Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
PETITIONER:
SMT.GOWRAMMA
Vs.
RESPONDENT:
LAO-CUM-MANDAL REVENUE OFFICER,PARTI RANGAREDDY DISTRICT
DATE OF JUDGMENT: 22/03/1996
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
G.B. PATTANAIK (J)
CITATION:
1996 SCALE (3)683
ACT:
HEADNOTE:
JUDGMENT:
WITH
CIVIL APPEAL NO. 6952-53 & 6948-51 OF 1996
------------------------------------------
(Arising out of SLP(C) Nos. 14686-87, and 16244-47 of 1994)
O R D E R
Leave granted.
Notification under Section 4(1) of the Land Acquisition
Act, 1894 (for short, the ’Act’) was published on August
29,1989 acquiring an extent of 9 acres 25 guntas of land in
Pargi Town, Ranga Reddy District in the State of Andhra
Pradesh for public purpose, namely, to provide house sites
to the weaker sections. Possession of the land was taken on
June 5, 1986 pursuant to an earlier notification which had
lapsed for failure to pass the award. The Land Acquisition
Officer in his award dated May 25, 1990 determined the
compensation @ Rs.7500/- per acre in respect of some lands
and Rs.15,000/- per acre in respect of other lands and in
addition granted Rs.5,000/- for well. On reference under
Section 18, the Subordinate Judge Vikarabad in his award and
decree dated February 12, 1992 determined the compensation a
Rs. 36/- per sq. yd. He determined the value of the well at
Rs. 18,100/- Both the State as well as the claimants filed
appeals in the High Court. In three different sets of
appeals the different Division Benches followed the judgment
of a learned single Judge of that Court in Ex.A-2 in which
Rs.11/- per sq.yd. was determined as compensation after
deductions and the same was proportionately increased to
Rs.22/- per sq.yd. due to time lag. Accordingly appeals of
the State were allowed and that of the claimants were
dismissed in A.S. Nos.2030/92 & A.S. No. 2597.>92 dated
8.9.93 and another judgment in A.S.No. 2024/92, 2028/92,
1662 & 1663/93 & A.S. Nos.2029/92 dated 16.9.93. Thus these
appeals by special leave.
Shri R. Venugopal Reddy, the learned senior counsel
appearing for the appellants contended that the reasoning
adopted by the Division Benches of the High Court is not
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
correct in law. According to the learned counsel, the lands
covered in the judgments under Ex.A-3 Ex.A-4 and Ex. A-5, in
addition to Ex.A-2 also offer comparable basis for
determination of the compensation The notifications therein
were issued during period from 1976 to 1982. The different
higher rates of compensation have been granted by the High
Court in the appeals, The Division Bench, therefore, was not
right in relying upon Ex.A-2 along as a basis and reducing
the compensation to Rs.22/- per sq.yd. he has placed before
us the site plan marked in the case as Ex.A-1. From a
perusal of the site plan, it is seen that the lands bearing
survey No. 18 is adjacent to the lands bearing Survey Nos.
24,/2 which are the subject matter of the acquisition under
Ex.A-2. The notification under Ex.A was dated 13.4.1979. A
learned single Judge of the high Court after taking into
consideration the situation of the lands and the
development, reduced the compensation to 50% of the
compensation towards developmental charges and determined
the compensation at Rs.11/- per sq.yd. that order has become
final. Therefore, the Division Bench has rightly placed
reliance upon that judgment and in view of the time lag
between the date of the notification under Ex.A-2 and the
date of the notification in these cases has proportionately
increased the compensation and fixed the market value at the
rate of Rs.22/- per sq.yd after due deductions The lands
under Ex.A-3 and Ex.A-4 are situated far away from the lands
covered in Survey No. 18. Therefore, the High Court was
right in not placing reliance on those judgments. Therefore,
we find that there is no justification for further increase
in respect of the lands covered in first set of appeals. But
with regard to the lands in Survey No. 271/2, 272/2 and
276/2, we find that there is no justification in awarding
the same compensation at Rs.22/- per square yard. It is seen
that these lands are situated on the main road and in
developed area. Though Mr. R. Venugopal Reddy, the learned
senior counsel repeatedly placed reliance on the judgments
of the courts in relation to Ex.A-3 and Ex.A-4, we do not
find that they do offer any comparable basis to determine
the compensation. But one important factor to be taken note
of is that the Land Acquisition Officer himself made a
distinction between the lands covered in Survey Nos. 18 &
20. While granting compensation @ Rs.7500/-, he had granted
double the rate to these lands, namely, Rs.15,000/- per
acre. In other words, he had taken the potential value of
these lands into consideration. It is seen that though there
was not much development except partial development in the
neighborhood, these lands having been situated on the main
road and abutting the developed area, on the facts and
circumstances, we think that there should be a uniform rate
of Rs.30/- per sq.yd.
Accordingly, the appeals and S.L.P.(C) Nos. 14244-14245
& 14686-14687/94 are dismissed and appeals and S.L.P.(C)
Nos.16244-16247/94 are allowed and the market value is
determined at Rs.30/- sq.yd. in respect of all the lands.
The claimants are entitled to the benefits under Sections
28, 23(2) and 23(1-A) of the Act of the enhanced solatium,
interest and additional amount @ 9% p.a. for one year and @
15% p.a. thereafter, from the date of taking possession till
date of the award. No costs.