Full Judgment Text
CIVIL APPEAL NOS. 1751-1763 OF 2019 (@ SLP(C) NOS.15937-15949/2017)
MUNICIPAL COUNCIL THANESAR VS. VIRENDER KUMAR ETC.
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 1751-1763 OF 2019
(Arising out of Special Leave Petition (Civil)Nos.15937-15949 of 2017)
MUNICIPAL COUNCIL THANESAR …Appellant(s)
VERSUS
VIRENDER KUMAR ETC. …Respondents
J U D G M E N T
Uday Umesh Lalit, J.
1. Leave granted.
2. These appeals challenge the final judgment and order dated
03.03.2017 passed by the High Court of Punjab and Haryana at Chandigarh in
C.R.Nos. 6765 of 2015 (O&M), 5198 of 2015(O&M), 5199 of 2015(O&M),
5200 of 2015(O&M), 5201 of 2015(O&M), 5202 of 2015(O&M), 5203 of
2015(O&M), 5204 of 2015(O&M), 5205 of 2015(O&M), 5510 of
2015(O&M), 5511 of 2015(O&M), 5512 of 2015(O&M) and 4253 of
Signature Not Verified
Digitally signed by
INDU MARWAH
2015(O&M).
Date: 2020.08.21
18:20:01 IST
Reason:
CIVIL APPEAL NOS. 1751-1763 OF 2019 (@ SLP(C) NOS.15937-15949/2017)
MUNICIPAL COUNCIL THANESAR VS. VIRENDER KUMAR ETC.
2
3. Pursuant to public notice for auction of shops/showrooms, the auction
was conducted by the appellant on 18.10.2016 in which the respondents
participated and were declared successful bidders. Thereafter, disputes arose
between the parties whether the auctioned premises were ready to be
delivered on the relevant dates; whether the construction was incomplete; and
whether the civic amenities were made available or not? The matters reached
the High Court in various Writ Petitions namely CWP Nos.13548 of 2008,
1015, 1016, 1017, 1018, 1020, 1062, 14793 and 19228 of 2009 and by a
common order dated 14.07.2010 the disputes were referred to a sole
Arbitrator. After considering the matters, the Arbitrator passed a common
Award on 14.10.2010. Para 21 of the Award was as under:-
“21. In view of the above findings, award is passed in
favour of the petitioners against the respondents with
costs of Rs.10,000/- (Rupees Ten Thousand only) and
Municipal Council, Thanesar, is directed to complete the
work in all the respects of the Shopping Complex,
situated in Kacha Gher, Thanesar, within one month; if
already completed, a notice be issued to the petitioners
to take possession of the respective shops and also to
execute the agreement within a week. Municipal
Council, is further directed to give interest on the
advance rent as well as non-refundable security, at the
rate of interest offered by Nationalised Bank, i.e. 7% per
annum, till physical/possession is handed over to the
petitioners/allottees. Petitioners are further awarded
damages by way of 12% interest on non-refundable
security till delivery of possession as they have suffered
CIVIL APPEAL NOS. 1751-1763 OF 2019 (@ SLP(C) NOS.15937-15949/2017)
MUNICIPAL COUNCIL THANESAR VS. VIRENDER KUMAR ETC.
3
mentally as well as loss of business due to delay in
completion of work of the shops and handing over their
possession. Requisite stamp papers be filed within
week.”
4. The appellants preferred objections under Section 34 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’)
which were dismissed by the Additional District Judge on 15.09.2012. The
appellants, being aggrieved, preferred First Appeals which were dismissed by
the High Court of Punjab and Haryana on 17.01.2014. The order of the High
Court was also affirmed by this Court by dismissing Special Leave Petition
(Civil) No.15550 of 2014 on 04.08.2014. The directions issued in the Award
thus became final.
5. In Execution Proceedings taken out by the respondents, the Executing
Court in its order dated 23.03.2015 dealt with the matter as under:-
“5. As per the award dated 14.10.2010 the arbitrator
had directed the judgment debtor i.e. Municipal
Council, Thanesar to give interest on the advance rent
as well as non-refundable security, at the rate of
interest offered by nationalized bank i.e. 7% per
annum till physical possession is handed over to the
petitioners/allottees. Petitioners were further awarded
damages by way of 12% interest on non-refundable
security till delivery of possession. It is a settled legal
position that an executing court cannot go beyond
decree. A plain reading of award dated 14.10.2010
shows that interest @ 7% per annum has been given to
CIVIL APPEAL NOS. 1751-1763 OF 2019 (@ SLP(C) NOS.15937-15949/2017)
MUNICIPAL COUNCIL THANESAR VS. VIRENDER KUMAR ETC.
4
the decree holder on the advance rent as well as non-
refundable security. “At the rate of interest offered by
nationalized bank” mentioned in the award has to be
read in continuation and cannot be isolated to give it a
separate meaning. The award clearly stipulates that the
rate of interest being awarded by the arbitrator is at the
rate which is offered by nationalized bank. The award
is silent about the manner of calculation of interest.
The award cannot be interpreted to mean that the
manner of calculation of the interest has to be in
accordance with the norms of a nationalized bank.
Interpreting the award as calculation of interest of 7%
per annum on advance rent and non-refundable
security with quarterly rests would mean that
compound interest has to be calculated. The same
does not appear to be the intention of the learned
arbitrator as it is not specifically stated that interest at
the rate of 7% per annum was awarded with quarterly
rests.
6. Even as per the Reserve Bank of India guidelines
liberty has been given to the nationalized banks to pay
interest on domestic savings deposit accounts either at
quarterly intervals or by giving longer rests.
Admittedly different nationalized banks have their own
rate of interest and are free to determine the manner of
calculation by giving shorter or longer period of rests.
In the absence of any specific direction given by the
learned arbitrator in the award dated 14.10.2010, no
further interpretation in the award is feasible and the
rate of interest has to be read as 7% per annum which
has to be calculated with yearly rests. As per award
dated 14.10.2010, the interest has to be calculated only
till the delivery of possession. The possession of the
respective shops has already been handed over to the
decree holders.”
CIVIL APPEAL NOS. 1751-1763 OF 2019 (@ SLP(C) NOS.15937-15949/2017)
MUNICIPAL COUNCIL THANESAR VS. VIRENDER KUMAR ETC.
5
5. The appellants being aggrieved, filed aforementioned Civil Revisions
in the High Court which were disposed of on 03.03.2017. The questions that
arose for consideration were formulated by the High Court as:
“Twin questions that fall for consideration of this Court
are; (i) whether the decree-holders are entitled to the
statutory benefits under Section 31(7)(a) and (b) of the
Act; and (ii) whether the decree-holders-petitioners are
also entitled to calculate the amount of interest on
advance rent and nonrefundable security, at the rate of
interest offered by nationalized bank, i.e. 7% per
annum, with quarterly rests.”
Relying on the majority view in Hyder Consulting (UK) Ltd. vs.
1
Governor, State of Orissa through Chief Engineer , the High Court
answered the first issue in favour of the respondents and concluded that they
were entitled to post award interest in terms of Section 31(7)(b) of the Act.
As regards second issue, it was held that the respondents were also entitled
to interest @ 7% per annum with quarterly rests. The view so taken by the
High Court is presently under challenge.
6. We have heard Mr. Ajay Majithia, learned counsel for the appellants
and Mr. A. Tewari, Mr. Anupam Raina, Mr. Raktim Gogoi and Mr. Chritarth
Palli, learned advocates for the respondents.
7. The first issue was rightly answered in favour of the respondents. The
question is no longer res integra and stands answered in clear terms in Para
1
(2015) 2 SCC 189
CIVIL APPEAL NOS. 1751-1763 OF 2019 (@ SLP(C) NOS.15937-15949/2017)
MUNICIPAL COUNCIL THANESAR VS. VIRENDER KUMAR ETC.
6
10 of the Judgment of Bobde, J. and paras 27-28 of the Judgment of Sapre, J.
in Hyder Consulting (supra) . The view taken by the High Court on this issue
is absolutely correct.
8. As regards the second issue, the Executing Court correctly
appreciated that the Award did not specifically state that the interest @ 7%
per annum was to be awarded with quarterly rests. In fact, the Award did not
specify anything; whether it be quarterly rests or yearly rests. It simply
awarded interest @ 7% per annum. Since the Award was completely silent on
that aspect, at the stage of execution, no addition or alteration could be made
in the operative directions issued in the Award. The Award had seen the
challenges at three levels and at none of those stages, there was any
modification in the operative directions of the Award.
9. The Executing Court found that it was doubtful whether the award of
interest was @ 7% with quarterly rests or yearly rests. In fact, the situation
was more fundamental, whether there was award of any compound interest at
all. The Executing Court put it with yearly rests which the High Court in
Revisions preferred by the appellants modified to quarterly rests. In our view,
both the Executing Court and the High Court completely erred and awarded
compound interest in favour of the respondents when the award had
CIVIL APPEAL NOS. 1751-1763 OF 2019 (@ SLP(C) NOS.15937-15949/2017)
MUNICIPAL COUNCIL THANESAR VS. VIRENDER KUMAR ETC.
7
stipulated it to be 7% per annum simplicitor. The Award did not even
remotely suggest that such award of interest would be with a direction that
interest be capitalized on yearly or quarterly basis. It was pure and simple
award of interest @ 7% and could not be taken to be a direction to award
compound interest.
10. We, therefore, accept the submission made by the learned counsel for
the appellants as regards second issue and direct that the direction issued in
the para 21 of the Award shall be construed as simple interest @ 7% per
annum.
11. Consequently, the pre-award interest on the amounts in question shall
be calculated @ 7% per annum simple interest. The respondents shall be
entitled to the benefit under Section 31(7)(b) of the Act and post award
interest shall also be @ 7% per annum – simple interest.
12. With the aforesaid modification the appeals are partly allowed. No
order as to costs.
……….………..…..……..……J.
(Uday Umesh Lalit)
………...………….……………J.
(Dr. Dhananjaya Y. Chandrachud)
New Delhi,
February 19, 2019.