G.A. BUILDERS PVT. LTD. vs. CHEMBUR NISHANT CHS LTD.

Case Type: N/A

Date of Judgment: 27-11-2012

Preview image for G.A. BUILDERS PVT. LTD. vs. CHEMBUR NISHANT CHS LTD.

Full Judgment Text


.. 1 ..    ARBAP­248/12
                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY .
                     ORDINARY  ORIGINAL CIVIL JURISDICTION  
 
               ARBITRATION APPLICATION NO.248 OF 2012
   
                        
G.A.BUILDERS PRIVATE LIMITED,   )
a company registered under the provisions  )
of the Companies Act, 1956 and a Group  )
Company of RNA Builders (A.A.) and having  )
its registered office at RNA Corporate Park,   )
next to Collector Office, Govt. Colony, 
Bandra (East), Kala Nagar, Mumbai – 400 051.      )   ...  Applicant. 
V/s.
CHEMBUR NISHANT CO­OPERATIVE 
HOUSING SOCIETY LIMITED,   )
a society registered under the Maharashtra   )
Co­operative Societies Act, 1960, having   )
its registered office at Building No.32,  ) 
Subhash Nagar, Chembur,  )
Mumbai 400 071.    )  ... Respondent. 
Mr Pratik Sakseria, with Ms. Nidhi Singh i/b M/s Vidhi Partners for the 
Petitioner. 
Mr Niranjan Shimpi i/b  Kishore G. Nagavekar for the Respondent. 
           CORAM :  R.D.DHANUKA  J.
          DATED  : NOVEMBER 27, 2012. 
JUDGMENT  
1.    By   this   application   filed   under   Section   11   of   the   Arbitration   and 
Conciliation Act 1996, applicant seeks appointment of Arbitrator relying upon 
Clause­47 of the alleged agreement dated 27 February 2010.  
Asmita
    1/6
::: Downloaded on - 26/06/2024 07:31:28 :::

.. 2 ..    ARBAP­248/12
2.  Respondent Society is owner of a plot of land adm.896.98 sq.metres 
along with building thereon being building no.32,  known as 'Chembur Nishant 
Co.Op. Housing Society Ltd',  bearing Survey No.67 to 71,  C.T.S. No. 826 situate 
at Subhash Nagar, Chembur.   The building was in need of urgent repairs.  It is 
the case of the applicant that the Society had proposed to redevelop the property. 
By letter dated 23 January 2009, applicant gave terms of the development to the 
respondent   Society.     On   1   February   2009,   Special   General   Meeting   of   the 
respondent Society came to be held in which, members unanimously gave their 
consent   and   approval   to   the   development   proposal   to   be   furnished   by   the 
applicant.  It is the case of the applicant that on 27 February 2010, applicant and 
respondent Society entered into development agreement,   whereby respondent 
Society agreed to grant development rights in respect of the property to the 
applicant.   
3.  It is the case of the applicant that the applicant paid a sum of Rs.
1,54,82,752/­ to Maharashtra Housing & Area Development Authority (MHADA) 
for seeking necessary application/permission for allotment of additional buildable 
area.   It is not in dispute that applicant submitted Confirmation Deed dated 17 
June 2011 and got the said alleged agreement registered unilaterally.    
   
Asmita
    2/6
::: Downloaded on - 26/06/2024 07:31:28 :::

.. 3 ..    ARBAP­248/12
4.  The applicant,   thereafter by letter dated 30 September 2011 called 
upon   the   Society   to   execute   irrevocable   Power   of   Attorney   in   its   favour   in 
accordance with the said alleged agreement dated 27 February 2010.  It is the 
case of the Society that Society has not received any such alleged letter dated 30 
September 2011.  
5.  The   applicant   thereafter   issued   notice   invoking   alleged   arbitration 
clause and filed this application for appointment of Arbitrator.   
6.  The respondent Society has filed detailed affidavit­in­reply.   It is the 
case of the Society that a draft of the proposed agreement to be finalized was 
furnished by the applicant to the Society which was undated consisting many 
blanks.        It  is  submitted  that  the  applicant  had  obtained  signature  of  the 
members of the Society on the said draft copy of the proposed agreement to be 
finalized,  by misrepresenting them that a member would get partial amount from 
the developer at the time of execution.  However, none of the members received 
any amount from the applicant.   It is averred in the affidavit that the applicant 
obtained consent of the members by playing fraud upon them.  It is averred that 
the agreement being relied upon by the applicant is unilaterally registered with 
Deed of Confirmation,  which is a manipulated document and is different than 
the copy of the agreement which was furnished to the respondent Society.  It is 
Asmita
    3/6
::: Downloaded on - 26/06/2024 07:31:28 :::

.. 4 ..    ARBAP­248/12
averred   that   petitioner   is   relying   upon   a   fabricated   document   and   is   thus 
unenforceable as against the respondent Society which the Society and/or its 
members have not executed at any point of time.  
 
7.  The learned counsel appearing for the applicant submits that it is not 
in dispute that Society passed a resolution to enter into development agreement 
with the applicant.  It is submitted that there is no dispute that copy of agreement 
being relied upon by the Society consists seal of the Society and also signature of 
office bearers.  It is submitted that initial consideration agreed to be paid by the 
applicant to the members was though tendered by the applicant to the members, 
the same was not accepted.    It is submitted that pursuant to the agreement, the 
applicant has taken steps and has paid a substantial amount to MHADA.    It is 
submitted that since the respondent Society has refused to comply with their part 
of obligation, dispute has arisen and thus, matter is required to be referred to 
arbitration under Clause­47 of the agreement.  
8.  The learned counsel appearing on behalf of the respondent Society on 
the other hand,   submits that applicant has manipulated and fabricated the 
material clause of the agreement as well as has played fraud in execution of the 
agreement.     It is submitted that only a draft agreement was furnished to the 
respondent Society.  Applicant never paid any consideration amount.  The final 
Asmita
    4/6
::: Downloaded on - 26/06/2024 07:31:28 :::

.. 5 ..    ARBAP­248/12
terms   and   conditions   of   the   agreement   were   never   agreed.     According   to 
respondent Society,  the terms and conditions of the final Deed of Development 
Agreement were not concluded and thus, no agreement has been arrived at.  The 
learned counsel for the respondent Society invited my attention to Clause­21 of 
the draft agreement,  which was furnished to the Society,  which has been scored 
off by the applicant in the agreement dated 27 February 2010 relied upon by the 
applicant.  The learned counsel invited my attention to various recitals and other 
clauses of the alleged agreement to demonstrate that various blanks which were 
found in the draft development agreement furnished to the respondent Society 
had been subsequently filled up.  It is submitted that after furnishing the draft of 
the agreement proposed to be entered into, the applicant never furnished any 
document nor any terms were finalized.  It is submitted that thus,  when there are 
serious allegations of forgery,  manipulation and fabrication in the material terms 
of the agreement and the agreement not having been concluded, dispute cannot 
be referred to the Arbitrator and such dispute can only be decided by the Civil 
Court.   
9.  On my query raised to the learned counsel appearing for the applicant, 
the learned counsel fairly admitted, on taking instructions, that copy of the 
agreement dated 27 February 2010 relied upon by the applicant, was never 
Asmita
    5/6
::: Downloaded on - 26/06/2024 07:31:28 :::

.. 6 ..    ARBAP­248/12
furnished to the respondent Society.  It is admitted position that at no point of 
time further consideration was offered to the Society.       It is also admitted 
position that before signing the Deed of Confirmation and getting the document 
registered, Society was never informed.   It is also admitted position that before 
making   payment   to   MHADA,   applicant   never   obtained   consent   from   the 
respondent Society.  
10.  The record produced by both the parties indicates that there is serious 
dispute about existence of arbitration Agreement. It is admitted position that 
there is difference in the copy of the agreement relied upon by the applicant and 
the copy furnished to the respondent Society.  The copy, admittedly furnished to 
respondent Society, does not bear signature of the applicant whereas copy relied 
upon by the applicant bears signature of the applicants.  
11.     In view of these   serious allegations of forgery, fabrication and 
manipulation and in the circumstances aforesaid, I am of the view that such 
dispute cannot be referred to arbitration and can be tried only by Civil Court. 
Application is therefore rejected. 
12. There shall be no order as to costs.  
                  ( R.D.DHANUKA, J.)
Asmita
    6/6
::: Downloaded on - 26/06/2024 07:31:28 :::