Full Judgment Text
1
Reportable
SUPREME COURT OF INDIA
| APPELL | ATE JUR |
|---|
CIVIL APPEAL NOS. 10182-10183 OF 2016
(@ SLP(C) Nos. 28959-28960 of 2015)
Tamil Nadu Generation and Distribution …Appellant(s)
Corporation Ltd. (TANGEDCO) Rep. By
Its Chairman & Managing Director
and Anr. Etc.
Versus
CSEPDI – Trishe Consortium, Rep. By its …Respondent(s)
Managing Director & Anr.
WITH
CIVIL APPEAL NOS. 10184-10185 OF 2016
(@ SLP Nos. 30098-30099 of 2015)
JUDGMENT
J U D G M E N T
Dipak Misra, J.
Leave granted.
2. The appellant, Tamil Nadu Generation and Distribution
Corporation Ltd (for short ‘the Corporation’) vide notification
dated 06.05.2013 floated a tender for setting up of two units of
Page 1
2
660 MW Ennore SEZ Supercricitcal Thermal Power Project at
Ash Dyke of NCTPS, Chennai wherein four bidders including
| alified a | s they |
|---|
Qualification Requirements (BQR) as a result of which bids of
Consortium of Trishe Energy Infrastructure Services Private
Limited (CSEPDI) and Bharat Heavy Electrical Ltd (BHEL) were
taken up for consideration. Prior to the opening of the price
bid, CSEPDI and BHEL submitted supplementary price bids
on 05.02.2014. Price bids were opened on 05.02.2014 by the
appellant in the presence of the representatives of the
respondents, the qualified bidders.
JUDGMENT
3. The uncurtaining of facts would depict that the
st
1 respondent sent series of representations dated 16.06.2014,
17.06.2014, 01.07.2014 and 08.07.2014 to the appellant
highlighting various aspects of the bid and the relevance of
para (viii) of Clause 29.0 of the “Instructions to Bidders” (ITB)
which also deals with the rejection of bids of the tenderer
whose past performance/vendor rating is not satisfactory.
Page 2
3
Since the appellant paid no heed to the request made by the
respondent No.1, it filed W.P. No. 19247 of 2014 seeking issue
| comply | with Tam |
|---|
Tenders Act, 1998 (for short, “the TTIT Act”). An undertaking
was given before the learned Single Judge by the learned
Advocate General that post-bid representations submitted by
the respondent No.1 will be duly considered while finalizing
the tenders and appropriate orders will be passed in
accordance with the tender specifications and the TTIT Act
and rules framed thereunder and in terms of the said
undertaking, learned Single Judge vide order dated
31.07.2014 directed the appellant to consider and pass orders
JUDGMENT
on the representations of the appellant herein after affording
them an opportunity of personal hearing and directed that till
such orders are passed, the tender should not be finalised.
4. Being aggrieved by the said order, the appellant filed writ
appeal W.A. No. 1065 of 2014 before the Division Bench
which, by judgment and order dated 19.08.2014, disposed of
Page 3
4
the writ appeal by modifying the order of the learned Single
Judge only to the extent that affording of opportunity of
| r the R | ules (for |
|---|
further permitted the respondent No.1 to submit additional
documents raising all its objections and the appellant was
directed to pass an order and communicate the same to the
respondents, CSEPDI and BHEL. However, the Division
Bench did not modify the direction of the learned Single Judge
which was to the effect that till a decision was taken on
st
representations of the 1 respondent, the bid shall not be
finalised.
JUDGMENT
5. After the disposal of the writ appeal, the respondent No.1
sent its representation on 25.08.2014 along with necessary
documents which was rejected by the appellant vide its
communication dated 27.09.2014. The legal propriety of the
said rejection was called in question by way of writ petition
W.P. No. 26762 of 2014 seeking quashment of the same and
further restraining the owner from taking steps to finalise the
Page 4
5
tender. During the hearing of the writ petition, a copy of letter
dated 27.09.2014 awarding the contract to BHEL, respondent
| negotiat | ion meet |
|---|
No. 2. The respondent No. 1 sent a letter dated 1.10.2014 to
the appellant, highlighting the arbitrariness, anomalies and
inconsistencies in its reasoning and the mala-fide intent in the
matter of evaluation of the bid submitted by it. However, the
st
appellant by letter dated 10.10.2014, informed the 1
respondent that the subject tender had been finalised and
awarded to BHEL.
6. The letter dated 27.9.2014 awarding the contract to
JUDGMENT
respondent No. 2 and letter dated 10.10.2014 were assailed by
the respondent No.1 by filing W.P. No. 27529 of 2014 for
annulments of the letters and further for issue of directions to
the Corporation to determine the award of the tender strictly
in terms of the Tender/Bid document and taking into account
the bid of respondent No.1 and that of BHEL, the respondent
No.2 herein.
Page 5
6
7. The learned Single Judge dismissed the writ petition
primarily based on the perusal of notes in the files containing
| duct of pr | ocess of |
|---|
did not appear to be arbitrary, capricious or unfair; and that
price bids of the bidders had been evaluated as per the
parameters indicated in the tender notification by an
independent consultant who was selected as per the Board
Resolution that was within the knowledge of both the bidders.
The reasoning of the learned Single Judge basically hinged on
the Consultant’s Report that had determined that the
respondent No.2 herein was L1 and, therefore, the decision of
the Corporation in treating BHEL as L1 and awarding the
JUDGMENT
contract was neither arbitrary nor malafide.
8. Aggrieved by the order of the learned Single Judge, the
respondent No.1 preferred writ appeals before the Division
Bench. The Division Bench took note of the various pleas
raised by the respondent No.1 including violation of the
statutory provisions, arbitrariness, adoption of unfair and
Page 6
7
non-transparent procedure, erroneous delineation of the
consultant’s report by the learned Single Judge and
Division Bench that there was no violation of procedure and
the award of the contract was not amenable to judicial review
in the obtaining factual matrix and any interference would
only delay the execution of the work. It was also urged that
Tender Accepting Authority (TAA) had accepted the lowest
tender and negotiations were held only with lowest bidder;
that Clause 25.4 of the Instruction to Bidders did not permit
the bidder to change the substance of the bids after the bids
JUDGMENT
were opened; that though the respondent No.1 had offered
lower rate on interest, the original interest rate offered was not
in accordance with tender terms, for as per clause 14.0(d)(5)
the rate of interest quoted should be fixed, whereas the
CSEPDI had not specified the fixed rate of interest; that there
was no perversity or arbitrariness in the decision taken as per
the terms of the tender, prevalent banking practice and the
Page 7
8
Term Sheet given by the lender; that the Consultant was
appointed pursuant to the Board Resolution dated 28.01.2012
| igned by | all the p |
|---|
and, therefore, CSEPDI was very much aware of appointment
of the consultant and the role played by consultant could
neither be criticised nor ignored.
nd
10. The 2 Respondent herein contended that respondent
No.1 lacked credibility to make any allegation against it; that
design was the core area of leader of the consortium and they
have no experience in India insofar as supercritical Thermal
Power Projects are concerned; and that the work was under
JUDGMENT
progress and they had expended substantial amount.
11. After hearing the rival contentions, the Division Bench
1
placed reliance on Jagdish Mandal v. State of Orissa and
observed that the approach of the owner was unfair in the
tendering process. It further analysed the scheme of Section
1
(2007) 14 SCC 517
Page 8
9
10 of the TTIT Act and held that the Tender Accepting
Authority (TAA) has a role to cause objective evaluation of the
| not com | plied wi |
|---|
it was a case of procedural impropriety, unfair approach and
arbitrariness. The appellate Bench referred to the authority in
Star Enterprises v. City and Industrial Development
2
Corporation of Maharashtra Ltd. and declined to accept
the stand of the Corporation by opining that reasons for
st
rejection of 1 respondent’s representations could not be
treated as reasons for rejection of its bid and hence, the
decision making process was flawed and in breach of Section
10(7) of the Act. It further held that in the “Tender Bulletin”,
JUDGMENT
absence of reasons for acceptance of tender, no statement of
evaluation of tenders and no comparative statement of tenders
received and, decision thereon was in clear violation of the
requirements of Section 6(1) read with Section 10 of the TTIT
Act and Rule 30(3) of the TTIT Rules. On the interest
2
(1990) 3 SCC 280
Page 9
10
component and commitment fee, the Division Bench held that
the approach was wholly arbitrary and the intention was to
| ne and re | ject the |
|---|
the process adopted and the decision taken by the owner was
arbitrary, unfair, irrational, biased and mala fide and did not
serve the larger public interest. In view of the said analysis,
the Division Bench allowed the appeals and directed the
Corporation to evaluate the price bid of the respondents in the
light of its findings and taking into consideration all relevant
parameters including the representations/documents
submitted by respondent No. 1 and to record detailed reasons
for the decision and communicate the same to the respondent
JUDGMENT
No.1 so as to comply with the requirement of the provisions of
the TTIT Act and TTIT Rules and various decisions of this
Court.
12. Being aggrieved by the aforesaid judgment, the
corporation and the successful bidder, by way of special leave,
have preferred separate appeals.
Page 10
11
13. We have heard Mr. Mukul Rohatgi, learned Attorney
General and Mr. Parag P. Tripathi, learned senior counsel for
| the appe | llant-Co |
|---|
Sibal, learned senior counsel for respondent No.1 and Mr.
Sriram Panchu, learned senior counsel for the respondent
No. 2.
14. It is apposite to note that in course of hearing it has been
opined that the singular issue that is required to be addressed
th
is “whether the Evaluation Report dated 30 May, 2014 by the
Consultant, is prima facie erroneous, requiring interference
within the parameters of judicial review”. Such a singular
JUDGMENT
point was required to be focused as Mr. Mukul Rohatgi,
learned Attorney General appearing for BHEL and Mr.
Subramonium Prasad learned senior counsel appearing for the
Corporation had submitted as the subsequent offers either by
st
BHEL or by the 1 respondent need not be considered. At that
juncture, Mr. Kapil Sibal learned senior counsel appearing for
st
the 1 respondent, the contesting party, had submitted that
Page 11
12
the Consultant’s Report would graphically exposit that the
respondent No.1 was entitled to be declared as L-1 even if it is
| t had | directed |
|---|
Consultant’s Report to the learned counsel appearing for the
st
1 respondent. In view of the aforesaid submission, the
opinion expressed on other issues by the learned Single Judge
or by the Division Bench need not be adverted to.
15. On a perusal of the facts brought on record, it is manifest
that the Corporation in its meeting held on 30.1.2014 had
decided to open the price bids on both the bidders and
thereafter the supplementary price bids were obtained from
JUDGMENT
both the parties for the additional implications items in
respect of technical deviation quoted by both parties and
thereafter the price bids were opened on 05.2.2014. As the
factual matrix would reveal, the price bids were evaluated by
the Consultant. The learned Single Judge has adverted to
price evaluation report submitted by the Consultant. Certain
Page 12
13
paragraphs from the report of the Consultant that were
reproduced by him are as follows:-
“4.0 Evaluation
4.1 BHEL
BHEL has arranged finance from M/s. Power Finance
Corporation of India.
They are arranged to finance 75% of the total cost as
debt at an interest rate of 12.25% p.a.
Attached Annexures 1 to 5 indicate the methodology
adopted in calculating the various components
required for evaluation like IDC-Debt, IDC-Equity,
IDC-UF Fess, Debt Repayment Schedule etc.
4.2 CSEPDI – TRISHE
CSEPDI-TRISHE has arranged finance from M/s.
ICBC, China.
They have arranged a finance 85% of the total cost as
debt at an interest rate of 7.2% p.a.
Attached Annexures 6 to 12 indicate the methodology
adopted in calculating the various components
required for evaluation like IDC-Debt, IDC-Equity,
IDC-UF Fess, Debt Repayment Schedule etc.
JUDGMENT
5.0 Evaluated Lower Cost
| BHEL | CSEPDI-TR<br>ISHE | |||
|---|---|---|---|---|
| All figures<br>in Rs.<br>(Crores) | All figures<br>in Rs.<br>(Crores) | |||
| Capacity | 1320 MW | 1320 MW |
Page 13
14
| A | Total EPC cost<br>excluding VAT | 7762.977 | 9207.264 | ||
|---|---|---|---|---|---|
| B | EPC Debt 75 | % | 5822.233 | 7826.174 | |
| C | EPC Equity 25 | % | 1940.744 | 1381.090 | |
| D | IDC Debt 12 | .25% | 1295.079 | 1228.378 | |
| E | EPC Debt<br>Including IDC<br>(B + D) | 7117.311 | 9054.552 | ||
| F | Upfront Fees<br>Including<br>Interest | 8.925 | 801.180 | ||
| G | Total Debt (E<br>+ F) | 7126.237 | 9855.732 | ||
| H | Interest on 14<br>Equity | % | 509.597 | 456.606 | |
| I | Total Equity<br>(C + H) | 2450.341 | 1837.695 | ||
| J | Total Project<br>Cost (G + I) | 9576.578 | 11693.427 | ||
| K | Total Cost per<br>MW | 7.255 | 8.859 | ||
| L | PV – Debt | 7553.364 | 8464.318 | ||
| M | PV – Equity | 2809.403 | 2106.984 | ||
| N | Total PV | 10362.767 | 10271.302 | ||
| O | PV Cost per `<br>MW | 7.851 | 7.781 | ||
| P | JUDG<br>Loading for<br>Deficiency | ME | NT<br>10.287 | 173.229 | |
| Q | Total (N+P) | 10373.054 | 10444.531 | ||
| R | Evaluated Bid<br>Price per MW | 7.858 | 7.913 |
Paragraphs 4.0 and 5.0 of the “Price Evaluation
Report” submitted by the Consultant, which I have
extracted above, show that the Consultant took into
account only the interest rate of 12.25% per annum
for the debt component arranged by BHEL from the
Power Finance Corporation of India. The Consultant
did not take note of the reduced rate namely 12.15,
Page 14
15
subsequently offered by BHEL, for arriving at the
conclusion that the “Evaluated Bid Price” of BHEL was
the lowest.”
16. There is no dispute that as per the Price Evaluation
| ultant, th | e EPC pr |
|---|
1 was Rs.9207.264 crores and respondent No.2 to whom the
contract was awarded was Rs.7762.977 crores. Thus, the
difference between the two EPC price is Rs.1444.287 crores.
st
The 1 respondent disputed the Price Evaluation Report by the
Consultant on the ground that it wrongly loaded the sum
towards (a) the commitment fee, (b) interest on management
fee during IDC period; and (c) interest of guarantee fee during
IDC period in its bid amount which had led to the evaluation
of quoted financial charges with interest to Rs.801.18 crores.
JUDGMENT
17. As regards the commitment fee, learned counsel for the
appellant submits that the contention of the respondent No.1
that since commitment fee was the fee to be charged on the
unutilised amount of the loan meaning thereby if the appellant
failed to draw the loan amount as undertaken, then only the
commitment fee would be charged and, therefore, the
Page 15
16
determination after addition of the same was without any
rationale as the respondent No.1 had quoted in the
| the tune | of Rs.16 |
|---|
be charged @ 1% p.a. on accrued drawals and if no
commitment fee was required to be paid, the respondent No.1
should have mentioned the same to be nil or zero. To show
that the commitment fee is a part of the financial charges,
learned senior counsel has drawn our attention to clause 14(d)
6 of the Instruction to Bidders under the tender, which reads
as follows:-
“6. Financing Charges : All financing charges of any
nomenclature relating to financing of the project
including but not limited to Finders Fees,
Commitment Fees, Arrangement Fees, Management
Fees, Up Front Fees, Syndication Fees, Service
Charges, Guarantee Charges, Other Fees and Taxes, if
any should be clearly outlined in the Financing Term
Sheet. No variation in Financing Charges is permitted
during the tenor of loan.
JUDGMENT
3.37 “Financing Cost” means all financing charges of
any nomenclature relating to financing of the project
including but not limited to Finders Fees, Arranger’s
Fees, Commitment Fees, Management Fees, Up Front
Page 16
17
Fees, Syndication Fees, Service Charges, Guarantee
Charges, Other Fees and Taxes, if any.”
18. At this juncture we may also refer to clause 3.37 of
| with the | General |
|---|
the Contract. It defines the “Financing Cost” as follows:-
“Financing Cost” means all financing charges of any
nomenclature relating to financing of the project
including but not limited to Finders Fees, Arranger’s
Fees, Commitment Fees, Management Fees, Up Front
Fees, Syndication Fees, Service Charges, Guarantee
Charges, Other Fees and Taxes, if any”.
19. Clause 14 that deals with the conditions for a Binding
Debt Financing Term Sheet, which needs to be reproduced in
entirety. It reads as follows:-
“ 14.0 Conditions for a Binding Debt Financing
Term Sheet
Bidder shall enter into a Memorandum of
Understanding (MoU) with the Lender for the Debt
Financing agreeing to provide Financing for the
Project and making payments directly to the Bidder
based on bills certified by TANGEDCO as per the
terms of payment clause.
JUDGMENT
The MoU shall be submitted by the Bidder along with
their offer for signing of the loan agreement.
The Bidder shall be responsible for arranging the
required financing and achieving Financial Closure of
the project within 4 (Four months) from the date of
Letter of Intent (LoI).
Page 17
18
| diligence<br>ill furnis | .<br>h the fo |
|---|
b. It shall be understood that the Financing Term
Sheet shall be based on preliminary appraisal of the
project jointly by the Bidder and the Lender satisfying
themselves on the project financial viability.
c. It shall be understood that the Award of Contract to
the Bidder is contingent upon successful Financial
Closure based on the Terms and Conditions provided
in the Financing Term Sheet and in the event of the
Financial Closure does not materialize due to reasons
attributable to the Bidder or the Lender or in the
event of withdrawal by the Lender from the Project,
the Bidder will forfeit the security deposit.
JUDGMENT
d. The Term Sheet should be full and complete with
all material terms of financing including but not
limited to:
1. Loan Amount : At least 75% of the Total EPC Cost +
100% of Interest during construction and Financing
Cost.
2. Currency of Loan: INR/USD/Euro or a combination
thereof.
Page 18
19
3. Tenor of the Loan : From the date of first drawal of
st nd
the Loan upto 6 months from COD of the 1 or 2
| est.<br>of Intere<br>g into ac | st till th<br>count th |
|---|
JUDGMENT
Page 19
20
13. Validity period of the Term Sheet will be
co-terminus with the validity of the bid.”
20. The stand of the respondent as regards the interpretation
| that it on | ly outlin |
|---|
mean that every such fee is to be loaded for evaluating the bid
to determine L1 and no commitment fee can be loaded for
such evaluation. It is also put forth that there can be no
question of loading interest on commitment fee.
21. As has been stated earlier, the issue pertaining to
correctness of Consultant’s report has to be adjudged and
scrutinized within the scope of limited power of judicial review
in the obtaining factual score. The Division Bench in the
impugned judgment has taken exception to the process
JUDGMENT
adopted in the identification of L1. It has referred to its order
st
dated 19.8.2014 wherein the 1 respondent was granted the
time to submit additional documents. The impugned order
takes note of the fact that at that point of time, the
Corporation had never averred that tender had been finalized.
It has referred to the earlier order of the Division Bench that
representations were to be considered and till then the bid
Page 20
21
should not be finalized. It has referred to the letter of the
Chairman-cum-Managing Director of the Corporation dated
fact.
22. Be it stated that the Division Bench has posed two
questions:-
“(i) Whether interest offered by appellant is vague; and
(ii) Whether the reduction of interest from 7.2% to
6.2% should be accepted.”
23. While dealing with the said issue, the Division Bench has
referred to the publication in the tender bulletin stating about
the decision on tender:-
“1. Name of the Tender: Chief Engineer/Civil/Projects
rd
& Environment, Inviting Officer, 3 Floor, NPKRR
Maaligai, 144, Anna Salai, Chennai – 600 002.
JUDGMENT
2. a) Name of the Project/Detail of Purchase & Works:
Establishment of coal based 2 x 660 MW Ennore SEZ
Supercritical Thermal Power Project in the ash dyke of
existing NCTPS under Single EPC cum Debt Finance
basis. Vayalurvillage, Thiruvallur District, Tamil
Nadu.
Page 21
22
| Sl.<br>No | Details | Tender<br>Value | Decision on<br>Tender | |
|---|---|---|---|---|
| 1<br>2 | M/s.<br>Bharat<br>Heavy<br>Electricals<br>Limited,<br>BHEL<br>House,<br>Sirifort,<br>New Delhi<br>– 110 049<br>Consortium<br>of Central<br>Southern<br>China<br>Electric<br>Power<br>Design –<br>JU<br>Ms. Trishe,<br>668, Minz<br>Road,<br>Ughan,<br>China – 430<br>071 | 7840.08<br>7 Crores<br>&<br>Lender:<br>Power<br>Finance<br>Corporat<br>ion<br>Limited<br>Rate of<br>Interest:<br>12.25%<br>9716.59<br>74<br>Crores &<br>Lender:<br>Industri<br>al &<br>Commer<br>DGMEN<br>ce Bank<br>of China<br>Rate of<br>Interest:<br>7.2%<br>(USD @<br>Rs.<br>59.26 at<br>SBI Bill<br>selling<br>rate) | Out of four bids<br>received for this<br>work and among<br>the qualified two<br>bidders,<br>negotiation was<br>called for & held<br>with the lowest<br>bidder viz<br>M/s.BHEL. After<br>negotiation,<br>tender value of<br>Rs. 7788 Crores,<br>Rate of Interest at<br>12.15% was<br>accepted by the<br>Chief<br>Engineer/Projects<br>and order for<br>acceptance of the<br>Ttender issued<br>vide this office<br>issue<br>Lr.No.CE/P/SE/<br>M/EE-10/E/File.<br>2x660MW Ennore<br>SEZ<br>STPP/D.No.60/dt<br>.27.09.2014 |
Page 22
23
| o.60/dt. | 27.09.20 |
|---|
24. Thereafter, the Division Bench has recorded as follows:-
“31.3 While it is the plea of the appellant that fixed
rate of 7.2-7.5% per annum or LIBOR floating rate
has been quoted by them, it is the case of the learned
Advocate General that Clause 12.1 of the Instructions
to Bidders stated that interest is to be quoted at fixed
rate and it is not subject to change, and since the
interest quoted is variable, it is not possible to
evaluate the bid.
31.4 It is seen from the records, that subsequently,
based on a query from the first respondent, the
appellant had confirmed that it would be fixed rate of
interest at 7.2%. the same was also confirmed in the
Repayment Schedule and the same rate of interest
was taken into consideration by the Consultant in his
report dated 30.5.2014. He did not find fault with the
rate of interest. It is to be noted that the Term Sheet
was submitted during July, 2013 and tender was
evaluated in the year 2014. The contention of
vagueness in rate of interest does not appeal to us.
When the Consultant’s report dated 30.5.2014 is
accepted by TANGEDCO for the purpose of
evaluation, it has to be accepted for all purposes,
though we have reservation on the Consultant’s
report dated 30.5.2014. There is, therefore, no
vagueness in the rate of interest quoted at 7.2%.
JUDGMENT
31.5 The second issue relates to the reduction of rate
of interest. It is not in dispute that various meetings
were held between the appellant and the TANGEDCO.
Page 23
24
| ant. He<br>onsultan | stated t<br>t’s appo |
|---|
31.6 Coming to the issue of reduction of rate of
interest, taking into consideration the prevailing
market rate, the appellant offered to reduce the rate of
interest from 7.2% to 6.2% on 5.6.2014, even prior to
any form of litigation. When such an offer was given
by the appellant the tender was not accepted in terms
of Section 10(6) of the Act. To recapitulate, what has
happened earlier is that the writ petition in W.P. No.
19247 of 2014 was filed on 17.7.2014, subsequent to
the offer made on 5.6.2014. The first interim order
was passed on 18.7.2014. The second interim order
was passed on 31.7.2014. The Division Bench passed
an order on 19.8.2014. At that point of time, there
was never a statement by the TANGEDCO that L1 was
identified and discussion was going on. We have also
clearly stated that the statement of the
Chairman-cum-Managing Director of TANGEDCO that
the representations of the appellant will be duly
considered by the Board of Directors while finalizing
the tender and appropriate orders will be passed
strictly in accordance with the tender specifications
and by following the provisions of TTIT Act and TTIT
Rules.
JUDGMENT
Page 24
25
| ANGEDC<br>earned S | O or on<br>ingle Ju |
|---|
31.8 Even otherwise, by virtue of the power under
Clause 25.3 of the Instructions to bidders, which
states that “The Purchaser reserves the right to relax
or waive any of the conditions of this Specification in
the best interests of the TANGEDCO ”, the TANGEDCO
could have considered such reduced rate of interest
offered by the appellant and the third respondent.”
25. With regard to commitment fee, the analysis of the
Division Bench is worth referring to:-
JUDGMENT
“It clearly states that Commitment Fee is only on the
cancelled portion of the loan. That apart, even as per
the Drawdown Schedule, the fee is to be paid only if
th th
the loan amount is not drawn by the 18 , 30 and
nd
42 month. Moreover, the appellant in the letters
dated 13.6.2014,16.6.2014 and 17.6.2014, clarified
that Commitment Fee is only on the unused credit
line and that there shall be no Commitment Fee if the
loan amount is fully utilized as per the Drawdown
Schedule. All these representations sent by the
appellant were not considered by TANGEDCO, despite
there being a specific direction by the Division Bench
of this Court to consider the same. It is a clear case
Page 25
26
of arbitrariness in approach and intended to oust the
appellant. This act of the TANGEDCO is nothing but
a case of malafide in evaluation process to suit one
and reject the other.”
| with the | consult |
|---|
Bench has proceeded to state thus:-
“33.3 Even as per the Consultant’s Report the
difference between the bid of the appellant and the
third respondent is around Rs.71 Crores. That being
the case, if either the Commitment Fee of Rs.156.184
Crores or the interest on Management Fee and
Guarantee Fee for the 36 month construction period
is not loaded on the appellant, it will have a bearing
on deciding which one of the two is the lowest bid.
Assuming the Consultant’s report is of any value,
such report without considering the relevant material
is of no use. The approach to add these figures
without taking note of the representations and
additional particulars/documents is, therefore,
arbitrary and tainted in bias. This is in violation of
the Division Bench judgment as well as the orders of
the learned Single Judge in the first round of
litigation.”
JUDGMENT
27. And again:-
“The financial implication in respect of two tenderers
has been specified by the Consultant. The issue is
what factors mean and how it impacts the bid. We
find that the Repayment Schedule submitted by the
appellant with regard to interest on management fee
and guarantee fee during IDC period is an accepted
document by the Consultant. If nothing more is to be
paid beyond that and that is clarified in the course of
representation in clear terms, we fail to understand as
Page 26
27
| ant docu<br>ot in co | ment/re<br>nformity |
|---|
“33.6 We, therefore, have no hesitation to hold that
the first respondent had erroneously added interest
on Management Fee and Guarantee Fee when there is
none and there is no ambiguity or vagueness. Once
the appellant has indicated in the representation, in
clear terms, as to how it should be treated, in the light
of the order of the Division Bench, which TANGEDCO
accepted to consider the bid of the appellant, the first
respondent ought not to have loaded this amount on
the basis of the Consultant’s Report. In all fairness,
the Tender Accepting Authority of the first respondent
should have excluded this amount, if both the bidders
are to be treated on the touchstone of fairness and on
the doctrine of level-playing field. This becomes
necessary because the entire tender is tested on the
larger public interest, that is to say, the
implementation of the project in a time bound manner
where cost is another important factor to be
considered in the decision making. In a Welfare
State, public authority cannot decide arbitrarily to
throw away such an offer which they agreed to
consider in the course of judicial proceedings, which
we have referred to above. These factors, namely,
JUDGMENT
Page 27
28
| as direct | ed as fol |
|---|
“The TANGEDCO is directed to evaluate the
appellant’s price bid along with the bid of the third
respondent, in the light of our findings as above and
also taking into consideration in all required
parameters and the clarifications submitted by the
appellant in its various representations, as directed
by the Single Judge in the order dated 31.7.2014 and
that of the Division Bench in its order dated
19.8.2014, afresh, at the earliest.”
29. Before this Court, the consultant’s report is criticized by
st
the 1 respondent stating thus:-
“2.3 The Consultant has made the following errors in
the calculation of the said ‘Upfront Fees Including
Interest’ in respect of CSEPDI’s bid:
JUDGMENT
Error 1 : Included Commitment Fees
Error 2 : Calculated and loaded interest on (a.)
Guarantee Fee, (b.) Management Fee and (c.)
Commitment Fee during the construction period of 36
months, i.e., IDC (Interest During Construction)
2.4 In 5.0 Item F – ‘Upfront Fees Including Interest’,
the Consultant has loaded BHEL with Rs.8.925
Crores and CSEPDI with Rs. 801.180 Crores. The
break-up of this Rs. 801.180 Crores in the
Consultant’s Report is as follows:
Page 28
29
a. Guarantee Fee : Rs. 371.743 Crores
b. Management Fee : Rs. 117.393 Crores
c. Commitment Fee : Rs. 156.184 Crores
| 36 month<br>127.613 | s<br>Crores) |
|---|
Total: Rs. 801.180 Crores
2.4.1 There is no issue on entries a. and b. above
2.4.2 The issue is with regard to entries c. and d.
above.
2.4.3. As regards c., no Commitment Fee can be
loaded, for the reasons explained below.
2.4.4 As regards d., no interest can be loaded for the
construction period of 36 months on Guarantee Fee
and Management Fee, for the reasons explained
below. The question of interest on Commitment Fee
does not arise at all because no Commitment Fee can
be loaded in the first place for evaluation of CSEPDI’s
bid.
JUDGMENT
2.4.5 e. above will stand reduced as it depends on c.
and d.
2.5 If the Consultant had correctly evaluated
CSEPDI’s price bid by not including Commitment Fee
and Interest on Guarantee Fee, Management Fee and
Commitment Fee for the construction period of 36
months, then CSEPDI would be L1 by Rs. 171.600
Crores. Neither TANGEDCO nor BHEL have disputed
this fact.
x x x x x x
2.7 The Consultant has confused Commitment Fee
with an Upfront Fee. Commitment Fee, as stated
Page 29
30
| ont Fee<br>s loaded | as distin<br>BHEL w |
|---|
30. With regard to the commitment fee, various financial
nuances have been stated. We think it apt to reproduce some
of them:-
“2.8.3 When the earmarked funds are drawn, the
interest agreed is payable. When the earmarked
funds are not drawn, the interest is not payable but
instead the Commitment Fee has to be paid on the
amount not drawn.
2.8.4 CSEPDI’s Term Sheet clearly mentions that
the Commitment Fee is payable on the cancelled
portion of the loan.
JUDGMENT
2.8.5 The term ‘Accrued Drawal’ refers to the
amount accured and available for drawal, but not
drawn.
2.8.6 Commitment Fee is therefore only a
contingent fee leviable if the funds are not drawn as
per the Drawdown Schedule. It is more in the nature
of a penalty in the event of a default by the borrower
TANGEDCO and is payable by TANGEDCO. This
cannot be added to the project cost for evaluation of
the price bid.
x x x x x x
Page 30
31
| t to eva<br>hedule. | luate th<br>The Re |
|---|
2.8.9 The EQI in the Repayment Schedule is
based on the figure of Rs. 15,038.2914 Crores, which
comprises of interest Rs. 5,025.3628 Crores on the
Net Loan amount of Rs. 10,012.9286 Crores. The
components of this Net Loan amount are:
a. Loan amount
(85% of Total EPC
Cost of 9709.3822 Crores) : Rs. 8252.9748/-
b. Interest at 7.2% p.a. on the
above loan amount during
the Construction Period of 36 : Rs. 896.2032/-
months
JUDGMENT
c. Guarantee Fee : Rs. 392.0163/-
d. Management Fee : Rs. 123.7946/-
Moratorium Period interest
th nd
for 37 to 42 month
(interest at 7.2% p.a. for
6 months on the total of
a,b,c and d. above) : Rs. 347.9396/-
Total : Rs.10,012.9286/-*
Page 31
32
| Crores.<br>PDI’s bid | The<br>at Rs. 9 |
|---|
31. With regard to no interest on guarantee fee and
management fee during the construction period of 36 months
st
and no interest on Commitment fee, the stand of the 1
respondent has been put forth in various compartments. We
think it apt to reproduce the relevant grounds:-
“2.9.1 The Consultant ought not to have loaded
interest on Guarantee Fee and Management Fee
during the construction period of 36 months, for the
evaluation of CSEPDI’s Price Bid.
2.9.2 The very same Repayment Schedule calculation
set out above shows that no interest is being charged
on Guarantee Fee and Management Fee during the
construction period of 36 months and does not form
part of the amount which TANGEDCO has to repay.
Not a single rupee needs to be paid over and above
the amounts mentioned in the Repayment Schedule.
JUDGMENT
2.9.3 The only interest payable during the
construction period of 36 months is interest
calculated at 7.2% p.a. on the basic loan amount
(85% of the EPC cost) and not on any other amount
like Guarantee Fee and Management Fee. This is
made clear in the specific calculation sheet for
Page 32
33
Interest During Construction submitted by CSEPDI in
its Price Bid.
| ed to be<br>in which<br>contract, | paid by<br>they ar<br>the ite |
|---|
2.9.5 In CSEPDI’s Term Sheet, mention is made of
Management Fee and SINOSURE Re-insurance
(Guarantee Fee). No mention is made of interest on
Management Fee and Guarantee Fee for the
construction period of 36 months.
2.9.6 As far as interest on Commitment Fee is
concerned, the same does not arise as Commitment
Fee itself cannot be loaded for evaluating CSEPDI’s
bid.”
st
32. The 1 respondent has also put forth that the Consultant
JUDGMENT
was not right in loading on CSEPDI bid the values for
Commitment Fee and interest thereon and Interest on
Guarantee Fee and Management Fee during the construction
period of 36 months, because that Clause 14.d.6 only states
that details of the Financing Charges should be clearly
outlined in the Financing Term Sheet and does not state that
it should be included in the price evaluation; that the
Page 33
34
reference to Commitment Fee in the Term Sheet clearly
indicates that it is only on the cancelled portion of the loan;
| nd 42nd | months |
|---|
Drawdown Schedule; that Clause 12.1 and Clause 32.1.1
makes no mention of interest on Financing Charges (i.e., on
Management Fee and Guarantee Fee) during the IDC period;
that the words ‘Interest and Financing Charges’ cannot mean
interest on financing charges; that there is absolutely no
variance between the Term Sheet and Repayment Schedule
submitted by CSEPDI; that the Term Sheet and the entire
Financial Proposal/Price Bid, including the Repayment
Schedule, are to be read together; that the CSEPDI’s Term
JUDGMENT
Sheet only mentions that a Management Fee is to be paid but
does not mention any interest on Management Fee for the 36
month construction period (IDC period) and that the
Consultant ought not to have loaded the disputed amounts for
evaluating the price bid of CSEPDI. It is also the stand that on
a perusal of the Comparison Sheet filed would indicate that
Page 34
35
CSEPDI is L1 by Rs.171.600 crores if the evaluation is done
st
correctly. That apart, the 1 respondent has raised other
| on in su | pport of |
|---|
st
has stated that the stand of the 1 respondent that Net Loan
Amount in the repayment schedule provided by respondent
No.1 gives no break up of how the said figure has been
reached; that one cannot find out from a bare perusal of the
said Repayment Schedule as to whether the respondent No.1
has factored the component of Commitment Fee in the Net
Loan Amount; that the respondent having not been declared
as L1 bidder as a post facto contention, now say that
Commitment Fee shall not be taken for evaluation in spite of
JUDGMENT
the fact that they themselves have quoted Commitment Fees
for Rs.164.702 crores with split up details in the price bid and
the above post facto contention is against all tenets of fairness
and justice; that had the respondent No.1 become L1, they
would have insisted that Commitment Fee being a financial
charge forms part of the loan and therefore is payable by the
Page 35
36
borrower i.e., the Corporation as per their price bids submitted
by respondent No.1; that since the respondent No.1 had not
| hould no | t be ta |
|---|
universal definition.
34. On interest on management and guarantee fee, the stand
of the Corporation is that the CSEPDI-TRISHE CONSROTIUM
have quoted Rs. 123.9746 crores as Management fees and Rs.
392.0163 crores as Guarantee fee in their Price bid. There is
no dispute on the quantum of fees. The Consultant during the
evaluation have worked out interest @ 7.2 per annum on the
above fees as per the term sheet of the Industrial and
Commercial Bank of China Limited from the date on which
JUDGMENT
they fall due since the above fees form part of the debt to be
repaid by the appellant; that it is clear from the Tender
Conditions as well as the Term Sheet provided by Industrial
and Commercial Bank of China Limited and the clarification
dated 21.10.2013 (issued by Industrial and Commercial Bank
of China Limited) that appellant herein would be bound to pay
Page 36
37
the interest on the whole loan amount which will include the
financial charges.
| has quo<br>t submit | ted the r<br>ted by In |
|---|
Bank of China Limited which are reproduced below:-
“Clause 14(d)1 of the
Instruction to Bidders
under the Tender
defines the “Loan
Amount” to include at
least 75% of the total
EPC cost + 100% of
interest during
construction and
Financing Cost. As
per clause 14(d) 6 of
the Instruction to
Bidders under the
Tender management
fee and guarantee fee
is part of the financial
charges/financial cost.
JUDGMENT
Under the term relating to “Interest
rate” in term sheet submitted by
Industrial and Commercial Bank of
China it is clearly provided that the
Borrower will pay interest on the full
loan amount at a fixed rate per
annum.
Under the terms defined as
“management fee” in the term sheet
Page 37
38
| of 60 d<br>closure. | ays from<br>Six mo |
|---|
Similarly, under the terms relating to
“Conditions Precedent”, the condition
(d) the term sheet specifies that
petitioners will be charged guarantee
fee (termed as Insurance Policy in the
term sheet) at the rate of 5% on 95%
of the loan amount and the same will
th
be payable from the end of the 6
month.
According to the term sheet the
amounts get debited to the Petitioners
th
account at the end of the 8 month
th
and 6 month respectively.
JUDGMENT
All financial costs form part of the
debt taken from the Industrial and
Commercial Bank of China Limited.
As per the clarification dated
21.10.2013 issued by Industrial and
Commercial Bank of China Limited
which is the Lender institution for
Respondent no.1 all costs and fee
charged by ICBC will form part of the
debt financing”.
Page 38
39
36. From the aforesaid, it is vivid that the Consultant has
analysed the offers regard being had to the tender conditions.
| sultant h | as been |
|---|
of any additional document from either side. The documents
were called for by the owner from both the qualifying bidders
in a transparent manner and the same have been considered
at the time of evaluation by the Consultant. Submission of
Mr. Sibal is that the evaluation is ex facie defective inasmuch
as the Consultant has loaded certain charges as a
consequence of which the price has gone up. Mr. Rohatgi,
learned Attorney General appearing for BHEL and Mr. Prasad,
learned senior counsel appearing for the Corporation would
JUDGMENT
submit that the evaluation is founded on definities leaving
nothing to any kind of contingency. They have referred to the
Term Sheet and what is put up by Industrial and Commercial
Bank of China Limited. At this juncture we are obliged to say
that in a complex fiscal evaluation the Court has to apply the
doctrine of restraint. Several aspects, clauses, contingencies,
Page 39
40
etc. have to be factored. These calculations are best left to
experts and those who have knowledge and skills in the field.
| e percep | tion of f |
|---|
the project have to be left to the wisdom of the financial
experts and consultants. The courts cannot really enter into
the said realm in exercise of power of judicial review. We
cannot sit in appeal over the financial consultant’s
assessment. Suffice it to say, it is neither ex facie erroneous
nor can we perceive as flawed for being perverse or absurd.
37. Before parting with the case we are constrained to add
something. We do so with immense pain. The respondent,
before finalization of the financial bid submitted series of
JUDGMENT
representations and seeing the silence of the owner it knocked
at the doors of the writ court which directed for consideration
of the representations. We are disposed to think that the High
Court at that stage should have exercised caution. If the
courts would exercise power of judicial review in such a
manner it is most likely to cause confusion and also bring
Page 40
41
jeopardy in public interest. An aggrieved party can approach
the Court at the appropriate stage, not when the bids are
| in kind | of tend |
|---|
negotiations to show fairness transparently. But the present
case is not a one of such nature. Once the price bid was
opened, a bidder could not have submitted representations on
his own and seek a mandamus from the Court to take certain
aspects into consideration. We have stressed this aspect only
to highlight the role of the Court keeping in mind the
established principle of restraint.
38. In view of our preceding analysis we are of the considered
opinion that the Division Bench through the delineation has
JUDGMENT
adopted the approach of an appellate forum or authority and
extended the principle of judicial review to certain areas to
which it could not have and, therefore, the judgment and
order of the Division Bench followed the path of error in
continuum. Consequently, the inevitable conclusion is
unsettlement of the impugned order and we so direct. In the
Page 41
42
ultimate eventual the appeals stand allowed. There shall be no
order as to costs.
..............................J.
(Dipak Misra)
..............................J.
(Shiva Kirti Singh)
New Delhi;
October 18, 2016.
JUDGMENT
Page 42