Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
CASE NO.:
Appeal (civil) 6348 of 2005
PETITIONER:
Bharat Heavy Electricals Ltd
RESPONDENT:
Anil and Ors
DATE OF JUDGMENT: 07/11/2006
BENCH:
Arijit Pasayat & S. H. Kapadia
JUDGMENT:
J U D G M E N T
KAPADIA, J.
What was the subject of the dispute decided by the Labour Court vide
its Award dated 5.7.1996 in ADJ case No. 31/90 to 44/90 ? This is the
question which we are required to answer in this civil appeal.
The facts giving rise to the civil appeal are as follows:
Bharat Heavy Electricals Limited ("BHEL") is the company
registered under the Companies Act, 1956 having its registered office at
New Delhi. Respondents 1 to 14 herein moved the Conciliation Officer
under Section 2-A of the Uttar Pradesh Industrial Disputes Act, 1947 ("the
said 1947 Act") stating, that there was a principal employer; that K.P. Singh
was a contractor under whom they were working as contract labour; that the
services were unlawfully terminated w.e.f. 1.12.1988, and accordingly, the
contractor should be asked to take them back in service with full back wages
w.e.f. 1.12.1988.
On 19.7.1989 BHEL filed its reply before the Conciliation Officer
inter alia stating that, respondents 1 to 14 herein were engaged by the
contractor; that the contractor was engaged by BHEL; and, that there was no
employer-employee relationship between BHEL on one hand and the said
respondents on the other hand.
Ultimately, the matter was referred to the Labour Court by way of a
reference under Section 4-K of the said 1947 Act. Before the Labour Court
BHEL contended, that respondents 1 to 14 were malis (gardeners); that they
were engaged by the contractor; that these malis were required to clean
parks; that in the vast area of land owned by BHEL, they were required to
keep the campus neat ant clean; that they had worked for a brief period
1.6.1988 to 24.10.1988; and, that they were casual workmen, who were not
entitled to be given work on all the days and, therefore, there was no
industrial dispute between BHEL and the said respondents within the
meaning of Section 2-A of the said 1947 Act. By the written statement,
BHEL further contended, that respondents 1 to 14 were never paid wages
by BHEL; that they never worked under their supervision and control, and
that the rights, if any, of the said respondents were only against their
contractor. BHEL further contended that the period of contract commenced
on 1.6.1988 and ended on 24.10.1988.
At this stage, we quote hereinbelow the terms of reference made to the
Labour Court:
"Whether termination of services of Anil son of
Shri Vikram Singh by his employers from 1.12.88
was justified and/ or lawful ? If not then the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
benefit/ relief the worker concerned is entitled to
\005."
By award dated 5.7.1996 the Labour Court held, that respondents 1 to
14 herein had worked for more than 240 days as malis; that work was taken
from them by the contractors; and, that the services stood terminated from
1.12.1988 without complying with the provisions of Section 6-N of the said
1947 Act. In the said award, the Labour Court observed that, the workers
themselves have proceeded on the footing that they were engaged by the
contractors, but the work which they performed was for BHEL. The Labour
Court came to the conclusion that non-employment of workers w.e.f.
1.12.1988 constituted termination under Section 2-A of the said 1947 Act.
The Labour Court held that, BHEL had retained its control over the workers
and, therefore, respondents 1 to 14 cannot be said to be the workers only of
the contractor. Consequently, the Labour Court held that, BHEL was the
principal employer and the contractor was the immediate employer. It
further opined that, respondents 1 to 14 had worked for 240 days and that
their services were wrongly terminated in breach of Section 6-N of the said
1947 Act. In the circumstances, the Labour Court held that the termination
of services of respondents 1 to 14 by the contractor was not justified and
lawful and that BHEL also was liable for wrongful termination.
Accordingly, the Labour Court directed BHEL to re-employ respondents 1
to 14 in their services or get them employed under the contractor.
The said award was challenged by BHEL in the High Court by way of
writ petition. By judgment and order dated 17.2.1999, the High Court upheld
the award of the Labour Court saying that it did not suffer from any
illegality or irregularity. The High Court affirmed the finding of the Labour
Court that respondents 1 to 14 had worked under the control of BHEL and
that BHEL was the principal employer of these workmen.
Aggrieved by the decision, BHEL carried the matter by way of special
leave petition to this Court. By judgment dated 21.7.2003 the Division
Bench of this Court held, that the services of these workmen were
wrongfully terminated, that they had worked for more than 240 days in
twelve calendar months. This Court further held, that control was retained by
BHEL; that respondents 1 to 14 had to work under the supervision of BHEL
and, in the circumstances, this Court refused to interfere with the award of
the Labour Court.
We need not go into the chequered litigation regarding execution of
the award which took place after the judgment of this Court. Suffice it to
state that, after the judgment of this Court dated 21.7.2003, the Assistant
Labour Commissioner ("ALC") passed an order on 1.12.2003 directing
BHEL to re-engage respondents 1 to 14 through the contractors in
compliance with award dated 5.7.1996.
Aggrieved by the order of the ALC, respondents 1 to 14 herein moved
the Uttranchal High Court vide Writ Petition No. 1279/03 stating that the
order of ALC be quashed and that BHEL should be directed to give
employment to respondents 1 to 14 herein and not through intermediary,
namely, the contractor.
By the impugned judgment dated 27.9.2004, after stating the above
facts, the High Court set aside the order of the ALC dated 1.12.2003 and
directed BHEL to reinstate respondents 1 to 14 herein in service directly.
Hence, this civil appeal.
Shri Sudhir Chandra, learned senior counsel appearing for BHEL,
contended that the doctrine of merger has limited application to the facts of
the present case. He submitted that, when the Division Bench of this Court
upheld the award vide its judgment dated 21.7.2003, this Court had
confirmed the operative part of the award of the Labour Court which
directed BHEL to re-employ respondents 1 to 14 in their service or get the
said workers employed through an intermediary, namely, the contractor. He
submitted that the doctrine of merger applies to the operative part of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
award and not to the reasoning or observations in the award. In this
connection, learned senior counsel submitted that, an individual dispute was
raised by the workers under Section 2-A of the said 1947 Act complaining
about termination of services w.e.f. 1.12.1988. Learned senior counsel
further pointed out that, before the Labour Court it was the case of the
workers themselves that they were engaged by the contractor but the work
which they had performed was for BHEL. In this connection, reliance was
placed on the observations made by the Labour Court in its award (see page
76 of the SLP paper book). He submitted that, in the above circumstances,
the Labour Court had treated BHEL as the principal employer and the
contractor as an immediate employer. He submitted that, operative part of
the order has become final by reason of the judgment of this Court dated
21.7.2003. He urged, that the award was given on the basis of an individual
dispute under Section 2-A of the said 1947 Act; that the terms of the
reference indicate that the only question which the Labour Court was
required to decide was whether termination of services was justified and
lawful and, if not, the benefits/ relief which each of the workers were
entitled to. Learned senior counsel submitted that the workers in the present
case cannot claim direct employment from BHEL. He urged that the Labour
Court while granting reinstatement made an enabling provision by which the
said workers (respondents 1 to 14) were directed to be re-employed by
BHEL in the service directly or get them employed under their contractor. It
is not in dispute that BHEL has got said workers employed through that
contractor. The said workers continue to be the employees of the contractor
even today. Even today, they are getting the work and salary from the
contractor.
Learned senior counsel for the appellant further submitted that, the
subject of the dispute before the Labour Court was the validity of the
termination and not direct employment from BHEL. He submitted that, if the
said workers were to ask for direct employment from BHEL, they were
required to raise a regular industrial dispute not under Section 2-A but under
Section 2(l) of the said 1947 Act. He submitted that the cause of the said
workmen herein was not espoused by any union. If the workmen wanted
direct employment from BHEL or regularization, they were required to raise
a substantial industrial dispute before the tribunal; they were required to join
the regular union of BHEL as party respondent and in such an event the
matter was required to be adjudicated upon not by the Labour Court but by
the tribunal. He further pointed out, that there is a regular union in the
industry; that the company was maintaining a waiting list of workers of
BHEL, who were required to be made permanent; that respondents 1 to 14
were never recruited directly by BHEL; that they had never applied for
employment against vacancies in BHEL, and if they had sought direct
employment with BHEL, then they were required to raise an industrial
dispute seeking abolition of contract labour after making the regular union a
party respondent. He, therefore, submitted that an individual dispute, though
need to be an industrial dispute under Section 2-A, cannot be converted into
an industrial dispute under Section 2(l) without a proper reference.
Shri V.C. Mishra, learned senior counsel appearing on behalf of some
of the respondents, submitted that in the earlier round of litigation, the
Labour Court, the High Court and the apex Court had held that respondents
1 to 14 were the employees of BHEL. He urged that, vide para 13 of the
decision of the apex Court, the findings recorded by the Labour Court and
the High Court were confirmed and that respondents 1 to 14 were directed to
be treated as employees of BHEL. In the circumstances, learned senior
counsel urged that the doctrine of merger was squarely applicable and,
therefore, the ALC had erred in directing BHEL to re-employ respondents
1 to 14 through the contractor. Learned senior counsel urged that, in the
circumstances, there was no reason to interfere with the impugned judgment
of the High Court directing BHEL to re-employ respondents 1 to 14 directly
as their workers.
Ms. Asha Jain Madan, learned counsel appearing for some of the
respondents, contended that in the earlier round of litigation respondents 1 to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
14 had succeeded in all the courts. She heavily relied upon the observations
made in the judgment of the High Court confirmed by this Court stating that,
BHEL had resorted to a camouflage in order to avoid the provisions of the
said 1947 Act. She contended, that respondents 1 to 14 were malis, they
were required to look after the lawns of the company; that in the earlier
round, even after the award the company had refused to pay compensation to
the workers either directly or through the contractor; that the contractor had
disowned their liability; and, in the circumstances, the workers had to file an
application for implementation of the award. She contended that the
workmen who get out of job unless and, in the circumstances, it was
submitted that this Court should not interfere with the impugned judgment.
She further contended that engagement of workers through a camouflage,
keeping control over their work, termination of services unlawfully and
refusal to produce relevant records before the Labour Court are
circumstances which show that BHEL was the employer and respondents 1
to 14 were entitled to be directly employed with the company. Learned
counsel further contended that, the very basis of the award in the present
case was unlawful termination of services by BHEL through its contractor.
She submitted that the judgments of the High Court and this Court
upholding the award show that BHEL was the real employer and a
camouflage was created by BHEL to show that respondents 1 to 14 were the
employees of the contractor and not of the BHEL. In the circumstances,
learned counsel contended that respondents 1 to 14 should be employed by
BHEL as their employees. In this connection, learned counsel relied upon
the order passed by this Court in the case of Hotel Corporation of India &
anr. v. Balwant Rai Saluja & Ors. . Learned counsel also relied upon the
judgment of this Court, referred above, in the case of Bharat Heavey
Electricals Ltd. v. State of U.P. and Ors. as also the judgment of this
Court in the case of Steel Authority of India Ltd. and Ors. v. National
Union Waterfront Workers and Ors. .
As stated above, the central question which we have to answer
concerns the subject of the dispute decided by the Labour Court vide award
dated 5.7.1996. The right to employment on setting aside of the earlier order
of termination, the right to wages and the right to obtain work from BHEL is
different from the right to status as employees of BHEL. Under the said
award respondents 1 to 14 were entitled to obtain work from BHEL through
its contractor. They were entitled to wages under the said award. However,
under the said award of the Labour Court there is no abolition of contract
labour. The Labour Court has not conferred the status of a workman qua
BHEL. The Labour Court has not granted permanency to them. Per contra,
after holding that the work of mali was supervised and controlled by BHEL,
the award makes an enabling provision by directing BHEL to re-employ the
said workmen in their service or employ them through the contractor. In
fact, the operative part of the award further states that it is the contractors
who had failed to retain the workmen and terminated their services in breach
of Section 6-N of the said 1947 Act. This enabling direction is given on the
footing that the work carried out by these workmen was under control and
supervision of BHEL. The observations made in the judgment of the High
Court as well as in the judgment of this Court in Bharat Heavy Electricals
Ltd.2 (supra) have to be read in the context of the operative part of the
award. It is true that, observations have been made by this Court in the
above judgment in agreement with the views expressed by the High Court
that BHEL had resorted to a camouflage to get the work done through
contractor. However, since the work was obtained under supervision and
control of BHEL, the award directed these workmen to be employed directly
or through the contractor. Therefore, the observations of the High Court and
this Court have to be read in the light of the operative part of the award.
For the above reasons, the judgments cited on behalf of respondents 1
to 14 have no application to the facts of the present case. In those
judgments, a substantial industrial dispute was raised which is not the case
herein. Therefore, they have no application to the present case.
There is one more reason for coming to the above conclusion. There is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
a difference between an individual dispute which is deemed to be an
industrial dispute under Section 2-A of the said 1947 Act on one hand and
an industrial dispute espoused by the union in terms of Section 2(l) of the
said 1947 Act. An individual dispute which is deemed to be an industrial
dispute under Section 2-A concerns discharge, dismissal, retrenchment or
termination whereas an industrial dispute under Section 2(l) covers a wider
field. It includes even the question of status. This aspect is very relevant for
the purposes of deciding this case. In the case of Radhey Shyam and anr.
v. State of Haryana and anr. it has been held after considering various
judgments of the Supreme Court that, Section 2-A contemplates nothing
more than to declare an individual dispute to be an industrial dispute. It does
not amend the definition of industrial dispute set out in Section 2(k) of the
Industrial Disputes Act, 1947 (which is similar to Section 2(l) of the said
1947 Act). Section 2-A does not cover every type of dispute between an
individual workman and his employer. Section 2-A enables the individual
worker to raise an industrial dispute, notwithstanding, that no other
workmen or union is a party to the dispute. Section 2-A applies only to
disputes relating to discharge, dismissal, retrenchment or termination of
service of an individual workman. It does not cover other kinds of disputes
such as bonus, wages, leave facilities etc.
As stated above, in the present case the award of the Labour Court has
also held that respondents 1 to 14 have proceeded their case on the footing
that they were engaged by the contractors, but the work they performed was
for BHEL. That is why the operative part of the award says that the said
respondents shall be given work by BHEL as direct workmen or through its
contractor. The question which we have to answer is: why did the Labour
Court provide for an enabling direction in its award? The answer is simple.
The Labour Court has not granted a status of direct employment per se
because BHEL has its own recognized union and that union was not made a
party respondent. Respondents 1 to 14 herein were not recruited directly in
BHEL; they had never applied for job in BHEL; the appointment letters
appear to have been given by the contractor; BHEL has its own waiting list
of workmen, who claimed permanency/ regularization; and they were not
before the Labour Court. In the circumstances, the Labour Court has enabled
BHEL either to directly employ respondents 1 to 14 or employ them through
the contractor. The contractor before us states that respondents 1 to 14 are
being given work by him, they were paid wages by the contractor. In the
circumstances, the ALC was right in directing BHEL to re-employ
respondents 1 to 14 either directly or through the contractor. This order was
passed by the ALC on 1.12.2003. The ALC was an execution court. The said
order is in terms of the award given by the Labour Court on 5.7.1996.
Accordingly, we set aside the impugned judgment of the High Court
by directing BHEL to re-employ respondents 1 to 14 directly or through its
contractor. This order will, however, not preclude the workmen from raising
an industrial dispute claiming status of direct workmen of the company after
joining the recognized union/ concerned union in the said Reference. This
order will not prevent the respondents herein from seeking abolition of
contract labour in accordance with law.
Accordingly, the civil appeal is disposed of. No order as to costs.