Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 8094 OF 2002
A.P. Electricity Regulatory Commission … Appellant
Versus
M/s. R.V.K. Energy Pvt. Ltd. and another … Respondents
WITH
CIVIL APEPAL NOS. 8101, 8102, 8096,
8095 AND 8093 OF 2002
J U D G M E N T
S.B. SINHA, J.
2
Interpretation and/or application of the provisions of the Andhra
Pradesh Electricity Reforms Act, 1998 (for short the 1998 Act) vis-a-vis
the orders passed by the Andhra Pradesh Electricity Regulatory
Commission (for short ‘the Commission’) are involved in these appeals
which arise out of the judgments and orders passed by a Division Bench
of the Andhra Pradesh High Court.
The matter relating to generation, supply and distribution of
electrical energy in the State of Andhra Pradesh used to be governed by
the provisions of the Electricity (Supply) Act, 1948 (For short, the 1948
Act).
With a view to bring reforms in the Power Sector and to meet
shortages in power supply, the State of Andhra adopted a policy decision
for generation of power through MPPs of 30 MW capacity in private
sector. For the said purpose it issued two G.Os. being G.O. No.116 dated
th th
5 August, 1995 and G.O. No. 152 dated 29 November, 1995.
In the said Government orders, the liberalization policy of the state
in respect of its industrial economy so as to enable the State Government
to attract investment from other parts of the country as also from outside
3
the country was highlighted. It intended to bring about competition in
the industry. It is stated to have taken a series of measures for
augmenting power including privatization. It took into consideration the
fact that the power plants costing less than Rs.100 crores and which do
not require Central Electricity Authority’s clearance, and in respect of
which project clearance at the State level would suffice as a result thereof
the period may be reduced considerably.
th
The relevant extract of G.O. No.116 dated 5 August, 1985 reads :-
“The state government have therefore felt that it
would be appropriate to setup mini power
plants based on residual fuels in the industrial
estates to relieve the burden of the industrial
load centres and tail end areas which are
suffering from stress on account of
transmission and distribution problem.”
It further provided:
“The Government have also felt it necessary to
take up mini power plants of 30 MW capacity
which could be implemented within a period of
12-18 months at suitable locations where
industries are concentrated and the power
plants can meet the demand of industries
without any interruption.”
4
The G.O. further provided that the residual fuel shall be used and
that the pricing arrangement was subject to fixation of tariff by the
Commission.
In this context, the supply of electricity generated by the MPP to
the identified consumers was allowed.
We, may, however, notice that at a later stage the capital costs
invested for the said purpose was raised to Rs.250 crores.
th
By G.O. Ms. No.152 dated 29 November, 1995 the terms and
conditions of setting up of MPPs were laid down, some of which read
thus :-
“3. Energy from the mini power plants can be
supplied to identified consumers using either
Andhra Pradesh State Electricity Board's
existing distribution network of setting up a
dedicated transmission after obtaining a licence
under section (3) of the Indian Electricity Act,
1910. In the case of the former, Andhra Pradesh
State Electricity Board may on request, lease
out the distribution net work to the developer.
Detailed arrangements like lease, rent etc., will
be worked out on mutually acceptable terms
between the Andhra Pradesh State Electricity
Board and the Mini Power plant developers.
Similar arrangement can also be finalised for
the dedicated net works established by Mini
5
Power Plant developers so as to confirm to
statutory requirement.
6. In the event of the mini power plants
generating power in excess of the requirement
of their consumers, the same can be purchased
by the Andhra Pradesh State Electricity Board.
Such purchases by the Andhra Pradesh State
Electricity Board may be upto 15% of
individual Mini Power Plant capacity. The
Andhra Pradesh State Electricity Board may
also purchase power beyond 15% of the Mini
Power Plant capacity, at Andhra Pradesh State
Electricity Board's option without conferring
any pre-emptive right of sale on the Mini Power
Plant. The price for supplies made to the
Andhra Pradesh State Electricity Board will be
weighted average price of purchase of power
made by the Andhra Pradesh state Electricity
Board from Central and other State Electricity
Enterprises on a monthly basis. Settlement of
accounts will be on a monthly basis. The above
procedure would be in force upto the end of
December 2000 AD and would be subject to
review thereafter.
8. The Mini Power Plant developer shall
necessarily sell power to the consumers above
the Board's High Tension tariff rate”
Indisputably, pursuant to or in furtherance of the said policy
decision, 31 companies in the private sector showed their interest for
setting up MPPs. The Government of Andhra Pradesh, upon taking into
consideration the said applications allowed the respondents herein to set
6
up MPPs capacity in private sector with residual fuel in industrial load
centres in the State, whereafter, approval for the same had been granted.
We may at this stage notice the fact of the mater involved in the
respective appeals including the proceeding before the Commission.
CIVIL APPEAL NO. 8093 OF 2002
Permission was granted to LVS Power Ltd. to set up a 37.8 MW
residual fuel based power plant at Visakhapatnam so as to enable it to
generate and supply power directly to specified industrial consumers by
using the existing transmission and distribution network of APT. In the
letter for grant of permission issued to LVS Power Ltd. by the Secretary
th
to the State Government letter dated 24 July, 1996. Clauses 1 and 4 of
the permission letter read :-
“1. The total completed cost of the project (MPP)
including the cost of land and the total EPC cost shall
not exceed Rs.100 crores”.
4. The copies of actual supply agreements with
the identified consumers shall be furnished to the
7
A.P. State Electricity Board in advance of
commencement of supply. Along with the
agreements, 3 months notices seeking termination of
the Agreements with the A.P. State Electricity Board
by the identified consumers of generating company,
if they so desire, shall be submitted to the A.P. State
Electricity Board.”
Alongwith the said letter it annexed the names of the consumers
with their possible demand, which read :-
“S.No. Name of the Consumer Demand
1. Hindustan Shipyard Ltd., Visakhapatnam 6,000 KVA
2. Hindustan Zinc Ltd., Visakhapatnam 22,000 KVA
3. Essar Steels Ltd., Visakhapatnam 40,000 KVA
4. Andhra Cements Ltd., Visakhapatnam 9,000
KVA
___________
77,000 KVA”
___________
All the aforementioned industries are located in the State of
Andhra Pradesh.
8
The proposal of the company was accepted in terms of Section
18A(a) of the 1948 Act.. The MPP was allowed to be operated on
multifuels (LSHS/Furnace Oil/Naptha) alongwith tie-line.
The terms and conditions of setting up of the MPP were amended
th th
from time to time in terms of letter dated 20 October, 1997; 18 May,
st
1999 and 21 August, 2001. We are not concerned with the details
thereof.
Pursuant to or in furtherance of the approval granted by the
Government of Andhra Pradesh to the company for setting up of MPP it
entered into Wheeling Agreement with APTRANSC wheeling power
from generating station to the consumers. In terms of the Wheeling
Agreement, the company was required to pay 8 % to 12 % of power
generated as wheeling charges to APTRANSCO for utilizing their
transmission lines. It also entered into Power Sales Agreements with 13
industrial consumers for sale of powers.
In the meantime in the year 1998, the Parliament enacted The
Electricity Reforms Act, 1998. The State of Andhra Pradesh also enacted
9
the 1998 Act; in terms whereof, Andhra Pradesh Electricity Regulatory
Commission (for short ‘the Commission’) was constituted on or about
rd
23 January, 2000.
Indisputably, after coming into force of the 1998 Act the MPPs
applied for grant of exemption under the said Act as envisaged in Section
14 thereof, before the Commission.
The said Act provided for grant of licence and the exemption
therefrom. The Company applied for grant of licence as provided in
th
Section 15 of the Act. By an order dated 18 May, 2000 the
Commission directed the company to come back to it for the said purpose
four months prior to the commencement of commercial operation. In
view of the said direction of the Commission, the company commenced
construction of the project in June, 2000. For the said purpose it drew
‘equity’ from the promoters and investors and term loans from the
lenders. The total cost of the project was said to be Rs.133 crores.
When the said plant was nearing completion, having regard to the
th
said direction dated 18 May, 2000, the company approached the
th
Commission on 5 March, 2001 as the project was expected to be
th
completed by July, 2001. The Commission, however, by a letter dated 4
10
May, 2001 informed the company that it was of the opinion that no third
party sale of power should be permitted and asked it to send specific
proposals to APTRANSCO for sale of entire power from the project
purported to be in terms of Central Government’s Notifications within
fifteen days.
It appears that before the Commission the Andhra Pradesh State
Electricity Board Engineers Association intervened. The said
intervention was entertained by the Commission.
The Commission noted that out of 31 MPPs which received
permission/sanctions of the State to generate energy based at residual
fuels, only 19 survived. The name of the respondent company was also
found therein. The Commission also noticed the essential features of the
grant of such permission, one of which being clause 5, which reads :
“(v) Copies of the supply agreements entered into
with the identified consumers should be supplied to
the APSEB. The agreement with the APSEB for
wheeling shall reflect the conditions in G.O.Ms.
No.152 dated 29.11.1995 besides other conditions.”
11
At paragraph 14 of the said order, the Commission recorded that
various Associations of the officers of the Andhra Pradesh State
Electricity Board inter alia submitted that third party right should not be
allowed as it affected the financial viability of the main licensee,
APTRANSCO, apart from the fact that they should not be permitted to
generate power with residual fuel as the same is too costly for the
purchase by the grid. It was also noted that third party sale should not be
allowed as MPPs would not suffer Transmission and Distribution losses
which the Licensee suffers and the Tariffs of the Licensee for industrial
consumers include considerable cross-subsidies.
The Government of Andhra Pradesh, was, however, not
represented. A contention, however, was raised by a letter representing
that the permission may be given to MPPs for third party sales to HT
Industrial consumers and in the event APTRNASCO loses on account of
the said arrangement, the Commission can fix appropriate wheeling
charges taking into account the cross subsidization forgone by
APTRANSCO on account of third party sales.
The Commission stated that it was not inclined to permit third
party sale for the following reasons :-
12
“(19). For reasons already stated elaborately in our
order in O.P. No.2/1999 (GBR Projects Ltd.) and O.P.
No.348/2000 (Astha Power Corporation Pvt. Ltd.) the
Commission is not inclined to permit third party sales.
Currently the tariffs include substantial cross subsidy
to the tune of about Rs.2,000 crores by industrial and
commercial consumers. If these consumers are
supplied power by MPPs, instead of the Licensee, the
cross subsidy element now existing will come down,
calling for increased tariffs for agriculture and
domestic consumers giving rise to a rate shock to
them or alternatively, the GoAP may have to bear the
increased burden in terms of subsidy. Further, to the
extent the government subsidy is limited the burden
of cross subsidy will increase on those industrial and
commercial consumers who stay with the Licensee.
This would in turn lead to these consumers going out
of the system as they would not be competitive for
their products in the market with such high tariffs.
Finally, the Licensee would be left with agricultural
and domestic consumers who are highly subsidized.
This would effect totally the viability of the Licensee
and will result in failure of Licensee to discharge its
functions in the matter of supply of power. It is,
therefore, evident that permitting mushroom growth
of MPPs and third party sales would not at all be in
the interest of the organized growth of the electricity
industry which is essential for the progress of any
civil society. Permitting third party sales would
create discrimination between industrial consumers
drawing power from IPPs and the industrial
consumers drawing power from APTRANSCO
DISCOMS who will be paying for power at different
rates. Further, the cost for supply of power for the
Licensee includes cross subsidization and
transmission and distribution losses in the system
spread over the entire State and approved by the
Commission whereas, the cost to the MPP developer
does not include cross subsidization and transmission
and distribution loss cost. Thus, allowing third party
13
sales by MPPs at the same rate at which the Licensee
supplies to HT consumers, would result in either
unjust enrichment of developers which is neither
contemplated nor permissible in a regulatory industry,
or in supply of power at lower prices than prescribed
resulting in differential prices for the same categories
of consumers, leading to discriminatory treatment.
(20) In O.P. No.2/1999 and O.P. No.348/2000, the
Commission has directed the developers to approach
APTRANSCO and negotiate the sale of power on the
basis of their project cost. It would be appropriate if
directions are also issued to the eight developers
mentioned in para 18 above to make an offer of price
on the basis of the various Government of India
Notifications (including the Notifications dated
30.03.1992). These Notifications set out the method
and manner of calculation of tariff for generating
companies mutually agree on the price for the pwer to
be supplied and other conditions, a PPA may be
drawn up and submitted to the Commission for its
approval under Section 21 of APER Act. If on the
other hand they are not able to agree on the price and
other terms and conditions, they may apply to the
Commission for appropriate orders.”
It noticed that pursuant to its interim order, the company had
th
entered into a Wheeling Agreement with APTRNASCO on 25 February,
1999. While directing renegotiations regarding price and other terms and
conditions at which they would be willing to supply power to APT it was
directed:-
“(22). The Commission hereby directs that the eight
MPPs mentioned above send a specific proposal in
writing based on the existing Central Government
14
Notifications on the basis of their project costs to
APTRANSCO within a fortnight of the receipt of this
order, with a copy to the Commission. APTRANSCO
shall respond by communicating views on the offer to
the MPPs and the Commission within another
fortnight. If the parties need more time for
negotiations in the matter, they are free to approach
the Commission in the matter. If APTRANSCO and
the MPPs agree on the price and the other terms and
conditions, a (fresh) PPWA may be drawn up and sent
for the consent of the Commission.
(23). If there is no agreement between APTRANSO
and the MPPs on supply terms within a month’s time,
the Commission will hear the eight MPPs and
APTRANSCO on 4.6.2001 for further orders.”
Pursuant to and in furtherance of the said order of the Commission
th
the Company submitted a proposal on or about 18 May, 2001 for sale of
its entire power from the project as per the norms laid down or set up by
the Central Electricity Authority alongwith necessary supporting
documents assuming the cost of the project at about Rs. 125 crores.
th
Negotiations took place inter alia on 17 August, 2001 when the
company agreed to the proposal of the APTRANSCO to sell power as
per the said norms assuming the project cost at Rs.125 crores. The said
proposal of the company was accepted in its entirety by the
APTRANSCO. According to it the tariff could be re-fixed after the
capital cost is approved by the Government of Andhra Pradesh
15
whereafter the consent of the Commission to purchase power from the
company was sought for.
The Commission accorded its consent to the said proposal by its
th
letter dated 18 August, 2001. Keeping in view the aforementioned
consent of the Commission on 24th August, 2001 the company
terminated the power sales agreements entered into by it with the
industrial consumers to avoid any liability
th
The project was completed on 18 October, 2001. APTRANSCO
asked for extension of time from the Commission to purchase power
th
from the company by its letter dated 30 November, 2001 till the end of
February, 2001 on the purported ground that firm proposal (PPA) could
not be sent since the project cost was yet to be approved by the
Government of Andhra Pradesh. A reminder was also sent by
th
APTRANSC on 9 November, 2001 to the Commission. The
th
Commission again by its letter dated 26 November, 2001 granted
permission sought for by APTRANSCO stating :-
“With reference to letter (1) and (2) cited above,
Commission accepts the proposal of APTRANSCO to
purchase power from M/s. LVS Power Limited at the
rates specified in letter (3) cited above and extends
the period of purchase of power from 31.10.2001 to
30.11.2001 purely as an interim measure. This is
16
without prejudice to the rights of the Commission to
pass any further order in this matter.
APTRANSCO is directed to send the Firm Proposal
with the approved Project cost from competent
Authority latest by 30.11.2001, for the Commission to
pass appropriate orders.”
th
On or about 26 November, 2001 by a letter addressed to the
Government of Andhra Pradesh, the APTRANSCO sought for its
approval of the project cost stating that it was willing to purchase power
from the company if the project cost was restricted to Rs.125 crores. As
the said consent was not forthcoming another extension was sought for
by the APTRANSCO from the Commission for purchase of power till the
rd
end of January, 2002 by its letter dated 3 December, 2001. The
th
Commission by its letter dated 27 December, 2001 directed the
APTRANSCO to submit firm proposal alongwith the approval of the
st
capital cost of the project from the competent authority by 31 January,
th
2001. The matter was posted for hearing on 7 February, 2002.
The Government of Andhra Pradesh in the meantime sought for
the opinion of the Central Electricity Authority as regards the
reasonableness of the project cost. It may be noticed that the Central
th
Electricity Authority by a letter dated 26 February, 2002 stated that the
17
capital cost of the company is lowest among the similar type of plants in
the country by observing :-
“Reference is invited to GOAP letter dated
29.12.2001 seeking the advice of CEA under Section
3 of Electricity (Supply) Act, 1948. The matter has
been examined based on the subsequent
details/clarifications received vide APTRANSCO
letters dated 28.1.2002 & 4.2.2002 and GOAP letter
dated 15.2.2002. The following observations are
made :
(i) Clarifications furnished vide GOAP letter dated 15.2.2002
do not indicate as to whether GOAP Order dated 29.11.1995
giving revised policy guidelines regarding generation of
power through Mini Power Plants in Private Sector had been
reviewed as contemplated in Para 6 of the said order w.r.t.
capital costs. Etc.
(ii) It is seen that the clarification on the increase in capial cost
ceiling from Rs.100 crores as earlier contemplated to Rs.250
crores was given to M/s. LVS only w.r.t. their request. It is
not clear whether all the MPP developers were informed of
this increase in capital cost ceiling and whether any
reference is made to capacity of the plant to be generated
within the capital cost of Rs.250 crores.
(iii) The capacity of the LVS plant has been reduced from 55
MW as originally approved in July, 1996 to 46.08 MW vide
GOAP letter dated 9.7.1997 and again to 37.8 MW vide
GOAP letter dated 11.4.2001 whereas the capital cost
ceiling was increased from Rs.100 crores as originally
approved in July, 1996 to Rs.250 crores in January, 1999.
The compulsions for reduction in plant capacity are not clear
from the documents received from GOAP/APTRANSCO.
(iv) The APTRANSCO’s consultant had in their report indicated
that revised capital copst of Rs.125.23 crores for 2 x 18.9
MW was without complete audit of the cost incurred and
18
physical verification. As now the project has been
completed, it will be necessary to look into the final audited
cost corrected to the admissible provisions.
In view of the above mentioned observations, it is not
possible for CEA to advise on the reasonableness of
the capital cost specific to LVS project. It may,
however, be mentioned that CEA, while granting TEC
for similar type of projects for IPPs have cleared the
estimated completion capital cost in the range of
Rs..3.62 crores to Rs.3.8 crores per MW as the ceiling
cost depending on the scope of work, site specific
features, financial package, debt-equity ratio,
exchange rate, taxes and duties, foreign exchange etc.
GOAP may please take further action based on the
above.”
In the meanwhile, the APTRANSCO informed the Commission by
th
its letters dated 6 February, 2002 that the plant may have to be backed
down on account of high tariff cost as such the company may be advised
to sell the power outside the State by paying wheeling charges as per the
th
order of the Commission. The matter was heard on 7 February, 2002.
APTRANSCO took a complete turn around stating that it was unable to
purchase power on the ground that the plant may have to be backed down
in the merit order dispatch due to high variable cost. A protest was made
nd
thereto by the company in terms of its order dated 22 February, 2002.
The discussion was held between the Managing Director of the Company
nd
and the Chief Engineer of APTRANSCO on 22 March, 2002 when the
19
company agreed to the demands of APTRANSCO for reduction in the
cost of power to prevent further losses to the investors and the lenders.
APTRANSCO increased the wheeling charges four fold.
It may, however, be noticed that the Commission by its order dated
rd
23 April, 2002 observed :-
“At the hearing the applicant argued that it had
always complied with the orders of the APERC
and on-off-on attitude of ANTRANSCO was
very confusing not only to LVS but also to
other energy developers and the credibility of
APTRANSCO and GoAP was at stake. It
requested the APTRANSCO should be directed
to enter into PPA on the basis of the latest
negotiations. On the other hand, Shri
Manmohan Rao, CE, APTRANSCO, stated the
APTRANSCO is unable to buy power as the
purchase cost might not pass muster in the
merit order and APTRANCO might not be able
to buy any power from LVS and end up only
paying fixed charges, even if a PPA is entered
into.”
The Commission for all intent and purport took a policy decision
that the electricity generated by the company would be transferred to
APTRANSCO. Whereas most of the respondents could not start
production, LVS Power did. We will state the facts of the same at some
details at an appropriate place but suffice it to point that pursuant to the
20
interim decision taken by the Commission, LVS Power cancelled the
agreements it had entered into with the consumers. Negotiations were
held for fixing the rate of the tariff. It did not succeed. The Commission
rd
by its order dated 23 April, 2002 stated that:
“The Commission can only grant or withhold
consent for a PPA submitted to the
Commission. If APTRANSCO does not wish to
enter into PPA with LVS there is no way the
Commission can compel APTRANSCO to do
the same. In the circumstances, there is no
need to pass any order u/s. 21(4) of the A.P.
Electricity Reform Act, 1998 either granting or
withholding consent.”
The writ petition filed by the company before the High Court was
allowed directing :-
“65. In the light of the above infirmities, the
order of the Commission is liable to be set aside
and we are of the opinion that there are
sufficient grounds to allow the appeal.
66. In the result, the appeal is allowed with
costs by setting aside the order of the A.P.
Electricity Regulatory Commission in OP No.
70-A(LVS)/2001 dated 23-4-2002 holding that
APTRANSCO cannot go back from its promise
and refuse to purchase the power on the pretext
of surplus power position in the State. We
direct the Commission to consider the matter
afresh as per the norms of Central Electricity
Authority and the directions given in the appeal
21
and to direct the APTRANSCO to enter into
Power Purchase Agreement and purchase the
power from the appellant.
67. Now the further question that falls for
consideration by this Court would be, what
should happen to the generation plant which is
ready for commercial operation till the
Commission decides the issue as per law, in the
light of the directions given by us?
68. It is not in dispute that apart from the
investment made by the private entrepreneur,
about 104 crores of rupees of public money was
invested by various financial institutions, under
the leadership of Industrial Development Bank
of India (IDBI) and everyday the appellant has
to suffer a loss of about rupees 8 lakhs towards
interest component itself. If we allow the
situation to continue, the losses of the unit will
be mounting up and it may reach a point of no
return and the public monies invested will go
waste. The burden will again fall on the man
with loin cloth in the shape of indirect taxes.
Hence, we cannot allow the situation to
continue further, more so, in the light of the
permission given by the Commission on 18-8-
2001 to the APTRANSCO to purchase the
power from the appellant. We therefore direct
the APTRANSCO to purchase the power at the
rate at which it purchased during the trial
operations, subject to the final orders to be
passed by the Commission, or to takeover the
plant from the appellant and to perform the
duties of a generating company, as provided
under Section 18-A(2) of the Electricity
(Supply) Act, 1948, until it enters into Power
Purchase Agreement with the appellant after
fixation of the terms by the Commission. The
above arrangement made to save the plant will
22
be subject to final orders to be passed by the
Commission in the matter.
69. Before we part with the case, we place on
record our displeasure over the unhelpful and
un-cooperative attitude of APTRANSCO in
accepting a reasonable suggestion made by this
Court i.e., the power generated by the appellant
may be purchased at the rate at which it is
purchasing from other units, pending disposal
of the appeal, since we are pre-occupied in
hearing a batch of electricity appeals preferred
against the orders of the A.P. State Electricity
Regulatory Commission regarding Wheeling
Charges and Grid Support Charges wherein the
senior Advocates from other States are
advancing arguments and granted sufficient
time to think over the matter and report to the
Court. The learned senior Counsel appearing
for APTRANSCO expressed his inability to
convince his client in accepting the suggestion
made by the Court. Therefore, in order to
dispose of this matter, we were made to take up
this appeal by stopping arguments in those
cases and complete the hearing by sitting in the
Court beyond Court hours.”
Re: Civil Appeal No. 8094 of 2002
On 29.2.96, permission was granted to RVK Energy Pvt. Ltd. to
set up a 32.7 MW residual fuel based power plant at Medak district so as
to enable it to generate and supply power directly to specified industrial
consumers by using the existing transmission and distribution network of
APT. On 5.12.98, the State Government on a request made by RVK Ltd.,
23
allowed the change of location for the project to Krishna district. On
1.2.99, the 1998 Act was brought into force whereby the licensing
provision under Section 14 became applicable in the State of Andhra
Pradesh. In terms of Section 14(4), the State Government issued
provisional licenses to all persons who were engaged in the business of
supply of electricity. On 23.2.99, the State government permitted RVK to
partly change the fuel for the project from Residual Fuel to Natural Gas.
On 2.4.99, the Andhra Pradesh Electricity Regulatory Commission
(APERC) was constituted under the Reform Act. On 6.5.99, a Power
Purchase Agreement was signed between RVK Pvt. Ltd. and Indian
Cements Ltd. The Agreement inter-alia provided that as RVK was in the
process of signing the Power Wheeling Agreement with APTRANSCO,
India Cements thus had notice of the execution of the Wheeling
Agreement between the parties as a pre-requisite of the implementation
of the Agreement between it and RVK Pvt. Ltd. On 10.9.99,
APTRANSCO requested APERC to approve the drafts of the Power
Purchase and Wheeling Agreement with RVK Pvt. Ltd. On 20.9.99,
RVK made an application being O.P. No. 2 of 1999 to APERC seeking
exemption from the requirement of license to supply electricity to its
consumers under Section 16 of the Reform Act. In response to the
application of APTRANSCO dated 10.9.99, APERC by its letter dated
24
22.9.99, listed the requirements to be complied with which inter-alia
included RVK Pvt. Ltd. to obtain a licence or exemption from APERC
and to agree to APERC deciding third party sales including the extent
and manner of the supply and affixing the tariff, transmission and
wheeling charges. APTRANSCO was called upon to amend the draft
agreement with RVK.
Vide its letter dated 24.9.1999, RVK requested APERC to process
the exemption application dated 20.9.1999 expeditiously.
On 14.10.1999, the Power Purchase and the Wheeling Agreement
was signed between RVK and APTRANSCO. In terms of the Agreement,
it was agreed by RVK to set up a power generating plant to generate
electricity upto 20.31 MW with natural gas as fuel in Krishna district and
to sell power through APTRANSCO to identified consumers via the
APTRANSCO grid. It was also agreed by RVK to pay the transmission
(wheeling) and banking charges as per the provisions of Section 26 of
the 1998 Act. RVK agreed to take a licence as required under Section 15
or an exemption under Section 16 of the Reform Act for third party sale
including supply to (other than a licensee) regardless of the general
approval granted under G.O.M. No. 152 dated 29.11.95. The agreement
25
also provided for RVK to take the consent of APERC for wheeling of
power and submit a list to APERC for its consent of the consumers to
whom RVK proposed to sell the power. The agreement stipulated the
submission of all disputes regarding third party sale and supply to sister
concerns including the extent and manner of such supply and the tariff
charged to the APERC.
On 9.12.1999, RVK entered into a Power Purchase agreement with
Super Spinnings/Precott mills for sale of electricity. The agreement noted
that Super Spinnings/Precott Mills had notice of the terms of the Power
Wheeling Agreement that had been entered into between RVK and
APTRANSCO.
By its letter dated 10.12.99, RVK sought orders from APERC to
sell electricity to third parties so as to avoid paying minimum guarantee
charges of Rs. 2.40 lacs per day to the Gas Authority of India for non-
utilization of the gas so allocated to generate electricity in the power
project. In the light of the urgency shown by RVK, APERC by its interim
order dated 3.1.2000 approved the W heeling Agreement and third party
sales which specifically stated that the order would not prejudice the
power of APERC to pass such an order as it may consider necessary at
26
any stage of the proceedings. The proceedings were however kept
pending.
On 10.2.2000, RVK entered into a Power Purchase agreement with
Super Nagarjuna Agro-Tech for sale of electricity. The agreement
referred to the Power Purchase agreement entered into between RVK and
APTANSCO.
After hearing RVK on 28.3.2000, APERC by its order dated
31.3.2000. rejected the request of RVK for grant of licence/exemption
from licence. It was held that G.O. Nos. 116 and 152 did not give any
vested right to the mini power plants to get a licence or an exemption
after the Reform Act had come into force. APERC directed RVK to sell
electricity to APTRANSCO only and not to third parties at a fair and
reasonable price to be mutually agreed to by the parties or in the event of
the failure to do so, to be decided by the APERC.
Aggrieved by the said order, RVK preferred an appeal under
Section 39 of the 1998 Act before the Andhra Pradesh High Court
wherein the prohibition of the third party sales was challenged. By an
order and judgment dated 8.6.2001, the High Court dismissed the said
27
appeal. Upholding the order of APERC, the High Court was of the
opinion that the license or sanction under the Reform Act was necessary,
notwithstanding any previous licence or sanction that was granted under
the 1910 Act. It furthermore held that any approval envisaged under
Section 43 A of the 1948 Act granted to a generating company for sale of
electricity did not authorize the supply of electricity to the consumers.
Re: Civil Appeal No. 8101 of 2002
On 9.12.1995, the State Government under Section 18A of the
1948 Act granted permission to M/s Astha Power Corporation Pvt. Ltd.
to set up a 28.7 MW residual fuel based power plant at Balanagar,
Hyderabad so as to enable it to generate and supply power directly to
specified industrial consumers by using the existing transmission and
distribution network of APT. Further, permission was granted by the
state government under Section 28 of the 1910 Act to Astha Power Pvt.
Ltd. for supplying energy to the identified consumers and also under
Section 43A of the 1948 Act for entering into a contract for the sale of
electricity to the consumers.
28
On 12.11.1996, the State Government on a request made by Astha
Power Pvt. Ltd., allowed the change of location for the project to
Pashamylaram, Medak district.
By a notification dated 19.8.1999 issued by APERC, the public
was informed that a licence was required to be taken from APERC for
the transmission or supply of electricity in the state.
On 10.9.1999, APTRANSCO requested the Commission to
approve the Power Purchase and Wheeling Agreement with Astha Pvt.
Ltd.
On 23.10.1999, the Power Purchase and the Wheeling Agreement
was signed between Astha and APTRANSCO. In terms of the
Agreement, it was agreed by Astha to set up a power generating plant to
generate electricity of about 28 MW with H.F.O. as fuel in Medak
district and to sell power through APTRANSCO to identified consumers
via the APTRANSCO grid. It was also agreed by RVK to pay the
transmission (wheeling) and banking charges as per the provisions of
Section 26 of the Reform Act. Astha agreed to take a licence as required
under Section 15 or an exemption under Section 16 of the Reform Act
for the third party sale including supply to (other than a licensee)
29
regardless of the general approval granted under G.O.M. No. 152 dated
29.11.1995. The agreement also provided for Astha to take the consent of
APERC for wheeling of power and submit a list to APERC for its
consent of the consumers to whom Astha proposed to sell the power.
The agreement stipulated the submission of all disputes regarding third
party sale and supply to sister concerns including the extent and manner
of such supply and the tariff charged to the APERC.
On 23.12.1999, Astha made an application to APERC seeking
exemption from the requirements of taking license to supply electricity to
its consumers under Sections 15 & 16 of the Reform Act.
After hearing Astha on 18.4.2000, APERC by its order dated
1.7.2000. rejected its request for grant of licence/exemption from licence.
It was held that G.O. Nos. 116 and 152 did not give any vested right to
the mini power plants to get a licence or an exemption after the Reform
Act had come into force.
APERC directed Astha to sell electricity to APTRANSCO only
and not to third parties at a fair and reasonable price to be mutually
agreed to by the parties or in the event of the failure to do so, to be
decided by the APERC.
30
Aggrieved by the said order, on 24.7.00, Astha preferred an appeal
under Section 39 of the Reform Act before the Andhra Pradesh High
Court wherein the prohibition of the third party sales was challenged.
In the meanwhile, on 23.4.01, APERC after observing that Astha
had not approached APTRANSCO as per its directions to arrive at an
agreement for sale of electricity, directed Astha again to negotiate with
APTRANSCO so as to arrive at an agreement.
By an order and judgment dated 8.6.01, the High Court dismissed
the said appeal. Upholding the order of Commission. The High Court
was of the opinion that the license or sanction under the Reform Act was
necessary notwithstanding any previous licence or sanction that was
granted under the 1910 Act. It furthermore held that any approval
envisaged under Section 43 A of the 1948 Act granted to a generating
company for sale of electricity did not authorize the supply of electricity
to the consumers.
Entry 38 of the Concurrent List in the Indian Constitution provides
for “Electricity”.
31
The Parliament enacted the Indian Electricity Act (for short the
1910 Act). Section 3 of 1910 Act provides for issue of licence to the
undertakings generating, supplying and distributing electrical energy.
Section 28 of the 1910 Act provides for grant of sanction required
by non-licensees in certain cases.
The State is an appropriate Authority both for grant of licence in
terms of Section 3 and sanction in terms of Section 28 of 1910 Act.
In the year 1948, the Parliament enacted the Electricity (Supply)
Act, 1948 (for short the 1948 Act) in terms whereof each State was
statutorily obliged to constitute Electricity Boards in their respective
States. Electricity Boards are ‘deemed licenses’ in terms of the said Act.
In terms thereof licence cannot be granted to any private party.
Sections 2(4)(A), 2(5), 2(6) of the 1948 Act provide for the
definitions of “Generating Company”, “Generating Station” and
“licensee”, respectively.
Section 18A specifies the duties of a generating company.
32
Section 26A of the 1948 Act provides for exemption grant of a
licence so far as a generating company is concerned.
Section 43A of the 1948 Act provides for terms, conditions and
sale of electricity by generating company.
The State of Andhra Pradesh enacted the 1998 Act to provide for
the constitution of an Electricity Regulatory Commission, restructuring
of the Electricity Industry, rationalisation of the generation, transmission,
distribution and supply of electricity avenues for participation of private
sector in the Electricity Industry and generally for taking measures
conducive to the development and management of the Electricity
industry in an efficient, economic and competitive manner and for
matters connected therewith or incidental thereto.
“APTRANSCO” has been defined in Section 2(b) of the 1998 Act
to mean Transmission Corporation of Andhra Pradesh Limited
incorporated as a transmission company under the Companies Act, 1956
(Central Act 1 of 1956) and as referred to in Section 13 thereof.
33
“Commission” has been defined in Section 2(c) of 1998 Act to
mean the Andhra Pradesh Electricity Regulation Commission constituted
under sub-section (1) of Section 3.
“Licensee” or “licence holder” has been defined in Section 2(e) of
1998 Act to mean a person licensed under Section 14 of the Act to
transmit or supply energy including APTRANSCO.
Section 3 of 1998 Act provides for establishment and constitution
of the Commission.
Functions of the Commission have been dealt with in Section 11 of
the 1998 Act, clauses (e) and (f) whereof read as under :-
“11. Functions of the Commission, :-
(e) to regulate the purchase, distribution, supply
and utilization of electricity, the quality of
service, the tariff and charges payable keeping
in view both the interest of the consumer as
well as the consideration that the supply and
distribution cannot be maintained unless the
charges for the electricity supplied are
adequately levied and duly collected.
34
(f) to promote competitiveness and progressively
involve the participation of private sector,
while ensuring fair deal to the customers.”
Section 12 provides for the general powers of the State
Government to issue policy directions on matters concerning electricity
in the State including the overall planning and co-ordination. All policy
directions are required to be issued by the State Government consistent
with the objects sought to be achieved by the said Act and accordingly
shall not adversely affect or interfere with the functions and powers of
the Commission including but not limited to determination of the
structure of tariffs for supply of electricity to various classes of
consumers.
Section 13 of the 1998 Act provides for constitution and functions
of APTRANSCO. Section 14 provides for licensing, sub-section (1)
whereof reads as under :-
“14. Licensing:- (1) No person, other than those
authorized to do so by licence or by virtue of
exemption under this Act or authorized to or
exempted by any other authority under the
Electricity (Supply) Act, 1948, shall engage in the
Sate in the business of, -
35
(a) transmitting electricity ; or
(b) supplying electricity.”
Section 15 of 1998 Act provides for grant of licences by the
Commission in respect of transmission of electricity in a specified area of
transmission and supply electricity in a specified area of supply including
bulk supply to licensees or any person.
Section 16 of 1998 Act provides for exemption from the
requirements of having a licence.
Section 17 of 1998 Act provided for general duties and powers of
the licensees. Section 21 imposes restrictions on licensees and
generating companies.
The Parliament enacted Indian Electricity Act, 2003 (in short 2003
Act).
Sub-section (2) of Section 10 of the said Act enables a generating
company to supply electricity to third parties. It reads :-
36
“Section 10 - Duties of generating companies
(2) A generating company may supply
electricity to any licensee in accordance with
this Act and the rules and regulations made
thereunder and may, subject to the regulations
made under sub-section (2) of section 42,
supply electricity to any consumer.
Section 14 of 2003 Act provides for grant of licence.
The Schemes of 1910 Act, 1948 Act and 1998 Act being different,
any licence or sanction granted in terms of Section 3 and 28 of the 1910
Act or permission under Section 43A of the 1948 Act would not mean
that no licence was required in terms of 1998 Act. The Regulatory
Commission in absence of any direction issued by the State in terms of
Section 12 of the Act, that too being an expert body was entitled to take
its own decision. The power of the Commission to regulate supply
would include a power to issue necessary direction (s) to supply
electrical energy only to the licenses under the 1948 Act. The 1998 Act
stipulates that the manner in which the power to regulate would be
exercised has been left with only an expert body.
There are principally two categories of cases before us, viz.:
37
i) Where the State of Andhra Pradesh had granted express
permission to establish Mini Power Plants (for short MPP)
prior to 1995 where residual fuel which were to be used as
raw-material had been specified.
ii) The Government of Andhra Pradesh also permitted the
producer of electricity to supply it to heavy industrial units
including public sector undertakings.
The issues involved in relation to these industries are two fold.
Where the industries had been asked to sell electrical energy to the
APTRANSCO, writ petitions filed thereagainst had been allowed by one
Division Bench of the High Court. It, however, appears that another
batch of cases where interim order had been passed by the Commission
to supply power to the APTRANSCO at one stage and pursuant to the
said directions, supply of energy had been taken for sometime but while
negotiations were going on for fixation of price between the parties at
first instance, which having failed, when the matter came up again before
the Commission, the APTRANSCO refused to enter into such an
agreement resulting in an order passed by the Commission, that it cannot
enforce the APTRANSCO to enter into such an agreement.
38
These orders were subject matter of writ petitions before the
Andhra Pradesh High Court. Another Division Bench of the said High
Court, keeping in view the stand taken from the very beginning by the
State of Andhra Pradesh; the power of the Commission as also the orders
passed by it from time to time as also the negotiations held between the
parties, directed APTRANSCO to enter into an agreement with the
MPPs.
Mr. Shanti Bhushan, learned senior counsel appearing on behalf of
the appellant- APTRANSCO, would submit :-
1) Whereas the Commission has the requisite power to regulate
supply of electrical energy in terms of Section 11 of the
1998 Act, it had no jurisdiction to compel the APTRANSCO
to enter into a Power Purchase Agreement.
2) Power of the Commission in terms of sub-section (4) of
Section 21 being limited, the High Court committed a
serious error in issuing the impugned directions.
39
3) The High Court while exercising its appellate jurisdiction in
terms of Section 39 of 1998 Act could not have issued any
direction which was beyond the power of the Commission.
4) In any event the High Court being not an expert body should
not have ordinarily interfered with an order of the
Commission which is an expert body, as has been held by
this Court in West Bengal Electricity Regulatory
Commission vs. C.E.S.C. Ltd. etc. etc : (2002) 8 SCC 715.
Mr. Ramachandran, learned counsel, appearing on behalf of the
Commission would submit :
1) That sanction granted in terms of Section 28 of 1910 Act or
permission granted under Section 43 A of the 1948 Act
would not lead to the conclusion that the MPPs were not
required to take fresh licence or apply for grant of
exemption.
2) Applications for grant of exemptions were filed by the
MPPs, as even they as also the financial institutions thought
that the same was necessary.
40
3) The Commission in its order did not interfere with the
agreements which had been entered into by and between the
MPPs and the third party prior to coming into force of the
1998 Act.
4) The decision to direct the MPPs to supply power to
APTRANSCO was taken with a view to adjust the equities
between the parties, as otherwise, whereas on the one hand
MPPs would be supplying power to industrial companies
and commercial concerns which would attract a higher
tariff, the APTRANSCO would have been left with only
agricultural consumers and domestic consumers for whom
the tariff was on a lower side resulting in sufferance of loss
by it
5) The Commission had the jurisdiction to issue such
directions, apart from its power to grant licence or grant
exemption in terms of Section 14 of the 1998 Act but also in
exercise of its power to regulate supply and all that is
contained in Section 11 thereof.
6) Apart from LVS Power, as no other company, had set up the
th
power plant, although the Commission in its order dated 4
May, 2001, in purported exercise of its suo motu power,
41
expressed its disinclication to permit third party sales and
fixation of rate, it asked the parties to negotiate thereabout
and only in the event such negotiations failed, they were
given the liberty to approach the Commission in the matter.
7) When, however, it was found that the cost of supply would
be beyond the capacity of APTRANSCO to bear, the
Commission refused to issue to it to make compulsory
purchase of electricity from LVS.
8) The Commission had no intention to restrict sale of
electricity to third party by MPPs, particularly when
APTRANSCO itself was unable to take supply.
Mr. Harish N. Salve, learned senior counsel appearing on behalf of
the respondent LVS Power, on the other hand, urged :-
1) Section 21(4) of the 1998 Act has no application to the facts
of the present case.
2) Sections 11(1)(e) and (f) of 1998 Act clearly postulate a
wide power in the Commission, which in effect and
substance, clearly go to show that while exercising its power
to regulate supply of electrical energy by generating station
42
to a consumer, it, while directing the MPPs to supply
electrical energy to APTRANSCO had the requisite power
to direct the APTRANSCO to purchase the same.
3) In any event the APTRANSCO itself having invited the
order and furthermore having suffered two directions of the
th
Commission as contained in its orders dated 18 August,
th
2001 and 26 November, 2001 whereby and whereunder the
Commission directed the APT to purchase electrical energy
from the company subject to fixation of rate by negotiations,
and in the event of failure, to come back to the Commission
cannot now turn round and question its jurisdiction to do so
and, thus the High Court was within its jurisdiction to issue
the directions.
4) APTRANSCO had been changing its stand from stage to
stage, in so far as at one point of time it complained of the
capital costs being too high; when the company came down
to fix costs, it did not accept the same and asked for the
factor of variable costs for the purpose of fixation of tariff
and when the company, as an act of desperation, keeping in
view its commitments to various financial institution, had
43
even agreed therefor, took a complete turn about to contend
that they do not require the power.
5) The Government of Andhra Pradesh having referred the
matter to Central Electricity Authority for its opinion and
having obtained the same, the Commission was bound to
compel APTRANSCO to agree thereto.
6) In any event, as by reason of the stand taken by
APTRANSCO, the company had to cancel all the
agreements of supply entered into by and between the
parties for supply of electrical energy, it could not have
resciled from its representation and refused to purchase
electrical energy from it.
7) Once it is contended by the APTRANSCO that the
Commission had the power to direct the MMPs to sell their
produce only to it, as a matter of policy, could not have
contended that the Commission can have only half a power
and it had no power to ask it to purchase the same.
8) The Commission which itself has made a mess of
everything, was bound as an expert body to take the interim
direction of the Commission to its logical conclusion.
44
9) The State having the power to lay down the policy decision
in terms of Section 12 of the 1998 Act, the Commission is
bound to give effect thereto having regard to its functions as
envisaged in Section 11(1)(f) of the Act. It was, thus, bound
to promote competitiveness involving participation of
private sector progressively and not regressively.
11) APTRANSCO having been constituted under the Act and its
functions being subject to supervision by the Commission,
was bound to obey the directions of the Commission.
Mr. Narsimhan and Mr. Dushyant Dave, learned senior counsel
appearing on behalf of G.V.K. and Astha Power submitted that having
regard to the fact that the MPPs had been granted licences by the State in
terms of Section 28 of 1910 Act and Section 43A (1)(c) of 1948 Act the
provisions of the 1998 Act as regards grant of licences would not be
applicable in their cases.
The learned counsel submitted that the Commission had no
jurisdiction to ignore the policy decision of the State, particularly when
the consumers to whom the MPPs would supply power upon generation
thereof had been fixed. Such a policy decision, in view of Section 12 of
45
the Act was binding on the Commission. Respondents were ill advised
to approach the Commission for grant of exemption which was not
necessary as has been found by the High Court. The Commission in any
event had no jurisdiction to direct sale of electricity only to
APTRANSCO. The power to regulate sale and supply of electrical
energy as contained in Section 11 of the 1998 Act must be held to be
subject to other provisions of the Act and in particular Sections 15(1)(h)
and 15(1(k) and Section 17 thereof.
The permission granted in terms of Section 43A of 1948 Act
having been repealed by 1998 Act, the Central Government had
recognized the same by introducing the Electricity (Removal of
Difficulties) Second Order, 2005 in the light of Section 10(2) of the
Electricity Act, 2003 The sanction and permission granted by the State,
which was the only competent authority therefor, having conferred a
benefit upon the MPPs by granting licences, as a result whereof the legal
rights vested in them, the same could not have been taken away.
While issuing a direction that MPPs must sell the electricity only
to APTRANSCO the Commission had not only failed to address the
question raised before., it passed an order only on the basis of misplaced
conception.
46
The State took a policy decision. It was with a view to develop
growth of generation and supply of electrical energy. Monopoly of the
State Electricity Board was sought to be given a go bye. The intention of
the State to lay down the policy decision in regard to privatization of
generation and supply of electrical energy is manifest from the GOMs.
issued by it.
There is absolutely no doubt whatsoever that the Commission,
which is a statutory authority, is bound by the direction of the State but it
would not be so bound if it is contrary to or inconsistent with any of the
provisions contained in 1998 Act. Respondents herein sought for an
exemption from the provisions thereof. They filed applications in terms
of Section 16 of 1998 Act. Whether such an application was filed on a
mistaken belief or not is one question but the action taken by the
Commission must be construed upon taking a holistic view of the matter.
Respondents herein acted pursuant to the promise made by the
State. They altered their position. They have invested a huge amount.
They secured foreign collaboration, raised huge loans from financial
institutions. They not only entered into Power Purchase Agreements but
also entered into Power Wheeling Agreements with APTRANSCO. The
47
said arrangements were entered into in view of the fact that the private
generating companies did not have the requisite infrastructure for
transmission of electrical energy from their generating stations to the
consumers.
It was in the aforementioned background, we must take into
account that the applications for exemptions were filed pursuant to the
order passed by the Commission as indicated hereinbefore. It was the
Commission which opined that such an application for exemption was
not required to be filed. However, while dealing with the application,
Commission issued a direction that the power generated by MPPs must
rd
be sold to APTRANSCO only and the sale to the 3 party was
prohibited. Direction was issued in this behalf in great details. The said
direction was the subject matter of appeal before the Andhra Pradesh
High Court.
th
Indisputably the letter dated 29 February, 1996 issued by the
State to the private entrepreneurs is also in consonance with the said
objective.
48
The power of the Commission in terms of 1998 Act must be
considered having regard to the provisions of Section 11 thereof. We
may at the outset notice two different functions specified under the Act.
Section 11 of 1998 states about the functions of the Commission whereas
Section 12 thereof states about the powers of the State Government.
No doubt the functions of the Commission is wide. It, in terms of
clause (e) of sub-section (1) of Section 11 of the 1998, is entitled to
regulate the purchase, distribution and supply as also utilization of
electricity but when the Act speaks of regulation, the same would not
ordinarily mean that it can totally prohibit supply to third parties. It may
do so in exceptional situations. Such an order is not to be passed.
The Commission, keeping in view the purported object of the Act,
ordinarily was bound to give effect to the policy decision of the State.
The Act was enacted to encourage competition. It speaks of privatization
of generation of power. The Commissioner’s power to regulate supply of
power must be considered keeping in view the purport and object of the
Act.
49
rd
In Advanced Law Lexicon, 3 edition, page 4026 “Regulation”
has been defined as under :-
“A regulation is a rule or order
prescribed by a superior for the management of
some business or for the government of a
company or society or the public generally.”
In State of Tripura and others vs. Sudhir Ranjan Nath : (1997) 3
SCC 665, this Court held :-
“This in turn raises the question, what is the meaning
and ambit of the expression "regulate" in Section 41
(1) of the Act? (Section 41(1) empowers the State
government "to regulate the transit of all timber and
other forest-produce".) The expression is not defined
either in the Act or in the rules made by the State of
Tripura. We must, therefore, go by its normal
meaning having regard to the context in which, and
the purpose to achieve which, the expression is used.
As held by this Court in Jiyajee Cotton Mills Ltd. and
Anr. v. Madhya Pradesh Electricity Board and Anr.
[1989] Suppl. 2 S.C.C. 52 the expression "regulate"
'has different shades of meaning and must take its
colour from the context in which it is used having
regard to the purpose and object of the relevant
provisions, and as has been repeatedly observed, the
court while interpreting the expression must
necessarily keep in view the object to be achieved and
the mischief sought to be remedied" (at page 79).
Having regard to the context and other relevant
circumstances, it has been held in some cases that the
expression "regulation" does not include "prohibition"
50
whereas in certain other contexts, it has been
understood as taking within its fold "prohibition" as
well.:
It has been held by this Court in Jiyajeerao Cotton Mills Ltd. and
another vs. Madhya Pradesh Electricity Board and another : 1989 Supp
(2) SCC 52 that the power to regulate does not include power to prohibit.
The Court held :-
“ The expression "regulate" occurs in other
statutes also, as for example, the Essential
Commodities Act, 1955, and it has been found
difficult to give the word a precise definition. It has
different shades of meaning and must take its colour
from the context in which it is used having regard to
the purpose and object of the relevant provisions, and
as has been repeatedly observed, the Court while
interpreting the expression must necessarily keep in
view the object to be achieved and the mischief
sought to be remedied.”
In Talcher Municipality vs. Talcher Regulated Market
Committee and another : (2004) 6 SCC 178, this Court held :-
51
“14. The power to regulate buying and selling of
agricultural produce must be interpreted in the context
in which the same has been used. Each person
whoever is engaged in buying and selling of the
agricultural produce in the market shall be subject to
the regulation for which the same has been enacted.
The expression "regulation" is a term which is
capable of interpreted broadly. It may in a given case
amount to prohibition.”
If the State had accorded sanction for sale of electrical energy
generated by the MPPs, the Commission save and except for cogent and
compelling reasons could not have directed the sale of entire production
of electricity energy to APTRANSCO. If that was the stand of the
Commission and the APTRANSCO, the question of entering into any
Wheeling Agreement did not arise. It is one thing to say that the
privileges conferred by G.O.Ms. issued by the State Government were
prior to the coming into force of the 1998 Act and appointment of the
Commission, but then the Commission was bound to give due weight to
the policy decision taken by the State even prior to its establishment and
coming into force of the 1998 Act, particularly when the Act was enacted
in furtherance thereof.
Indisputably respondents were entitled to produce electrical energy
under Section 28 of 1910 Act. They were authorized to generate
52
electrical energy. The question which arises is as to whether they were
required to file appropriate applications for grant of licence or for
exemption which should have been dealt with accordingly. At that point
of time, the Commission was not exercising its other functions. A
condition, which is per se unreasonable should not have been imposed.
It is one thing to say that the statutory authority exercised its powers one
way or the other but it is other thing to say that in the garb of exercising
power of grant of licence and/or exemption thereunder, it issued a
direction which has nothing to do directly therewith.
Commercial relationship between a generating company and the
consumer has all along been accepted. Public interest would not mean
the interest of APTRANSCO alone. Equity in favour of one of the
generating companies could not have been the sole ground for coming
out with such a policy decision and that too while considering
application for grant of exemption from the purview of the licensing
provision..
We will assume that the Legislature of the State with some
purpose in mind provided for taking of licence under the 1998 Act but
the very fact that they had the requisite licence in terms of the provisions
53
of 1910 Act, itself was one of the relevant considerations for the purpose
of grant of exemption. It could have been rejected in which event the
MPPs would have applied for grant of licence. Indisputably the State
Government has the power to grant provisional licence. In terms of sub-
section (4) of Section 14 of 1998 Act, the provisional licences are also
issued by the State Government. Indisputably again the said provisional
licences have been granted to avoid a situation as a result whereof the
MPPs would be forced to stop their function during interregnum period.
Even if the licences were required to be issued, each case should have
been considered on its own merit.
When an application for grant of exemption is filed, the same is
required to be dealt with independently. What was necessary for the said
purpose was interest of the consumers as well as the consideration that
supply and distribution cannot be maintained unless the charges for
electricity supply are adequately levied and duly collected.
The Commission, therefore, was bound to strike a balance. It
should have given due consideration as to how and in what manner the
MPPs were established. They were not per se inconsistent with the
object sought to be achieved by the 1998 Act.
54
Reliance in this behalf has been placed on Andhra Pradesh Gas
Power Corporation Ltd. vs. Andhra Pradesh State Regulatory
Commission : (2004) 10 SCC 511 and Grid Corporation of Orissa Ltd.
vs. Indian Charge Chrome Ltd. : (1998) 5 SCC 438 para 15, which reads
:-
“15. Another question which was seriously
contested on behalf of GRIDCO before the
Regulatory Commission as well as before the
High Court was that ICCL is not a licensee
within the meaning of Section 2( h ) of the
Indian Electricity Act, 1910 and also under
Sections 2( e ) and ( f ) of the Reform Act, 1995.
The High Court recorded a finding that ICCL is
a licensee under the Indian Electricity Act,
1910 and it continued to be a licensee even
after the Reform Act, 1995 came into force.
The High Court placed reliance on Section 14
(1) of the Reform Act and held that ICCL is
authorised by the State Authority in the
business of supplying the electricity. It was thus
concluded that ICCL in view of Section 14 of
the Reform Act, 1995 shall continue to be a
licensee. In view of this finding the High Court
held that the dispute is arbitrable under Section
37(1) read with Section 33 of the Reform Act,
1995. It is not seriously disputed that ICCL
after a long-drawn correspondence with the
Orissa Government had received no objection
to put up the Captive Power Plant at Choudwar
to generate power. Accordingly in 1989 the
Captive Power Plant started generating power
which was supplied to the OSEB. This
arrangement continued till 1994 when MOU
55
and agreement were entered into between ICCL
and OSEB. The GRIDCO being a successor of
OSEB, naturally the MOU of 1994 and
agreement of 1995 will be binding upon the
GRIDCO in the absence of any material to the
contrary. It is not the contention of the
GRIDCO that ICCL did not supply any power
at all during the period for which the bills were
raised on ICCL. Despite this factual position it
appears that no formal licence was issued under
Section 2( h ) of the Indian Electricity Act, 1910
or under the Reform Act, 1995. It cannot be
ignored that the investment of ICCL in putting
up a Captive Power Plant at Choudwar is
running into few hundred crores. Sections 2( e )
and ( f ) of the Reform Act read as under:
“( e ) ‘licence’ means a licence granted under
Chapter VI;
( f ) ‘licence’ or ‘licence-holder’ means a
person licensed under Chapter VI to
transmit or supply energy including
GRIDCO.”
Chapter VI deals with licensing of transmission
and supply.
Section 14(1) reads as under:
No person, other than those authorised to do
so by licence or by virtue of exemption
under this Act or authorised or exempted by
any other authority under the Electricity
(Supply) Act, 1948 shall engage in the State
in the business of
( a ) transmitting; or
( b ) supplying electricity.
From the facts noted hereinabove and in
view of Section 14(1) of the Reform Act it is
56
quite clear that ICCL was/is authorised and
engaged in supplying the electricity to
OSEB and thereafter to GRIDCO and if this
be so the dispute between the GRIDCO and
ICCL could be arbitrable under Section 37
(1) read with Section 33 of the Reform Act,
1995.”
Reference made to the decision of Grid Corporation of Orissa Ltd.
(supra) is not apposite. The same was rendered in a different fact
situation. The question as regards the effect of Section 14 has not been
considered therein.
We are, therefore, of the opinion that it was necessary for the
MPPs to apply for licence under Section 14 of the Act.
We are, however, of the opinion that while considering the
application for grant of exemption, the Commission did not have any
jurisdiction to issue a direction that all MPPs must supply electricity to
APTRANSCO only. The power and extent of jurisdiction of the
Commission to regulate supply is a wide one but the same, in our
opinion, does not extend to prohibition or positive direction that the
supply of total energy produced must be made to APTRNASCO while
exercising the said jurisdiction. In fact there was no occasion for issuing
57
such a direction. It is one thing to say that the Commission is entitled to
fix tariff but therefor then it cannot take into consideration the case of
APTRANSCO alone.
What should be the basis for issuing any tariff could have been the
question which was to be posed by the Commission to itself. For the said
purpose, the Commission was required to take into consideration all
aspects of the matter including the fact that Wheeling Agreement had
already been entered into and only by reason thereof, the APTRANSCO
may generate a lot of revenue. The decision of the Commission,
therefore, being illegal has rightly been set aside by the High Court.
This takes us to the case of LVS Powers Ltd.. So far as LVS
Powers Ltd. is concerned it had acted on the basis of the directions of the
Commission. It for all intent and purport proceeded on the basis thereof.
It not only held negotiations with APTRNASCO for the purpose of
arriving at a mutually settled tariff, it having regard to huge loan taken by
it and presumably on the pressure of IDBI accepted almost all the
suggestions made by APTRANSCO.
58
th
From the letter dated 24 July, 1996 to M/s. LVS Power Ltd. it is
evident that its consumers were Hindustan Shipyard Ltd.; Hindustan
Zinc Ltd.; Essar Steels Ltd. and Andhra Cements Ltd. all situated at
Visakhapatnam i.e. within the State of Andra Pradesh. The Commission
appears to have even succumbed to the pressure of the employees of the
State Electricity Board. It allowed the employees to be impleaded as
parties. It heard them. Why the employees of APTRANSCO had to be
heard is beyond our comprehension.
th
From the order dated 4 May, 2001 it appears that APSEB
Engineers’ Association and Assistant Engineers’ Association, APSEB
were heard. The main contention appears to have been advanced was as
to whether MPPs should be allowed to generate power with residual fuel.
The Commission noticed that out of 31 MPPs permission granted to 12
were cancelled. Out of 19, LVS Power Ltd. survived.
It noticed that some of the MPPs changed their capacities. It
furthermore took notice of the fact that LVS had already drawn moneys
from the financiers and the extension granted by GOAP in their case was
th
to expire on 30 April, 2001.
59
Interestingly the State of Andhra Pradesh did not put in their
appearance before the Commission. The Commission merely received a
communication from the Principal Secretary to the Government which
was noticed as under:-
“Nobody appeared on behalf of the GoAP. But
a letter has been filed in which the principal
Secretary to Government has urged that
permission may be given to MPPs for third
party sales to HT Industrial consumers. If
APTRANSCO loses on account of this
arrangement, the Commission can fix
appropriate wheeling charges taking into
account the cross subsidization foregone by
APTRANSCO on account of third party sales.”
The same per se was illegal.
It took into consideration the question of subsidy. The
Commission reiterated that it was not inclined to permit third party sale.
It unfortunately laid serious emphasis on the contentions raised by civil
societies at the relevant time. It furthermore noticed that its earlier order,
and directions were issued to eight developers to make an offer of price
on the basis of the various Government of India notifications, by
abdicating its own jurisdiction. On the one hand, it was conscious of its
functions but, on the other hand, it failed to determine the issues between
the parties.
60
th
However, the order dated 30 March, 1992 was not challenged by
APTRANSCO. The Commission furthermore noticed that wheeling
agreement had been entered into by and between the parties on or about
th
25 February, 1999. After taking into consideration some submissions of
the parties, directions were issued as has been noticed hereinbefore.
What for, it asked the parties to negotiate is evident from that in
the event of their failure to agree on the price and the other terms and
conditions, the Commission itself would do it. The aforementioned order
th
dated 4 May, 2001 has also not been challenged by APTRANSCO.
It is in the aforementioned backdrop that we will notice the letter
th
dated 17 August, 2001 written by Chief Engineer, Vidyut Soudha to the
Commission where after duly noticing that since finalization of PPA has
to be done after the abovecited GoAP approvals are received, it was
proposed to purchase power produced at the above cited rate from the
COI as the plant, subject to consent of the Commission. From the said
letter it appears that APTRANSCO had reviewed the capital cost
furnished by the developer. They were agreeable to the levelised tariff
mentioned therein with payment on year to year basis as per CEA norms
61
and variable charge. As per CEA, APTRANSCO was permitted to
purchase the power from LVS Powers Ltd. at the rate specified in
paragraph 5 of the letter which is to the following effect:-
“5. APTRANSCO’s consultants have reviewed the
capital cost furnished by the developer and opined
that the capital cost can be brought down to the order
of Rs.125.00 Crs. The revised tariffs with this capital
cost and CEA norms for unit generated will work out
to as follows:
Unit generated
FC VC
Total
With FE variation - 115.4 157.5
272.9
Without FE variation - 112.6 157.5
270.2
The above tariff projections have been informed to
the developer on 17.8.2001. In reply, the project
company has informed that they are agreeable to the
levelised tariff of 115.4 FC 157.5 VC per unit
generated and with foreign exchange variation on
ROE, presently accepting the capital cost of Rs. 125
Crs. Subject to condition that the tariff is to be re-
fixed after the capital cost is approved by the GoAP.”
62
Supply commenced in September, 2001. On the aforementioned
basis only the private agreements were terminated. Important
developments took place in the next three months.
th
By a letter dated 26 November, 2001, APTRANSCO asked the
Principal Secretary to the Government of Andhra Pradesh inter alia the
following :-
“ In view of the above, it is requested that
the capital cost of the project may be limited to
that of Rs.125.33 Crs. It is also to inform that
in case APTRANSCO is unable to purchase
power from this MPP, the MPP may be
permitted to sell the power outside the State
subject to consent of APERC allowing
APTRANSCO to collect wheeling charges. It
is requested that the approval of the capital cost
may be communicated early to fix the final
fixed cost of the tariff and seek the approval of
APERC to continue purchase of power if it is
found on part with the earlier ad hoc tariff
fixed. Early action is solicited since the
permission given by APERC for purchase of
power from the developer has expired on
31.10.2001.”
It was suggested that the capital cost is too high and, therefore, the
tariff should be fixed on the basis of fixed costs. It was opined that there
was no need to consider variable costs. What would be the effect of
63
th
power purchase beyond 30 November, 2001 was stated in the letter of
rd
APTRANSCO dated 3 December, 2001 to the Commission, which was
in the following terms :-
“This has reference to the correspondence cited
regarding purchase of power from M/s. LVS
Power Ltd.
2) In the reference 4 dated 26.11.2001 cited
above. APERC permitted the APTRANSCO to
purchase power from M/s. LVS Power Ltd. at
the rate as per APERC Order in the reference
(2) cited and extended the period of purchase of
power from 31.10.2001 to 30.11.2001 purely as
an interim measure and directed APTRANSCO
to send the firm tariff proposal with the
approved project cost from competent authority
latest by 30.11.2001 for the commission to pass
appropriate order.
3) In this connection, the following are
submitted –
i) The GOAP have been requested vide this
office letter dated 26.11.2001 ref (5)
cited to limit the capital cost of the LVS
Power Ltd. to Rs.125.33 Crs. and for
approval of the capital cost to fix the
final fixed cost of the tariff and seek the
approval of APERC to continue purchase
of power.
ii) After the project cost is approved by
GOAP the tariff is to be worked out and
a firm proposal is to be submitted to
APERC for approval.
iii) It may take some time for approval of
capital cost and finalization of tariff and
64
approval of power purchase from
APERC.
iv) APTRANSCO cannot take power from
the project in the absence of provisional
approval from APERC.
4) In view of the above, it is requested that
the time limit of power purchase from M/s.
LVS Limited may kindly be extended for a
further period of two months i.e. from
30.11.2001 to 31.1.2002 early to enable
APTRANSCO to avail supply beyond
30.11.2001.”
A stand appears to have been taken by the Commission in its letter
th
dated 27 December, 2001 addressed to the Chief Engineer,
APTRANSCO by the Commission stating :-
“This is to inform you that further proceedings
th
in the above matter will be held at 11 AM on 7
February 2002 at the Commissions office with
the APTRANSCO, GOAP and LVS
representatives must attend. In the meanwhile
APTRANSCO shall finalise all the documents
and issue outstanding including with the
Government of Andhra Pradesh as stated in the
letter dated 03.12.2001 addressed to the
Commission and file with the Commission
relevant documents, details etc. by
31.01.2002.”
65
In the meantime the State referred the matter to the Central
Electricity Authority seeking advise under Section 3 of the 1948 Act
about the reasonableness of the capital cost of the project proposed by
APTRANSCO in view of the experience and expertise of the Authority
in Power Projects.
APTRANSCO thereafter filed its written submissions before the
Commission expressing its inability to purchase power from the MPPs.
The Government of Andhra Pradesh was asked to consider the question
as to whether they can sell power outside the State duly permitting
APTRANSCO to collect wheeling charge as per the Commission’s order.
Several other new contentions were raised with which we are not
concerned but we are noticing the same only for the purpose of showing
as to how and in what manner APTRANSCO has been changing its stand
from stage to stage.
However, it is of some significance to notice that Central
th
Electricity Authority in terms of its letter dated 26 February, 2002
opined that the capital costs works out to be on lower side from the other
projects by stating :-
66
“It may, however, be mentioned that CEA,
while granting TEC for similar type of projects
for IPPs have cleared the estimated completion
capital cost in the range of Rs.3.62 crores to
Rs.3.8 crores per MW as the ceiling cost
depending on the scope of work, site specific
features, financial package, debt-equity ratio,
exchange rate, taxes and duties, foreign
exchange etc.
GOAP may please take further action based on
the above.”
The Government of Andhra Pradesh in view of that letter asked
APTRANSCO to proceed with the exercise for arriving at PPA and
submit the same to the Commission for approval. APTRANSCO by its
th
letter dated 11 April, 2002 addressed to the Commission, inter alia
stated :-
“After detailed examination of the above offer
by APTRANSCO, I am directed to convey that
in the context of surplus power situation and
APTRANSCO’s proposal to surrender NTPC
Eastern Region Power and not to draw Power
from Central Generating units due to Merit
Order Dispatch, dispatch from the power
station poses a serious problem. Further,
APTRANSCO’s inability to dispatch the station
will lead to payment of fixed charges
irrespective of generation by this power station.
In view of the above, it is requested to take
67
necessary action and pass appropriate orders in
this regard.”
It is in the aforementioned background that the order of the
rd
Commission dated 23 April, 2002 stating that it had no jurisdiction to
direct APTRANSCO to purchase power from LVS must be considered.
It is strange that while Commission was so conscious of is own
power as envisaged under clause (e) of sub-section (1) of Section 11 of
the Act in prohibiting third party sale so far as MPPs are concerned, it
even could not take its own order to its logical conclusion. It is with
some displeasure that we must notice as to how Commission mis-
directed itself at every stage. Despite the State supported the application
for grant of exemption, the third party sale was prohibited. Parties were
asked to negotiate and come back for fixation of tariff but then without
realizing the consequence which has to be suffered by the parties, it says
it could not do anything in the matter. If APTRANSCO was not
agreeable to the orders passed by the Commission, which might have
been passed during the pendency of the proceedings, it could have
questioned the same. It did not do that. It accepted the orders. It for all
intent and purport forced the respondent to alter its position to its great
detriment. The Commission itself is responsible for the said situation.
68
If it has the power to regulate, as it has been contending, it should have
proceeded progressively and not regressively. It could have taken into
consideration the provisions of Section 11 (1)(f) whereby one of its
function is to promote competitiveness and progressively involve the
participation of private sector, while ensuring fair deal to the customers.
The Commission, as we have noticed, hereinbefore had been
waiting for some directions of the Government of Andhra Pradesh. It is
from that angle it must be held that the decision of the State to allow
MPPs. to generate electricity was a matter of policy. The Commission
for all intent and purport has frustrated the policy and object of the Act.
APTRANSCO in terms of Chapter V of the Act also acts as a statutory
authority. The Commission must function within the fourcorners of the
1998 Act. It is again subject to the power of the State Government under
Section 12. It has referred the matter again and again to the State and
when the State asked it to proceed in the manner, it backed out and
APTRANSCO was constituted with the principal object of engaging the
business of promoting and supply of electrical energy. It is required to
obtain licence for the said purpose. Sub-sections (4) and (5) of Section
13 of the 1998 read as under :-
69
“13.(4) APTRANSCO shall undertake the
functions specified in this section and such
other functions as may be assigned to it by the
licence to be granted to it by the Commission
under this Act.
(5) Upon the grant of licence to the
APTRNASCO under clause (a) of sub-section
(1) of Section 15 of this Act, the APTRNASCO
shall discharge such powers and perform such
duties and functions of the Andhra Pradesh
State Electricity Board including those under
the Indian Electricity Act, 1910 and the
Electricity (Supply) Act, 1948 or the rules
framed thereunder as the Commission may
specify in the licence and it shall be the
statutory obligation of the APTRNASCO to
undertake and duly discharge the powers,
duties and functions so assigned.”
We have held hereinbefore that licence under section 14 is
necessary but the same is only for transmission and supply and not for
generation of electrical energy. Such a licence is required so as to enable
the Commissioner to effectively control and regulate transmission and
supply. It is also relevant to note that Section 21 provides for restriction
on licensees and generating companies. Sub-section (4) empowers a
holder of supply or transmission licence to enter into arrangements for
the purchase of electricity. Sub-section (5) provides that any agreement
relating to any transaction of the nature described in any of the sub-
70
sections unless made with or subject to such consent as aforesaid, shall
be void. It, therefore, restricts the power and activities of APTRANSCO.
It is in the aforementioned situation that the doctrine of promissory
estoppel should be held to be applicable.
In Southern Petrochemical Industries Co. Ltd. vs. Electricity
Inspector and ETIO and others : (2007) 5 SCC 447, on the question of
doctrine of promissory estoppel, it was held :-
“121. The doctrine of promissory estoppel
would undoubtedly be applicable where an
entrepreneur alters his position pursuant to or in
furtherance of the promise made by a State to
grant inter alia exemption from payment of
taxes or charges on the basis of the current
tariff. Such a policy decision on the part of the
State shall not only be expressed by reason of
notifications issued under the statutory
provisions but also under the executive
instructions. The appellants had undoubtedly
been enjoying the benefit of ( sic exemption
from) payment of tax in respect of
sale/consumption of electrical energy in
relation to the cogenerating power plants.”
The Court further opined :
“128. In MRF Ltd. it was held that the doctrine
of promissory estoppel will also apply to
statutory notifications.”
71
As regards setting up of MPPs the principle of estoppel shall also
apply. It is now a well settled principle of law that nobody should suffer
for the wrong done to by a quasi-judicial body. In view of the principle
analogous to ‘ actus curiae neminem grvabit’ , we are of the opinion that
because of the unreasonable stand taken by APTRANSCO before the
Commission, LVS Powers should not suffer. In the aforementioned
situation the High Court has issued the directions.
APTRANSCO did not intend to increase its efficiency. It did not
equip itself so as to be able to compete with others. It might have been
in a disadvantageous position. On the one hand the Commission asked
for total prohibition for third party sale on the premise that it had to
supply electricity to agriculturist, but then when a situation came that it
must purchase the power pursuant to the impugned directions of the
Commission from MPPs it made a contradictory stand that MPPs can
sell the power outside the State.
Before us IDBI intervened. Indisputably it had granted financial
assistance to the first respondent-LVS Power. IPDB granted loan only
on the basis that the unit shall be functional.
72
th nd
This Court on 11 October, 2002 and 2 December, 2002 passed
interim orders
Mr. Shanti Bhushan states that the first respondent has been paid a
huge amount pursuant to the said orders and this Court may issue a
direction for refund thereof. We do not agree. The interim order by this
Court was passed to maintain a balance and in the interest of the parties.
We are, therefore, of the opinion that in this case interest of justice
would be subserved if in modification of the order passed by the High
Court, the impugned judgments are set aside and the Commission
constituted under the 2003 Act is directed to consider the matter afresh in
the light of the new statute.
We hope and trust that the Commission shall pass appropriate
orders upon taking into consideration all the material factors. It would
be at liberty to vary, modify, rescind the order of the old Commission and
issue directions as may be considered just and reasonable. It may, in the
changed situation, also allow the parties to effect third party sale. It will
be at liberty to evolve a scheme for revival of the companies, keeping in
73
view the public interest involved and in particular the interest of the
financial institutions. The time granted for completion of the projects
should be extended by one year. Till such time as the Commission may
not pass an appropriate interim order, the interim order passed by this
court shall continue.
The appeals are disposed of in the abovesaid terms. In the facts
and circumstances of the case, there shall be no order as to costs.
………………………….J.
[S.B. Sinha]
..…………………………J.
[ D.K. Jain ]
New Delhi;
May 16, 2008