Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
PETITIONER:
MARKET COMMITTEE, HODAL
Vs.
RESPONDENT:
KRISHAN MURARI & ORS.
DATE OF JUDGMENT06/11/1995
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
KIRPAL B.N. (J)
CITATION:
1996 SCC (1) 311 JT 1995 (8) 494
1995 SCALE (6)485
ACT:
HEADNOTE:
JUDGMENT:
O R D E R
Leave granted.
Having heard the learned counsel on both the sides we
think that it is a case for our interference. Though there
is an inordinate delay of 3240 days, merely 9 years, from
February 26, 1985 to May 30, 1994, the date on which S.L.P.
was filed, there is proper explanation given by the
appellants in this case for the inordinate delay in filing
the appeal. It was not in dispute that the matter was sent
to the Central Agency and since the matter is of the State
of Haryana, the Central Agency did not pursue the matter.
When it was discovered that the Central Agency had not taken
the steps in filing the appeal, the S.L.P. came to be filed
on May 30, 1994. The explanation offered is just and
rational and can be acceptable. It is accordingly accepted.
Delay is accordingly condoned.
It is contended by Shri Datta, learned Senior counsel
for the respondents that on account of the delay the
appellants have constructed oil mill expending considerable
money. Though they have received the compensation under
protest the respondents are prepared to return the
compensation with suitable interest as may be determined by
the Court and that, therefore, it may not be a case
warranting interference. We find that there is no
justification for accepting the contention.
It is seen that the notification under s.4(1) of the
L.A. 1 of 1994 for short ‘the Act’ was published on January
22, 1981. Declaration under s.6 was published on January 23,
1981. and possession was taken on April 29, 1981. "though it
is claimed that the possession was with the respondent". The
award came to be made on April 19, 1984. Compensation was
offered as required under s. 31 of the Act and it now
transpires, though it was not mentioned in the High Court,
that the amount was received under protest. The Writ
Petition was filed four months thereafter, namely, on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
December 19, 1984. The High Court allowed the Writ Petition
on February 16, 1985 holding that dispensing with enquiry
under s.5A is invalid. It would be seen that the award
having been validly made on May 19, 1984 and possession of
the lands having been taken, the lands vest in the
Government under s.16 absolutely free from all encumbrances.
The High Court was not justified in interfering with the
exercise of power by the Government under s.17(4) dispensing
with the enquiry under s.5A at that belated stage. Under
these circumstances the appeal is to be allowed.
However, since the respondents had claimed to have
constructed the oil mill, on the facts and circumstances in
this case, it would be proper that the District Judge,
Faridabad is directed to have an enquiry made as to when the
oil mill came to be constructed. If it was constructed
between January 22, 1985 and December 19, 1984 or pending
writ petition without permission of the court, the
respondents are not entitled to claim any equities by way of
compensation. On the other hand, if the mill came to be
constructed after February 16, 1985 i.e. after writ petition
was allowed till date, then equity requires that the
appellants shall have to make ex-gratia compensation for the
value of the building. The learned District Judge also would
cause an enquiry to be made with regard to the value of the
construction that was made on. In the event of the finding
that it was constructed after the judgment of the High
Court, the appellant shall pay the compensation for the
value of the construction of the mill within a period of
four months from the date of the decision made by the
learned District Judge. If the respondents had not made any
application for reference, it may be open to them to make
the application under s.18 within one month from today.
The appeal is accordingly allowed. No costs.