Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Appeal (civil) 4315 of 1991
PETITIONER:
MOTILAL JAIN
Vs.
RESPONDENT:
SMT.RAMDASI DEVI & ORS.
DATE OF JUDGMENT: 20/07/2000
BENCH:
S.V.Patil, S.S.M.Quadri
JUDGMENT:
L.....I.........T.......T.......T.......T.......T.......T..J
J U D G M E N T SYED SHAH MOHAMMED QUADRI, J. This
appeal, by special leave, is directed against the judgment
of the Gauhati High Court (Assam) in First Appeal No.43 of
1981 passed on October 22, 1990. The plaintiff in the suit,
out of which this appeal arises, is the appellant and the
respondents are legal representatives of the defendant -
Ambika Prasad Ram. Hereinafter the parties will be referred
to as the plaintiff and the defendant. The plaintiff
entered into a contract with the defendant to purchase the
suit property for a consideration of Rs.25,000/- out of
which a sum of Rs.17,000/- was paid at the time of the
execution of the contract on February 20, 1977 (Ext.2); the
balance of the consideration, Rs.8000/-, was stipulated to
be paid within five months from the date of Ext.2, at the
time of execution of registered sale deed in favour of the
plaintiff. Alleging that the defendant was evading to
receive the balance amount of Rs.8000/- and execute the sale
deed, the plaintiff sent notices through his advocate on
March 15, 1978 (Ext.5), and again on April 4, 1978 (Ext.3)
and finally on November 26, 1978 (Ext.4). The plaintiff
then filed the suit, T.S.No.36 of 1979, against the
defendant in the court of the Assistant District Judge of
Goalpara at Dhubri, praying for a decree of specific
performance of contract for sale of the suit property
(Ext.1) and claimed in the alternative damages in the sum of
Rs.38,000/- on August 10, 1979. The defendant denied the
execution of Ext.2, receipt of Rs.17,000/- as part
consideration thereunder, his signature on it and submitted
that, therefore, the question of avoiding to execute the
sale deed would not arise. He pleaded that the appellant
was entitled to neither the specific performance of contract
nor the damages, the alternative claim. On considering the
evidence produced by the parties, the trial court found that
the defendant executed Ext.2 and decreed the suit for
specific performance of Ext.2 on July 25, 1981. The
defendant filed First Appeal No.43 of 1981 against the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
judgment of the trial court in the Gauhati High Court
(Assam). During the pendency of the appeal the said
defendant died and the respondents were brought on record as
his legal representatives. The High Court confirmed the
finding of the trial court that the defendant executed Ext.2
but noted: (i) that the suit was filed after two years of
the accrual of the cause of action on July 21, 1977 and
after about one year of last notice issued on November 26,
1978 (Ext.4); (ii) from the averment in the plaint the
readiness and willingness could not be inferred; and (iii)
even assuming that the averment made out the readiness and
willingness, there was no evidence to prove the readiness
and willingness of the plaintiff. In that view of the
matter, by the impugned judgment, the High Court set aside
the judgment of the trial court with regard to relief of
specific performance of the contract (Ext.2) but granted a
decree for compensation in a sum of Rs.22,094/-(Rs.17,000/-
counsel for of the
findings of of the
such delay of as
Ext.2. He of brought
to show of readiness
perform his of part
with the of requirements
Relief Act, of 1963,
of Appendix of A
decision of of this
Vs. of Chuni
1971 SC of 1238]
Judges Bench of in
[1999 (6) of SCC
judgment of of the
Jain (PW of 1)
in proof of of
Mr.N.R. of Choudhary,
contended that of paras
to Forms of 47
Civil Procedure of and
in Ouseph of Varghese
539] and of Abdul
1990 SC of 682).
framed an of issue
appellant but of it
the trial of court
further contended of that
wife is of the
existence Ext.2 of which
justify granting of of
performance and of the
Here, the of short
the High of Court
which the of High
suit. of It
of of delay
performance of of contract
Delay running of beyond
Limitation Act; of (ii)
is within of the
the third of parties
of suit; of
delay may of give
be inequitable of to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
of of the
factually also, of the
assumption with of regard
executed on of February
to be of executed
was issued of on
was filed of only
year as of noted
this case of the
relief to of the
favour from of the
show that of the
part of of the
record to of prove
placing reliance of on
In that of case,
sale of of the
oral agreement of and
to which of the
subsequent pleading of and
Court pointed of out
should conform of to
the Code of of
Abdul Khaders of case
struck by of this
case A of agreed
was not of having
Government nor of was
however, received of earnest
for sale of which
would be of paid
the registered of sale
obligation to of obtain
Government before of the
not take of any
Government. of A
the contract of for
was that of A
of the of contract.
willingness could of not
and that of had
circumstances relevant of to
party concerned. of
material to of show
willing to of perform
have the of necessary
would be of executed
entitled to of a
That decision of was
this Court of in
held that of in
keep in of mind
science but of an
law of of ones
India most of of
they inevitably of differ
gather true of spirit
whole and of to
obligations, one of has
plea. of It
requires a of plea
any form. of No
to take of such
Specific Relief of Act,
phraseology but of only
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
has performed of or
his part of of
and willingness of has
in letter of and
readiness of and
mathematical formula of which
If the of averments
indicate the of readiness
fulfil his of part
is subject- of matter
differently worded of will
and willingness of of
performance of of contract
perusal of of paras
the readiness of and
obligation which of he
balance of of consideration.
the defendant of to
Rs.8000/- and of execute
Patna (Bihar) of at
to his of place
support of of his
Special Leave Petition (crl.) of The
consideration at of the
no reason of why
consideration of of Rs.8,000/-
his favour. of We
that the of conduct
relief of of specific
Mr.Choudhary of that
compensation in of lieu
disentitled to of claim
contract, is of to
claim was of in
Specific Relief of Act,
claims damages of in
contract as of alternative
not entitled of to
contract itself. of
Court is of sustainable
judgment and of decree
judgment of of the
accordingly we of do
the trial of court.
deposited the of balance
judgment of and
representatives of of the
ordered to of execute
within three of months
plaintiff is of entitled
defendant/respondents. to of receive
to of receive