Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
THE COMMISSIONER, CORPORATION OF THE CITY OF BANGALORE, BANG
Vs.
RESPONDENT:
K.N. VASUDEVA MURTHY (DEAD) THROUGH L.RS. & ORS.
DATE OF JUDGMENT: 28/07/1998
BENCH:
K. VENKATASWAMI, A.P. MISRA
ACT:
HEADNOTE:
JUDGMENT:
O R D E R
Special leave granted.
These two appeals are filed against the two orders of
the Division Bench of the Karnataka High Court dated 23.8.95
in W.A. No.2825/95 and dated 10.11.95 in I.A. VI for
recalling the order dated 23.8.95.
We do not consider it necessary to give full facts of
the case relating to these appeals in view of the order
proposed to be passed. Brief facts are given below:-
The husband of the first respondent and father of
respondents Nos.2 to 9 (hereinafter called the "Contractor")
was entrusted with the execution of a work for the
construction of storm water drain by the appellant-
Corporation. It is common ground that the Contractor failed
to complete the work within the stipulated time, which
necessitated the Corporation to entrust the balance work to
a new Contractor, namely, M/s J.K. Construction Company, who
completed the work. The Contractor claimed that he was to be
paid some amount by the appellant-Corporation for the work
executed by him. The Corporation, however, was not prepared
to accept the liability which necessitated the appointment
of an Expert Committee. The Expert Committee seems to have
recommended that the Corporation has to pay the contractor a
sum of Rs.39,53,096.50 with interest from 1.10.81 to
10.8.94. It appears that the Corporation has paid the said
sum of Rs.39,53,096.50 but did not pay the interest as
recommended by the Expert Committee.
Aggrieved by the non-payment of interest, the
Contractor has moved the Karnataka High Court under Article
226 of the Constitution for a direction to the Corporation
for payment of the interest as noticed above. When the
matter came up before a learned Single Judge, the learned
counsel appearing for the Corporation said to have made the
following statement:-
"Smt. B.L. Hemavati, learned
counsel appearing for respondent
No. 2 would not dispute that the
second respondent is liable to pay
interest as recommended by the
Expert Committee and the approval
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
is being sought from the Standing
Committee of the Works and Taxation
and Finance."
It may be noticed at this stage that the grievance of
the appellant-Corporation is that before the learned Single
Judge the Corporation was not given sufficient time to file
a Counter/Reply to the claim of the Contractor. Be that as
it may. The learned Single Judge has directed the appellant-
Corporation to pay the interest on Rs.39,53,096.50 paise
from 1.10.81 to 10.3.94 holding that since Government had
accepted the Report of the Export Committee there was no
need to seek the approval of the Standing Committee of the
Works and Taxation and Finance.
The Corporation, feeling aggrieved by the order of the
learned Single Judge, preferred a Writ Appeal (FR) No.
1056/95 before the Division Bench. Unfortunately, the
learned counsel for the Corporation could not be present
when the matter was taken up by the Division Bench and the
Division Bench, however, disposed of the appeal on 23.8.1995
holding as follows:-
"In fact the whole case proceeded
on the basis of the concession made
before the Court by the learned
counsel for the appellant. The
learned counsel did not dispute
that they are liable to pay
interest as recommended by the
Expert Committee appointed by them.
All that was needed was approval of
the Standing Committee. The Court
noticed, that seeking of the
approval of Standing Committee in
such a matter is wholly unnecessary
because the Expert Committee had
already given its recommendation.
In the circumstances, without going
into the question of delay this
appeal is rejected."
The Corporation moved the Division bench for recalling
the order dated 23.8.1995 passed in Writ Appeal on the
ground that the counsel for the appellant was not heard. The
application for recalling the order was disposed of on
10.11.1995 by the Division Bench by observing as follows:-
"Even after hearing Sri P.
Vishwanatha Shetty, we find no
grounds to change the order in
Appeal or recall the order made on
23.8.95."
Aggrieved by the above two orders, these appeals are
now filed by special leave.
Mr. Oavali, learned senior counsel appearing for the
appellant-Corporation, while arguing on merits also
submitted that the Division Bench was not right in
proceeding that there was an unconditional/absolute
concession before the learned Single Judge, which enabled
the Court to allow the Writ Petition. According to the
learned senior counsel, there was no concession and the
learned counsel before the learned Single Judge, as a
statement of fact, has stated that the Corporation was
liable to pay as recommended by the Expert Committee, but
after the approval by the Taxation Committee. We must bear
in mind, for what it is worth, the grievance of the
Corporation that it was not given an opportunity to file its
return before the learned Single Judge.
Mr. Naik, learned senior counsel appearing for the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
respondents, while answering the submissions made by the
learned senior counsel for the appellant-Corporation on
merits, also submitted that the Division Bench was perfectly
in order in construing the statement of the learned counsel
appearing for the Corporation before the learned Single
Judge as a concession and further the Court was also right
in holding that the approval of the Taxation Committee was
not required on the facts of the case.
After considering the rival submissions and bearing in
mind the huge public amount involved in this case and also
the circumstances attending to the disposal of the matters
before the learned Single Judge and the Division Bench, we
are of the view that the Division should considered the
question whether the statement made before the learned
Single Judge (extracted supra) by the counsel for the
Corporation amounted to an unqualified concession and,
therefore, no further question arose. Even assuming that
there was a qualified concession, whether the circumstances
brought out in the memorandum of grounds required any
consideration especially when the Division Bench disposed of
the writ appeal on merits in the absence of counsel for the
appellant-Corporation. We set aside the impugned orders of
the Division Bench and remand the matter to the High Court.
We deliberately refrained from considering the merits at
this stage for obvious reasons. The High Court will restore
on its file the Writ Appeal (FR) No. 10526/95 (W.A. No.
2825/95) and dispose of the same in accordance with law.
The appeals are disposed of accordingly with no order
as to costs.