Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Arbitration Petition 1 of 2006
PETITIONER:
SEDCO FOREX INTERNATIONAL DRILLING INC
RESPONDENT:
THE OIL & NATURAL GAS CORPORATION LTD
DATE OF JUDGMENT: 20/04/2006
BENCH:
S.H. KAPADIA
JUDGMENT:
JUDGMENT
O R D E R
Applicant is a foreign company incorporated in
Panama. It is engaged in providing rigs on charter-
higher basis for offshore drilling.
In April, 1988, the rig was brought into India.
It operated in territorial waters, continental shelf
and other maritime zones.
Under the contract dated 23.8.1988, ONGC
(non-applicant) is liable to reimburse the applicant
for customs duty paid on import of rig. This is
under clause 15.5 of the contract. Under this
clause, ONGC is liable to reimburse/pay all
customs duty payable on the rig.
In July 1999, the customs department issued
a show-cause notice to the applicant and to the
non-applicant, in which it alleged that customs
procedure had not been followed for the initial entry
of rig in 1988.
By order dated 27.1.2000, the commissioner of
customs held that the import of the rig had taken
place in 1988 and on several occasions thereafter
and that the duty was payable on the rig in respect
of its movement to a designated platform in 1988.
Aggrieved by the adjudication order, the
applicant herein preferred an appeal to the
Customs, Excise and Service Tax Tribunal (for short
"the tribunal"). By order dated 2.2.2001, the
tribunal came to the conclusion that the duty was
payable on the import in 1988 on a value of US$ 13
million; that, in the absence of an essentiality
certificate, the applicant was not entitled to
exemption under notification no.516/86. However,
the tribunal permitted the applicant herein to
pursue its claim for the essentiality certificate.
Applicant had imported the rig without filing of the
bill of entry.
Suffice it to state that in February 2001, the
applicant made payment of the customs duty
amounting to Rs.26,67,94,320/-. This was in
accordance with the order of the tribunal.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
On the strength of the essentiality certificate,
the applicant applied for refund of the customs duty
paid by the assessee. However, by order dated
1st/4th February, 2002, the additional commissioner
of customs rejected the claim for refund.
On 11.2.2002, the applicant called upon the
ONGC to reimburse the applicant with the said
amount of Rs.26,67,94,320/-. ONGC responded by
letters dated 20.3.2002 and 13.6.2002 denying its
liability to reimburse the customs duty paid.
Ultimately, vide letter dated 31.3.3003, the
applicant herein invoked the arbitration clause 28.0
and suggested that the dispute be referred to
arbitration. By the said letter, the applicant
appointed its nominee on the Arbitral Tribunal and
called upon the ONGC to appoint its nominee, so
that both the arbitrators could jointly appoint a
third arbitrator.
It is not necessary, at this stage, to go into the
chequered history of the earlier round of litigation
and the circumstances under which the non-
applicant did not agree to the continuance of the
proceedings before the duly constituted Arbitral
Tribunal. Suffice it to state, that the applicant had
called upon the non-applicant to appoint its
nominee to the Arbitral Tribunal, failing which it
has been constrained to move this application for
appointment of an arbitrator to the Arbitral
Tribunal to decide the disputes referred to
arbitration under the 1988 contract by applicant
vide its letter dated 31.3.2003.
By way of counter affidavit, the ONGC has
inter alia contended that the applicant is estopped
from moving this arbitration application because
ONGC had issued the essentiality certificate to
enable the applicant to seek refund of the customs
duty already paid; that, the certificate was issued
as far back as 21.12.2001 and that the same was
handed over to the applicant to enable them to avail
of the exemption as provided under notification
no.516/86 dated 30.12.1986, as amended from
time to time. ONGC contends by its counter
affidavit that non-utilization of the essentiality
certificate is a matter between the applicant and the
customs department in which ONGC has no role to
play. At this stage, it may be stated that till today,
the respondent has not received the revalidated
essentiality certificate from the office of the Director
General of Hydrocarbons, New Delhi. In the
circumstances, ONGC has denied the demand of the
applicant for arbitration.
On the factual aspect, my attention is invited
to the judgment of the Division Bench of the
Bombay High Court dated 22.3.2006 in writ petition
No.481/2001 filed by the applicant herein against
the customs department in the matter of
computation of duty paid on the value of the rig as
it existed in 1988. This writ petition was essentially
on the working out of the liability. By the said
judgment, the High Court has directed the customs
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
department to compute the duty liability to the
assessee in terms of para 48 of the judgment of the
tribunal. By the said judgment, the additional
commissioner of customs is directed to assess the
duty liable as per the order of the tribunal dated
2.2.2001 treating the import of the rig in 1988
having the value of US$ 13 million. By the said
judgment, the High Court left it open to the
applicant to claim its entitlement under the
essentiality certificate before the additional
commissioner of customs, who is directed to pass
appropriate orders in that regard. Till today, the
decision of the additional commissioner is awaited.
On the above facts, it is argued on behalf of
the non-applicant that the matter is pre-mature,
particularly, when the additional commissioner of
customs has not pronounced its decision on the
entitlement of the applicant under the essentiality
certificate and, therefore, invocation of the
arbitration clause by the applicant was pre-mature
and consequently, the application under section
11(4) of the Arbitration & Conciliation Act, 1996 is
not maintainable.
In the present case, the applicant has paid
customs duty amounting to Rs.26,67,94,320/- as
far back as February 2001. It seeks reimbursement
of the duty paid in terms of the contract. The
applicant has invoked the arbitration clause as far
back as 31.3.2003. The accrual of liability, as a
concept, is different from quantification of the
liability. In the present case, the liability to pay
customs duty has accrued. In the circumstances, it
cannot be said that the application under section
11(4) of the Arbitration & Conciliation Act, 1996 is
pre-mature.
Accordingly, Hon’ble Mrs. Justice Sujata V.
Manohar (retired) and Hon’ble Mr. Justice V. N.
Khare (former CJI) are appointed as Arbitrators to
decide all disputes and differences between the
parties. The two arbitrators shall appoint an
umpire in terms of clause 28.0 of the contract.
Learned arbitrators may fix their own terms
and conditions as to their remuneration.
As far as fixing of date of hearing is concerned,
liberty is given to the parties to approach the
arbitrators, who will decide the due date according
to their convenience.
The arbitration petition is accordingly disposed
of.