of interest”
has been explained in the Explanation to the said Section to have the same
meaning as assigned under Section 2(b) of the Interest Act, 1978. The
High Court has referred to the decision in Vedanta Ltd. (supra) to hold that
a Court may reduce interest awarded by the Arbitrator when such interest
does not reflect the prevailing economic condition or where it is not found
reasonable or where it promotes interest of justice. We do not find any
basis in the impugned judgment of the High Court for reducing the rate of
interest, as in the case of Vedanta Ltd. , wherein this Court was dealing
with an International Commercial Arbitration involving rupee as well as euro
components. Moreover, in the case of Vedanta Ltd. , the rate of interest
was reduced in respect of the foreign currency component to bring the
interest rate in line with the international rate on the ground that the rate of
interest prevailing on the rupee debt in India and on international currency
abroad were different and the international rates were lower. Such a
situation is not obtaining in the present case.
34.1. The High Court seems to have not considered the relevant factual
aspects. On the contrary, as has been submitted before us as well as the
70
High Court, the prevailing interest rate being the prime lending rate of State
Bank of India was in the range of 13% to 14% per annum. Thus, the Arbitral
Tribunal was justified in granting interest at the rate of 15% per annum post-
award. In our view, the Arbitral Tribunal was well within its jurisdiction under
Section 31 of the Act to award interest at the rate of 15% p.a. and there
was no justification to reduce the same to 10% p.a. We may observe with
respect that the High Court was not exercising any equity jurisdiction so as
to resettle the rate of interest as deemed fit by it. It had been a matter
relating to an award made by the Arbitral Tribunal in a commercial dispute.
Final comments, observations, and conclusion
35. In the foregoing discussion, we have not elaborated on the
discussions and findings of the Commercial Court in its order dated
12.09.2019. Instead, we have directly dealt with the consideration of the
High Court vis-à-vis the award in question. As noticed, the High Court could
only be said to have misdirected itself on the major issues concerning
merits of the award. However, before concluding, we may observe that it
had not been as if the Commercial Court did not examine the material
issues arising for determination while dealing with the case in terms of
Section 34 of the Act of 1996.
35.1. It is noticed that after taking note of the submissions of parties, the
Commercial Court precisely framed the points for determination and then,
dealt with every point on the anvil of Section 34 of the Act of 1996. With
respect, we do not find the High Court justified in making a comment about
71
framing of points for determination by Commercial Court and then
observing that the Commercial Court merely reproduced the findings of the
award. The Commercial Court dealing with Section 34 application was not
acting as a Court of Appeal. Yet, looking to the long-drawn arguments, the
Commercial Court enumerated the issues raised and then returned the
findings after examining the record and while rejecting the submissions
made on behalf of the State. There had been no such flaw in the judgment
and order passed by the Commercial Court which called for interference by
the High Court on the parameters and within the periphery of Sections
34/37 of the Act of 1996. We may, for illustration, reproduce paragraph 49
of the order of the Commercial Court where, in relation to the issue of
variable charges, after taking note of all the factual aspects and contentions
of the parties, the Commercial Court held as under: -
“49. Above facts clearly show that GOG clearly accepted and
understood that the price of electricity was to be calculated on
the basis of price of fuel and dollar conversion rate and that letter
dated 30.08.2013 and cabinet note were on a guiding factor to
know the understanding between parties. The Ld. Arbitrator
rightly appreciated that the cabinet of GOG took a decision
clearly in favour of the stand of the claimant. Ld. Advocate
General has argued that the cabinet decision was not binding
because pursuant to it no any decision was taken by the State
Government nor any decision was conveyed to the claimant.
Reference was made to Judgment in the case of Bachhittar
Singh (supra) wherein it is held that unless the cabinet decision
is followed by a formal order drawn up by The State Government,
it does not have binding effect. Ld. Advocate General also made
reference to judgment in the case of Bombay Chemicals Ltd. v/s.
Union of India – 2006(201) ELT 167 Bombay wherein cabinet
note was considered on merits but it was held that the cabinet
note was only to make budgetary provision. Without prejudice
Ld. Advocate General also submitted that even if the cabinet note
72
was to be considered it could at the most be for an amount of Rs.
0.76 paise increase and nothing more than that. In the present
case subsequent conduct of GOG in making payments based on
variable fuel price shows that they implemented the said cabinet
decision. In the present case even if the said cabinet note is
considered to be internal note, it will have to be considered
because GOG accepted variable fuel price and also made
payments. Making of payments thereafter are variable factors
which distinguish the above two judgments.
For the reasons mentioned above, Point No.1 is answered in
the Affirmative.”
36. The narrow scope of “patent illegality” cannot be breached by mere
use of different expressions which nevertheless refer only to “error” and not
to “patent illegality”. We are impelled to reiterate what has been stated and
underscored by this Court in Delhi Airport Metro Express (supra) that
restraint is required to be shown while examining the validity of arbitral
award by the Courts, else interference with the award after reassessing the
factual aspects would be defeating the object of the Act of 1996. This is
apart from the fact that such an approach would render several judicial
pronouncements of this Court redundant if the arbitral awards are set aside
by categorizing them as “perverse” or “patently illegal” without appreciating
the contours of these expressions.
37. In the passing, we cannot help noticing that in the impugned
judgment, the High Court though referred to the principles laid down by this
Court in Ssangyong Engineering (supra) but then, reproduced an
analysis by a learned Single Judge of the High Court and proceeded to
decide the matter with reference to the passages so extracted. With
respect, we are of the view that enunciation of this Court ought to have
73
been examined by the Division Bench of the High Court while dealing with
the matter at hand, rather than relying on the analysis by a learned Single
Judge of the High Court. We say no more in this regard, essentially
because the latter decisions of this Court like those in Delhi Airport Metro
Express and Haryana Tourism Limited were not available before the
High Court at the time of passing of the impugned judgment and order
dated 08.03.2021. Nevertheless, the principles expounded by this Court in
Associate Builders and Ssangyong Engineering (supra) were available
and the matter was required to be dealt with in reference to those
principles. Leaving this aspect at that, suffice it would be to observe for the
present purpose that the impugned judgment and order dated 08.03.2021,
insofar it interferes with the findings and the conclusions of the award in
question, cannot be sustained and is required to be set aside.
38. For what has been discussed hereinabove, a few other
submissions made by the learned Attorney General in regard to the
calculation of the awarded amount and ancillary aspects do not require
elaborate discussion. Fact of the matter remains that nothing of a patent
illegality apparent on the face of the award has been pointed out. The
submissions essentially are of indicating some alleged errors on the merits
of the case which, as noticed, do not fall within the parameters of Section
34 of the Act of 1996.
39. Hence, that part of the impugned judgment and order dated
08.03.2021 as passed by the High Court, which modifies the award dated
74
16.02.2018 and the order of the Commercial Court dated 12.09.2019, is
set aside and consequently, the award in question is restored in its entirety.
40. The appeal filed by the claimant is allowed accordingly and that filed
by the State is dismissed. No costs.
……....……………………. J.
(DINESH MAHESHWARI)
……....……………………. J.
(SANJAY KUMAR)
NEW DELHI;
MAY 10, 2023.
75