Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2908 OF 2022
UTTAR HARYANA BIJLI VITRAN
NIGAM LIMITED AND ANOTHER ...APPELLANT(S)
VERSUS
ADANI POWER (MUNDRA)
LIMITED AND ANOTHER ...RESPONDENT(S)
J U D G M E N T
B.R. GAVAI, J.
1. The present appeal challenges the judgment and order
st
dated 21 December 2021 passed by the Appellate Tribunal
for Electricity (hereinafter referred to as ‘APTEL’), in Appeal
No. 231 of 2021, filed by the appellants herein, thereby
th
challenging the order dated 8 July 2019, passed by Central
Electricity Regulatory Commission (hereinafter referred to as
‘CERC’) in Petition No. 269/MP/2018. The APTEL has held
Signature Not Verified
th
the communication dated 19 June 2013, issued by Coal
Digitally signed by
Narendra Prasad
Date: 2023.04.20
11:59:44 IST
Reason:
1
India Limited (for short, “CIL”) not to be a ‘Change in Law’
event.
2. The facts, in brief, giving rise to the present appeal are
as under:
The respondent No.1 – Adani Power (Mundra) Limited
(hereinafter referred to as “AP(M)L”) had set up a generating
station of capacity 4620 MW (Phase I & II – 4 x 330 MW,
Phase III – 2 x 660 MW and Phase IV – 3 x 660 MW) at
Mundra in the State of Gujarat. AP(M)L had entered into
Power Project Agreements (hereinafter referred to as “PPA”)
th
dated 7 August 2008 with Uttar Haryana Bijli Vitran Nigam
Limited and Dakshin Haryana Bijli Vidyut Nigam Limited
(hereinafter referred to as “Haryana Utilities”), the appellants
herein, for supply of 1424 MW power from Phase IV of the
generating station.
th
3.
CERC, vide its order dated 6 February 2017, allowed
the compensation towards certain ‘Change in Law’ events
claimed by AP(M)L in Petition No. 156/MP/2014. AP(M)L has
submitted that Haryana Utilities were already making
payments in terms of the supplementary invoices raised by
2
AP(M)L. Subsequently, on account of the judgment of this
Court in the case of Energy Watchdog v. Central
1
Electricity Regulatory Commission and Others , AP(M)L
filed another petition being Petition No. 97/MP/2017
claiming compensation on account of change in New Coal
Distribution Policy, 2007 (for short, “NCDP 2007”).
Subsequently, certain interim directions were issued by
CERC. Haryana Utilities, thereafter, filed I.A. No. 21 of 2018
in Petition No. 97/MP/2017, stating therein that the
compensation as claimed by AP(M)L was incorrect inasmuch
as AP(M)L had not taken into consideration the benefits
accruing to them on account of Inter Plant Transfer (for
th
short, “IPT”) permitted under the communication dated 19
June 2013 issued by CIL.
4. Per contra, it was claimed by AP(M)L that the Haryana
Utilities unilaterally revised a huge amount from the monthly
bills on the ground of IPT. It was submitted by AP(M)L that
the contention of the Haryana Utilities with regard to IPT has
st
already been rejected by CERC in its order dated 31 May
2018.
1 (2017) 14 SCC 80
3
5. In this background, AP(M)L filed Petition No.
269/MP/2018 before CERC claiming the following reliefs:
“(a) Clarify and declare that the findings of this
Ld. Commission at paragraph 61 of the Order
of the Commission dated 31.05.2018 in
Petition No. 97/MP/2017 and IA No. 21 of
2018, are applicable to the Change in Law
compensation pertaining to taxes and duties
approved under Order dated 06.02.2017 in
Petition No. 156/MP/2014 as well; and
(b) Direct the Respondents to pay Rs. 895.41
Crores (Rs. 566.83 Crores related to Domestic
Coal Shortfall + Rs. 328.58 Crores related to
taxes and duties) unilaterally deducted from
the monthly bills/supplementary invoices
along with the applicable Late Payment
Surcharge.”
6. CERC framed the following issues:
“Issue No.1: Whether the Petition is
maintainable under Section 142 of the Act?
Issue No. 2: Whether our finding in respect of
IPT coal at Para 61 of the order dated
31.5.2018 in Petition No. 97/MP/2017 is
applicable for the compensation payable for
various taxes and duties approved as change
in law in the order dated 6.2.2017 in Petition
No. 156/MP/2014?
Issue No. 3: What should be the treatment of
Inter Plant Transfer of Coal, if it is considered
as change in law?
4
Issue No. 4: What should be the basis for
calculating shortfall of domestic coal?”
7. Insofar as Issue No. 1 is concerned, CERC held the
dispute to be maintainable.
8. Insofar as Issue No. 2 is concerned, CERC held that in
th
view of its order dated 6 February 2017 in Petition No.
156/MP/2014, the coal supply, under Fuel Supply
th
Agreement (for short, “FSA”) dated 9 June 2012, to other
plants has to be accounted for the generation and supply of
power to Haryana Utilities from Units 7, 8 and 9 of Mundra
TPP for all commercial purposes. It, therefore, rejected the
contention of Haryana Utilities that it was liable to pay taxes
and duties only for the coal that it has actually consumed
and not for IPT coal.
9. Insofar as Issue No. 3 is concerned, CERC held that the
transfer of coal by AP(M)L under IPT Policy also affects other
generating stations that are consuming IPT coal and other
distribution companies who are also supplied power by the
generating stations that have used IPT coal. Since other
distribution companies were not parties to the proceedings
5
before CERC, it did not find it appropriate to deal with the
issue.
10. Insofar as Issue No. 4 is concerned, CERC, in view of
the judgment of this Court in the case of Energy Watchdog
(supra), held that the quantum of shortfall has to be
calculated taking into consideration the Assured Coal
Quantity (for short, “ACQ”) and the quantity actually
supplied by the coal companies.
11. Being aggrieved thereby, Haryana Utilities filed an
appeal before APTEL.
12. Insofar as Issue No. 4 is concerned, APTEL, vide its
st
judgment and order dated 21 December 2021, relying on
Energy Watchdog
the judgment of this Court in the case of
(supra), held that ‘Change in Law’ compensation needs to be
calculated as ACQ – actual supply.
13. Insofar as the issue with regard to communication
th
dated 19 June 2013 being ‘Change in Law’ is concerned,
APTEL held the same not to be ‘Change in Law’. Being
aggrieved thereby, the present appeal.
6
14. We have heard Shri Shubham Arya, learned counsel
appearing on behalf of the appellants and Dr. A.M. Singhvi,
learned Senior Counsel appearing on behalf of the
respondents.
15. Shri Arya submitted that, considering the definition of
th
“Law” given in the PPA, the communication dated 19 June
2013 would squarely fall under the term “Law”. He
submitted that in any case, CERC had refused to answer the
said issue in the absence of other distributors. It is
submitted that APTEL has grossly erred in holding the same
not to be a ‘Change in Law’ event.
16. Dr. Singhvi, on the other hand, submitted that the
th
communication dated 19 June 2013 is an inter-
departmental communication and the same cannot be held
to be ‘Change in Law’.
17. When we heard this batch of Electricity appeals, it was
agreed between all the parties that this Court should first
decide Civil Appeal No. 684 of 2021 ( Maharashtra State
Electricity Distribution Company Limited v. Adani Power
7
| Maharashtra Limited and Others2) [“MSEDCL v. APML<br>and Others”, for short] and Civil Appeal No. 6927 of 2021<br>(Maharashtra State Electricity Distribution Company<br>Limited v. GMR Warora Energy Ltd. and Others)<br>inasmuch as three of the issues involved in all the appeals in<br>the batch were common. It was submitted that those two<br>appeals could be decided by deciding the three common<br>issues. However, insofar as the other appeals are concerned,<br>it was submitted that, in addition to the three common<br>issues, certain additional issues were also involved and it was<br>agreed that after those two appeals are decided, the other<br>appeals should be heard for considering these additional<br>issues. | |
|---|---|
| 18. The said three common issues are thus: | |
| (i) Whether ‘Change in Law’ relief on account of NCDP<br>2013 should be on ‘actuals’ viz. as against 100% of<br>normative coal requirement assured in terms of<br>NCDP 2007 OR restricted to trigger levels in NCDP |
2 2023 SCC OnLine SC 233
8
2013 viz. 65%, 65%, 67% and 75% of Assured Coal
Quantity (ACQ)?
(ii) Whether for computing ‘Change in Law’ relief, the
operating parameters be considered on ‘actuals’
OR as per technical information submitted in bid?
(iii) Whether ‘Change in Law’ relief compensation is to
st
be granted from 1 April 2013 (start of Financial
st
Year) or 31 July 2013 (date of NCDP 2013)?
19. After extensively hearing all the learned counsel for the
rd
parties, vide the judgment and order dated 3 March 2023 in
the case of MSEDCL v. APML and Others (supra), this Court
decided those two appeals after considering the aforesaid
three issues.
20. The first issue was answered by this Court, holding that
the ‘Change in Law’ relief for domestic coal shortfall should
be on ‘actuals’ i.e. as against 100% of normative coal
requirement assured in terms of NCDP, 2007. Insofar as the
second issue is concerned, it was held that the Station Heat
Rate (“SHR” for short) and Auxiliary consumption should be
9
considered as per the Regulations or actuals, whichever is
lower. The third issue was answered holding that the Start
st
date for the ‘Change in Law’ event for the NCDP, 2013 is 1
April 2013.
21. As such, Issue No. 4 stands squarely covered by our
rd
judgment dated 3 March 2023 in the case of MSEDCL v.
APML and Others (supra) so also by the earlier judgment of
this Court in the case of Energy Watchdog (supra).
22. Insofar as Issue Nos. 2 and 3 are concerned, we find
that the said issues are interlinked and the same would
depend on the decision as to whether the communication
th
dated 19 June 2013 providing for IPT would amount to
‘Change in Law’ or not.
23. It will be relevant to refer to the definition of “Law” as
defined under the PPA, which reads thus:
“Law means, in relation to this Agreement, all
taws including Electricity Laws in force in
India and any statute, ordinance, regulation,
notification or code; rule, or any interpretation
of any of them by an Indian Governmental
Instrumentality and having force of law and
shall further include all applicable rules,
regulations, orders, notifications by an Indian
Governmental Instrumentality pursuant to or
under any of them and shall include all rules,
10
regulations, decisions and orders of the
Appropriate Commission.”
24. It can, thus, clearly be seen that the definition of “Law”
is wide enough to include all rules, regulations, orders,
notifications by the Governmental instrumentalities.
25.
It will be relevant to refer to the communication dated
th
19 June 2013, which reads thus:
“ Sub: Modification in Model FSA applicable
for New Power plants in respect of
“Interplant transfer of coal”
A proposal for allowing inter power plant
transfer of coal from one Power Plant to
another under the modified FSA applicable for
New Power Plants (for both PSU/Govt. PUs and
Private PUs ) was placed before the 298th CIL
Board in its Meeting held on 27.5.13.
The CIL Board while approving to the proposal
allowed such dispensation subject to the
following conditions which stand as below after
legal vetting.
a) Transfer of coal shall be allowed only
between the power plants wholly owned by
the Purchaser or its wholly owned
subsidiary. No transfer of coal shall be
allowed for a JV company of the Purchaser.
The supply of coal, shall for all commercial
purpose under the FSA remain unchanged
and on account of the original Power Plant.
b) Both the Power Plants should have executed
FSA in the modified FSA Model applicable
11
for new power plants and not having any
supplies linked to coal blocks. In case of
IPPs both the plants must have valid long
term PPAs with DISCOMS.
c) In no case the transferred quantity to a
plant together with the quantity supplied
under the applicable FSA shall exceed the
ACQ of the Transferee Plant for a particular
year which is proportional to the long term
PPA with DISCOMS.
d) Transfer of coal will not be allowed to those
plants who are allotted coal blocks under
this arrangement.
e) In case of change in the ownership and no
environmental clearance of the plant this
facility shall stand withdrawn, and
f) Penalty/ incentive under this arrangement
would be considered in terms of (a) above.
A statement showing the modification in the
FSA models applicable for New Power plants
(for both PSU/ Govt. PUs and Private PUs) is
enclosed.”
26. It can thus be seen that the said communication refers
th
to the decision of the CIL taken in its meeting held on 27
May 2013. A perusal thereof would reveal that the transfer
of coal which was not allowed hitherto, has been allowed only
between the power plants owned by the purchaser or its
wholly owned subsidiary. It further provides that no transfer
of coal shall be allowed for a JV Company of the purchaser.
12
It further provides that the supply of coal shall, for all
commercial purpose under the FSA, remain unchanged and
on account of the original Power Plant. It further provides
that both the Power Plants should have executed FSA in the
modified FSA Model applicable for new power plants and not
having any supplies linked to coal blocks. It further provides
that in case of IPPs, both the plants must have valid long
term PPAs with DISCOMS. It further provides that in no
case the transferred quantity to a plant together with the
quantity supplied under the applicable FSA shall exceed the
ACQ of the Transferee Plant for a particular year which is
proportional to the long term PPA with DISCOMS. It further
provides that transfer of coal will not be allowed to those
plants who are allotted coal blocks under this arrangement.
It further provides that in case of change in the ownership
and no environmental clearance of the plant, this facility
shall stand withdrawn.
27. It could thus be seen that the said communication
reflects the decision of CIL. The CIL is an instrumentality of
the Government of India. As such, we find that APTEL erred
13
th
in holding the said communication dated 19 June 2013 not
to amount to ‘Change in Law’.
28. APTEL has held that the said communication is an
administrative instruction addressed to all the subsidiaries.
It will be apposite to refer to the following findings of APTEL:
“109. There is no denial of the fact that the
letter dated 19.06.2013 addressed by CIL
intimating to all subsidiaries the decision
th
taken at its 298 board meeting (27.05.2013),
allowing IPT of coal was conditional upon
transfer (of coal) to be allowed only between
the power plants wholly owned by the
purchaser or its wholly owned subsidiary and
supply of coal for all commercial purpose
under the FSAs to remain unchanged and on
account of original power plant. In particular
context of the first respondent, it follows as a
sequitur that IPT of coal is allowable if Mundra
TPS transfers its portion of linkage coal from
MCL coal mine, Talcher to Tiroda TPS (both
owned by Adani group) for utilization of such
coal at Tiroda TPS and that even though
linkage coal from MCL coal mine, Talcher of
Mundra TPS (original power plant in terms of
the FSA) was actually utilized at Tiroda TPS
(transferee plant), it will be accounted as if it
were consumed at Mundra TPS. To put it
simply, the effect of IPT of coal is that IPT coal
cost (linkage domestic coal) will continue to be
booked in the account of Mundra TPS (original
power plant in terms of the FSA/transferor
plant under IPT scheme) and alternate coal
cost (imported coal or market-based e-auction
coal used in the absence of linkage coal) will
continue to be booked on ‘attributed cost’
14
basis in the accounts of Tiroda TPS (transferee
plant under IPT scheme).”
29. We find that APTEL has failed to take into consideration
that CERC had not decided the said issue, inasmuch as the
decision on the said issue would have affected the other two
DISCOMS, i.e., MSEDCL and Rajasthan DISCOMS. It will
further be relevant to note that the very same Tribunal,
immediately after three months, in the case of Rattan India
Power Limited v. Maharashtra Electricity Regulatory
3
Commission and Another , has taken a totally contrary
view. In the said case, it was sought to be argued on behalf
of MSEDCL that the Evacuation Facility Charge (for short,
th
“EFC”) imposed by CIL vide its circular dated 19 December
2017 did not constitute ‘Change in Law’. It will be apposite
to refer to the following observations:
“9. It is incorrect to argue that to be covered as a
change in law event under such contractual clauses
as quoted earlier, the instrument whereby the law is
claimed to have undergone a change must have
been published in official gazette to have the force of
law. In Energy Watchdog & Ors. (supra), for
illustration, even a letter of the Ministry of Power in
nd
3 Appeal Nos. 118 of 2021 and 40 of 2022 dated 22 March 2022
15
the Government of India was accepted as an
instrument having the “force of law”. Similarly, in
Kusum Ingots & Alloys v. Union of India (2004) 6
SCC 254 executive instructions without any
statutory backing were also considered as “law”.
That Coal India is Government instrumentality and
the notifications, circulars, etc. issued by it have a
force of law under Regulation 77(3) of the
Constitution of India was accepted by this tribunal
in GMR Kamalanga Energy Ltd. (supra).”
30. Vide judgment of even date, in Civil Appeal Nos. 5005 of
2022 and 4089 of 2022, we have upheld the concurrent view
of Maharashtra Electricity Regulatory Commission (for short,
“MERC”) and APTEL holding the said EFC to be ‘Change in
Law’.
31. In that view of the matter, we are of the opinion that the
th
finding of APTEL that the communication dated 19 June
2013 permitting IPT is not a ‘Change in Law’ would not be
sustainable.
32. It is to be noted that, while submitting the bid, AP(M)L
must have factored in the cost of transportation of linkage
coal from MCL Coal Mine, Talcher to its plant at Mundra. As
per the details given in the PPA, the mode of transportation is
through railway. As such, prior to the IPT being permitted,
16
AP(M)L was bound to utilize the linkage coal from MCL Coal
Mine, Talcher, only for the purpose of its original power
plant, i.e., AP(M)L. Only on account of the IPT would it be in
a position to utilize the coal from MCL Coal Mine, Talcher
either for its plant in Maharashtra or in Rajasthan.
Similarly, it will be entitled to utilize the coal linkages for its
plant in Maharashtra or in Rajasthan for production of
energy in its other power plants. As such, there is bound to
be a variance in the cost of transportation by railways. For
example, if the coal is to be transported from MCL Coal Mine,
Talcher to AP(M)L, the cost of railway transportation would
be higher as compared to the cost of railway transportation
from MCL Coal Mine, Talcher to Tiroda TPS. We are only
giving this example as an illustration. We find that the
savings made in the cost of transportation, i.e., the cost
which would have been incurred for transporting the coal
from MCL Coal Mine, Talcher to ‘X’ plant minus the actual
cost of transportation has to be passed on to the DISCOMS,
which, in turn, has to be passed on to the end consumers.
For example, if the cost of transportation per ton from MCL
17
Coal Mine, Talcher to AP(M)L is Rs.100/- and from MCL Coal
Mine, Talcher to Tiroda TPS is Rs.50/- per ton, the benefit of
Rs.50/- per ton will have to be passed on.
33. We, however, find that the changes occurring on
account of permitting IPT would affect AP(M)L as well as the
appellants and two other DISCOMS, i.e., MSEDCL and
Rajasthan DISCOMS. This was also observed by the CERC in
th
its order dated 8 July 2019. We do not possess any
expertise for working out as to what benefit any of the parties
would be entitled to on account of the said ‘Change in Law’.
However, we are of the considered view that cost of saving in
the railway transportation on account of ‘Change in Law’ in
the light of our observation in the aforesaid paragraph needs
to be worked out and passed on to the appropriate
DISCOMS, which can further be passed on to the consumers.
CERC, which is a body of experts, is best suited to do so.
34. We, therefore, find that the present appeal deserves to
be partly allowed. Though the issue with regard to allowing
‘Change in Law’ compensation on the basis of ACQ – actual
18
supply deserves to be upheld, the issue with regard to IPT
not being ‘Change in Law’ deserves to be set aside.
35. In the result, we partly allow the appeal and pass the
following order:
(i) The finding of the APTEL to the effect that the
th
communication dated 19 June 2013 providing for
IPT does not amount to ‘Change in Law’ is set
aside;
(ii) We hold that IPT amounts to ‘Change in Law’.
36. In the light of our observations made in paragraphs 32
and 33, the matter is remitted to CERC for working out the
effect of the aforesaid ‘Change in Law’ after giving notice to
MSEDCL as well as Rajasthan DISCOMS and hearing all the
parties including the appellants and the respondents herein.
37. However, since the said issue has been pending since a
long time, we direct CERC to decide the said issue and
calculate the benefits that would be accruable to any of the
parties within a period of six months from today.
38. Pending application(s), if any, shall stand disposed. No
costs.
19
…..….......................J.
[B.R. GAVAI]
…….........................J.
[VIKRAM NATH]
NEW DELHI;
APRIL 20, 2023.
20