Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 2466 of 2005
PETITIONER:
Amarendra Komalam & Anr.
RESPONDENT:
Usha Sinha & Anr.
DATE OF JUDGMENT: 07/04/2005
BENCH:
Ashok Bhan & Dr. AR. Lakshmanan
JUDGMENT:
J U D G M E N T
(Arising out of S.L.P. (Civil) No. 21945 OF 2003)
Dr. AR. Lakshmanan, J.
Leave granted.
The main issue that arises for consideration in this appeal is whether an issue,
already settled in a suit between the same parties in respect of certain subject matter,
can be allowed to be raised again between the very same parties in regard to the same
subject matter, but in a different suit.
The issue involved in the earlier proceedings was whether respondent No.1
could raise the issue that there was interpolation in the clause relating to renewal of
lease deed in the agreement between the parties dated 02.09.1978. The High Court
held that the said respondent could not raise that issue as she had expressly given it
up. This was affirmed by this Court when the respondent challenged the order of the
High Court before this Court in S.L.P.(C) No. 16513 of 2001 dated 13.09.2002. Now
respondent No.1 seeks to re-agitate the very same issue in another suit between the
same parties. According to the appellants, the said issue cannot now be raised as the
said respondent is barred by the principles of res judicata, waiver and estoppel.
However, the sub-Judge as also the High Court of Patna have now allowed the
respondent to raise the said issue.
To appreciate the above question, the following facts are necessary to be
stated:
Appellant No.1, Amarendra Komalam, is a lessee of a piece of land situated at
Mauza Dujra, Lodhipur Market, now in the city of Patna. Appellant No.2, M/s S.K. Puri
Service Station, is a petroleum dealership firm. Respondent No.1, Smt. Usha Sinha, is
the land owner and respondent No.2 is M/s I.B.P. Co. Ltd., a Government of India
Undertaking company, which has given the dealership of the petroleum outlet to
appellant No.1.
Pursuant to the negotiations between the parties for taking the land in question
on lease for opening of the petroleum outlet, an application was filed by the appellant to
M/s I.B.P. Co. Ltd. for approval of the site of the land in question for motor spirit outlet
.
A letter was issued by M/s I.B.P. Co. Ltd. to appellant No.1 specifying in detail the
requirement of a renewal clause in the Lease Deed Agreement. Vide Memo No. 4788,
the office of the District Magistrate, Patna issued no objection certificate for installatio
n
of HSD filling station on the aforesaid land in question in favour of appellant No.1.
Lease deed for a period of 15 years was executed by respondent No.1 in favour of
appellant No.1 with respect to aforesaid property on 01.06.1978 and the same was
registered on 12.08.1978 and given effect to between the parties from 01.06.1978. A
Clarification Agreement was appended to the main registered lease deed on
12.08.1978. A written agreement for being appended as Clarification Agreement to the
main registered lease deed dated 12.08.1978 was executed on 02.09.1978 mainly
incorporating two clauses firstly, the renewal of lease deed and the second clause was
that private passage to respondent No.1’s bounded land behind the land in question.
The stamp paper for the written agreement dated 02.09.1978 was purchased by
respondent No.1 who got it typed and signed after fully understanding the same, as
admitted by her in her deposition. Thus respondent No.1 executed fresh agreement
dated 02.09.1978 inserting the following words in the original deed in compliance to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
I.B.P company’s demand:
"Whereas as per the IBP guidelines renewal option is must so the
following words at the end of paragraph 5 of the deed No. 5115 dated
12.8.1978 is added."
"Provided if it is required to be renewed by Lessee then possession
shall not be given."
After expiry of the lease, the appellant, as per the terms of the renewal
agreement dated 02.09.1978, gave a notice through registered post to respondent No.1
on 28.05.1993 for execution of a fresh lease deed renewing it for a further period of 15
years. Respondent No.1 instead of renewing the lease filed Title Suit No. 382 of 1993
seeking the following reliefs:
a) That on adjudication the decree of eviction be passed in
favour of the plaintiff as against the defendant (appellant
No.1 herein) and plaintiff be put in possession by process of
law at the cost of the defendants over schedule I premises.
b) That by grant of interim injunction defendant No.1 be
restrained to run the petrol pump, namely, M/s S.K. Puri
Service Station and defendant No.3 be restrained to supply
fuelling of the said pump pending the suit in breach of the
contract.
c) Cost of the suit be awarded to the plaintiff.
d) Any other relief or reliefs to which the plaintiff be found
entitled be awarded to the plaintiff."
The defendant-respondent purposely suppressed the existence of written
agreement dated 02.09.1978 in the original plaint of Title Suit No. 382 of 1993.
Appellant No.1 (the defendant in Title Suit No. 382 of 1993) filed written statement and
in paragraph 7 of the written statement averted as follows:
"That when the deed was sent to the company for approval they
pointed out that there should be renewal clause in the deed as per
guidelines of the Company (Marketing Manual). Respondent No.1 in
compliance to the company demand, thereafter executed a fresh agreement
and gave option of renewal in these words:-
"Whereas as per IBP guidelines, renewal option is must. So the
following words at the end of para 5 of the deed No. 5315 dated 12.08.1978
is added "provided if it is required to be renewed by the lessee then the
possession shall not be given."
It is thus apparent from the pleadings that at the earliest point of time, the
plaintiff-appellant pleaded about the renewal clause as the renewal clause is
incorporated in the agreement dated 02.09.1978.
When the lease was not renewed, then on the basis of the renewal clause
incorporated in the agreement dated 02.09.1978, the appellants filed Title Suit No. 15
of 1996 for a suit of specific performance in which respondent No.1, Smt. Usha Sinha,
was made the defendant. The following reliefs were sought by appellant No.1 :
a) Decree of specific performance of agreement for lease
dated 2.9.1978 executed by the defendant No.1 and the
plaintiff in respect of land described in Schedule 1 of the
plaint be passed in favour of the plaintiff and against the
defendant and defendant No.1 be directed to execute the
registered lease deed in respect of the land in suit for a
further period of 15 years on the terms and conditions as
mentioned in para 3 of this plaint, within a reasonable
time fixed by the Court failing which the said lease deed
be executed and registered by the Court on behalf of the
defendant No.1 aforesaid.
b) The defendant No.1 be injuncted from taking any step
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
for vacation of the plaintiff from the premises in suit fully
detailed in schedule 1 below till the disposal of the suit.
c) Cost of the suit be awarded to the plaintiff and against
the defendant.
d) Any other relief or reliefs for which the plaintiff may be
found entitled be passed in favour of the plaintiff and
against the defendant."
Respondent No.1 filed written statement and denied the existence of agreement
dated 02.09.1978 in following words:
"The said alleged deed, if any, is forged manufactured and
antedated and this defendant never executed such alleged deed nor
there was any such negotiation."
It is relevant to state here that vide order dated 03.09.1998 passed in Title Suit
No. 382 of 1993, the sub-Judge-VI, Patna ordered that both the suits bearing Title Suit
No. 382 of 1993 and 15 of 1996 will be tried simultaneously as agreed by the parties
though it will be decided by separate judgments. This was done only because the
conflicting judgments may not be delivered in the matter. As such both the suits are
pending in one and the same Court.
The son of respondent No.1 was examined as a witness in the Title Suit No. 382
of 1993 as PW-1. While being cross-examined, he was shown the signature on the
written agreement dated 02.09.1978 through pin hole method, when he identified the
signature of the plaintiff, his mother-respondent No.1 herein. Then the document was
disclosed to be the bilateral agreement dated 02.09.1978 which contained the signature
of respondent No.1 herein. The son of respondent No.1 has admitted in paragraph 15
of his deposition as follows:
"The signature on the document of 3 pages is of my mother which I
identify/acknowledge (the witness gives this statement when only signature
portion of the agreement dated 2.9.1978 shown to him through pin hole
method)."
When respondent No.1’s son admitted the signature on the written agreement
dated 02.09.1978 of his mother, Smt. Usha Sinha, respondent No.1 herein, then took a
U-turn in her stand and instead of denying the total existence of the written agreement
dated 02.09.1978, started accepting the existence of the agreement dated 02.09.1978
but pleaded interpolation in the renewal clause. Subsequently in the course of cross-
examination, respondent No.1 herself in paragraph Nos. 19 and 26 admitted that while
signing the bilateral lease agreement dated 02.09.1978 she had read the agreement
and thereafter she had signed. She had also admitted that stamp paper on which the
bilateral lease agreement was signed was purchased by her. When respondent No.1
admitted the existence of the agreement dated 02.09.1978 after identification of her
signature by her son in cross-examination on 01.12.1998, she filed a petition on
04.12.1998 objecting the admissibility of the written agreement dated 02.09.1978 by
changing her stand and stating that only the renewal clause was interpolated.
Appellant No.1 filed the rejoinder and contended that the witness of respondent No.1
cannot be examined without deciding the petition dated 04.12.1998 by which
interpolation has been alleged in the renewal clause of agreement dated 02.09.1978.
The Court below did not allow the prayer of appellant No.1. However, as respondent
No.1 was not ready to press the petition dated 04.12.1998, the sub-Judge allowed the
petition of the appellants dated 01.12.1998 by which the prayer for appointment of
Advocate Commissioner to find out whether the present passage existing in the west as
per the written agreement dated 02.09.1978 or in the east as per the registered lease
deed dated 12.08.1978. The appellants filed rejoinder to the petition dated 04.12.1998
of respondent No.1 and submitted that there is no interpolation nor it change the nature
of the suit. Respondent No.1 filed a petition stating that question of interpolation in the
renewal clause of the agreement dated 02.09.1978 alleged through the petition dated
04.12.1978 would not be pressed at present. The appellants filed rejoinder on
09.12.1998 to the petition dated 07.12.1998 to the effect that without deciding the
question of interpolation finally, the evidence cannot be adduced. Hence they prayed
that the petition dated 04.12.1998 of the defendant-respondent may be disposed of first
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
and then the evidence should proceed. The sub-Judge vide order dated 09.12.1998
directed the appellants to cross-examine the witness otherwise they would be
discharged, since respondent No.1 was not pressing the petition dated 04.12.1998 at
present and when the petition would be pressed by respondent No.1, the appellants
would get the chance of rebuttal.
The appellants filed Civil Revision No.18 of 1999 before the High Court of Patna
against the order dated 09.12.1998 of the sub-Judge contending therein that if the
contention of respondent No.1 raised vide petition dated 04.12.1998 that there is
interpolation in the renewal clause is not decided finally, then after closing of the
evidence if such petition is pressed and allowed then the whole evidence has to be
recorded de novo. As such the contention of the appellants was that the issue in
respect of the interpolation of the agreement be decided first before proceeding with the
evidence. Respondent No.1 appeared in Civil Revision No. 18 of 1999 and submitted
that the pleading of interpolation would never be raised at later stage also and the
objection to that effect shall be considered as withdrawn. In such view of the matter
and in view of the aforesaid undertaking, the High Court vide order dated 15.02.1999
disposed of the Civil Revision No. 18 of 1999 as infructuous recording the statement of
the counsel of respondent No.1 which reads as under:
"A petition was filed by the plaintiff alleging some interpolation in
respect of bilateral unregistered document which was introduced in the
evidences. Objection was filed. Then there was prayer from the side of the
petitioners to dispose of that matter prior before proceeding further in
recording evidences. The plaintiff then filed Ann.4 stating that she was not
pressing her earlier petition "at that stage". The learned Court below
accepted that petition and ordered for proceeding further in the suit. Hence
this revision petition.
Learned counsel for the O.P. submits that she is not at all inclined to
press her earlier petition regarding interpolation. But the words ’at this
stage’ in the later petition raised confusion in the mind of the petitioner.
Now it has been clearly stated before this Court that the plea of interpolation
would never be raised at later stage also and the petition to that effect shall
be considered as withdrawn."
In view of the above position, this revision petition has become
infructuous."
Against the order dated 15.02.1999 passed in Civil Revision No. 18 of 1999,
respondent No.1 filed Civil Review No. 88 of 1999 on the ground that the undertaking
recorded in order dated 15.02.1999 were never taken. Civil Review No.88 of 1999 was
dismissed by the High Court on 19.07.2001 observing as under:
"Heard learned counsel for the petitioner.
This review petition has been filed against the order dated 15.2.1999
passed by this Court in Civil Revision No. 18/99. In presence of both the
parties admission has been made from the side of the petitioner and the
order was passed. Now, the petitioner wants to deviate from the admission
made before this Court which cannot be a ground for review.
Accordingly, this Civil review application has got no force and the
same is rejected."
Against the order dated 19.07.2001 passed in Civil Review No. 88 of 1999,
respondent No.1 filed Special Leave Petition (Civil) No. 16513 of 2001 before this Court
and took the ground of the agreement dated 02.09.1978 being a forged document.
Apart from other contentions, she also contended that action should be taken under
Section 340 Cr.P.C. against the appellant, though the pleading of Section 340 Cr.P.C.
was never raised either in the trial Court or before the High Court and the same was
raised for the first time in the special leave petition.
The appellants herein who were the respondents in the said special leave
petition filed their counter affidavit before this Court stating in detail that the agreemen
t
dated 02.09.1978 is an admitted document in the trial Court and that the initial order
dated 15.02.1999 passed in Civil Revision No. 18 of 1999 was never challenged and it
attained finality and no appeal lies against the review order. This Court, after hearing
both the parties, dismissed the special leave petition on 13.09.2002. It is thus evident
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
that the question of interpolation stood settled by the aforementioned decisions and it
was concluded that respondent No.1 could not raise the said issue at any stage.
When the plaintiff’s evidence started in Title Suit No. 15 of 1996, counsel for
respondent No.1 started putting question to the plaintiff witness with regard to the
forgery and interpolation of agreement dated 02.09.1978. An objection was raised by
the plaintiff-appellant vide objection petition dated 24.01.2003 that as per her own
undertaking before the High Court in Title Suit No. 382 of 1993, respondent No.1 could
not raise the question of interpolation with regard to the renewal clause in agreement
dated 02.09.1978. It was contended that respondent No.1 has waived the issue of
interpolation. Hence, she is barred from raising the same under the principle of
estoppel. When witness Nausad was being examined, then the Court vide order dated
04.02.2003 decided that this issue with regard to giving liberty to respondent No.1 on
questioning the witness with regard to the interpolation of renewal clause in agreement
dated 02.09.1978 will be considered at the time of final adjudication of the case and it
will not amount to create the right of respondent No.1 to raise such issue subsequently
and thereby the objection filed by the appellant was rejected vide order dated
04.02.2003. In view of the observation given in order dated 04.02.2003, the objection
was again raised when appellant No.1 was being cross-examined and again
respondent No.1 asked the question relating to the interpolation in renewal clause in
the agreement dated 02.09.1978, then again the objection was filed that respondent
No.1 cannot raise the issue of interpolation in the agreement dated 02.09.1978 in view
of her undertaking given in Civil Revision No. 18 of 1999 before the High Court and
which was affirmed by this Court. A rejoinder was filed by respondent No.1 herein on
10.06.2003 on the ground that the objection was rejected by the trial Court on
04.02.2003 and suits are not analogous moreover since the beginning respondent No.1
is saying that the alleged deed is forged and fabricated. The sub-Judge allowed
respondent No.1 to raise the question relating to interpolation in the agreement dated
02.09.1978 from the witnesses. The appellants filed Civil Revision No. 1178 of 2003
against the order of sub-Judge X, Patna dated 17.06.2003 in Title Suit No. 15 of 1996
whereby the sub-Judge allowed respondent No.1 to raise the question relating to
interpolation in the agreement dated 02.09.1978 from the witnesses. Civil Revision No.
1178 of 2003 was dismissed by the High Court on 23.09.2003 with a direction to the
Court below to conduct the trial on a day-to-day basis and dispose of both the suits
within six months and report it to the High Court. Aggrieved by the said order, the
appellants preferred the present appeal by way of special leave petition.
We heard Mr. Raju Ramachandran, learned senior counsel, appearing for the
appellants and Mr. L.R. Singh, learned counsel, appearing for contesting respondent
No.1.
Learned senior counsel appearing for the appellants invited our attention to the
earlier set of orders passed by the sub-Judge as affirmed by the High Court in Civil
Revision No. 18 of 1999, the order dated 19.07.2001 in Civil Review No. 88 of 1999 of
the High Court and the order dated 13.09.2002 of this Court in Special Leave Petition
(civil) No. 16513 of 2001. He submitted that as the matter between the same parties
with regard to the interpolation in the agreement dated 02.09.1978 has already been
settled by which respondent No.1 will not raise the issue of interpolation/forgery with
regard to the agreement in question and particularly, in view of the undertaking of
respondent No.1 before the High Court, respondent No.1 will never raise the issue of
interpolation with regard to the said agreement, respondent No.1 is estopped from
raising the issue again. Title Suit No. 382 of 1993 was filed by respondent No.1 for
eviction whereas Title Suit No. 15 of 1996 was filed by the appellant for specific
performance of the contract. Moreover, in both the suits, the parties are the same and
the agreement dated 02.09.1978 is the main issue. He would further contend that
respondent No.1 having admitted execution of the agreement and having signed the
bilateral agreement and having admitted that while signing the bilateral agreement, she
read the agreement and thereafter signed cannot now be allowed to re-agitate the said
issue which has been concluded by the orders of the High Court and also of this Court.
According to the learned senior counsel, the facts stated above clearly show that the
renewal clause in the agreement dated 02.09.1978 was not inserted or interpolated as
asserted by respondent No.1.
Mr. L.R. Singh, learned counsel, appearing for contesting respondent No.1,
reiterated the contentions raised before the Courts below and submitted that the
appellant has virtually inserted the alleged renewal clause and that the said renewal
clause is not at all a renewal clause giving a right to the appellant to exercise the right
to renew the lease at his option. He would further submit that nothing is set out in the
document regarding the terms and conditions on which the renewal will be given effect
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
to or the manner in which the alleged right of renewal shall be exercised. He would
further submit that the sub-Judge has rightly rejected the objection made by the
appellant which was later affirmed by the High Court and, therefore, the order passed
by the High Court rejecting the prayer of appellant No.1 cannot at all be faulted. He,
therefore, prayed for dismissal of the appeal.
On the facts and circumstances of the case, the following questions of law arise
for consideration by this Court:
"1. Whether the issue of interpolation in the agreement
dated 2.9.1978 which stands settled between the
same parties by the orders of the High Court and
affirmed by this Court in regard to the same subject
matter can be allowed to be raised in another
proceedings between the very same parties in the
same Court.
2. Whether the sub-Judge failed to appreciate that
respondent No.1 is precluded from raising the issue
of interpolation in agreement dated 2.9.1978 in the
course of examination and he is precluded on the
principle of issue estoppels and res judicata.
3. Whether respondent No.1 who gave her
undertaking in Civil Revision No. 18 of 1999 that
she would not raise the question of interpolation in
the said agreement and on the basis of which the
order dated 15.2.1999 was passed by the High
Court and affirmed in Civil Review and also
subsequently in the Special Leave Petition filed by
her before this Court can be allowed to raise the
very same issue again in another suit filed by her.
4. Whether respondent No.1 is precluded from alleging
interpolation in renewal clause of agreement dated
2.9.1978 when the said fact was otherwise
admitted by her that she will never raise the issue
of interpolation."
We have carefully perused the entire pleadings and the various documents
annexed along with this appeal including the agreement.
In our opinion, the High Court has miserably failed to appreciate that the
undertaking of first respondent in Civil Revision No. 18 of 1999 that she will not raise
the issue of interpolation is binding on her in the present suit and as such she was
barred by the principles of res judicata, waiver and estoppel from being allowed to raise
the same issue again between the very same parties in relation to the same subject
matter. The Agreement dated 02.09.1978 is an admitted document. Respondent No.1
had sought to raise the issue of its forgery in earlier proceedings, but finally undertook
not to do so. This was recorded by the High Court and the Civil Revision filed by
respondent No.1 was disposed of accordingly. Later respondent No.1 sought to resile
from her stand and filed an application for review before the High Court, which was also
dismissed. The said order was challenged in Special Leave Petition (Civil) No. 16513
of 2001. This Court dismissed the same after hearing the parties at the stage of final
disposal. In that view of the matter, we are of the opinion that the respondent is
precluded from raising the same issue of interpolation/forgery in the renewal clause of
the said agreement deed again.
The undertaking and the acceptance not to raise the issue of interpolation is a
matter of record. It is well settled that once a issue of fact has been judicially
determined finally between the parties by a Court of competent jurisdiction and the
same issue comes directly in question in subsequent proceedings between the same
parties then the persons cannot be allowed to raise the same question which already
stands determined earlier by the competent Court. For that the question of interpolation
in the renewal clause of the said deed has been finally decided and the same issue has
been raised in the present suit when in both the suits the parties are the same and the
basic claim of both the parties are same as in eviction suit, the plaintiff is claiming
eviction by termination of lease and denying the renewal clause whereas in the specific
performance suit, the appellants are claiming the renewal of the lease on the basis of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
the said renewal clause. Hence in both the suits, the main issue is substantially and
materially one and the same and both the cases are being tried simultaneously. This
apart, the judgment of the High Court and of this Court is a judgment in personam
which is binding upon both the parties. It is also seen that the order dated 15.02.1999
in Civil Revision is a consent order which creates an estoppel by judgment as the
judgment dated 15.02.1999 operates as estoppel as records of the findings are
essential to ascertain the judgment. By passing of the impugned judgment, the High
Court has virtually allowed the suit in favour of respondent No.1. In any view of the
matter, the impugned order is bad in law and fact as well and, therefore, the same is
liable to be set aside.
In our view, respondent No.1 wants to revive the dispute which has finally set at
rest by this Court by challenging the genuineness of the agreement dated 02.09.1978
on the plea that the said order was passed in Title suit No. 382 of 1993 which has no
binding effect in the present case. In our view, respondent No.1 cannot be allowed to
challenge the genuineness of the agreement dated 02.09.1978.
We are told that in the Title Suit No. 382 of 1993 filed by respondent No.1 herein
against the appellant, after examining five witnesses, the respondent has closed the
evidence and now the defendant-appellant herein are examining their witnesses. In
Title Suit No. 15 of 1996, the plaintiff-appellant herein have closed the evidence after
examining 31 witnesses. The defendant-respondent herein has commenced her
witnesses. Three witnesses have already been examined and only one witness
remains to be examined. We, therefore, restrict respondent No.1, Smt. Usha Sinha,
from putting any question challenging the genuineness of the agreement dated
2.9.1978 in the light of our findings made above. It is stated that some witnesses have
already been examined on both the sides. If any question is put and any answer is
extracted with regard to the genuineness/interpolation or forgery of agreement dated
02.09.1978, the said evidence cannot be looked into by the trial Court and should be
eschewed from consideration and the judgment be passed on the merits of the rival
claims on other related issues.
We answer all the questions in favour of the appellant and hold that respondent
No.1 is precluded from raising the genuineness/interpolation or forgery of agreement
dated 02.09.1978.
For the foregoing reasons, the appeal succeeds. Though it is eminently a fit
case for awarding exemplary cost, we refrain from doing so. No costs.