Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
M/S. PREMIER FABRICATORS, ALLAHABAD
Vs.
RESPONDENT:
HEAVY ENGINEERING CORPN. LIMITED, RANCHI
DATE OF JUDGMENT: 21/03/1997
BENCH:
MADAN MOHAN PUNCHI
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
Punchhi, J.
The sole and subtle question arising in this appeal is
whether in the facts and circumstances, it was required of
the Umpire making the award to formally express in terms
that items nos.2 to 5 of the dispute were arbitrable on the
terms of the contract?
The appellant herein M/S. Premier Fabricators Allahabad
is the contractor. The Respondent Corporation engaged the
contractor to execute some works. On May 25, 1971, a deed of
agreement was executed in writing between the Parties.
Clause 78 thereof made provision for settlement of disputes
by arbitration. That clause reads as follows:
"SETTLEMENT OF DISPUTES BY
ARBITRATION
78(1) All questions, disputes or
difference of any kind, whatsoever,
arising out of, or in connection
with, the contract, at any time,
whether during the progress of work
of after its completion, or whether
before or after the determination
of the contract, other than
questions, disputes or differences
for the decision of which specific
provisions have been made in the
foregoing clauses of these
conditions (hereinafter referred to
as "excepted matters") according to
the said specific provisions shall
be final and binding on the
contractor and shall not be re-
opened on the ground of any
informality, omission, delay or
error in the proceeding in or about
the same or on any other ground
whatsoever, shall be submitted in
writing by the contractor to the
employer, and the employer shall
within a reasonable time, after the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
submissions of the same, make and
notify its decisions thereon in
writing.
(2) If the contractor be
dissatisfied with the decision of
the employer on any matter in
question, dispute or difference, on
any ground, or as to the
withholding by the employer of any
certificate to which the contractor
may claim to be entitled to, or if
the employer fails to make a
decision within a reasonable time,
then and in any such case but not
including any of the excepted
matters, the contractor may, within
ten days of the receipt of such
decision or after the expiry of a
reasonable period of time, as the
case may be, demand in writing that
such matter in question, dispute or
difference be referred to
arbitration. Such demand for
arbitration shall be delivered to
the employer by the contractor and
shall employer by the contractor
and shall specify the matters which
are in question, dispute or
difference and only such question,
dispute or difference of which the
demand has been made and no other
shall be referred to arbitration.
(3) The further progress of any
work under the contract shall,
unless otherwise directed by the
Engineer, continue during the
arbitration proceedings, and no
payment due or payable by the
employer shall be withheld on
account of such proceedings,
provided however that it shall also
be open to the arbitrators, to
consider and decide whether or not
such work shall continue during the
arbitration proceedings.
(4) (a) Matters in question,
dispute or difference to be
submitted to arbitration as
aforesaid shall be referred for
decision to two arbitrators, one to
be nominated by the Chairman and
the other to be nominated by the
contractor. In the event of the two
arbitrators being divided in their
opinion, the matter under dispute
shall be referred for decision to
an umpire to be appointed by the
two arbitrators not later than one
month from the latest date of their
respective appointments and, in any
case, before they enter upon and
proceed with the reference.
(b) The Arbitrators or the umpire
shall have power to call for such
evidence by way of affidavits or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
otherwise as the arbitrators or the
umpire, as the case may be, shall
think proper, and it shall be the
duty of the parties to do or cause
to be done all such things as may
be necessary to enable the
arbitrators or umpire to make the
award without any delay.
(c) Unless otherwise agreed upon by
the parties, the venue of the
arbitration proceedings under these
conditions shall be at Ranchi in
the State of Bihar.
(d) Subject to aforesaid, the
provisions of the Arbitration Act,
1940 or any statutory modification
or enactment thereof and of the
rules force, shall apply to all
arbitration proceeding under this
clause.
provided, however, that the
arbitrators or, as the case may be,
the umpire may, from time to time,
with the consent of the parties,
enlarge the time for making the
award."
The appellant-contractor laid claim for payments in
terms of items nos. 1 to 5, as mentioned in its claim, from
the Corporation which was rejected by the latter. Thereupon,
the contractor asked for arbitration in terms of Clause 78.
The Corporation denied arbitration in respect of items
2,3,4, and 5 as being not referable to arbitration in terms
of the contract. On the basis of the disputes and
differences thus existing between the parties in respect of
the claims of the contractor, the Managing Director of the
Corporation nominated Shri K.N. Mehra, its Works Manager
(Production) as an arbitrator to give a joint award on all
the above claims after deciding whether claims referred to
in items 2,3,4 and 5 were or were not referable for
arbitration in terms of the contract. The contractor on its
part nominated Shri S.B. Gadodia as the arbitrator to make a
joint award in respect of the terms of the arbitration made
by the Corporation.
On entering upon arbitration, the arbitrators on 6-2-
1973 recorded on their respective files their decision that
items nos. 2,3,4 and 5 of the claim of the contractor were
referable and could be decided by the arbitrators. This
meant that all the items 1 to 5 were arbitrable. Proceeding
further went on but the joint arbitrators ultimately could
not arrive at a joint award. Therefore by a joint letter
dated November 2, 1973, they requested Professor G.B. Pant
of Birla Institute of Technology, Ranchi to enter upon the
reference as Umpire and give his award. As given out in
their joint letter they forwarded separately their
respective files for perusal of the Umpire, as also rest of
the record.
The Umpire then went into the matter. As is evident
from the record, he took into account the fact that the
matter had come to him in pursuance of a contract dated May
25, 1971 executed between the parties and that the parties
in terms thereof had referred to S/Shri Mehra and Gadodia by
letter of reference the matters of difference between them
concerning items 1 to 5 (as detailed out) and that since
there was reported failure by the joint arbitrators to
arriver at a joint award in respect of the referred matters,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
the case was referred to him as the Umpire. Therefore he
observed in his award that having heard both the parties and
having seen all the documents submitted and having given the
matter a careful consideration he would direct the
Corporation to Pay a sum of Rs. 80, 000/- to the contractor
bearing interest at the rate of 6 per cent per annum from
the date of order till the date of decree.
The contractor applied for the award of the Umpire
being made Rule of Court, which was registered as a suit in
the Court of Third Additional Sub-Judge, Ranchi. The
Corporation objected on a number of grounds of the award
being made Rule of Court. Despite objection the award, all
the same, was made Rule of Court. The Corporation then went
up in appeal before the High Court of Patna which was placed
before a Bench of two Hon’ble Judges of the High Court. It
was contended on behalf of the Corporation before the Bench
that there was error of law apparent on the face of the
award because the Umpire, who was the substitute of the
arbitrators, had not recorded the preliminary finding
whether items nos. 5 to 5 of the claim could be subject
matter of arbitration under the terms of the contract an,
therefor, the award was vitiated. It was urged that the
Umpire could give his award on merits only after deciding
the preliminary question as to whether claim under item nos.
2 to 5 were arbitrable. Both the Hon’ble Judges of the High
Court constituting the Division Bench were in agreement that
the order passed by the arbitrators on 6 2 1973 to that
affect could not, on its own, be said to have disposed of
the preliminary question once for all and that on reference
to the Umpire the entire dispute including the question of
referability was required to be decided by him. Upto this
point the Hon’ble Judges were in concurrence but not
thereafter. One Hon’ble Judge took the view that the Umpire
must in the facts and circumstances be deemed to have
decided the question of referability of items 2 to 5 in the
affirmative and the award must therefore be accepted as
valid. The other Hon’ble Judge differed by stating that in
the facts and circumstances of the case, it was not possible
to inferentially hold that the Umpire must have decided the
preliminary question about referability while making the
award to the tune of Rs. 80,000/- only, a sum much below
than what was claimed. The matter then had to be, and was,
referred to a Third Hon’ble Judge of that High Court.
The controversy before the Third Hon’ble Judge was thus
narrowed to the facts and circumstances of the case, i.e.
whether a deemed decision on referability should or should
not be inferred? The Third Hon’ble Judge noticing that since
the members of the Division Bench had agreed that it was for
the Umpire to have considered and decided the preliminary
question, went on to opine that the Umpire may not have
appreciated the position as to his obligation and there was
a possibility that he might not have considered it necessary
to form his opinion on the point due to the decision of the
Arbitrators. The Third Hon’ble Judge also was of the view
that inference in favour of the contractor could not be
drawn from the conclusion merely because an award in terms
of money had been made, unless he had stated so in express
terms in the award. On this basis, the Third Hon’ble Judge
agreed with the view of one of the Hon’ble Judges of the
Division Bench holding that the contractor had failed to
show that the Umpire had decided the preliminary question in
its favour before proceeding to consider the claim on
merits. It is on that account that the Award was set aside
leaving it for the parties to move the court below to
proceed further in the matter in accordance with the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
provision of the Indian Arbitration Act.
As is evident, no abstract question of law or of legal
import has arisen herein. It is from the facts and
circumstances of the case that one would have to draw and
record inferences. There are four reasons detailed hereafter
which call to infer that (i) the Umpire was alive to his
duties as such, knowing fully well that he was not a
superior between the two arbitrators, but their sole
substitute assigned their duties; (ii). The Umpire did not
consider the decision of the joint arbitrators dated 6 2
1973 holding that claims under items 2 to 5 were referable
to arbitration, as binding on him as if in the nature of an
interim award, nor was it treated as such by the arbitrators
by delivery and dispatch to the parties concerned; (iii)
that since the said order was part of the proceedings
recorded by the joint arbitrators, the Umpire on receiving
the matter is presumed to have gone through the terms of the
contract and the arbitration proceedings; and (iv) it is
also implied that the Umpire as a substitute of the
arbitrators must be presumed to have known that before he
entered upon reference to decided item nos. 2 to 5 on their
merits, he would have to decide whether those items were
arbitrable but the same need not have been in express terms.
To hold it otherwise would be to negate his independence. It
may be true that the joint decision dated 6 2 1973 of the
arbitrators regarding referability of those items might have
been of some support to his view. Yet it cannot be presumed
that he considered himself bound by those orders, absolving
him of the duty from going into the question. It would thus
in the circumstances be seen that obligating the Umpire to
make a speaking award in so far as the question of
referability is concerned, lest it vitiates his non speaking
award on merit, goes to the very root of the independence of
the arbitrator. This is impermissible in law and against the
spirit of the Arbitration Act, 1940. The award of the
Umpire, as is plain, is a non-speaking award in entirety. He
has preluded it with the recorded awareness that differences
between the parties had arisen, and the matter stood
referred to arbitration in pursuance of the contract in
writing dated may 25, 1971. He is then presumed to have real
the terms of the contract, the terms of reference and scope
of items 2 to 5 of the claim. He is presumed to have
examined whether those claims were referable to arbitration
in terms of the contract. He is further presumed to have
read the respective files of the two arbitrators and to have
heard both parties at length, screening all the documents
submitted, to come to the base finding that items 2 to 5
were referable. All the five items were thus arbitrable,
resulting in the award for a sum of Rs. 80,000/- in favour
of the contractor. The award must therefore be upheld for
the afore-reasons, holding that there is no error apparent
on the face of the record which would justify its vitiation.
For the afore-going reasons, it must be held that the
Third Hon’ble Judge was in error in not agreeing with the
view of one of the Hon’ble Judges in the Division Bench who
had held that there was a deemed/presumed decision on
referability inferable from the award of the Umpire.
Therefore, the impugned order of the High Court is set
aside by allowing this appeal, as a result of which appeal
from original order NO. 240 of 1975 in the Civil Appellate
Jurisdiction of Patna High Court shall stand dismissed with
costs, maintaining that of the court of first instance.