Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 10
PETITIONER:
VISHWANATH SOOD
Vs.
RESPONDENT:
UNION OF INDIA & ANR.
DATE OF JUDGMENT24/01/1989
BENCH:
RANGNATHAN, S.
BENCH:
RANGNATHAN, S.
MUKHARJI, SABYASACHI (J)
CITATION:
1989 AIR 952 1989 SCR (1) 288
1989 SCC (1) 657 JT 1989 (1) 585
1989 SCALE (1)154
ACT:
Arbitration Act, 1940: Section 3, 14, 17, 30, 31 and
33--Arbitration agreement--Clause providing penalty as com-
pensation to Department for default on part of contractor in
adhering to time schedule--Compensation to be determined by
Superintending Engineering and none else--Award of compensa-
tion--Whether liable to be questioned before Arbitrator.
HEADNOTE:
The appellant undertook the construction of a Farmers’
Community Centre Building by an agreement entered into with
the Union of India and the State of Himachal Pradesh, the
respondents in the appeal.
The agreement dated June 20, 1968 provided, by Clause 2,
for the payment of compensation for delay, if the contractor
should have been guilty of delay in commencing the work or
in completing it, the quantum of compensation to be deter-
mined by the Superintending Engineer and that his decision
was final. Clause 25 provided for settlement of disputes by
arbitration. It excluded from arbitration matters or dis-
putes in respect of which provision had been made elsewhere
or otherwise in the contract.
Certain disputes arose between the parties, and in terms
of clause 25 of the agreement they were referred to a sole
arbitrator.
The Contractor submitted a claim in respect of 9 items,
and the department filed a counter claim to the effect that
they were entitled to receive from the Contractor a sum of
Rs.24,000 on account of payment of 10 per cent compensation
for not executing the work in accordance with the terms and
conditions of the agreement. The arbitrator gave his award,
and the same was filed in the Court.
The Contractor filed objections for modification in
respect of items 1, 8 and 9 of his claim and item no. 1 of
the respondents’ counter claim. The department also filed
its objections.
The Single Judge dismissed the objections of the respondents
and
289
allowed the appellants’ claim only in respect of item no. 1
of the respondents’ counter claim. The single Judge took the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 10
view that a reading of clause 2 with clause 25 made it clear
that any compensation under clause 2 could be adjudicated
upon only by the Superintending Engineer or the Development
Commissioner and that it was not open to the arbitrator to
have entered upon a reference in regard to this claim at
all.
Both parties filed appeals to the Division Bench. The
Bench reversed the order of the Single Judge and restored
the award to its original terms. It held that inasmuch as a
bonafide dispute can be raised by the contractor in regard
to his liability to compensation under clause 2 and as no
machinery was provided in clause 2 for the resolution of
such dispute, there is ample justification for holding that
resort can be had to arbitration under clause 25. On this
view of the matter, the Bench did not agree with the Single
Judge that the arbitrator had traveled outside his jurisdic-
tion in awarding compensation to the Government against the
contractor for the delay in executing the work.
In the appeal to this Court it was contended on behalf
of the appellants that the terms of Clause 2 clearly envis-
age the determination of the amount of compensation for the
delay in the execution of the work only by the Superintend-
ing Engineer and specifically mentions that the decision of
the Superintending Engineer in writing shall be final. The
opening words of Clause 25, "Except otherwise provided in
the contract" clearly take out of the purview of Clause 25
any dispute in respect of a claim under Clause 2. Even if
Clause 25 be held applicable, the question of submitting a
dispute in this regard to the arbitrator could only arise if
there had been a determination and a dispute under Clause 2.
It was further submitted that there was no dispute at all
between the parties on the question of compensation and that
a dispute cannot be said to arise merely because a counter-
claim was for the first time put forward by the Department
before the arbitrator.
On behalf of the respondent-Department the appeal was
contested by contending that Clause 2 was in the natore of a
penal clause which automatically takes effect irrespective
of any default. The clause made the contractor liable for
the penalty prescribed therein whenever there was a delay in
the completion of the contract, whatsoever might have been
the reason therefore, the question as to whether the con-
tractor was at default or not being totally immaterial. The
Department was, therefore, entitled to automatically deduct
from the bills payable to the contractor, the compensation
or penalty at the rate mentioned in Clause 2
290
or such reduced amount as may be determined in a particular
case by the Superintending Engineer and that if the contrac-
tor objected to the deduction that would give risc to a
dispute which can be the subject matter of arbitration under
Clause 25.
Allowing the appeal,
HELD: 1. Clause 2 of the contract makes the time speci-
fied for the performance of the contract a matter of essence
and emphasises the need on the part of the contractor to
scrupulously adhere to the time schedule approved by the
Engineer-in-charge. With a view to compel the contractor to
adhere to this time schedule, this clause provides a kind of
penalty in the form of a compensation to the Department for
default in adhering to the time schedule. [297E-F]
2. Clause 2 contains a complete machinery for determina-
tion of the compensation which can be claimed by the Govern-
ment on the ground of delay on the part of contractor in
completing the contract as per the time schedule agreed to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 10
between the parties. The decision of the Superintending
Engineer is in the nature of a considered decision which
has to arrive at after considering the various mitigat-
ing circumstances that may be pleaded by the contractor or
his plea that he is not liable to pay compensation at all
under this clause. [298E-F]
3. The question regarding the amount of compensation
leviable under Clause 2 has to be decided only by the Super-
intending Engineer and no one else. [298G]
4. The opening part of Clause 25 clearly excludes mat-
ters like those mentioned in Clause 2 in respect of which
any dispute is left to be decided by a higher official of
the Department. [299C]
5. The question of awarding compensation under Clause 2
is outside the purview of the arbitrator and the compensa-
tion, determined under Clause 2 either by the Engineer-in-
Charge or on further reference by the Superintending Engi-
neer will not be capable of being called in question before
the arbitrator. [299D]
6. Clause 25 which is the arbitration clause starts with
an opening phrase excluding certain matters and disputes
from arbitration and these are matters or disputes in re-
spect of which provision has been made elsewhere or other-
wise in the contract. These words can have reference only to
provisions such as the one in paranthesis in Clause 2
291
by which certain types of determination are left to the
administrative authorities concerned. [299B-C]
7. The question of any negligence or default on the part
of the contractor has many facets and to say that such an
important aspect of the contract cannot be settled by arbi-
tration but should be left to one of the contracting parties
might appear to have far reaching effects. In the instant
case, it is made clear that the decision regarding non
arbitrability is only on the question of any compensation
which the government might claim in terms of Clause 2 of the
contract. This is not an undefined power. The amount of
compensation is strictly limited to a maximum of 10 percent
and with a wide margin of discretion to the Superintending
Engineer. It is this power that is kept outside the scope of
arbitration. [299E, F, H; 300A]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1524 of
1982.
From the Judgment and Order dated 5.9.1977 of the Hima-
chal Pradesh High Court in F.A.O. No. 8 of 1975.
A.B. Rohtagi, Mrs. Urmila Kapoor, Miss S. Janani and
Naresh K. Sharma for the Appellant.
Miss A. Subhashini for the Respondents.
The Judgment of the Court was delivered by
RANGANATHAN, J. The appellant Vishwanath Sood undertook
the construction of a Farmers’ Community Centre Building at
Thanedhar by an agreement entered into with the Union of
India and the State of Himachal Pradesh dated 20.6.1968.
Certain disputes arose between the parties to the agreement
and in terms of clause 25 of the agreement, they were re-
ferred to a sole arbitrator. The contractor submitted a
claim of Rs. 1,28,000 while the respondents also submitted a
counter-claim. By an award dated 20.3.1972, the abritrator
awarded an amount of Rs.31,932 to the contractor and a sum
of Rs.21,504 to the respondents. The award was filed in the
court. The contractor filed an application in the court for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 10
modification or correction of the award in respect of three
items of his claim ( 1, 8 and 9) and item no. 1 of the
respondent’s counter claim. The Department also filed its
objections to the award and prayed that a sum of Rs.8,080.29
should be awarded in favour of the Department or the award
remitted to arbitrator. The
292
learned single Judge dismissed the objections of the re-
spondents. So far as the appellant’s prayers were concerned,
he allowed the same only in respect of item 1 of the re-
spondent’s counter claim. He held that the arbitrator was
not justified in granting to the Government a sum of
Rs.20,000 against the contractor. Both the contractor and
the respondents preferred appeals to the Division Bench. The
Bench reversed the order of the learned single Judge. It set
aside the order of the learned single Judge in so far as the
sum of Rs.20,000 was deleted thereby from the award of the
arbitrator. The award was restored to its original terms and
the contractor was held entitled to interest at 6 per cent
on the amount found due to him after adjusting the sum
awarded by the arbitrator in favour of the Government
against the sum awarded in favour of the contractor.
The contractor has preferred this appeal by special
leave from the order of the Division Bench of the High
Court.
Learned counsel for the appellant pressed the conten-
tions in respect of the four items to which he had objected
before the learned single Judge and the Division Bench.
Three of these items pertain to the claims put forward by
the contractor which were rejected by the arbitrator and
held by the courts to have been rightly rejected. The first
claim (item no. 1) made by the contractor was of a sum of
Rs. 12,720 which, according to him, was the loss incurred by
him by reason of the Department’s delay in handing over the
site to him for executing the contract. The learned single
Judge discussed this aspect of the matter at length. He
observed that, on this point, there was, on the one hand,
oral evidence adduced on behalf of the Department while
there was only the bare denial of the contractor on the
other. He pointed out that the arbitrator had fully consid-
ered the matter and that it was not open to the court to
re-assess the evidence and that there was no error apparent
on the face of the record. The second claim (item no. 8) was
for a sum of Rs.6,172 being the amount kept as security with
the respondent. In respect of this item also the learned
single Judge discussed the evidence which showed that the
security amount had been properly adjusted by the Department
which had been constrained to take up the work departmental-
ly at the cost and risk of the contractor. He held that this
was an aspect which had been considered by the arbitrator
and a proper conclusion arrived at. The third claim put
forward by the petitioner (item no. 9) was for a sum of
Rs.30,000, claimed as compensation for an amount spent by
the contractor for the purchase of a truck for this work.
The learned single Judge here again pointed out that no
material had been placed before
293
the arbitrator by the contractor to show that he was enti-
tled to the amount and that, in any event, having regard to
the fact that the work was executed by the Department at the
cost and risk of the contractor, there was no question of
the contractor preferring any claim in respect of this item.
The above three claims of the petitioner were also rejected
by the Division Bench which pointed out that the award made
by the arbitrator was not a speaking award and that the face
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 10
of the award did not show any error. We do not think that so
far as these claims are concerned, that the appellant has
any arguable case at all. As pointed out by the Division
Bench of the High Court, the award was a non-speaking award.
The arbitrator had considered the materials placed before
him and had arrived at his conclusions. The award does not
on the face of it disclose any error, much less any error of
law, which needs to be set fight. We therefore, hold that
the High Court was justified in affirming the award so far
as the rejection of these three claims is concerned.
The position in regard to the counter claim of the
respondents which was allowed by the arbitrator and the
Division Bench stands on a different footing. The respond-
ents’ claim before the arbitrator was that they were enti-
tled to receive from the contractor "Rs.24,000 on account of
payment of 10 per cent compensation on the tendered amount
for not executing the work in accordance with the terms and
conditions of the agreement". As against this claim the
arbitrator awarded the respondents a sum of Rs.20,000. The
learned single Judge took the view that having regard to
clause 2 of the contract (pertaining to the claim by the
respondent) read with clause 25 it was clear that any com-
pensation under clause 2 could be adjudicated upon only by
the superintending Engineer or the Development Commissioner
and that it was not open to the arbitrator to have entered
upon a reference in regard to this claim at all. In order to
appreciate the finding of the learned single Judge it will
be useful to set out clauses 2 and 25 of the conditions of
contract on which his decision was based:
"Clause 2: Compensation for delay: The time
allowed for carrying out the work as entered
in the tender shall be strictly observed by
the contractor and shall be deemed to be the
essence of the contract on the part of the
contractor and shall be reckoned from the
fifteenth day after the date on which the
order to commence the work is issued to the
contractor. The work shah throughout the
stipulated period of the contract be proceeded
with all due diligence and the contractor
shall pay as compensation an amount
294
equal to one per cent, or such smaller amount
as the Superintending Engineer (whose decision
in writing shall be final) may decide on the
amount of the estimated cost of the whole work
as shown in the tender for every day that the
work remains uncommenced, or unfinished, after
proper dates. And further, to ensure good
progress during the execution of the work, the
contractor shall be bound in all cases in
which the time allowed for any work exceeds,
one month (save for special jobs to complete
one-eighth of the whole of the work before
one-fourth of the whole time allowed under the
contract has elapsed; three-eighth of the
work, before one-half of such time
has elapsed, and threefourth of the work,
before three-fourth of such time has elapsed.
However, for special jobs if a time-schedule
has been submitted by the Contractor and the
same has been accepted by the Engineer-in-
charge, the contractor shall comply with the
said time-schedule. In the event of the con-
tractor failing to comply with this condition,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 10
he shall be liable to pay as compensation an
amount equal to one per cent or such smaller
amount as the Superintending Engineer (whose
decision in writing shall be final) may decide
on the said estimated cost of the whole work
for every day that the due quantity of work
remains incomplete; provided always that the
entire amount of compensation to be paid under
the provisions of this clause shall not exceed
ten per cent, on the estimated cost of the
work as shown in the tender."
"Clause 25: Settlement of disputes by Arbitra-
tion: Except where otherwise provided in the
contract, all questions and disputes relating
to the meaning of the specifications, designs
drawings and instructions hereinbefore men-
tioned and as to the quality of workmanship or
materials used on the work or as to any other
question, claim, matter or thing whatsoever,
in any way arising out of or relating to the
contract, designs, drawings, specifications,
estimates, instruction, order, or these condi-
tions or otherwise concerning the works or the
execution or failure to execute the same
whether arising during the progress of the
work or after the completion or abandonment
thereof shall be referred to the sole arbitra-
tion of the person appointed by the Chief
Engineer, Himachal Pradesh Public Works De-
partment ........ "
295
The Division Bench did not agree with the view of the
learned single Judge. It pointed out that, while in the
ordinary course, the rate of compensation payable by the
contractor is one per cent of the amount of the estimated
cost of the whole work, under clause 2, the Superintending
Engineer is authorised to depart from this figure and deter-
mine the compensation at a smaller amount if there are any
extenuating circumstances in favour of the contractor. The
question however was whether the compensation determined
under clause 2 is excluded from the scope of arbitration
under clause 25. The Division Bench answered this question
in the negative. It pointed out that the sine qua non of
clause 2 was that the contractor should have been guilty of
delay in commencing the work or in completing it but the
clause did not specify either the authority or the procedure
for determining whether the contractor is responsible for
the default. Observing that there can be a serious dispute
in a particular case as to the person who is responsible for
the delay, the Bench took the view that the determination of
this dispute cannot be excluded from the scope of clause 25.
The Bench observed that inasmuch as a bona fide dispute can
be raised by the contractor in regard to his liability to
compensation under clause 2 and no machinery is provided in
clause 2 for the resolution of that dispute, there is ample
justification for holding that resort can be had to arbitra-
tion under clause 25. The statement in clause 2 that the
decision of the Superintending Engineer is final, according
to the Bench, merely constituted a declaration that no
officer in the Department could disturb his quantification.
But this finality cannot be construed as extending to ex-
clude the jurisdiction of the arbitrator under clause 25. On
this view of the matter, the Division Bench found itself
unable to agree with the learned single Judge that the
arbitrator had traveled outside his jurisdiction in awarding
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 10
a sum of Rs.20,000 as compensation to the Government against
the contractor for the delay in executing the work.
It will be seen from the narration above that so far as
this item was concerned, both parties proceeded on the
footing that the claim of the Government was a claim under
clause 2 and that the arbitrator had awarded the sum only in
terms of clause 2. This is also borne out by the fact that
the claim of the Department was based on a percentage of the
total cost of the work and the restriction of the claim to
10% also appears to have been the result of the proviso to
clause 2. The award, therefore, on a fair reading of it,
contains a grant by the arbitrator of compensation to the
Government in terms of clause 2. It is therefore open to the
parties to urge before this Court, as they did before the
High Court also, that, on a proper construction of clauses 2
and 25,
296
this award was not justified. It is in this respect that
this counter claim of the Department stands on a different
footing from the earlier claims of the contractor which have
been rejected and which, we have held above, have been
rightly rejected.
Learned counsel for the appellants contends that the
terms of clause 2 clearly envisage the determination of the
amount of compensation for the delay in the execution of the
work only by the Superintending Engineer and specifically
mentions that the decision of the Superintending Engineer in
writing shah be final. The opening words of clause 25:
"Except where otherwise provided in the contract" clearly
take out of the purview of clause 25 any dispute in respect
of a claim under clause 2. He submitted that the clause
authorised only the Superintending Engineer to go into the
question whether there is any delay or not and the reasons
therefore and to determine the rate at which compensation
should be charged from the contractor. If the Engineer-in-
charge levies a compensation under clause 2, the contractor
can apply to the Superintending Engineer. If the Superin-
tending Engineer finds that there was no fault on the part
of the contractor at all he could waive the compensation
under clause 2 and that cannot be challenged by the Depart-
ment before the arbitrator. Per contra, where the Superin-
tending Engineer confirms that there has been a delay for
which compensation should be charged, it will not be open to
the contractor to challenge the conclusion before the arbi-
trator. Learned counsel also submitted that even if clause
25 were to be held applicable, the question of submitting a
dispute in this regard to the arbitrator could only arise if
there had been a determination and a dispute under clause 2.
Clause 2 envisages that the Engineer-in-charge should, in
appropriate cases, levy a compensation at the rate specified
in that clause. If he did, it was open to the contractor to
dispute the same and approach the Superintending Engineer to
reduce or waive the compensation for any reason whatsoever.
Or, it may be that, even where the Engineer-in-charge levied
no compensation, the Superintending Engineer could, either
on his own motion or on being moved by the department, after
considering the facts charge a compensation with the quantum
of which the department may not be satisfied in which event
a dispute could arise. But in the present case neither the
Engineer-in-charge nor the Superintending Engineer had
determined any liability at all under clause 2. There was no
compensation levied against which there was any protest by
the contractor, and there was no matter submitted to the
Superintending Engineer for determination. In these circum-
stances, the submission of the learned counsel for the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 10
appellant is that there was no dispute at all between the
parties on
297
the question of compensation and that a dispute cannot be
said to arise merely because a counter claim is for the
first time put forward by the Department before the arbitra-
tor.
On the other hand, the learned counsel for the Depart-
ment contended that clause 2 is in the nature of a penal
clause which automatically takes effect irrespective of any
default. He described it as an "agreed penalty" clause. He
stated that the clause made the contractor liable for the
penalty prescribed therein whenever there was a delay in the
completion of the contract, whatsoever might have been the
reason therefore, the question as to whether the contractor
was at default or not being totally immaterial. The Depart-
ment was, therefore, entitled to automatically deduct from
the bills payable to the petitioner the compensation or
penalty at the rate mentioned in clause 2 or such reduced
amount as may be determined in a particular case by the
Superintending Engineer and that if the contractor objected
to this deduction that would give rise to a dispute which
can be the subject matter of arbitration under clause 25. He
therefore submitted that the Division Bench has rightly
construed the terms of the contract and confirmed the award
made by the arbitrator.
We have gone through the judgment of the Division Bench
of the High Court and we have also considered the arguments
advanced on both sides. With great respect, we find our-
selves unable to agree with the interpretation placed by the
Division Bench on the terms of the contract. Clause 2 of the
contract makes the time specified for the performance of the
contract a matter of essence and emphasises the need on the
part of the contractor to scrupulously adhere to the time
schedule approved by the Engineer-in charge. With a view to
compel the contractor to adhere to this time schedule, this
clause provides a kind of penalty in the form of a compensa-
tion to the Department for default in adhering to the time
schedule. The clause envisages an amount of compensation
calculated as a percentage of the estimated cost of the
whole work on the basis of the number of days for which the
work remains uncommenced or unfinished to the prescribed
extent on the relevant dates. We do not agree with the
counsel for the respondent that this is in the nature of an
automatic levy to be made by the Engineer-in charge based on
the number of days of delay and the estimated amount of
work. Firstly, the reference in the clause to the require-
ment that the work shall throughout the stipulated period of
the contract be proceeded with due diligence and the refer-
ence in the latter part of the clause that the compensation
has to be paid "in the event of the contractor failing to
comply with" the prescribed time
298
schedule make it clear that the levy of compensation is
conditioned on some default or negligence on the part of the
contractor. Secondly, while the clause fixes the rate of
compensation at 1 per cent for every day of default it takes
care to prescribe the maximum compensation of 10 per cent on
this ground and it also provides for a discretion to the
Superintending Engineer to reduce the rate of penalty from 1
per cent. Though the clause does not specifically say so, it
is clear that any moderation that may be done by the Super-
intending Engineer would depend upon the circumstances, the
nature and period of default and the degree of negligence or
default that could be attributed to the contractor. This
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 10
means that the Superintending Engineer, in determining the
rate of compensation chargeable, will have to go into all
the aspects and determine whether there is any negligence on
the part of the contractor or not. Where there has been no
negligence on the part of the contractor or where on account
of various extraneous circumstances referred to by the
Division Bench such as vis major or default on the part of
the Government or some other unexpected circumstance which
does not justify penalising the contractor, the Superintend-
ing Engineer will be entitled and bound to reduce or even
waive the compensation. It is true that the clause does not
in terms provide for any notice to the contractor by the
Superintending Engineer. But it will be appreciated that in
practice the amount of compensation will be initially levied
by the Engineer-in-charge and the Superintending Engineer
comes into the picture only as some sort of revisional or
appellate authority to whom the contractor appeals for
redress. As we see it, clause 2 contains a complete machin-
ery for determination of the compensation which can be
claimed by the Government on the ground of delay on the part
of the contractor in completing the contract as per the time
schedule agreed to between the parties. The decision of the
Superintending Engineer, it seems to us, is in the nature of
a considered decision which he has to arrive at after con-
sidering the various mitigating circumstances that may be
pleaded by the contractor or his plea that he is not liable
to pay compensation at all under this clause. In our opinion
the question regarding the amount of compensation leviable
under clause 2 has to be decided only by the Superintending
Engineer and no one else.
The Division Bench has construed the expression in
clause 2 in parenthesis that "the Superintending Engineer’s
decision shall be final" as referring only to a finality qua
the department; in other words, that it only constitutes a
declaration that no officer in the department can determine
the quantification and that the quantum of compensation
levied by the Superintending Engineer shall not be
299
changed without the approval of the Government. After refer-
ring to certain judicial decisions regarding the meaning of
the word "final" in various statutes, the Division Bench
concluded that the finality cannot be construed as excluding
the jurisdiction of the arbitrator under clause 25. We are
unable to accept this view. Clause 25 which is the arbitra-
tion clause starts with an opening phrase excluding certain
matters and disputes from arbitration and these are matters
or disputes in respect of which provision has been made
elsewhere or otherwise in the contract. These words in our
opinion can have reference only to provisions such as the
one in parenthesis in clause 2 by which certain types of
determinations are left to the administrative authorities
concerned. If that be not so, the words "except where other-
wise provided in the contract" would become meaningless. We
are therefore inclined to hold that the opening part of
clause 25 clearly excludes matters like those mentioned in
clause 2 in respect of which any dispute is left to be
decided by a higher official of the Department. Our conclu-
sion, therefore, is that the question of awarding compensa-
tion under clause 2 is outside the purview of the arbitrator
and that the compensation, determined under clause 2 either
by the Engineer-in-charge or on further reference by the
Superintending Engineer will not be capable of being called
in question before the arbitrator.
We may confess that we had some hesitation in coming to
this conclusion. As pointed out by the Division Bench, the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 10
question of any negligence or default on the part of the
contractor has many facets and to say that such an important
aspect of the contract cannot be settled by arbitration but
should be left to one of the contracting parties might
appear to have far reaching effects. In fact, although the
contractor in this case might object to the process of
arbitration because it has gone against him, contractors
generally might very well prefer to have the question of
such compensation decided by the arbitrator rather than by
the Superintending Engineer. But we should like to make it
clear that our decision regarding non arbitrability is only
on the question of any compensation which the Government
might claim in terms of clause 2 of the contract. We have
already pointed out that this is a penalty clause introduced
under the contract to ensure that the time schedule is
strictly adhered to. It is something which the Engineer-
incharge enforces from time to time when he finds that the
contractor is being recalcitrant, in order to ensure speedy
and proper observance of the terms of the contract. This is
not an undefined power. The amount of compensation is
strictly limited to a maximum of 10% and with a wide margin
of discretion to the Superintending Engineer, who might not
only reduce the percentage but who, we think, can even
reduce it
300
to nil, if the circumstances so warrant. It is this power
that is kept outside the scope of arbitration. We would like
to clarify that this decision of ours will not have any
application to the claims, if any, for loss or damage which
it may be open to the Government to lay against the contrac-
tor, not in terms of clause 2 but under the general law or
under the Contract Act. As we have pointed out at the very
outset so far as this case is concerned the claim of the
Government has obviously proceeded in terms of clause 2 and
that is the way in which both the learned single Judge as
well as the Division Bench have also approached the ques-
tion. Reading clauses 2 and 25 together we think that the
conclusion is irresistible that the amount of compensation
chargeable under clause 2 is a matter which has to be adju-
dicated in accordance with that clause and which cannot be
referred to arbitration under clause 25.
As stated earlier, an alternative ground was urged by
the learned counsel for the appellant that, no penalty under
clause 2 having been imposed by the respondents in the first
instance, no dispute had at all arisen which could have been
referred to arbitration. This point was not taken before the
High Court and the relevant facts are not on record. That
apart, in the view we have taken, it is unnecessary to
express any opinion on this argument and we refrain from
doing so.
For the reasons above mentioned, we restore the judgment
of the learned single Judge. In the result, the amount of
compensation of Rs.20,000 awarded by the arbitrator in
favour of the Government will stand deleted. The amount of
interest payable to the contractor, if any, will be worked
out on the basis of the award as modified by us above.
The appeal is allowed. We however make no order as to
costs in the circumstances of the case.
N.V.K. Appeal allowed.
301