Full Judgment Text
‘REPORTABLE’
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 11826 OF 2018
HARYANA POWER PURCHASE CENTRE Appellant(s)
VERSUS
SASAN POWER LTD & ORS. Respondent(s)
WITH
CIVIL APPEAL NO. 11927 OF 2018
CIVIL APPEAL NO. 12190 OF 2018
CIVIL APPEAL NO. 1670 OF 2019
CIVIL APPEAL NO. 12232 OF 2018
CIVIL APPEAL NO. 1742 OF 2019
J U D G M E N T
K. M. JOSEPH, J.
(1) The six appeals with which we are concerned
Signature Not Verified
Digitally signed by
Nidhi Ahuja
Date: 2023.05.03
12:52:01 IST
Reason:
have been filed under Section 125 of the Electricity
Act, 2003 (hereinafter referred to as ‘Act’ for
1
CIVIL APPEAL NO. 11826 OF 2018 etc.
brevity). The appeals are directed against the
order passed by the Appellate Tribunal for
Electricity (hereinafter referred to as ‘Tribunal’
for brevity) in an appeal carried by the first
respondent under Section 111 of the Act.
(2) The appeal before the Tribunal, in turn, was
lodged against the order passed by the Central
Electricity Regulatory Commission (hereinafter
referred to as ‘Commission’ for brevity). The
Commission passed the order purporting to be one
under Section 79(b) inter alia of the Act in a
petition filed by the first respondent.
F A C T S
(3) It was decided to set up an Ultra Mega Power
Project. Towards this end, the Power Finance
Corporation Limited of India was to be the nodal
agency. It incorporated a Special Purpose Vehicle,
which is the first respondent. The idea was to set
up the Ultra Mega Power Project which would be
operated by the successful bidder selected through
2
CIVIL APPEAL NO. 11826 OF 2018 etc.
an international competitive bidding. The power
generated by the successful bidder was to be
supplied through procurers (the appellants before
us), who can be described also as the distribution
licensees under the Act. The appellants were to
supply the power so procured finally to the
consumers.
(4) Since what was contemplated was seeking shelter
under Section 63 of the Act, we must refer to the
guidelines which have been issued by the Central
Government purporting to act under Section 63.
Guidelines were issued on 19.01.2005. We deem it
appropriate to set out the following guidelines:
“2.1 These guidelines are being issued under
the provisions of Section 63 of the
Electricity Act, 2003 for procurement of
electricity by distribution licensees
(Procurer) for:
(a) long-term procurement of electricity for
a period of 7 years and above;
(b) Medium term procurement for a period of
upto 7 years but exceeding 1 year.
2.2 The guidelines shall apply for
procurement of base-load and seasonal power
requirements through competitive bidding,
through the following mechanisms:
i. Where the location, technology, or fuel is
not specified by the procurer (Case 1);
3
CIVIL APPEAL NO. 11826 OF 2018 etc.
ii. For hydro-power projects, load center
projects or other location specific projects
with specific fuel allocation such as captive
mines available, which the procurer intends
to set up under tariff based bidding process
(Case 2).”
(5) The guidelines are binding on the procurers.
Guideline 3.2 which is related to preparation for the
invitation of bids would assume relevance. It reads
as follows:
“3.2 For long-term procurement from hydro
electric projects or for projects for which
pre-identified sites are to be utilized (Case
2), the following activities should be
completed by the procurer or authorized
representative of the procurer, before
commencing the bid process:
- Site identification and land acquisition
required for the project
- Environmental clearance
- Fuel linkage, if required (may also be
asked from bidder)
- Water linkage
- Requisite Hydrological, geological,
meteorological and seismological data
necessary for preparation of Detailed Project
Report (DPR), where applicable.
The bidder shall be free to verify geological
data through his own sources, as the
geological risk would lie with the project
developer.
The project site shall be transferred to the
successful bidder at a declared price.
4
CIVIL APPEAL NO. 11826 OF 2018 etc.
Provided that for the projects from which
more than one distribution licensees located
in different States intend to procure power
and if the preparations for such projects are
being facilitated by the Central Government,
the activities referred to above shall be
initiated before the bidding process and
should be completed before signing the power
purchase agreement with the selected bidder.
(6)
Under the guidelines, tariff structure is
contemplated which consists of capacity charges and
energy charges which are dealt with in detail. It
also deals with bidding process. The bidding
process itself is divided into two stages, viz., a
determination of the qualification by a pre-
qualification system and thereafter submission and
consideration of essentially what consists of the
financial bid. There is a guideline which deals with
arbitration and it was contained in guideline 5.17:
“5.17 The procurer will establish an Amicable
Dispute Resolution (ADR) mechanism in
accordance with the provisions of the Indian
Arbitration and Conciliation Act, 1996. The
ADR shall be mandatory and time-bound to
minimize disputes regarding the bid process
and the documentation thereof.
If the ADR fails to resolve the dispute, the
same will be subject to jurisdiction of the
appropriate Regulatory Commission under the
5
CIVIL APPEAL NO. 11826 OF 2018 etc.
provisions of the Electricity Act 2003.”
(7) It is, accordingly, purporting to act in terms
of the guidelineS that a Request for Qualification
(for short RFQ) came to be issued on 31.03.2006.
Reliance Power Limited was one of the bidders which
was pre-qualified in terms of the RFQ. On
18.08.2006, there was a change notified in the
guidelines. It brought about the following changes
in the guidelines 5.17 besides guideline No. 4.7.
The unamended and the amended guidelines 4.7 and
5.17 read as follows:
| S.<br>No. | CBG as on 19.01.2005 | CBG as amended on 18.08.2006 |
|---|---|---|
| 1. | 4.7 Any change in tax on<br>generation or sale of electricity<br>as a result of any change in Law<br>with respect to that applicable<br>on the date of bid submission<br>shall be adjusted separately.<br>[Pg. 345,CC-I] | 4.7 Any change in law impacting<br>cost or revenue from the business<br>of selling electricity to the<br>procurer with respect to the law<br>applicable on the date which is 7<br>days before the last date of RFP bid<br>submission shall be adjusted<br>separately. In case of any dispute<br>regarding the impact of any<br>change in law, the decision of the<br>Appropriate Commission shall<br>apply. |
| 2. | Arbitration<br>5.17 The procurer will establish<br>an Amicable Dispute Resolution<br>(ADR) mechanism in<br>accordance with the provisions | Arbitration<br>5.17 Where any dispute arises<br>claiming any change in or<br>regarding determination of the<br>tariff or any tariff related matters, |
6
CIVIL APPEAL NO. 11826 OF 2018 etc.
| of the Indian Arbitration and<br>Conciliation Act, 1996. The<br>ADR shall be mandatory and<br>time-bound to minimize<br>disputes regarding the bid<br>process and the documentation<br>thereof. | or which partly or wholly could<br>result in change in tariff, such<br>dispute shall be adjudicated by the<br>Appropriate Commission.<br>All other disputes shall be resolved<br>by arbitration under the Indian<br>Arbitration and Conciliation Act,<br>1996. |
|---|
(8) On 21.08.2006, a Request for Proposal, for
short RFP, came to be issued. We deem it appropriate
to refer to the following provisions of the RFP.
“4. While this RFP has been prepared in good
faith, neither the Procurers, Authorised
Representative and Power Finance Corporation
Limited (PFC) nor their directors or
employees or advisors/consultants make any
representation or warranty, express or
implied, or accept any responsibility or
liability, whatsoever, in respect of any
statements or omissions herein, or the
accuracy, completeness or reliability of
information contained herein, and shall incur
no liability under any law, statute, rules or
regualations as to the accuracy, reliability
or completeness of this RFP, even if any loss
or damage is caused to the Bidder by any act
or omission on their part.
1.3 The objective of the bidding process is
to select a SuccessfulBidder for development
of the Project as per the terms of the RFP.
The Project will have a Contracted Capactiy
of minimum of 3500 MW and maximum of 3800 MW
in accordance witht he terms of the PPA. The
Selected Bidder shall purchase the entire
shareholding of the Authorised Representative
7
CIVIL APPEAL NO. 11826 OF 2018 etc.
from PFC and its nominees in accordance with
Share Purchase Agreement and cause the Seller
to enter into the RFP Project Documents. The
Selected Bidder shall be responsible for
ensuring that the Seller undertakes
development, finance, ownership, design,
engineering procurement, construction,
commissioning, operation and maintenance of
the Project as per the terms of the RFP
Project Documents. The Selected Bidder shall
also ensure:
(i) All equipment and auxiliaries shall be
suitable for continuous operation in the
frequency range of 47.5 to 51.5 Hz (-5% to
+3% of rated frequency of 50.0 Hz).
(ii)The plant shall be capable of delivering
contracted capacity continously at 47.5 Hz
grid frequency.
1.4 The Procurers through the Authorised
Representative, have initiated development of
the Project at Sasan, District Sidhi, Madhya
Pradesh and shall complete the following
tasks in this regard by such time as
specified hereunder:
iv. Allocation of main Captive Coal Mine(s)
and providing geological report (GR) for the
same; at least ninety (90) days prior to Bid
Deadline. Allocation of other Captive Coal
Mine(s) and available information regarding
quality and quantity of coal (GR related
information) would be made available at least
thirty (30) days prior to Bid Deadline. The
Seller shall pay the final cost of geological
reports (Grs). The Indicative Cost of
geological reports (Grs), would be made
available at least thirty (30) days prior to
bid Deadline;
8
CIVIL APPEAL NO. 11826 OF 2018 etc.
v. Tying up water linkage for the Project
requirement along with approval of Central
Water Commission, at least thirty (30) days
prior to Bid Deadline;
Water intake study report and Project Report
including geo-technical study, topographical
survey, area drainage study, socio-economic
study and EIA study (rapid) would be made
available at least ninety (90) days prior to
Bid Deadline;
vi. issue of certificate by Ministry of
Power, Government of India extending the
benefits to power generation projects under
Mega Power Policy upto the Scheduled COD of
the Power Station by Government of India at
least thrity (30) days prior to Bid Deadline;
It may be noted that noe of the Procurers,
Authorised Representative and PfC, nor their
directors, employees or advisors/consultants
make any representation or warranty, express
or implied, or accept any responsibility or
liability, whatsoever, in respect of any
statements or omissions made in the water
intake study report and Project Report, or
the accuracy, completeness or reliablility of
information contained therein, and shal incur
no liability under any law, statute, rules or
regualtions as to the accuracy, reliability
or completeness of such water intake study
report and Project Report, even if any loss
or damage is caused to the Selected Bidder by
any act or omission on their part. The
Ministry of Power and the State Government of
Madhya Pradesh have expressed their support
to the Seller, on best endeavour basis, in
enabling the Seller to develop the Project.
9
CIVIL APPEAL NO. 11826 OF 2018 etc.
2.7.2.1 The Bidder shall make independent
enquiry and satisfy itself with respect to
all the required information, inputs,
conditions and cirumstances and factors that
may have any effect on his Bid. In assessing
the Bid, it is deemed that the Bidder has
inspected and examined the site conditions
and its surroundings, examined the laws and
regulations in force in India, the
transportation facilities available in India,
the grid conditions, the conditions of roads,
bridges, ports, etc. For unloading and/or
transporting heavy pieces of material and has
based its design, equipment size and fixed
its price taking into account all such
relevant conditions and also the risks,
contingencies and other circumstances which
mayh influence or affect the supply of power.
2.7.2.2 In their own interest, the Bidders
are requested to familiarize themselves with
the Electricity Act, 2003, the Income Tax Act
1961, the Companies Act, 1956, the Customs
Act, the Foreign Exchange Management Act,
IEGC, the regulations framed by regulatory
commissions and all other related acts, laws,
rules and regulations prevalent in India. The
procuers shall not entertain any request for
clarifications from the Bidders regarding the
same. Non-awareness of these laws or such
information shall not be a reason for the
Bidder to request for extension of the Bid
Deadline. The Bidder undertakes and agrees
that before submission of its Bid all such
factors, as generally brought out above, have
been fully investigated and considered while
submitting the Bid.
ANNEXURE 5
SITE DETAILS ALONG WITH SITE MAP
The Site is located near Sasan village in
Singrauli Tehsil in District Sidhi of Madhya
10
CIVIL APPEAL NO. 11826 OF 2018 etc.
Pradesh. The nearest Railway Station is
Shakti Nagar (18km) and nearest Airport is
Varanasi (250 km). The site is situated at
23°58’30”N latitude and 82°37’03”E longtitue.
About 3500 acres of land has been identified
for the project covering villages of
Sidhikala, Harhawa, Tiara, Jhanjitola and
Sidhikhud. Out of this, about 2000 acres of
land has been identified for main plant,
about 1100 acres for ash disposal/dyke and
400 acres for colony.
Water source for the project is Govind
Ballabh Pant Sagar (Rihand Reservoir), which
is about 6-7 km from the main plant site.
Water will be brought to site by suitable
pumping arrangement and pipelines.
Coal blocks (mines) in Singrauli area with
reserves of about 700-800 million tons will
be allocated as Captive Coal Blocks (mines)
for this Project. The Project will require
the development of a coalmine with production
of 18-20 million tons per annum (MTPA)
Vicinity map of Site is enclosed.
Further details are provided in the Project
Report."
(9) We may, at this juncture, notice also that the
Special Purpose Vehicle which was put in place for
carrying out the activities also, commissioned a
study by WAPCOS (a public sector body of the Central
Government). It was tasked with the project to
11
CIVIL APPEAL NO. 11826 OF 2018 etc.
ascertain about the availability of water inter
alia . Water is an indispensable factor for the
successful running of the power plant which was
contemplated. WAPCOS made available its report on
03.08.2006.
(10) Reliance Power Limited applied pursuant to the
RFP. Though, initially, its bid was not the lowest,
but on account of the fact that the lowest bidder
was found to be not eligible, Reliance Power Limited
emerged as the lowest bidder. In keeping with the
conditions, Reliance Power Limited acquired 100 per
cent share holding of the first respondent and it
was favoured with the Letter of Intent on
01.08.2007. It entered into a Power Purchase
Agreement (hereinafter referred to as ‘PPA’) on
07.08.2007. In the second week of December, 2007,
it would appear that the first respondent which now
stood transformed as a fully owned company of the
successful bidder Reliance Power Limited,
commissioned a new Study by WAPCOS. WAPCOS
submitted its report on 04.04.2008. We must at this
juncture notice that ‘21.07.2007’ has been
12
CIVIL APPEAL NO. 11826 OF 2018 etc.
determined as the cut off date, the relevance of
which will be unfolded in the later part of the
judgment.
(11) The PPA contemplated two phases. The first
phase was the construction of the power plant. The
second was the operation of the power plant. The PPA
was to be enforced for a period of 25 years.
Therefore, we can safely characterise it as a long
term agreement to purchase power. Since this was a
case of competitive bidding, leading to the finding
out of the lowest bidder, but faced with the regime
under Section 63 of the Act which stood attracted,
after the PPA was entered into, a petition was moved
before the Commission for adopting the rates as
contemplated in the PPA. By order dated 17.10.2007,
the Commission after considering the relevant
matters, adopted the rates in accordance with the
PPA. It is, thereafter, that the present petition
was moved by the first respondent on 19.02.2013. It
is relevant at this stage to set out certain
portions of the petition. The petition has been
filed under Section 79 of the Act read with the
13
CIVIL APPEAL NO. 11826 OF 2018 etc.
statutory framework governing procurement of power
through competitive bidding and articles 13 and 17
of the PPA between the parties for compensation due
to change in law ‘during the construction period’.
After setting out the facts which we do not consider
relevant to advert to, the following is noticed.
“5. It is submitted that the following
Changes in Law have occurred during the
Construction Period of the Project which
have caused the Capital Cost of the Project
to increase substantially:
a) Increase in Declared price of Land for
the Project which includes the land for the
Power Station, the Moher, Moher-Amlohri
Extension and Chhatrasal captive coal
blocks;
b) Increase in cost of implementation of the
Resettlement and Rehabilitation Plan (“R&R
Plan”) for the Moher, Moher-Amlohri
Extension and Chhatrasal captive coal
blocks;
c) Increase in cost of Geological Reports
for the Moher, Moher-Amlohri Extension and
Chhatrasal captive coal blocks;
d) Increase in cost of compensatory
afforestation for the Moher, Moher-Amlohri
Extension and Chhatrasal captive coal
blocks;
e) Increase in cost of Water Intake system
due to an incorrect assessment of conditions
in the original report supplied to the
bidders at the RFP stage;
f) Levy of excise duty on cement and steel
used in the Project; and
g) Levy of Customs Duty on mining equipment
14
CIVIL APPEAL NO. 11826 OF 2018 etc.
imported for the Project.”
(12) Since, in this case, we are concerned only with
two aspects, namely claims under clause(e) and
clause(g) we deem it appropriate only to refer to
the pleadings of the first respondent in regard to
the same.
Increase in cost of Water Intake System
“65. As per Clause 1.4(v) of RFP for Sasan
UMPP, the Procurers through the Authorized
Representative had to provide water intake
study report. WAPCOS (a premier Government
of India agency) was appointed to conduct
the water intake study. WAPCOS, as the
expert agency identified the water intake
pump house location and the pipeline route
from the intake pump house to the power
plant in its Report. This report was made
available to all the bidders before bid
submission so that the bidders could factor
in the cost of the water intake system in
preparation of their financial bid i.e.,
the tariff at which power would be supplied
to the Procurers. The total estimated cost
for the construction of water intake system
for the location and route indicated in the
report by WAPCOS was estimated to be
approximately Rs.92 Crores. The WAPCOS
Report along with the estimated cost are
annexed herewith and marked as Annexure P-
24 (Colly).”
“66. After RPower acquired the Petitioner,
WAPCOS was appointed to confirm the
15
CIVIL APPEAL NO. 11826 OF 2018 etc.
technical feasibility as part of detailed
engineering exercise. During this process,
it was discovered that the water intake
location as finalized by WAPCOS before the
bidding was not an appropriate location and
does not ensure reliable supply of water to
the power plant. It was also found that the
water intake at the original location
indicated by WAPCOS in the pre-bid report
would have resulted in shutdown of power
plant for a considerable period during the
lean season.”
“67. Thereafter, WAPCOS conducted detailed
bathymetric studies and recommended a new
location for water intake, which was 23 km
from the power plant as against 12.5 km
initially indicated at the time of bidding
(original location). It was highlighted
that new location would ensure reliable
water supply to the power plant. Due to
increase in distance, submergence area
along the route and construction time,
there has been considerable increase in the
cost of the water intake system as detailed
below. The report of WAPCOS recommending
the revised location is annexed herewith
and marked as Annexure p-25.”
“68. The cost for the construction of water
system for the new location is Rs. 244 Cr.
Out of the aforesaid amount, a sum of
Rs.185 Crores has already been incurred and
balance of Rs. 59Crores is to be spent. The
estimated increase in cost of the water
intake system due to the change in location
of the water intake system is Rs.152
Crores. Since this increase is directly
attributable to the error in the WAPCOS
report provided to the bidders at the pre-
bid stage, the Petitioner is required to be
compensated for the same. The cost break up
16
CIVIL APPEAL NO. 11826 OF 2018 etc.
for the new/appropriate location which will
ensure reliable water supply is annexed
herewith and marked as Annexure P-26.”
“75. It is submitted that the UMPP Policy
envisages domestic coal based UMPPs as
integrated projects where the power station
and the captive coal mines are treated as an
integrated unit. This is also recognized in
the PPA as well as other project documents
like the RFQ and the RFP.”
“76. As per Notification 21 of 2002-Customs
dated 01.03.2002 issued by the Ministry of
Finance, Government of India, the customs
duty on goods required for setting up mega
power projects has been prescribed as nil
meaning thereby that no customs duty will be
levied on goods imported for setting up a
mega power project. A copy of Notification
21 of 2002-Customs is annexed herewith and
marked as Annexure P-32.”
“77. Sasan UMPP was accorded in-principle
mega power project status as per Ministry of
Power's letter no. F.No. 12/18/2006-P&P
dated 20.10.2006. The final certificate was
issued on 21.09.2007.”
“78. Sasan UMPP is an integrated power
project with captive coal mines viz. Moher,
Moher Amlohri Extension and Chhatrasal Coal
Blocks. The captive coal mines allocated for
Sasan UMPP form an integral and essential
part of the Project and any equipment
imported in relation to the captive coal
mines would therefore be treated as goods
imported for setting up the Project.”
17
CIVIL APPEAL NO. 11826 OF 2018 etc.
“79. The Petitioner was required to import
mining equipment for setting up the captive
coal mines from which coal will be sourced
for the Project since the required mining
equipments were not available in India.”
“80. On 05.05.2011, the Petitioner applied
to the Energy Department, Government of
Madhya Pradesh for recommendation letter to
import mining equipments for Sasan UMPP
under nil custom duty as is applicable for
the other equipment such as power plants of
the Project. This application was premised
on Notification 21 of 2002-Customs. However,
vide an Office Memorandum dated 17.06.2011,
the Ministry of Power has intimated that the
exemption for customs duty for UMPPs is
given only with respect to power equipment,
which was forwarded to Petitioner by
Government of Madhya Pradesh on 20.06.2011.
Copies of letters dated 05.05.2011 and
17.06.2011 are annexed herewith and marked
as Annexure P-33(Colly)”
“81. Based on Ministry of Power's Office
Memorandum's, the Energy Department,
Government of Madhya Pradesh declined to
issue the recommendation letter which was
required by the Petitioner to claim nil
customs duty. In view of the refusal by
Energy Department, Government of Madhya
Pradesh and in the interest of the Project
and power consumers, Petitioner had to seek
recommendation letter from Energy
Department, Government of Madhya Pradesh to
import mining equipments at project import
rate of 20.94%, which is now reduced to
18
CIVIL APPEAL NO. 11826 OF 2018 etc.
16.85% with effect from 17.03.2012.”
“82. The decision of the Ministry of Power
detailed in its office memorandum dated
17.06.2011 and refusal by Energy Department,
Goverment of Madhya Pradesh to provide
recommendation letter to import mining
equipments for Sasan UMPP under nil custom
duty amounts to a Change in Law under
Article 13.1 of the PPA and Petitioner is
entitled to be compensated for the same.”
“83. The total amount of customs duty paid
by the Petitioner on mining equipments
imported for Sasan UMPP is Rs. 361.47 Crores
till date. The total custom duty for mining
equipments is estimated to be about Rs. 531
Crores. The details of the custom duty paid
on mining equipments and estimated to be
paid in future are annexed herewith in
Annexure P-34 (Colly).”
“84. It is submitted that the Petitioner has
already surpassed the indicative costs
provided by the Procurers and in certain
instances as indicated hereinabove, the
Petitioner will be required to pay the
increased Capital Cost in the future. In
this regard, the Petitioner is claiming the
following reliefs:
(a) In relation to the Changes in Law where
the additional Capital Cost has already been
incurred, this Hon'ble Commission may direct
the Procurers to compensate the Petitioner
for such increase in Capital Cost; and
(b) In relation to the Changes in Law for
19
CIVIL APPEAL NO. 11826 OF 2018 etc.
which the liability is yet to be incurred,
the Petitioner is seeking a declaration from
this Hon'ble Commission that the increased
expenditure amounts to Change in Law. The
actual payment will be claimed as and when
it falls due.”
“89. From the above discussions and facts,
it is clear that:-
(a) One of the objectives of the National
Electricity Policy and the Tariff Policy is
to secure commercial viability of
electricity sector while ensuring fair
pricing and quality of supply.
(b) Power procurement under Section 63 of
the Act is governed by the statutory
framework comprising (i) Section 63 of the
Act, (ii) Government of India's Guidelines
and (iii) standard documents being RFP and
PPA.
(c) In terms of Section 63 of the Act the
successful bid must be selected consistent
with the guiding principles under Section 61
of the Act meaning thereby that while
adoption of tariff under Section 63 of the
Act, the principles as laid down under
Section 61 need to be complied.
(d) Power procurement pursuant to the
statutory framework constitutes a statutory
contract in terms of the pre-approved and
finalized PPA governed by provisions of the
Act as well as the Guidelines.
(e) The PPA envisages the adjustment of
20
CIVIL APPEAL NO. 11826 OF 2018 etc.
tariff by this Hon'ble Commission to
restore/restitute the party adversely
affected (the Petitioner in the present
case).”
“90. It is also pertinent to note that
under Section 79(1)(b) of the Act, this
Hon'ble Commission has been given the power
to regulate the tariff of generating
companies like the Petitioner which have a
composite scheme for generation and sale of
electricity in more than one state.”
“91. The present Petition has been filed for
compensation on account of Changes in Law
which have impacted the Capital Cost of the
Project as well as for compensation for
costs incurred in excess of the indicative
costs provided by the Procurers, which were
the basis for formulation of the financial
bid of Rpower.”
“92. The Petitioner had approached the
Procurers for an amicable resolution.
However, all efforts made by the Petitioner
to seek an amicable resolution to the
unforeseen and undeserved commercial
implication with the Procurers have proved
fruitless. In this backdrop, it has become
imperative and necessary for the Petitioner
to invoke jurisdiction of this Hon’ble
Commission to issue appropriate orders as
prayed for in the Petition.”
“93. It is submitted that the present
Petition has been filed invoking:-
(a) Section 79(1)b) of the Act under which
21
CIVIL APPEAL NO. 11826 OF 2018 etc.
this Hon'ble Commission has the power to
regulate the tariff of the Petitioner.
(b) Section 79(1)(f) of the Act which gives
this Hon'ble Commission the power to
adjudicate upon disputes involving the
Petitioner.
(c) Regulations 82, 92 and 113 of the
Central Electricity Regulatory Commission
(Conduct of Business) Regulations, 1999.
(d) Article 13 of the PPA read with Article
17 and Paragraph 5.17 of the Competitive
Bidding Guidelines in terms of which this
Hon’ble Commission has the power to
adjudicate upon any dispute that arises
claiming any change in or regarding
determination of the tariff or any tariff
related matters, or which partly or wholly
could result in change in tariff.”
“104. As detailed in Paragraphs 75-83
above, Notification 21 of 2002-Customs
issued by the Ministry of Finance,
Government of India granted 100% exemption
from Customs duty to goods required for
setting up mega power projects. The
Petitioner was required to import equipment
for operation of the coal mine which is an
integral part of the Project.”
“105. It is submitted that as per the said
Notification, any entity which intended to
claim the customs duty exemption was
required to apply to the Sponsoring
Authority for an exemption certificate. This
was essential to claim the customs duty
22
CIVIL APPEAL NO. 11826 OF 2018 etc.
exemption. In this regard, the Petitioner
wrote to the Government of Madhya Pradesh to
recommend the Petitioner’s case to the
Commissioner of Customs on 5.5.2011 for nil
custom duty on mining equipments.”
“106. It is submitted that vide an Office
Memorandum dated 17.06.2011, the Ministry of
Power intimated Government of Madhya Pradesh
that the exemption for customs duty for
UMPPs is given only with respect to power
equipment. The total amount of customs duty
paid by the Petitioner on mining equipments
imported for Sasan UMPP is Rs.361.47 Crores
till date. Total custom duty for mining
equipments is estimated to be about Rs. 531
Crores.”
“107. It is submitted that the decision of
the Ministry of Power amounts to a Change in
Law under Article 13.1 of the PPA and the
Petitioner is entitled to be compensated for
the same. It is further submitted that the
Petitioner not being allowed to import
mining equipment under nil customs duty as
is granted for the other equipment such as
power plants of the Project qualifies as
Change in Law under Article 13.1 of the
PPA.”
“108. It is submitted that as per RFP for
Sasan UMPP, the Procurers had to provide
water intake study report. This study was
conducted by WAPCOS and the report was made
available to all the bidders before bid
submission. The cost of the water intake
system as per the report was approximately
Rs.92 Crores. This estimation was factored
23
CIVIL APPEAL NO. 11826 OF 2018 etc.
into the bid at the time of submission of
the financial bid.”
“109. It is submitted that after Rpower
acquired the Petitioner, WAPCOS was tasked
with confirming the technical feasibility
during the detailed engineering exercise.
During this process, it was discovered that
the water intake location as intimated in
the pre-bid report was not appropriate.
After, conducting another detailed study,
WAPCOS determined that a new location would
be suitable. The new location is 23 km from
the power plant as against 12.5 km initially
indicated at the time of bidding (original
location).”
“110. It is submitted that due to the
increase in distance, submergence area along
the route and construction time there has
been considerable increase in cost of the
water intake system. The cost for the
construction of water system for the new
location is Rs. 244 Cr. The estimated
increase in cost of the water intake system
due to the change in location of the water
intake system is Rs.152 Crores.”
“111. It is submitted that the increase in
cost of the water intake system is on
account of the errors in the report provided
by the Procurers and therefore, the
Procurers are obligated for compensating the
Petitioner for the difference in cost. It
is further submitted that since the water
pipeline corridor is part of the Power
Station Land and the water intake pipeline
24
CIVIL APPEAL NO. 11826 OF 2018 etc.
is an integral part of the Power Station,
any change in the indicative cost of the
water intake system will be covered under
Change in Law.”
“120. Section 79 of the Act, inter alia ,
empowers the Hon’ble Commission to:-
(a) Regulate the tariff of generating
companies other than those owned or
controlled by the Central Government if such
generating companies entered into or
otherwise have a composite scheme for
generation and sale of electricity in more
than one State; and
(b) To adjudicate upon the disputes
involving the distribution companies or
transmission licensees with regard to the
matters connected with regulation of tariff
of generating companies.”
“128. It is submitted that the present case
involves a situation where the compensatory
mechanism under the PPA for compensation for
Change in Law has failed. It does not meet
the objective of restoring an affected party
to the same economic condition as if the
change in law had not occurred. Therefore,
this is a fit case for this Hon’ble
Commission to exercise its powers under
Section 79 and devise a mechanism to uphold
the objective and purpose of Article 13 – to
provide economic restitution.”
“129. It is further submitted that PPA
envisages a scenario where this Hon’ble
25
CIVIL APPEAL NO. 11826 OF 2018 etc.
Commission can interfere with the issues
relating to the claim made by a party for
any change and/or determination of the
tariff or any matter relating to the tariff
or claims made by any party which partly or
wholly related to any change in the tariff
or determination of any such claim which can
result in change in the tariff. In this
context, Articles 13 and 17 are noteworthy.
While Article 13 of the PPA envisages tariff
adjustment in the event of “Change in Law”,
Article 17 of the PPA provides for dispute
resolution, by the Hon’ble Commission in
case of claim made by any party for any
change in or determination of tariff or any
matter related to tariff or claims made by
any party, which partly or wholly relate to
any change in the tariff or determination of
any of such claims could result in change in
tariff.”
“142. The Petitioner therefore most humbly
and respectfully prays that this Hon’ble
Commission be pleased to adjudicate upon the
present Petition to:-
(a) Declare that the items set out in
Paragraph 5 above as Change in Law during
Construction Period and/or changes which has
led to an increase in the Capital Cost of
the Project;
(b) Restitute the Petitioner to the same
economic condition as if the said Changes in
Law had not occurred and devise a mechanism
by which the Petitioner is compensated for
the aggregate financial impact and increase
26
CIVIL APPEAL NO. 11826 OF 2018 etc.
in capital cost of account of the Changes in
Law, the details of which are set out in
Paragraph 113 above; and
(c) Pass any such other and further reliefs
as this Hon’ble Commission deems just and
proper in the nature and circumstances of
the present case.”
(13) After exchange of pleadings, the Commission
passed the order dated 04.02.2015. Since we are in
these appeals to be detained only by two aspects, we
notice the following findings:
“30. The petitioner has submitted that as per
Clause 1.4(V) of RFP for Sasan UMPP, the
Procurers through the Authorized
Representative had to provide water intake
study report. WAPCOS (a premier Government of
India agency) was appointed to conduct the
water intake study. WAPCOS, as the expert
agency identified the water intake pump house
location and the pipeline route from the
intake pump house to the power plant in its
Report. This report was made available to all
the bidders before bid submission so that the
bidders could factor in the cost of the water
intake system in preparation of their
financial bid i.e. the tariff at which power
would be supplied to the Procurers. The total
estimated cost for the construction of water
intake system for the location and route
indicated in the report by WAPCOS was
estimated to be approximately ₹ 92 Crore.
27
CIVIL APPEAL NO. 11826 OF 2018 etc.
After RPower acquired the project, WAPCOS was
appointed to confirm the technical
feasibility as part of detailed engineering
exercise. During this process, it was
discovered that the water intake location as
finalized by WAPCOS before the bidding was
not an appropriate location and does not
ensure reliable supply of water to the power
plant. It was also found that the water
intake at the original location indicated by
WAPCOS in the pre-bid report would have
resulted in shutdown of power plant for a
considerable period during the lean season.
Thereafter, WAPCOS conducted detailed
bathymetric studies and recommended a new
location for water intake, which was 23 km
from the power plant as against 12.5 km
initially indicated at the time of bidding
(original location). It was highlighted that
new location would ensure reliable water
supply to the power plant. Due to increase in
distance, submergence area along the route
and construction time, there has been
considerable increase in cost of the water
intake system as per following details
(Annexure P-26 of the petition) and as per
the earlier report of WAPCOS:-
| S.<br>No. | Cost Item | As per<br>earlier<br>WAPCOS Report | Current<br>estimate |
|---|---|---|---|
| (₹ Crore) | (₹<br>Crore) | ||
| 1 | Cost of Pump House | 21.00 | 62.97 |
| 2 | Cost of Bridge | 10.50 | |
| 3 | Supply of Pipe<br>line | 30.50 | 73.91 |
28
CIVIL APPEAL NO. 11826 OF 2018 etc.
| 4 | Laying of pipe<br>line | 16.70 | 57.97 |
|---|---|---|---|
| 5 | Mechanical | 10.20 | 20.32 |
| 6 | Electrical | 3.50 | 4.02 |
| 7 | Dredging for Pump<br>House | 25.13 | |
| 8 | Total | 92.40 | 244.32 |
31. MPPMCL has submitted that it is an
expense incurred by the petitioner but is not
covered under “Change in Law” under Article
13.1.1 of the PPA. However, it is concluded
that the cost has been incurred by the
petitioner and exceeds the estimates given by
the procurer's authorized representative
prior to bid submission. HPCC has submitted
that the price and other details given in the
bidding document were by way of information
and it was for the bidders to conduct
independent enquiry and verify the
information and details. There is no
misrepresentation by the procurers or by the
Bid Process Coordinators at the time of
bidding in relation to water intake for the
project. In view of the specific disclaimer
and the requirement to conduct independent
enquiry, the petitioner was required to make
appropriate enquiries into the matter before
bidding and the bidders were not entitled to
proceed only on the basis indicative
information given by the Bid Process
Coordinator.
32. We have considered the submission of the
petitioner and respondent. As against the
indicative cost of ₹ 92.40 crore, the cost for
the construction of water system for the new
29
CIVIL APPEAL NO. 11826 OF 2018 etc.
location is ₹ 244 crore out of the aforesaid
amount, a sum of ₹ 185 crore has already been
incurred and balance of ₹ 59 crore is to be
spent. The estimated increase in cost of the
water intake system due to the change in
location of the water intake system is ₹ 152
crore. The petitioner has submitted that
since this increase is directly attributable
to the error in the WAPCOS report provided to
the bidders at the pre-bid stage, the
petitioner is required to be compensated for
the same.
33. In our view, the claim is not covered
under any of the provisions of Article 13.1.1
of the PPA. The petitioner being aware that
the cost of water intake system being
indicative in nature and being not covered
under the “Change in Law” under Article 13
should have informed itself fully with the
actual site conditions before preparing the
bid and accordingly factored the possible
estimates of water intake system while
quoting the bid instead of relying on the
indicative cost. In this connection, para
2.7.2.1 of the RfP document provides as
under:
“2.7.2.1 The Bidder shall make
independent enquiry and satisfy
itself with respect to all the
required information, inputs,
conditions and circumstances and
factors that may have any effect on
his Bid. In assessing the Bid, it is
deemed that the Bidder has inspected
and examined the site conditions of
roads, bridges, ports etc. for
30
CIVIL APPEAL NO. 11826 OF 2018 etc.
unloading and/or transporting heavy
pieces of material and has based its
design, equipment size and fixed its
price taking into account all such
relevant conditions and also the
risks, contingencies and other
circumstances which may influence or
affect supply of power.”
Further para 4 of the RfP document provides
that the pricing and other details given in
the bidding documents are by way of
information only and it was for the bidders
to conduct independent enquiry and verify the
details and information. Para 4 are extracted
as under:
“4. While the RFP has been prepared
in good faith, neither the
Procurers, Authorised Representative
and Power Finance Corporation (PFC)
nor their directors or employees or
advisors/consultants make any
representation or warranty, express
or implied, or accept any
responsibility or liability,
whatsoever, in respect of any
statements or omission herein, or
the accuracy, completeness or
reliability of information contained
herein, and shall incur no liability
under any law, statute, rules or
regulations as to the accuracy,
reliability or completeness of this
RFP, even if any loss or damage is
caused to the Bidder by any act or
omission on their part.”
31
CIVIL APPEAL NO. 11826 OF 2018 etc.
Therefore, it is the responsibility of the
petitioner to verify the suitability of the
location of water intake and ensure reliable
water supply for the power plant and workout
the relevant approximate cost of water intake
system independently and factor in the
estimates in the bid so that a realistic cost
is reflected in the bid. The petitioner
having failed to do so, the increase in cost
on account of this head is not admissible.”
(14)
As far as the question relating to imposition
of customs duty on mining equipment is concerned,
the same is dealt with in paragraphs 40 and 41.
“40. We have considered the submission of
the petitioner and respondents. The
Notification No.49/2006 provides as under:
Notification No. 49/2006-Customs
In exercise of the powers conferred by sub-
section (1) of Section 25 of the Customs Act,
1962 (52 of 1962), the Central Government, on
being satisfied that it is necessary in the
public interest so to do, hereby makes the
following further amendments in the
notification of the Government of India in
the Ministry of Finance (Department of
Revenue) No. 21/2002- Customs, dated the 1st
March, 2002, which was published in the
Gazette of India, Extraordinary vide number
G.S.R. 118(E), dated the 1st March, 2002,
namely:-
32
CIVIL APPEAL NO. 11826 OF 2018 etc.
In the said notification,-
(I) in the Table, against S.No.400,
for the entry in column (3), the
following entry shall be
substituted, namely:-
“Goods required for setting up of
any Mega Power Project, so certified
by an officer not below the rank of
a Joint Secretary to the Government
of India in the Ministry of Power,
that is to say-
(a) an inter-state thermal power
plant of a capacity of 700MW or
more, located in the States of Jammu
and Kashmir, Sikkim, Arunachal
Pradesh, Assam, Meghalaya, Manipur,
Mizoram, Nagaland and Tripura; or
(b) an inter-state thermal power
plant of a capacity of 1000MW or
more, located in States other than
those specified in clause (a) above;
or
(c) an inter-state hydel power plant
of a capacity of 350MW or more,
located in the States of Jammu and
Kashmir, Sikkim, Arunachal Pradesh,
Assam, Meghalaya, Manipur, Mizoram,
Nagaland and Tripura; or
(d) an inter-state hydel power plant
of a capacity of 500MW or more,
located in States other than those
specified in clause (c) above”;
33
CIVIL APPEAL NO. 11826 OF 2018 etc.
(II) in the Annexure, in Condition
No. 86, for sub-clauses (ii) and
(iii) of clause (a), the following
shall be substituted, namely:-
“(ii) the power purchasing State
undertakes, in principle, to
privatize distribution in all
cities, in that State, each of which
has a population of more than one
million, within a period to be fixed
by the Ministry of Power.”.
[F.No.354/104/2003-TRU]
It is noticed that the revised policy
guidelines issued by Government of India,
Ministry of Power vide its letter No. A-
118/2003-IPC dated 2.8.2006 has stated that
an inter-State thermal power plant of a
capacity of 1000 MW or more is eligible for
grant of mega power status. It further states
as under:
“Zero Customs Duty: In terms of the
notification of the Government of
India in the Ministry of Finance
(Department of Revenue) No. 21/2002-
Customs dated 1.3.2002 read together
with No. 49/2006-Customs dated
26.5.2006, the import of capital
equipment would be free of customs
duty for these projects.”
41. It is to be considered whether under the
notification as stated above, mining
equipments were exempted from customs duty.
General Exemption No.122 under the Customs
34
CIVIL APPEAL NO. 11826 OF 2018 etc.
Notification No.21/2002 as amended from time
to time contains the list of items which are
exempted from customs duty. It is observed
that Notification 21 of 2002-Customs clearly
demarcates the power projects and mining
projects separately. It is seen that at Ser
No.399 of the list, coal mining projects are
liable to pay customs duty. Ser No. 400 only
exempts the mega power project from payment
of customs duty and there is no mention that
it includes captive power plants. Therefore,
it cannot be said that as on the cut-off
date, there was exemption on mining equipment
and the petitioner had taken into
consideration such exemption while quoting
the bids. Nothing has been produced in the
petition which could indicate that any such
impression was given by the procurers or
their representative prior to bidding. In
view of the foregoing discussion, the
submission of the petitioner that the
decision of the Ministry of Power detailed in
its office memorandum dated 17.06.2011 and
refusal by Energy Department, Government of
Madhya Pradesh to provide recommendation
letter to import mining equipments for Sasan
UMPP under nil custom duty amounts to a
"Change in Law" under Article 13.1 of the PPA
and the petitioner is entitled to be
compensated for the same is not acceptable
and hence no compensation would be available
in this regard.”
THE APPEAL BEFORE THE TRIBUNAL
(15) This led to the appeal being filed by the first
respondent under Section 111 of the Act. It is
35
CIVIL APPEAL NO. 11826 OF 2018 etc.
apposite that we set out the exact case which has
been set up by the first respondent before the
Tribunal.
“9.5 The Report identified the water intake
pump house location and pipeline route from
the intake pump house to the power plant in
its report. This report was made available
to all the bidders before bid submission so
that the bidders could factor in the cost of
water intake system in preparation of their
financial bids i.e., the tariff at which
power be supplied to the Procurers. The
total cost for the construction of water
intake system for the location and route of
indicated in the report by WAPCOS was
estimated to be Rs.92 Crores. The water
intake system is an integral part of the
Project without with it is not possible to
set up and operate the Project. The WAPCOS
report along with estimated cost are annexed
herewith and marked as Annexure A-14.
9.6 After RPower was declared the successful
bidder and the Appellant Company was
transferred to RPower, WAPCOS was re-
appointed to confirm the technical
feasibility as part of the detailed
engineering exercise. During this process,
it emerged that the water intake location as
finalized by WAPCOS vide its earlier report
prepared for PFC/ Procurers and made
available to all bidders prior to bid
submission was not an appropriate location
and does not ensure reliable supply of water
to the power plant. It also emerged that the
water intake at the original location
indicated by WAPCOS in the pre-bid report
would have resulted in shutdown of the power
plant for a considerable period in a year
36
CIVIL APPEAL NO. 11826 OF 2018 etc.
during the lean season. Therefore, WAPCOS
recommended a new location for water intake,
which was 23 km from the power plant as
against the 12.5 kms initially indicated at
the time of bidding (original location). It
was highlighted that the new location would
ensure reliable water supply to the power
plant. Due to increase in the distance,
submergence area along the route and
construction time, there has been
considerable increase in the cost of water
intake system due to change in location as
detailed below. The report of WAPCOS
recommending the revised location is annexed
herewith and marked as Annexure A-15.
9.7 It is submitted that due to the change
in location, cost for water intake system
has increased on following counts:
(a) While the route length itself increased
to 23 kms, the increase in piping length
increased from 24 km (2 Pipe Lines each of
12 Kms) to 59.5 km (2 Pipe Lines each of 8
km & 3 Pipes each of 14.5 km)
(b) Increased cost due to deeper Pump House.
(c) Additional dredging for creation of
intake channel for the offshore pump house.
(d) Additional cost due to HT transmission
line.
There has been considerable increase of
approximately Rs.176 Crores in cost of the
water intake system, which now is estimated
to be approximately Rs.268 Crores. The cost
break-up for the new location for the water
intake system is annexed herewith and marked
as Annexure A-16.
9.8 It is submitted that the increase in
cost of the water intake system is on
account of the errors in the report provided
37
CIVIL APPEAL NO. 11826 OF 2018 etc.
by the Procurers and therefore, the
Procurers are required to compensate the
Appellant for the difference in cost.
9.9 It is further submitted that since the
water pipeline corridor is part of the Land
for the Power Station and the water intake
pipeline is an integral part of the Power
Station, any change in the indicative cost
of the water intake system is covered under
Change in Law in terms of Article 13 of the
PPA since it amounts to change in cost of
land of the Project. In fact, the Ld.
General Commission has noted in the impugned
Order that the estimate for Declared Price
of Land for the Power Station includes the
Water Intake System. The operative part of
the Impugned Order is reproduced below:
“19. Change in the declared price of land is
covered under “Change in Law”. The procurers
have also agreed that this item of
expenditure is admissible under “Change in
Law”. The declared price of land for the
Power Station was stated to be 190.677
crore. This has been verified from the
communication dated 23.10.2006 from the
representative of the procurers to the
bidders. This included the power plant area,
the fuel transport system land, the water
pipeline corridor and the ash pipeline
corridor.”
9.11 It is submitted that pre-bid site visit
and project reports were prepared and made
available by Authorized Representative
(Power Finance Corporation) to all bidders.
The disclaimer, if at all applicable, will
only apply to such instances where the
bidders were able to identify any issues or
liability with reasonable diligence. Based
on the information and material provided,
there was no indication that the water
38
CIVIL APPEAL NO. 11826 OF 2018 etc.
intake system proposed in the WAPCOS Report
was unfeasible. Therefore, the disclaimer
does not absolve the Procurers of their
liability to compensate the Appellant for
the increase in cost. It is submitted that
due to the error in WAPCOS’s report, the
Appellant is faced with an additional burden
of Rs.176 Crore which has adversely impacted
the project economics. It is submitted that
the disclaimers contained in Para 2.7.2.1
and Para 4 of the RFQ ought not to be
considered absolute in nature so as to
prevent loading of costs which are incurred
by the Appellant as a direct result of
omission or error on part of the Procurers
in providing information during the pre-bid
stage. This approach is counter-intuitive to
ensuring that the Appellants Project is able
to supply cheap and affordable power to over
42 million consumers in the Procurer States.
It is further submitted that the disclaimers
cannot act as an absolute bar to the
liability of the Procurers. Any duty to
independently verify inputs, information
factors etc. require only a reasonable duty
of care. The grave technical deficiencies
and huge differences between actual cost and
estimates provided to the bidders defeat the
fundamental objective of providing
information to the bidders especially when
the nature of expense in this case was of
buying a report from a Government Company
which had carried out a detailed study. The
Appellant had no other option but to rely on
the information provided by the authorized
representative of the Procurers. Therefore,
Ld. Commission’s reliance on the disclaimers
contained in the bid documents to reject the
claim of the Appellant is not sustainable.”
(16) In regard to the complaint about the
notification issued by the Joint Secretary in the
39
CIVIL APPEAL NO. 11826 OF 2018 etc.
Ministry of Power having brought about a change in
law, we find the following complaint, inter alia :
“9.20. It is submitted that as per Notification
21 of 2022- Customs dated 01.03.2002 issued by
the Ministry of Finance, Government of India,
the customs duty on goods required for setting
up mega projects has been prescribed as nil
meaning thereby that no customs duty will be
levied on goods imported for setting up a mega
power project. Notification 21/2022- Customs
which provides as under:
“
S.
No.
Chapter or
Heading or
sub-heading
Description of Goods Standard
Rate
Additional
Duty Rate
Condition
No.
(1) (2) (3) (4) (5) (6)
98.01 Goods required for setting
up any Mega Power Project
specified in List 42 if such
Mega Power is (a) An inter-
state thermal power plant of
1000 MW or more (b) an
inter-state hydel power plant
of a capacity of 500 MW or
more As certified by an
officer not below the rank of
joint secretary to the
Government of India in the
Ministry of Power.
9.22 It is submitted that captive Coal Blocks
being an integral part of the Project, the
mining equipment would be covered under this
provision as well. It is submitted that RFP
clearly stated that Procurers through the
Appellant (which was a wholly-owned
subsidiary of PFC at that time) will procure
a certificate from the Ministry of Power that
the benefits of the Mega Power Policy would
40
CIVIL APPEAL NO. 11826 OF 2018 etc.
be extended to the Project till scheduled
Commercial Operations Date of the Power
Station. As per definition, Project includes
captive mine and hence, it was Procurer’s
obligation to provide for the exemption to
the coal mining equipment.
9.24 It may also noted that:-
Xxx xxx xxx
(b) PPA defines Project as power plant along
with captive coal mines.
9.35 It is submitted that the Appellant has
set up an ultra-mega power project which
comprises of captive coal mines. It is not
separately indulging in mining activities.
Moreover, the coal from the Project is being
used only for the Project. The entire capital
cost of the power project includes the cost
of the coal mines. This is also evident from
Article 13 of the PPA where increase in cost
of land and R&R expenditure for the coal
mines is included as change in law.
Therefore, the finding that the captive coal
mines are a separate activity and will fall
under Serial No. 399 is incorrect and ought
to be set aside.
FINDINGS OF THE TRIBUNAL
(17) As far as the complaint about the increased
costs on account of change in water intake system,
the following is the finding of the Tribunal.
“12.4 After due consideration of the rival
contentions of both the parties, what emerges
is that after being declared as the
41
CIVIL APPEAL NO. 11826 OF 2018 etc.
successful bidder, the SPL with a view to
affirm the technical suitability of the
preliminary report of the WAPCOS on Water
Intake System, re-engaged the same agency for
finalization of the said report. It is not in
dispute that the Consultant, WAPCOS reviewed
its earlier report and came to a conclusion
that the earlier location of Water Intake was
not at proper place and would result in non-
availability of water for the plant during
lean period. It is relevant to note that
based on the recommendations of WAPCOS, SPL
decided to go ahead for selection of new
location as recommended and got carried out
the requisite design and engineering of the
entire Water Intake System which resulted
into longer piping system, increased
submergence area along the route, additional
construction period etc.. On account of these
factors, the cost of Water Intake System went
up by over Rs.176 crores. The learned counsel
appearing for the Appellant pointed out that
the judgment of this Tribunal in Nabha Power
case is not applicable to the present case
since no cost relating to seismic zone data
was provided to Nabha whereas in the instant
case, costs were provided to the bidders. The
Appellant has further reiterated that para
2.7.2.1 and para 4 of RFP which were relied
upon by the Respondent procurers cannot be
taken as obsolute in nature so as to absolve
procurers of their responsibility for
providing grossly incorrect information
leading to substantial increase in cost of
Water Intake System.
12.5 After thoughtful consideration of the
submissions made by the learned counsel for
42
CIVIL APPEAL NO. 11826 OF 2018 etc.
the Appellant and the Respondents and the
findings of the Central Commission, we find
that while the responsibility of carrying out
due diligence before bidding and verifying
the correctness of information provided in
the bid documents rested with the bidders, at
the same time, Respondent procurers cannot
justify providing grossly erroneous report on
Water Intake System taking shelter under the
disclaimer in the bid document. As a matter
of fact, the water availability for a thermal
power station of this magnitude on regular,
reliable and uninterrupted basis is essential
and is a vital input for successful operation
of the plant. It is noticed that the report
of WAPCOS supplied to bidders at the time of
bidding was deficient in ensuring adequate
water supplies throughout the year
uninterrupted and if the same would have been
taken for construction and implementation,
the same could have resulted into huge loss
to the Respondent procurers being deprived of
power supply for some period of the year due
to less/ non-availability of water during the
lean period. It is not in dispute that Sasan
UMPP is supplying power to the Respondent
procurer at one of the most competitive
tariff in the country. It is noted from the
contentions of the Respondent procurers that
such an issue has not been dealt with either
in the PPA or in the competitive bidding
guidelines issued by Ministry of Power under
Section 63 of the Act, however, in view of
the criticality of such situation, we opine
that the matter needs afresh re-look for
suitable redressal. While the Central
Commission has correctly concluded that it
does not qualify as change in law under
43
CIVIL APPEAL NO. 11826 OF 2018 etc.
Articles 13.1.1 of the PPA, it, however,
needs to be addressed on the basis of settled
principles of law and equity also, in the
light of the Hon’ble Supreme Court findings
in its judgment at Para 19 in Energy Watchdog
vs. CERC dated 11.04.2017. Thus, we are of
the considered view that this issue involving
substantial additional expenditure basically
arising out of erroneous report of the
consultants needs to be re-examined afresh by
the Central Commission. Hence, this issue is
answered in favour of the Appellant.”
(18) In regard to the complaint relating to the O.M.
dated 17.06.2011 forming change in law, we note the
following findings:
“14.5 We have considered the submissions of
the learned counsel for the Appellant and
learned counsel for the Respondents along
with the consideration of the Central
Commission on this issue pertaining to the
claims of the Appellant regarding
compensation on account of additional payment
towards custom duty on mining equipment.
After careful consideration and critical
evaluation of the same, the key question
arises for consideration, whether the
equipment required for captive coal mines
allocated to UMPP should be considered at par
with the equipment required for setting up
the power plants as far as exemption from the
custom duty is concerned. The contention of
the Appellant that the captive coal mines
allocated to Sasan UMPP are integral &
essential part of the project as a whole and
44
CIVIL APPEAL NO. 11826 OF 2018 etc.
as such, the exemption of custom duty was
applicable to all equipments being imported
for the entire project i.e. captive coal
mines as well as power plants. It is not in
dispute that the captive coal mines were
allotted for UMPP for its exclusive use for
power generation and in no way, meant for
commercial utilization elsewhere.
14.6 In this regard, we also take the note
of Hon’ble Supreme Court directions in
judgment dated 24.08.2014 in Manohar Lal
Sharma Vs. Principal Secy., in W.P.(CRL) 120
of 2012 (Para 158) that coal from captive
coal mines is to be used for UMPP alone and
no diversion of coal for commercial
exploitation would be permitted. Keeping
these facts in view, we notice the glowing
difference between an independent coal mines
up for exploitation and selling coal on
commercial lines and a captive coal mine set
up to meet requirement of UMPP only to
generate power for the ultimate benefit of
the Respondent procurers and in turn,
consumers for obtaining electricity at
cheaper rates. The actual positions purported
the assumption made by the Appellant that the
customs duty exemptions will be available for
import of the equipment for the entire
project including captive mines and power
plants. We find force in the argument of the
learned counsel for the Appellant that being
the integral and inseparable part of the
UMPP, the custom duty rates applicable for
stand alone coal mining projects would not be
applicable in the present case and the
exemption would need to be given effect to.
We, thus opine that the Central Commission
45
CIVIL APPEAL NO. 11826 OF 2018 etc.
appears to have been mechanically guided by
the mere description of the relevant entry
(Sl.No.399 & 400) in the said custom duty
notifications and has not appreciated that
the captive coal mines being integral part of
the UMPP cannot be equated to a stand alone
coal mines, having commercial line of
utilization. The Appellant was thus right in
assuming that Custom Duty exemption will be
available for the coal mining equipments. As
such, this issue needs to be examined afresh
in accordance with law and various provisions
of the RFQ/RFP/PPA. Therefore, we answer this
issue in favour of the Appellant.”
(19) On the basis of the aforesaid findings, the
Tribunal remanded the matter back to the Commission.
We may also notice the sequel to the impugned
judgment. Pursuant to the remand, the Commission
reconsidered the matter in regard to the water
intake. The Commission ordered payment of sum of
Rs.176 crores. As far as the claim for compensation
on the basis that the issuance of the office
memorandum by the Joint Secretary in the Ministry of
Power having brought about a change in law, it was
found that the goods in question had been imported
not by the first respondent but by its parent
company. This, in turn, has triggered two sets of
46
CIVIL APPEAL NO. 11826 OF 2018 etc.
appeals again before the Tribunal and they are still
pending. Their fate, undoubtedly, will depend upon
the decision which we will be rendering in these
cases.
(20) We have heard Mr. P. Chidambaram, Mr. Dhruv
Mehta, Mr. Rana Mukherjee, Mr. M. G. Ramachandran,
Mr. G. Umapathy, learned senior counsel, assisted by
Mr. Nikunj Dayal and Ms. Pallavi Sehgal. We have
also heard Mr. Shubham Arya, learned counsel
appearing on behalf of the appellant in one of the
appeals. On the other hand, we also heard Mr.
Sajjan Poovayya, learned senior counsel assisted by
Mr.Rahul Kinra, learned counsel and Mr. Amit Kapoor,
learned counsel.
SUBMISSION OF APPELLANTS
(21) Shri P. Chidambaram, learned senior counsel
appearing for the appellant, would submit that the
Tribunal has clearly acted in error and illegally in
passing the impugned order.
(22) He would submit that as far as the finding
47
CIVIL APPEAL NO. 11826 OF 2018 etc.
given by the Tribunal in regard to the water intake
system being located at a different place, is
concerned, the Tribunal agreed with the Commission
that there was no change in law. Once, it was found
that there was no change in law, there is no power
with the Tribunal to do what it did. The PPA
signifies an agreement between the parties. The PPA
goes into meticulous details. It follows an
internationally competitive bidding and the
obligations of the parties have been carved out and
articulated with great care. Once the party, viz.,
the first respondent went to the Commission
complaining that there is a change in law and it was
found that there is no change in law, there ended
the jurisdiction of the Tribunal. Instead of
terminating the lis , the Tribunal has clearly
strayed outside its jurisdiction in granting relief
on the basis that report of WAPCOS was grossly
erroneous. In this regard, he enlisted in support
of his contention, various clauses which
unambiguously disclaimed any liability with the
procurers on account of any inaccuracies which may
48
CIVIL APPEAL NO. 11826 OF 2018 etc.
be reflected in the WAPCOS report. A report
submitted by WAPCOS which is a public sector body
was only by way of providing information. The
bidders were provided with the report well before
they decided to put in their bids. Having regard to
the various disclaimer clauses, it did not lie in
their mouth to thereafter seek to construct a case
based on the report being erroneous. In this
regard, it is pointed out that the clauses clearly
indicate that the bidder was to satisfy itself by
conducting a study of the site. Nothing prevented
the first respondent from carrying out inspection of
the site and verifying for itself the information
which was provided through the report of the WAPCOS.
(23) Mr. P. Chidambaram, learned senior counsel,
further pointed out that a perusal of the second
WAPCOS report, which is the sole basis for the huge
claim raised by the first respondent, would show
that the second report does not, in any manner,
rubbish the first report. It is not in dispute, it
is pointed out, that the procurers were in no way
associated with the carrying out of the second
49
CIVIL APPEAL NO. 11826 OF 2018 etc.
WAPCOS report. Unilaterally, the first respondent
without any basis gets the second report
commissioned and it is on the said basis alone that
the claim was made and what is more, allowed by the
Tribunal. This is clearly impermissible. As
regards the claim for compensation alleging change
in law brought about by the Office Memorandum issued
by the Joint Secretary is concerned, in the first
place, it is pointed out that the proper thing for
the first respondent to do would have been to take
up the matter with the Department and claim a refund
and he would submit it is strange instead of doing
that the burden is sought to be passed on to the
procurers and which, in turn, would necessarily be
passed on to the ultimate consumers.
(24) Further, it is pointed out that the Tribunal
has actually proceeded to take into consideration
the earlier notifications which prevailed at the
time of the cut off date with reference to which
alone change in law is projected. Thereafter, it
has come to the conclusion that for the goods
imported from abroad for the purpose of the captive
50
CIVIL APPEAL NO. 11826 OF 2018 etc.
mines, there was an exemption. Such an inquiry
itself could not have been done. In other words, it
is not a case where the first respondent had
indisputable material on hand which established
unambiguously that there was a change in law. This
is for the reason that there is no material to
establish that prior to the cut off date, the goods
which are the subject matter of dispute, were exempt
under the notification. On the other hand, our
attention is drawn to the decision of the Advance
ruling authority which has gone into the issue and
found that goods in question were not exempt. In
fact, it is the contention of the appellants that
the office memorandum issued by the Joint Secretary,
Ministry of Power, merely follows the advance
ruling.
(25) Another argument which is raised in this regard
is that the Joint Secretary in the Ministry of Power
is not the final Governmental authority within the
meaning of clause 13.1.1. What we are concerned
with is notification issued under Section 25 of the
Customs Act. It is not as if any authority which is
51
CIVIL APPEAL NO. 11826 OF 2018 etc.
competent within the meaning of Article 13.1.1 has
issued a notification or even an interpretation
within the meaning of the said article which has
resulted in a change in law within the meaning of
Article 13.1.1.
(26) We have also heard Shri Dhruv Mehta, as we have
already stated. We have heard the other senior
counsel who have essentially adopted the arguments
which have been addressed by Mr. P.Chidambaram,
learned senior counsel, and they are one in
contending that the Tribunal has strayed outside the
contours of its jurisdiction and this has resulted
in an order which is clearly illegal and erroneous.
SUBMISSIONS OF THE FIRST RESPONDENT
(27) Per contra , Mr. Sajjan Poovayya, learned senior
counsel for the first respondent, took us through
the other side of the picture and projected a
totally different scenario. He would point out, in
the first place, that the Court may not view the PPA
in question as an ordinary contract. He pointed out
that what is at stake is the interpretation to be
52
CIVIL APPEAL NO. 11826 OF 2018 etc.
placed on a long term power procurement contract.
It is not as if in such a contract, the matters are
fixed with reference to the point of time when the
contract is entered into. It is not cast in stone,
in other words. It is open to change. More
appropriately, it is open to regulation. We are
invited to consider that the Act represents a
paradigm shift from the previous regime under which
the price of power was fixed essentially at the
whims and caprice of the State Electricity Boards.
There was a stagnation in the production and supply
of power. It is realising the need for increasing
private participation in the generation of power
that the Act was enacted in the year 2003. Being
the subject matter of regulations means that tariff
was open to be revisited from time to time. It is
precisely this regime which is reflected by Section
79 of the Act. It is further pointed out that the
complaint of the appellants regarding the Tribunal
in regard to the water intake system despite
agreeing with the Commission that there was no
change in law rendering the findings it did and
53
CIVIL APPEAL NO. 11826 OF 2018 etc.
therefore, being unsustainable, the Court may
consider that in fact there was a change in law.
This argument is sought to be buttressed with
reference to the provisions of clause (iii) of
Article 13.1.1. It is contended, in other words,
that a perusal of the various clauses of the PPA
would show that the procurers (the appellants) were
obliged under the contract to provide initial
consent. One of the initial consents related to the
water linkage for the project. He would submit that
in view of the provisions of Schedule II to the PPA
the initial consent also consisted of carrying out
the task of making available land for the power
plant and for the laying of the pipeline. Since as
it turned out and as supported by the second report
of the WAPCOS, there was clearly insufficient
availability of water at the site supported by the
first report, the first respondent was compelled to
take water from a distant point of the reservoir in
question. This led to the colossal increase in the
expenditure towards laying of the pipeline inter
alia . This constituted, therefore, a change in law.
54
CIVIL APPEAL NO. 11826 OF 2018 etc.
(28)
As far as the contention based on the
disclaimer clauses which are relied upon by the
appellant is concerned, it is pointed out that the
width of the disclaimer clause could not be
stretched to the point that is canvassed by the
appellants. We are dealing with a case where a
public sector unit viz., WAPCOS has given its
report. Not unnaturally, the first respondent
relied upon the same. It is factored in its price
and once it is found that the report was entirely
fallacious, no shelter can be sought by the
appellants under the disclaimer clauses. Our
attention was drawn to various judgments. They
include Energy Watchdog v. Central Electricity
Regulatory Commission and Others (2017) 14 SCC 80,
Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. v.
Adani Power Limited & Ors. (2019) 5 SCC 325, Gujarat
Urja Vikas Nigam Ltd. v. Essar Power (2008) 4 SCC
755, Skandia Insurance Co. Ltd. v. Kokilaben
Chandravan & Ors. (1987) 2 SCC 654, DLF Universal
Limited v. Director, Town and Country Planning
Department, Haryana (2010) 14 SCC 1 and Sumitomo
55
CIVIL APPEAL NO. 11826 OF 2018 etc.
Heavy Industries v. Oil and Natural Gas Commission
of India (2010) 11 SCC 296, Nabha Power Limited v.
PSPCL (2018) 11 SCC 508.
(29) The respondents have also relied upon the
judgments of this Court which are detailed
hereinafter essentially for the proposition that
there is power under Order XLI Rule 22 and Rule 33:
Prahlad & Ors. v. State of Maharashtra & Anr. (2010)
10 SCC 458, State of Punjab & Ors. v. Bakshish Singh
(1998) 8 SCC 222, Mahant Dhangir & Anr. v. Madan
Mohan & Ors. (1987) (Supp) SCC 528.
(30) It is contended by Mr. Sajjan Povayya, learned
senior counsel that there is indeed power, at any
rate, under the provisions of Section 79(1)(b) of
the Act to revisit the fixation of tariff de hors
even the specific relief which is contemplated under
the contract. In this regard, emphasis is laid on
the fact that clauses 4.7 and 5.1.17 of the
guidelines came to be amended and it is the amended
guidelines which apply to the facts of the case.
That it is the amended guidelines which were applied
can be perceived from the fact that the amended
56
CIVIL APPEAL NO. 11826 OF 2018 etc.
guidelines are seen reflected in the PPA. The
amended provisions are found in 17.3.1 and 13.1.1
(31) Amended Guideline 4.7 is reflected in 13.1.1
whereas amended guideline 5.17 is reflected in
Article 17.3.1.
(32)
With regard to 17.3.1, it is pointed out that a
reading of the same, in particular, the opening limb
of the provision would show that there is clearly
general power for the purpose of changing
determining or increasing the tariff. It is sought
to be contrasted with specific instances which would
notify the jurisdiction of the Commission which
included Article 13.1 which deals with change in
law. In other words, the contention is that de hors
a change in law, it becomes the duty of the
Commission and the Tribunal and of this Court to
factor in the need to arm the Tribunal and the
Commission with ample power in the interest of
justice, to deal with situations which call out for
a fair and equitable treatment to be meted out to
the private player as well in a long term contract.
57
CIVIL APPEAL NO. 11826 OF 2018 etc.
(33)
Mr. Amit Kapoor, learned counsel, who
supplemented the submissions of Mr.Sajjan Poovayya,
learned senior counsel, would draw our attention to
Section 61 of the Act. He would submit that Section
61 read with Sections 63 to 79(b) provided a
statutory framework which enabled the Commission to
devise an equitable tariff even in a PPA governed
scenario having regard to the very nature of the
services involved and the changed system evolved
under the Act.
(34) Mr. Amit Kapoor, learned counsel, laid stress
on the principle of contra proferentem . He would
point out along with Mr. Sajjan Poovyya, learned
senior counsel, that the Court must not be oblivious
of the fact that this case represents a case 2
scenario under the RFP. This means that unlike a
situation where the contractor is free to choose the
site and the other facilities, in a case 2 situation
which is the situation prevailing in this case,
everything is dictated to by the employer viz., SPV.
Expatiating the said point, it is pointed out that
the bidders did not have a control over the water
58
CIVIL APPEAL NO. 11826 OF 2018 etc.
source from which water had to be taken. In other
words, the water could not have been sourced from
any other water body. This aspect is relevant for
the purpose of considering the free play with the
Commission in the matter of fixing tariff based on a
situation which was created as are exemplified by
two grounds which have been made out and which are
the subject matter of the appeals. Another point
which is projected is that in regard to geological
matters, the bidders were warned that they would
have to on their own make an assessment. But such a
caveat was not entered with regard to pertinently
the hydrological conditions. Since water intake
system related to hydrology, it is not open to the
appellants to ward off a just fixation of tariff
based on the discovery of the fact that the first
WAPCOS report was highly flawed. We are reminded
that it was of the greatest importance for the first
respondent that it ran the power plant on a yearly
basis. The second report of the WAPCOS would
clearly indicate that if the appellant had to take
water in terms of the first WAPCOS report, during
59
CIVIL APPEAL NO. 11826 OF 2018 etc.
the lean months, the first respondent would not get
sufficient water supply to operate the plant. If
such an eventuality had taken place, the result
would be that the procurers would end up paying the
charges towards capacity charge even though, it
would not get power. The appellants would be
compelled to buy power from outside and finally the
end consumer would have to bear the brunt of the
loss. It is to avoid all this that the first
respondent has acted in a manner which was not only
in tune with its best interest but also ensuring
that the procurers and finally the consumers were
best protected. It is further pointed out by the
learned counsel that the Court must bear in mind
that the contract in question permits the passing of
the benefit not only to the contractor but also to
the employer viz., the appellants. In other words,
if it was a case where the first respondent were to
be found to be making an unjust enrichment under the
regulatory mechanism, the appellants could have
moved the Commission for bringing down the rates.
Therefore, the regulatory mechanism is meant to work
60
CIVIL APPEAL NO. 11826 OF 2018 etc.
both ways, in both directions and the Court must
bear in mind the unique nature of a regulated
contract.
(35) Shri Amit Kapoor also referred to the theory of
incomplete contracts. This is explained as meaning
that being a long term contact, the parties may not
expect and factor in all possible developments which
may take place. This also necessitates the
Commission being endowed with sufficient power to
reach the contractor as also the employer a just
tariff bearing in mind the regime under Section 61
of the Act.
(36)
Upon being queried as to what would be the
position at law outside of the PPA and of the
jurisdiction of the Commission and if the matter
were to be considered with reference to the law of
contract, Shri Amit Kapoor drew our attention to
Sections 18 and 19 of the Indian Contract Act, 1872.
He would point out that even an innocent
representation within the meaning of Section 18 can
result in the contact becoming voidable under
Section 19. Section 19 contemplates that the party
61
CIVIL APPEAL NO. 11826 OF 2018 etc.
whose consent is obtained by misrepresentation
within the meaning of Section 18 can insist upon the
other side to perform the contact. But the wronged
party retained the right to insist that it shall be
put in the same position it would have occupied if
there was no misrepresentation. Therefore, it is
pointed out that there is foundation even in the law
of contract for contending that the Commission armed
with its powers under Section 79(b) could compensate
the contractor in the situation we are concerned
with.
(37) The judgment of this Court reported in Uttar
Pradesh Power Corporation Limited v. National
Thermal Power Corporation Limited and Others (2009)
6 SCC 235 rendered by a Bench of three learned
judges with Justice S. B. Sinha speaking for the
Court had occasion to consider the impact of
regulations made purporting to act under the
Electricity Regulatory Commission Act, 1998. In the
said judgment, it has been inter alia held that
there is power under regulation 92, in particular,
to revise the tariff (see para 35 read with 38 and
62
CIVIL APPEAL NO. 11826 OF 2018 etc.
40)
(38) Noticing this aspect, when we sought assistance
from the learned counsel. We heard the following
submissions. Mr. M. G. Ramachandran, learned senior
counsel, would point out that the observations
relating to the power under Section 92 must be
understood as confined to the situation obtaining
under Section 61 read with Section 62 of the Act.
The said power may not be available when the tariff
is fixed under Section 63 of the Act. When we
queried as to whether the provisions of Section 61
are totally unconnected with Section 63, Mr. M. G.
Ramachandran, learned senior counsel, would submit
that Section 61 may not be entirely inapplicable. He
would submit that particular provisions of Section
61 may, in fact, apply. They include Section 61(b).
He would submit that even the guidelines issued
under Section 63 have their echo in Section 61 and,
therefore, it cannot be said that Section 61 and 63
are strange bedfellows.
(39) He would, however, contend that in no
circumstances can the power under regulation 92 of
63
CIVIL APPEAL NO. 11826 OF 2018 etc.
1999 regulations apply when parties have after
competitive bidding and approval of the tariff under
Section 63 become bound by a long term contract
under the PPA. In a case where there is a
determination of tariff within the meaning of
Section 62, on the other hand, Regulations of 1999
may apply. He would further point out that the
power under regulation 92 which provides for
reviewing of tariff and which has been understood as
power of revision of tariff as a whole must be
subject to the rider that the revision of tariff can
be done only strictly in accordance with the tariff
regulations brought in the year 2001 and as
subsequently, amended from time to time. In fact,
he would draw our attention to the Regulations of
2014 which expressly excludes tariff determination
done under Section 63 of the Act from the ambit of
the said regulation. In this regard, Shri Sajjan
Povayya, learned senior counsel, on the other hand,
drew our attention to the judgment of this Court
Gujarat Urja Vikas Nigam Limited v. Tarini
Infrastructure Limited and Others (2016) 8 SCC 743
64
CIVIL APPEAL NO. 11826 OF 2018 etc.
2022 SCC Online SC 1615 2023 SCC Online SC 233. He
would on the strength of these judgments point out
that there is regulatory power available even in a
case covered by Section 63 of the Act.
ANALYSIS
(40)
We, in these cases, are concerned only with two
issues. As we have noticed, the first respondent
filed a petition before the Commission invoking its
power inter alia under Section 79(b). The matter
relates expressly to the construction period. It is
at this point apposite to notice the relevant
provisions under the PPA.
(41) Article 13 deals with change in law. Article
13.1.1. defines what a change in law is. It reads
as follows:
“ARTICLE 13: CHANGE IN LAW
13.1 Definitions
In this Article 13, the following terms
shall have the following meanings:
13.1.1 “Change in Law” means the
occurrence of any of the following events after
the date, which is seven(7) days prior to the
65
CIVIL APPEAL NO. 11826 OF 2018 etc.
Bid Deadline:
(i) the enactment, bringing into effect,
adoption, promulgation, amendment,
modification or repeal, of any Law or (ii)
a change in the interpretation of any Law by
a Competent Court of Law, tribunal or Indian
Governmental Instrumentality provided such
Court of Law, tribunal or Indian
Governmental Instrumentality is final
authority under law of such
interpretation or (iii) change in any
consents, approvals or licenses available or
obtained for the Project, otherwise than
for default of the Seller, which results
in any change in any cost of or revenue
from the business of selling electricity by
the Seller to the Procurers under the terms
of this Agreement, or (iv) any change in the
(a) Declared Price of Land for the Project
or (b) the cost of implementation of the
resettlement and rehabilitation package of
the land for the Project mentioned in RFP
or (c) the cost of implementing
Environmental Management Plan for the Power
Station mentioned in the RFP or (d) the
cost of implementing compensatory
afforestation for the Coal Mine, indicated
under the RFP and the PPA;
but shall not include (i) any change in any
withholding tax on income or dividends
distributed to the shareholders of the
Seller, or (ii) change in respect of UI
Charges or frequency intervals by an
Appropriate Commission.
Provided that if Government of India
does not extend the income tax holiday for
power generation projects under Section 80
IA of the Income Tax Act, upto the
Scheduled Commercial Operation Date of the
Power Station, such non-extension shall be
deemed to be a Change in Law.”
66
CIVIL APPEAL NO. 11826 OF 2018 etc.
(42)
Article 13.1.2 declares that the Supreme Court
or High Court or a Tribunal or in similar judicial
or quasi judicial body in India that has
jurisdiction to adjudicate upon issues relating to
the project will be treated as competent Court.
(43) Article 13.2 provides for the actual
application and the principles for computing the
impact of change in law. It reads as follows:
“13.2 Application and Principles for computing
impact of Change in Law.
While determining the consequence of Change
in Law under this Article 13, the Parties shall
have due regard to the principle that the
purpose of compensating the Party affected by
such Change in Law, is to restore through
Monthly Tariff Payments, to the extent
contemplated in this Article 13, the affected
Party to the same economic position as if such
Change in Law has not occurred.
a) Construction Period
As a result of any Change in Law, the
impact of increase/decrease of Capital
Cost of the Project in the Tariff shall
be governed by the formula given below:
For every cumulative increase/decrease of
each Rupees Fifty crores (Rs.50 crores)
in the Capital Cost over the term of this
Agreement, the increase/decrease in Non
67
CIVIL APPEAL NO. 11826 OF 2018 etc.
Escalable Capacity Charges shall be an
amount equal to zero point two six seven
(0.267%) of the Non Escalable Capacity
Charges.
Provided that the Seller provides to the
Procurers documentary proof of such
increase/decrease in Capital cost for
establishing the impact of such Change in
Law. In case of Dispute, Article 17
shall apply.
It is clarified that the above mentioned
compensation shall be payable to either
Party, only with effect from the date
on which the total increase/decrease
exceeds amount of Rs. Fifty (50)crores.
b) Operation Period
As a result of Change in Law, the
compensation for any increase/decrease in
revenues or cost to the Seller shall be
determined and effect from such date, as
decided by the Central Electricity
Regulatory Commission whose decision
shall be final and binding on both the
Parties, subject to rights of appeal
provided under applicable Law.
Provided that the above mentioned
compensation shall be payable only if and
for increase/decrease in revenues or cost
to the seller is in excess of an amount
equivalent to 1% of Letter of Credit in
aggregate for a Contact Year.
(44) Article 13.4.2 provides for the manner in which
68
CIVIL APPEAL NO. 11826 OF 2018 etc.
the payment for changes in law is to be effected.
It reads as follows:
“13.4.2 The payment for Changes in Law shall
be through Supplementary Bill as mentioned in
Article 11.8. However, in case of any change
in Tariff by reason of Change in Law, as
determined in accordance with this Agreement,
the Monthly Invoice to be raised by the
Seller after such change in Tariff shall
appropriately reflect the changed Tariff.”
(45) We may notice the other foundational articles
relied upon by the first respondent. Article 17
relates to Governing law and Dispute resolution.
Article 17.2.1 reads as follows:
“17.2.1 Either Party is entitled to raise any
claim, dispute or difference of whatever
nature arising under, out of or in connection
with this Agreement including its existence or
validity or termination (collectively
“Dispute”) by giving a written notice to the
other Party, which shall contain:
(i) a description of the Dispute;
(ii) the grounds for such Dispute; and
(iii) all written material in support of its
claim.”
(46)
The further articles which we need not capture
contemplate that the claim may be met even with a
counter claim and an attempt should be made to
69
CIVIL APPEAL NO. 11826 OF 2018 etc.
settle the dispute amicably (see Article 17.2.3).
Failure to arrive at a settlement opens the doors of
Article 17.3. It is justifiable as the caption is
‘Dispute Resolution’.
(47) Article 17.3.1 is the crucial article. It
reads: -
“Where any Dispute arises from a claim made
by any Party for any change in or
determination of the Tariff or any matter
related to Tariff or claims made by any
Party which partly or wholly relate to any
change in the Tariff or determination of
any of such claims could result in change
in the Tariff or (ii) relates to any matter
agreed to be referred to the Appropriate
Commission under Articles 4.7.1, 13.2, 18.1
or clause 10.1.3 of Schedule l 7 hereof,
such Dispute shall be submitted to
adjudication by the Appropriate Commission.
Appeal against the decisions of the
Appropriate Commission shall be made only
as per the provisions of the Electricity
Act, 2003, as amended from time to time.
The obligations of the Procurers under this
Agreement towards the Seller shall not be
affected in any manner by reason of inter-
se disputes amongst the Procurers.”
(48) It is thereafter that as we have noticed,
Article 17.3.2 appears which we are not setting out,
deals with the settlement of disputes which are
outside the ambit of Article 17.3.1.
70
CIVIL APPEAL NO. 11826 OF 2018 etc.
(49)
We may at the very beginning notice the change
that is brought about in the guideline. True it is
that as we have noticed that the earlier guidelines
which were formulated on 19.01.2005 contemplated a
different regime both as regards change in law and
also dispute resolution. The question would however
be the extent to which the first respondent can
derive benefit out of the same. As far as Article
13.1.1 is concerned, clauses 1 and 2 are clearly an
inapplicable in regard to the claim based on the
change brought about in the water intake system.
(50) It is clause (iii) which is referred to and
relied upon by Mr. Sajjan Povayya. It reads as
follows:
“(iii) change in any consents, approvals or
licenses available or obtained for the
Project, otherwise than for default of the
Seller, which results in any change in any
cost of or revenue from the business of
selling electricity by the Seller to the
Procurers under the terms of this
Agreement.”
(51) It is the case of the first respondent that
since in the schedule the initial consent which was,
71
CIVIL APPEAL NO. 11826 OF 2018 etc.
in fact, a deemed initial consent consisting of
performing of the task of making available land for
the power plant and for the pipeline and there is a
change in the same in view of what transpired
pursuant to the second report of the WAPCOS, the
first respondent was entitled to relief. In regard
to the said argument, we must notice the following
obstacles which are indisputable. We notice that
the pleadings which we have set out, position before
the Commission and what is more, even before the
Tribunal, do not reveal that the first respondent
has taken such a stand. No express reference is
found to Schedule 2 containing the alleged deemed
initial consent being overridden by the subsequent
consent as a foundation for the claim based on
change in law.
(52) The second obstacle which we must notice is
that we are dealing with an appeal under Section 125
which is based on the existence of a substantial
question of law. In this regard, indisputably both
the Commission and the Tribunal have rendered the
concurrent finding that the first respondent has
72
CIVIL APPEAL NO. 11826 OF 2018 etc.
failed to establish any change in law. Thus, the
first respondent is up against concurrent findings
which we cannot lightly disregard.
(53) Thirdly, we may notice that the first
respondent has not independently challenged the
finding rendered by the Tribunal holding that there
is no change in law. We have noticed that the
Tribunal has proceeded to premise the grant of
relief to the first respondent and remanding the
matter on a totally different basis. Here, we may
notice no doubt that treating it as a part of the
power of appellate Court to correct errors in the
findings in the impugned order passed may extend in
appropriate cases by the principle of Order XLI Rule
22. However, objection is seen raised by the
Appellants to permitting of the principle in Order
XLI Rule 22 CPC to govern in the situation such as
in an appeal under Section 125 of the Act. We
proceed on the basis that there is power to permit
the respondent to impugn a finding given by the
Tribunal against the respondent even without filing
any appeal or cross petition.
73
CIVIL APPEAL NO. 11826 OF 2018 etc.
(54)
Examining the claim on merits, we find that the
first respondent would fail. It is categorically
stated in para 68 of the petition that the increase
in the cost is directly attributable to the error in
the WAPCOS report provided to the bidders at the
pre-bid stage. It is contended that the first
respondent is required to be compensated for the
same.
(55) In para 108, it is stated that as per the RFP,
the procurers had to provide the water intake study
report. As per the said report, the cost of water
intake system was approximately Rs.92 crores. It is
further stated in para 110 that there was
considerable increase in the cost of water due to
the water intake system. It is stated that it is on
account of errors in the report. It is, however, no
doubt, in para 111 stated that since water pipeline
is part of the power station land and the water
intake pipeline is an integral part of the power
station, the indicative cost of the water intake
system will be covered by change in law. In the
appeal also, we have noticed the stand elaborately.
74
CIVIL APPEAL NO. 11826 OF 2018 etc.
(56)
Initial consent, has been defined in the PPA as
meaning the consents listed in Schedule 2. Article
5.5 of the PPA reads as follows:
“5.5 Consents
The Seller shall be responsible for obtaining
all Consents (other than those required for
the Interconnection and Transmission
Facilities and the Initial Consents) required
for developing, financing, constructing,
operating and maintenance of the Project and
maintaining/renewing all such Consents in
order to carry out its obligations under this
Agreement in general and this Article 5 in
particular and shall supply to the Lead
Procurer promptly with copies of each
application that it submits, and copy/ies of
each consent/approval/license which it
obtains. For the avoidance of doubt, it is
clarified that the Seller shall also be
responsible for maintaining/renewing the
Initial Consents and for fulfilling all
conditions specified therein.”
(57) It is true that the procurers were to secure
certain initial consents whereas the vast majority
of the consents were to be procured by the seller.
Whatever was to be procured by the procurers
apparently has been described as initial consents.
It is also not in dispute that though the word
consent is used in Article 13.1.1, the initial
consent would also qualify as consent. The
75
CIVIL APPEAL NO. 11826 OF 2018 etc.
contention of the appellants is that as far as the
initial consent contemplated which was to be
performed by the procurers it was to provide the
water linkage. The water linkage consisted of
making available the source of water which consisted
of the Govind Ballabh Pant Sagar(Rihand Reservoir).
There has been no change in the said consent. It is
not a case of the first respondent, in other words,
that the first respondent has been forced to take
water from any other water source. In this regard
by communication dated 23.10.2006, we find the
following:
“6. Reference Clause: RFP 1.4(v) –
regarding tying up water linkage for the
Project requirement alongwith approval of
Central Water Commissioner
th
(i) This has already been provided on 12
October, 2006.
(ii) The water intake study report and
Project Report including geo-technical
study, topographical survey, area drainage
study, socio-economic study and EIA
rd
(rapid), were provided on 3 August, 2006.”
(58) While on this document, we may also notice the
following in regard to the declared price of land
contemplated in the RFP under clause 1.4 (ii):
76
CIVIL APPEAL NO. 11826 OF 2018 etc.
“2. Reference Clause: RFP 1.4(ii) – regarding
Declared Price of Land for Power Station
Indicative Declared Price of Land for Power
Station is as follows:
(i) Power Plant Area – Rs.110 Crores
(ii) MGR Land – Rs.80 Crores.
(iii) Water Pipeline Corridor– Rs.0.63 Crores
(iv) Ash Pipeline Corridor – Rs.0.047 Crores”
(59) There is no dispute regarding this aspect. In
this regard, we notice that under Schedule 1A to the
PPA it has been clearly indicated that water source
in the project is Govind Ballabh Pant Sagar(Rihand
Reservoir).
(60) It is, thereafter, we must notice that under
the caption initial consent in Schedule 2, on behalf
of the procurers, the SPV was expected to issue the
notification under Section 6 of the Land Acquisition
Act, obtain necessarily environmental and forest
clearance for the power stations, allocate captive
coal mines and finally, give the water linkage for
the reasonable project requirements. It is this
water linkage for the reasonable project
requirements which was contemplated to be fulfilled
from the water source Govind Ballabh Pant
77
CIVIL APPEAL NO. 11826 OF 2018 etc.
Sagar(Rihand Reservoir). The communication dated
23.10.2006 would indicate that the Central Water
Commission had given its approval for sourcing the
water need from the water body in question. In the
said sense, the procurers had fulfilled their
obligation as contemplated in RFP.
(61)
The RFP which preceded the PPA provided for
certain conditions which we have already indicated.
Clause 1.4 inter alia contained undertaking for
providing the water linkage for the project with the
requisite approval of the Central Water Commission
at least 30 days prior to Bid deadline. In the PPA,
it is indicated that the procurers have completed
the initial studies as contained in the project
report and obtained initial consent required for the
project which are set out in Part I of Schedule 2
and have been made available to the seller on the
date of the PPA except two matters: (1) Forest
clearance and the declaration under Section 6 of the
Land Acquisition Act. It is in Part I Schedule 2 of
the PPA stated that the notification under Section 6
of the Land Acquisition Act was an act to be
78
CIVIL APPEAL NO. 11826 OF 2018 etc.
performed by the procurers. It is this act which was
not done initially at the stage of the PPA. Also
forest clearance is mentioned in the Part I of
Schedule 2. Even the said clearance was also
apparently not obtained as is indicated at the
beginning of the PPA. Thereafter, Part II of
Schedule 2 contains the clause which is the
fountainhead of the argument based on initial
consent.
(62) It contemplated performing of the task
mentioned in Article 3.1.2A also shall be part of
the initial consent on their completion within the
time provided. Article 3.1.2A contemplated
performance of the task with which we are concerned
viz., making available the land for the power plant
and for the water intake pipeline. This task was to
be performed within a period of eight months from
the date of the letter of intent being issued or six
months from the PPA whichever is later. It is true
that the task which was to be performed by the
procurers in terms of Article 3.1.2A was performed
belatedly by the procurers. In other words, the
79
CIVIL APPEAL NO. 11826 OF 2018 etc.
time limit was overshot by nearly 18 months. But
this delay is not the basis for the claim based on
change in law.
(63) The question would then arise as to whether the
delay in the performance of the task which has been
characterised on its performance within the time as
a deemed initial consent would lead to a change in
law within the meaning of Article 13.1.1. We find
that Article 3.3.3 of the PPA reads as follows:
“3.3.3 In case of inability of the Seller to
fulfil the conditions specified in Article
3.1.2 due to any Force Majeure event, the
time period for fulfilment of the Condition
Subsequent as mentioned in Article 3.1.2 and
Article 3.1.2A, shall be extended for the
period of such Force Majeure event, subject
to a maximum extension period of ten (10)
Months, continuous or non-continuous in
aggregate. Thereafter, this Agreement may be
terminated by either the Procurers (jointly)
or the Seller by giving a notice of at least
seven (7) days, in writing to the other
Party.
Similarly, in case of inability of the
Procurers to fulfil the conditions specified
in Article 3.1.2A due to any Force Majeure
event, the time period for fulfillment of
the Condition subsequent as mentioned in
Article 3.1.2 and Article 3.1.2A, shall be
extended period of ten (10) Months,
continuous or non-continuous in aggregate.
Thereafter, this Agreement may be terminated
by either the Procurers (jointly) or the
80
CIVIL APPEAL NO. 11826 OF 2018 etc.
Seller by giving a notice of at least seven
(7) days, in writing to the other Party.”
(64) We must next notice Article 3.3.3A which
follows:
“3.3.3A In case of inability of the Procurers
to perform the activities specified in Article
3.1.2A within the time period specified
therein, otherwise than for the reasons
directly attributable to the Seller or Force
Majeure event, the Condition Subsequent as
mentioned in Article 3.1.2 would be extended on
a ‘day for day’ basis, equal to the additional
time which may be required by the Procurers to
complete the activities mentioned in Article
3.1.2A, subject to a maximum additional time of
six (6) Months. Thereafter, this Agreement may
be terminated by the Seller at its option, by
giving a notice of at least seven (7) days, in
writing to the Procurers. If the Seller elects
to terminate this Agreement, the Procurers
shall, within a period of thirty days, purchase
the entire shareholding in the Seller for the
following amount. Provided such purchase of
shares shall be undertaken by the Procurers in
the ratio of their then existing Allocated
Contracted Capacity:
a) total amount of purchase price paid by
the Successful Bidder to the shareholders
of the Seller acquire the equity shares
of the Seller as per the RFP; plus
b) total amount of the Declared Price of
Land and Geological Report (GR) to the
extent already paid by the Seller after
the acquisition of its 100% shareholding
by the Selected Bidder; plus
c) an additional sum equal to ten percent
(10%) of the sum total of the amounts
81
CIVIL APPEAL NO. 11826 OF 2018 etc.
mentioned in sub-clauses (a) and (b).
In addition, the Performance Guarantee of
the Seller shall also be released
forthwith.”
(65) A perusal of the aforesaid articles would
reveal that the parties have provided for the
consequences of failure on the part of the procurers
to make available land as contemplated in Article
3.1.2A. The long and short of it is that if a
certain timelimit is crossed by the procurers in the
performance of its obligations in this regard, the
seller (the first respondent) has been given the
right to repudiate the contract. What is more, it
could insist on the procurers purchasing the entire
share capital of the company viz., the first
respondent as provided therein. It is not the case
of the first respondent that by invoking the
aforesaid articles, the first respondent purported
to repudiate the contract. On the other hand, it is
the common case that the contract continued to be
alive and it has survived subject to the claims
which have been raised thereunder. This would mean
82
CIVIL APPEAL NO. 11826 OF 2018 etc.
that as the consequences of failure to perform the
task having been provided in the contract in the
manner provided, we should not ordinarily tarry
further to ask as to whether this would provide the
premise for a change in law as contemplated under
Article 13.1.1. We necessarily pose the question
still, whether this would be change in law. Not
that we are unmindful of the fact that the two
bodies have concurrently found that there is no
change in law and the attempt is to dislodge such a
finding by a side wind in the manner of speaking by
an attack lodged by the respondent in the appeal.
This is not a case where the first respondent has
made use of the land for the purpose of laying the
pipeline through the corridor as contemplated and
found that drawing water from the water intake
system as contemplated would have resulted in water
not being available in sufficient quantity through
the length of the year. There is no such case.
(66) The case of the first respondent, on the other
hand, is that the PPA having been signed on
07.08.2007, in the second week of December of the
83
CIVIL APPEAL NO. 11826 OF 2018 etc.
very same year-2007, in order to confirm the
availability of water through water intake system as
contemplated in the first WAPCOS report, the second
report was commissioned ironically through the very
same consultant. There is no case, whatsoever, that
having made attempts to draw water in terms of the
first WAPCOS report and having found that such an
effort failed, they were compelled to seek recourse
to a second study albeit by the same body. No
reasons are forthcoming as to what inspired the
first respondent to commission the second study.
Secondly, this is not a case where the procurers
brought about any change in law in the study on
their own or they persuaded or compelled the first
respondent to change the corridor for the route for
laying of the pipeline. The first respondent did
not even involve the procurers in the second study.
There is no intimation given that the first
respondent was commissioning a new study. There is
no basis forthcoming as to what prompted the first
respondent to commission a fresh study. What is
stated is only that it wished to confirm the
84
CIVIL APPEAL NO. 11826 OF 2018 etc.
availability of water in terms of the first water
intake study. In other words, we must sum up as
follows:
(67) Even in terms of the case built around Part II
of Schedule 2 to the PPA under which the performing
of the task mentioned in Article 3.1.2A within the
time provided was to be treated as a deemed initial
consent, the consequence of failure to do that have
been expressly spelt out as we have already noticed.
At best or at worst, it could have empowered the
first respondent to rescind the contract. That
apart, we are not in a position, for the reasons
which we have indicated already, to come to the
conclusion that it would amount to change in law.
While on change in law, we may notice another aspect
of the matter.
(68) Article 13.3.1 reads as follows:
“13.3.1 If the Seller is affected by a Change
in Law in accordance with Article 13.2 and
wishes to claim a Change in Law under this
Article, it shall give notice to the
Procurers of such Change in Law as soon as
reasonably practicable after becoming aware
of the same or should reasonably have known
of the Change in Law.”
85
CIVIL APPEAL NO. 11826 OF 2018 etc.
(69)
Thus, the PPA contemplates that if the seller
is affected by change in law and wishes to claim
change in law, it has to notify the procurers of the
change in law as soon as is reasonably practicable
after becoming aware of the same. It may be true
that on the basis of the request made by the first
respondent apparently based on the second WAPCOS
report that the first respondent has taken steps for
acquiring the land needed for laying the pipeline.
It may be true that the said pipeline had to cross a
greater distance. It is not as if it was on the
basis that the procurers rendered themselves liable
in law or held themselves liable in law to make good
the escalation in cost. There is no such material
made available indicating that the procurers have
held out that they will be liable. It is not in
dispute that the first unit from the power plant was
in fact commissioned in August, 2012. In fact, when
we asked as to whether a notice was given in terms
of Article 13.3.1, Shri Amit Kapur, learned counsel,
could not point out to any such notice except the
notice which was given on 15.12.2012. In this regard
86
CIVIL APPEAL NO. 11826 OF 2018 etc.
also, we may notice the contents of the said notice:
“5.2 Additional expenditure incurred due to
change in Declared Price of Land, cost of
implementation of resettlement and
rehabilitation package of land, change in
customs duty on mining equipment, water
intake system etc.
(a) the actual expenditure incurred by SPL
towards land, implementation of resettlement
and rehabilitation package of land for the
project, water intakes system, customs duty
on mining equipment and excise duty on
cement and steel.”
(70) Therein all that is indicated is that for the
water intake the original cost was put Rs.92 crores
whereas the estimated cost has been Rs.238 crores
Contemporaneous with the change in law alleged and
in keeping with Article 13.3.1, there is no notice
brought to our notice.
(71) No doubt, Shri Amit Kapur, learned counsel for
the first respondent, did attempt to draw
inspiration from the Minutes of the Meeting which
took place on 20.03.2013 as per which the lead
procurer appears to have agreed to the change. The
case of Mr. Amit Kapur, learned counsel, that the
lead procurer can bind the other procurers is
87
CIVIL APPEAL NO. 11826 OF 2018 etc.
M. G.
contested by Shri Ramachandran, learned senior
counsel.
(72) We have noticed that a notice in terms of
Article 13.3.1 notifying the change in law as
claimed today before the Court was not given at the
relevant time.
(73) The argument that the procurers agreed to the
acquisition of the land through which the new route
had to travel also does not appeal to us as firmly
founding the claim of the first respondent in law.
The matter must be viewed from the prism of the
specific provisions defining the change in law and
the actual change in law which is as we have
explained above. In short, being awarded a contract
and having entered into the PPA and without any
basis as such in facts, the first respondent
ventured to commission a new study and acting on the
same, a new pipeline corridor came on the scene.
Necessarily the cost may go up. But the question we
are to decide is as to whether it is change in law
and we are of the view that it could not be a change
in law as contemplated in the agreement as it is not
88
CIVIL APPEAL NO. 11826 OF 2018 etc.
a change in initial consent which is the only case
which has been argued in this regard.
(74) The argument further is only that the estimated
cost was Rs.92 crores and a further sum in excess of
the same had to be spent. In this regard, we may
notice the following clause in the PPA:
“5.2 The Site
The Seller acknowledges that, before entering
into this Agreement, it has had sufficient
opportunity to investigate the Site and
accepts full responsibility for its condition
(including but not limited to its geological
condition, on the Site, the adequacy of the
road and rail links to the Site and the
availability of adequate supplies of water)
and agrees that it shall not be relieved from
any of its obligations under this Agreement
or be entitled to any extension of time or
financial compensation by reason of the
unsuitability of the Site for whatever
reason.
The State Government authorities would be
implementing the resettlement and
rehabilitation package (“R&R”) in respect of
the Site for the Project, for which the costs
is to be borne by the Seller. The Procurers
shall endeavour to ensure that the State
Government implements such R&R ensuring that
land for different construction activities
becomes available in time so as to ensure
that the Power Station and each Unit is
commissioned in a timely manner. Assistance
of the Seller may be sought, which he will
provide on best endeavour basis, in execution
of those activities of the R&R package and as
per estimated costs, if execution of such
89
CIVIL APPEAL NO. 11826 OF 2018 etc.
activities is in the interest of expeditious
implementation of the package and is
beneficial to the Project affected persons.”
(75) Moving on to the findings actually which have
been rendered by the Tribunal, the Tribunal has, in
the impugned order, found that the first report of
the WAPCOS is grossly erroneous. We are at a loss
to understand as to what was the basis for rendering
such a finding. Without any material, it is a
little inexplicable as to how the Tribunal could
have rendered such a finding which has serious
consequences as we have noticed. This is after
finding undoubtedly that there is no change in law.
Virtually, the Tribunal has brushed aside the
disclaimer clauses. Before we go to the disclaimer
clauses, we may also indicate that a perusal of the
first WAPCOS report indicates that it is a fairly
elaborate report. The second WAPCOS report apart
from it being prepared without reference to the
procurers as we have noticed does not appear to say
anything which is critical of the first WAPCOS
report. At least, there is, in fact, no express
90
CIVIL APPEAL NO. 11826 OF 2018 etc.
whisper about the first report. All that the second
WAPCOS report seems to indicate is upon being
awarded the work, WAPCOS has gone about preparing
another report. At least we are unable to find as
to how the Tribunal could on the basis of the second
report find that the first WAPCOS report was grossly
erroneous. The Tribunal has not undertaken a
comparative study of the two reports. There is no
discussion whatsoever of the two reports. Nor is
there any other material provided to render such a
finding. The only area where we find what could
perhaps be understood as a reference to the first
report is clause 4.2.2. It reads as follows:
“4.2.2. As intimated by project authority
that and acquisition of pipeline corridor on
the right side of Vallabhh Pant Sagar is in
the final stages and other information
gathered during site visit by WAPCOS/CWPRS
team by local enquiry survey area ‘A’ was
identified for detailed survey during
detailed survey it is found that sufficient
depth is not available for intake well as bed
level of the reservoir is around 252.5 and
this was also in a small patches. So, this
area is discarded.”
(76) It would appear that the word ‘project
91
CIVIL APPEAL NO. 11826 OF 2018 etc.
authority’ according to Shri M.G. Ramachandran is to
be understood as the first respondent. All that
even clause 4.2.2 indicates is that the first
respondent intimated that the acquisition for the
pipeline corridor was in its final stages and
thereafter it is indicated that during the detailed
survey, it was found sufficient depth is not
available.
(77) We do not think this can be the basis for
acting upon the second report after describing the
first report as grossly erroneous.
(78) Now we may consider the disclaimer clauses.
The disclaimers have their genesis in the
guidelines. Note 4 of the RFP indicates that the
procurers apart from their Directors, employees must
not be treated as having made any representation or
warranting whatsoever in respect of any statements
or omissions or the accuracy, completeness or
reliability of information contained therein. They
were not to incur any liability under any law inter
alia even if any loss or damage is caused to the
bidder by any act or omission on their part. Again
92
CIVIL APPEAL NO. 11826 OF 2018 etc.
clause 1.4 of the RFP clearly indicated to the
bidders that the procurers inter alia do not make
any representation or accept any responsibility or
liability in respect of any statements or omissions
made in the water intake study report and the
project report. There is a specific disclaimer also
about the accuracy, completeness or reliability of
information contained therein. This is even if any
loss or damage is caused to the selected bidder by
any act or omission on their part. Thus, in respect
of the water intake study report, the prospective
seller or the bidders were specifically told in no
uncertain terms that any statements or omissions in
water intake study report would not result in the
procurers being visited with liability even if there
was loss or damage caused to the selected bidder.
This must be borne in mind at this juncture for the
following reasons.
(79) The first respondent has a case that water
intake system goes to hydrology whereas in relation
to geology, the first respondent was duty bound to
make its own inquiries. Since the connect between
93
CIVIL APPEAL NO. 11826 OF 2018 etc.
hydrology and water intake system is real and since
in regard to conditions about hydrology, the first
respondent relied on the procurers or the report
prepared by a public sector unit, in particular,
they should stand relieved of any obligation to
conduct any further inquiry on their own, runs the
argument.
(80) We are afraid that this argument cannot hold
water as the need for making more inquiry in
relation to geology cannot relieve the bidder from
the operation of other clauses. A just result in
the matter of what a contract produces by way of a
legal relationship must be viewed holistically on a
harmonious survey of all the relevant clauses. In
any other approach, the result would have the effect
of rendering specific clauses dealing with the topic
in question dead letter. In view of clause 1.4 of
the RFP, in other words, the bidder was duty bound
if it felt advised to check the correctness of the
report made by the WAPCOS. It could have undertaken
its own study. What it did four months after it was
granted the contract and entered into the PPA, it
94
CIVIL APPEAL NO. 11826 OF 2018 etc.
could have done before it decided to make the bid
and enter into the PPA. At least we are not shown
anything which stood in the way of the bidder
conducting its own study and being convinced by the
correctness of the report. We say this for the
reason that what is involved is an international
competitive bid. The bidding process is the
foundation for the determination of the price in
terms of section 63 of the Act. The Commission
approves the rates on being convinced that the rates
are fair and competitive and arrived at on the basis
of a fair bidding process. The provisions of the
RFP must, therefore, be viewed from the perspective
of it placing on alert the bidders about the
imponderables which are inevitably involved in
pricing process. This means that having regard to
clause 1.4 of the RFP, no bidder could possibly come
forward with the claim that the contents of the
WAPCOS report must be treated as sacrosanct and
infallible and that it should not be taken without a
generous pinch of salt as it stands. At least this
was the message which is writ large in the said
95
CIVIL APPEAL NO. 11826 OF 2018 etc.
clause. He who acted disregarding the caveat about
the report acted at his own peril.
(81) Again, we do notice clause 2.7.2 of the RFP
which we have indicated already. It contemplates
the duty on the part of the bidder to make
independent inquiry and to satisfy itself with
regard to the required information, inputs,
conditions, circumstances, which may affect the bid.
This is apart from the site as referred to in the
PPA in clause 5.2 which we have already referred to.
(82) With the wealth of disclaimer clauses which we
have noticed, we are unable to subscribe to the
reasoning adopted by the Tribunal. We are of the
view that the Tribunal was wrong in brushing aside
the specific and unambiguous disclaimers under which
the procurers stood exonerated from liability.
(83) One argument which we must notice at this stage
is the effect of Article 13.2. We have already
adverted to Article 13.2. Article 13.2, no doubt,
indicates that while determining the consequence of
change in law, the parties shall have due regard to
96
CIVIL APPEAL NO. 11826 OF 2018 etc.
the principle that the purpose of compensating the
party affected by any change in law is to restore
through monthly tariff payments the affected party
to the same economic position as if such change has
not occurred. We have tested the hypothesis by
deliberately omitting a crucial part in Article 13.2
which are the words ‘to the extent contemplated in
this Article 13’. When we read the words ‘to the
extent contemplated in this Article 13’ as part of
the Article 13.2, it necessarily brings in clause
(a) and (b) of Article 13.2. In other words, what
the parties have contemplated is that consequence of
change in law would result in it being addressed
through the mechanism of monthly tariff payments
through supplementary bills(see Article 13.4.2).
But it is to the extent as contemplated in Article
13. The question would arise as to whether the
parties contemplated that it gave authority to the
competent body viz., the Commission to discard the
formula which is provided in Article 13.2(a) and
(b). We are of the view that what the parties
contemplated under Article 13.2 was that change in
97
CIVIL APPEAL NO. 11826 OF 2018 etc.
law must be viewed through the specific provisions
of clauses (a) and (b). In other words, a change in
law may occur during the period of construction.
Then it is to be treated as falling under Article
13.2(a). A change in law may occur during the
period of its operation. It would then appear to be
dealt with under clause (b). If a change in law
takes place during the period of construction then
its impact is to be measured with reference to the
capital cost of the project. The word ‘capital
cost’ understandably has been defined in PPA. A
formula has been engrafted. The formula
contemplates that for every increase/decrease of
each Rs.50 crores in the capital cost as a result of
the change in law, the increase/decrease in the non-
escalable capacity charges is to be 0.267 per cent
of the non-escalable capacity charges. No doubt,
this is if the seller provides to the procurers
documentary proof of such increase/decrease in
establishing the impact of such change.
(84)
In other words, the effect of change in law
during the construction period is captured by
98
CIVIL APPEAL NO. 11826 OF 2018 etc.
13.2(a). We must understand that this is a
meticulously thought through contract which emerged
after a long rigorous process. Parties were clear
about how the change in law had to be compensated
and methodology has been set out clearly.
Therefore, any appeal made to the general part in
Article 13.2 which speaks about the affected party
being restored to the same economic condition as if
such change in law had not occurred cannot result in
departing from the specific formula which has been
set in place. This meaning is inevitable from the
words “to the extent contemplated in this Article
13, which precedes the general words. In this
regard, we may refer to the judgment of this Court
1
in Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. .
In the said judgment, it has been relied upon
understandably by the first respondent also and
which also arose under the same clause (Article
13.2), this Court has held inter alia as follows:
“10. Article 13.2 is an in-built
restitutionary principle which compensates
1 Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. v. Adani
Power Limited & Ors. (2019) 5 SCC 325
99
CIVIL APPEAL NO. 11826 OF 2018 etc.
the party affected by such change in law and
which must restore, through monthly tariff
payments, the affected party to the same
economic position as if such change in law
has not occurred. This would mean that by
this clause a fiction is created, and the
party has to be put in the same economic
position as if such change in law has not
occurred i.e. the party must be given the
benefit of restitution as understood in civil
law. Article 13.2, however, goes on to divide
such restitution into two separate periods.
The first period is the “construction period”
in which increase/decrease of capital cost of
the project in the tariff is to be governed
by a certain formula. However, the seller has
to provide to the procurer documentary proof
of such increase/decrease in capital cost for
establishing the impact of such change in law
and in the case of dispute as to the same, a
dispute resolution mechanism as per Article
17 of the PPA is to be resorted to. It is
also made clear that compensation is only
payable to either party only with effect from
the date on which the total increase/decrease
exceeds the amount stated therein.
13. A reading of Article 13 as a whole,
therefore, leads to the position that subject
to restitutionary principles contained in
Article 13.2, the adjustment in monthly
tariff payment, in the facts of the present
case, has to be from the date of the
withdrawal of exemption which was done by
administrative orders dated 6-4-2015 and 16-
2-2016. The present case, therefore, falls
within Article 13.4.1( i ). This being the
case, it is clear that the adjustment in
monthly tariff payment has to be effected
from the date on which the exemptions given
were withdrawn. This being the case, monthly
invoices to be raised by the seller after
such change in tariff are to appropriately
100
CIVIL APPEAL NO. 11826 OF 2018 etc.
reflect the changed tariff. On the facts of
the present case, it is clear that the
respondents were entitled to adjustment in
their monthly tariff payment from the date on
which the exemption notifications became
effective. This being the case, the
restitutionary principle contained in Article
13.2 would kick in for the simple reason that
it is only after the order dated 4-5-2017
[ Adani Power Ltd. v. Uttar Haryana Bijli
Vitran Nigam Ltd. , 2017 SCC OnLine CERC 66]
that CERC held that the respondents were
entitled to claim added costs on account of
change in law w.e.f. 1-4-2015. This being the
case, it would be fallacious to say that the
respondents would be claiming this
restitutionary amount on some general
principle of equity outside the PPA. Since it
is clear that this amount of carrying cost is
only relatable to Article 13 of the PPA, we
find no reason to interfere with the judgment
of the Appellate Tribunal.
19. Lastly, the judgment of this Court in
Energy Watchdog v. CERC [ Energy Watchdog v.
CERC , (2017) 14 SCC 80 : (2018) 1 SCC (Civ)
133] was also relied upon. In this judgment,
three issues were set out and decided, one of
which was concerned with a change in law
provision of a PPA. In holding that change in
Indonesian law would not qualify as a change
in law under the guidelines read with the
PPAs, this Court referred to Clause 13.2 as
follows : (SCC p. 131, para 57)
“ 57 . … This being so, it is clear that so far
as the procurement of Indian coal is
concerned, to the extent that the supply from
Coal India and other Indian sources is cut
down, the PPA read with these documents
provides in Clause 13.2 that while
determining the consequences of change in
law, parties shall have due regard to the
101
CIVIL APPEAL NO. 11826 OF 2018 etc.
principle that the purpose of compensating
the party affected by such change in law is
to restore, through monthly tariff payments,
the affected party to the economic position
as if such change in law has not occurred.”
There can be no doubt from this judgment that
the restitutionary principle contained in
Clause 13.2 must always be kept in mind even
when compensation for increase/decrease in
cost is determined by CERC.”
(Emphasis supplied)
(85) We are of the view that the view which we have
taken does not in any way conflict with the view
which has been laid down by this Court.
2
(86) No doubt, in Energy Watchdog again a judgment
which is relied upon by both the sides, the Court
was dealing with a case under the Act and has
expressed the following view:
"19. The construction of Section 63, when
read with the other provisions of this Act,
is what comes up for decision in the present
appeals. It may be noticed that Section 63
begins with a non obstante clause, but it is
a non obstante clause covering only Section
62. Secondly, unlike Section 62 read with
Sections 61 and 64, the appropriate
Commission does not “determine” tariff but
only “adopts” tariff already determined under
Section 63. Thirdly, such “adoption” is only
2 Energy Watchdog v. Central Electricity Regulatory
Commission and Others (2017) 14 SCC 80
102
CIVIL APPEAL NO. 11826 OF 2018 etc.
if such tariff has been determined through a
transparent process of bidding, and,
fourthly, this transparent process of bidding
must be in accordance with the guidelines
issued by the Central Government. What has
been argued before us is that Section 63 is a
standalone provision and has to be construed
on its own terms, and that, therefore, in the
case of transparent bidding nothing can be
looked at except the bid itself which must
accord with guidelines issued by the Central
Government. One thing is immediately clear,
that the appropriate Commission does not act
as a mere post office under Section 63. It
must adopt the tariff which has been
determined through a transparent process of
bidding, but this can only be done in
accordance with the guidelines issued by the
Central Government. Guidelines have been
issued under this section on 19-1-2005, which
guidelines have been amended from time to
time. Clause 4, in particular, deals with
tariff and the appropriate Commission
certainly has the jurisdiction to look into
whether the tariff determined through the
process of bidding accords with Clause 4.
20. It is important to note that the
regulatory powers of the Central Commission,
so far as tariff is concerned, are
specifically mentioned in Section 79(1). This
regulatory power is a general one, and it is
very difficult to state that when the
Commission adopts tariff under Section 63, it
functions dehors its general regulatory power
under Section 79(1)( b ). For one thing, such
regulation takes place under the Central
Government's guidelines. For another, in a
situation where there are no guidelines or in
a situation which is not covered by the
guidelines, can it be said that the
Commission's power to “regulate” tariff is
completely done away with? According to us,
this is not a correct way of reading the
103
CIVIL APPEAL NO. 11826 OF 2018 etc.
aforesaid statutory provisions. The first
rule of statutory interpretation is that the
statute must be read as a whole. As a
concomitant of that rule, it is also clear
that all the discordant notes struck by the
various sections must be harmonised.
Considering the fact that the non obstante
clause advisedly restricts itself to Section
62, we see no good reason to put Section 79
out of the way altogether. The reason why
Section 62 alone has been put out of the way
is that determination of tariff can take
place in one of two ways — either under
Section 62, where the Commission itself
determines the tariff in accordance with the
provisions of the Act (after laying down the
terms and conditions for determination of
tariff mentioned in Section 61) or under
Section 63 where the Commission adopts tariff
that is already determined by a transparent
process of bidding. In either case, the
general regulatory power of the Commission
under Section 79(1)( b ) is the source of the
power to regulate, which includes the power
to determine or adopt tariff. In fact,
Sections 62 and 63 deal with “determination”
of tariff, which is part of “regulating”
tariff. Whereas “determining” tariff for
inter-State transmission of electricity is
dealt with by Section 79(1)( d ), Section
79(1)( b ) is a wider source of power to
“regulate” tariff. It is clear that in a
situation where the guidelines issued by the
Central Government under Section 63 cover the
situation, the Central Commission is bound by
those guidelines and must exercise its
regulatory functions, albeit under Section
79(1)( b ), only in accordance with those
guidelines. As has been stated above, it is
only in a situation where there are no
guidelines framed at all or where the
guidelines do not deal with a given situation
that the Commission's general regulatory
104
CIVIL APPEAL NO. 11826 OF 2018 etc.
powers under Section 79(1)( b ) can then be
used.”
(87) It is true that as far as the said case is
concerned, the case arose from claims which were
made under the PPA on the basis that there were
changes in law apart from the argument that a case
of Force Majeure was made out. It is not a case
which actually on facts involved the Court dealing
with a case arising from the fixation of tariff
under Section 63. In fact, it arose after a PPA was
approved and the rates were fixed already under
Section 63. However, if we notice the contents of
para 19 and 20, the principle which the first
respondent seeks to canvas before us does not appear
to emerge. The argument of the first respondent is
that even de hors the terms of the contract, there
is general regulatory power available under Section
79 of the Act. There is an overarching authority
with the Commission exercising power under Section
79 which would enable it and which would empower it
to grant compensation even de hors the terms of the
contract it is contended. The argument appears to
105
CIVIL APPEAL NO. 11826 OF 2018 etc.
be that unlike generality of contracts, a regulated
contract which is a long term contract or an
incomplete contract generates space for power with
the appropriate regulatory body to revisit the rates
and thereby vouchsafe a fair deal to both sides, be
it a seller or the procurer.
(88)
What this Court has laid down in para 19 and 20
3
in Energy Watchdog may be summarized as follows:
(89) In the case of fixation of tariff under Section
63 of the Act, what is contemplated is to begin with
guidelines which have been issued under Section 63.
When the Commission is asked to exercise power under
Section 63, it is beholden to the guidelines as it
cannot depart from the same. In a area where the
guidelines do not occupy the field, undoubtedly, the
Commission is clothed with power as a regulatory
body to act in the best interest of all sides and to
fix the tariff in a manner which is fair in the
sense bearing in mind the paramount interest of
increased generation of power, the interest of the
3 Energy Watchdog v. Central Electricity Regulatory
Commission and Others (2017) 14 SCC 80
106
CIVIL APPEAL NO. 11826 OF 2018 etc.
consumer, as also ensuring of a fair return to the
seller. So far so good. When the Commission
exercises the power under Section 63, this power is
not abridged when there are no guidelines holding
the field.
(90) We are not dealing with a case where the
exercise of power of the Commission under Section 63
is under review. In a case where, however, the
rates are approved under Section 63 and PPA is
entered into, the question would undoubtedly arise
as to whether there is a power which can be
described in a manner of speaking to be plenary
power with the Commission under Section 79? Can
there be a power which can be christened as omnibus?
Can the Tribunal, in other words, disregard the
express words of the contract? Can it discover a
new change in law which the parties have not
contemplated as change in law? In short, can the
Tribunal rewrite the contract and create a new
bargain?
(91) We are of the view that the Tribunal cannot
indeed make a new bargain for the parties. The
107
CIVIL APPEAL NO. 11826 OF 2018 etc.
Tribunal cannot rewrite a contract solemnly entered
into. It cannot ink a new agreement. Such
residuary powers to act which varies the written
contract cannot be located in the power to regulate.
The power cannot, at any rate, be exercised in the
teeth of express provisions of the contract.
(92)
We notice this for the reason that the first
respondent has a case that what is provided in
Article 13.2(a) (since we are dealing with the case
of alleged change in law during the construction
period) does not do justice to the parties or that
it is incapable of producing a fair result and
therefore, the Tribunal would necessarily be clothed
with power bearing in mind its regulatory nature.
In a matter where the parties have entered into a
contract with express provisions, we are unable to
agree with the first respondent that the Tribunal
would have power to disregard the express provisions
of the contract on the score that as it turns out
that with passage of time and even change in
circumstances, it is found that the contract cannot
be worked except at a loss for the contractor.
108
CIVIL APPEAL NO. 11826 OF 2018 etc.
(93)
We may, at this juncture, also notice an
argument which has been raised by Shri Amit Kapur,
learned counsel for the first respondent, when
queried as to what would be the position if a claim
of the nature were canvassed in a civil suit. The
answer came that Section 18 and 19 of the Indian
Contract Act, 1872 (hereinafter referred to as
‘Contract Act’ for brevity), provided the gateway.
Section 18 of the Contract Act deals with the effect
of representation or rather misrepresentation by a
party made to another party to the contract. It,
undoubtedly, includes a representation, however,
innocent it may be. In other words, an innocent
representation made to one party by another party
which forms the basis for consent of the person can
lead to the contract becoming voidable under Section
19. It is undoubtedly true that Section 19 also
contemplates that the wronged party can insist upon
the contract being performed and further, however,
persevere in requiring that he be placed in the same
position if he had not been led astray by the
misrepresentation. There may be no dispute about
109
CIVIL APPEAL NO. 11826 OF 2018 etc.
this principle. However, we have noticed the
various clauses as contained in the disclaimer
clauses. When a party to the contract states that
what is contained in the first WAPCOS report and
anything else as contemplated in the RFP and the PPA
does not amount to a representation, we are unable
to agree with the contention that it would still be
considered as a representation within the meaning of
Section 18 and thereby leading to a claim under
Section 19 of the Contract Act. Therefore, we find
that the contentions which the first respondent
seeks to raise under the provisions of Section 18
and 19 untenable.
(94)
Reliance was placed on the judgment of this
Court PTC India Limited v. Central Electricity
Regulatory Commission (2010) 4 SCC 603. In PTC
4
India Limited , the actual question which arose was
as to whether the appellate Tribunal under the Act
has jurisdiction under Section 111 to examine the
validity of regulations framed in exercise of power
4 PTC India Limited v. Central Electricity Regulatory
Commission (2010) 4 SCC 603
110
CIVIL APPEAL NO. 11826 OF 2018 etc.
under Section 178 of the Act. The further question
which arose was whether Parliament has conferred
power of judicial review on the Tribunal under
Section 121 of the Act. In the course of this
judgment, the Court inter alia held as follows:
“53. Applying the abovementioned tests to the
scheme of the 2003 Act, we find that under
the Act, the Central Commission is a
decision-making as well as regulation-making
authority, simultaneously. Section 79
delineates the functions of the Central
Commission broadly into two categories —
mandatory functions and advisory functions.
Tariff regulation, licensing (including
inter-State trading licensing), adjudication
upon disputes involving generating companies
or transmission licensees fall under the head
“mandatory functions” whereas advising the
Central Government on formulation of National
Electricity Policy and tariff policy would
fall under the head “advisory functions”. In
this sense, the Central Commission is the
decision-making authority. Such decision-
making under Section 79(1) is not dependent
upon making of regulations under Section 178
by the Central Commission. Therefore,
functions of the Central Commission
enumerated in Section 79 are separate and
distinct from functions of the Central
Commission under Section 178. The former are
administrative/adjudicatory functions whereas
the latter are legislative.
55. To regulate is an exercise which is
different from making of the regulations.
However, making of a regulation under Section
178 is not a precondition to the Central
Commission taking any steps/measures under
Section 79(1). As stated, if there is a
111
CIVIL APPEAL NO. 11826 OF 2018 etc.
regulation, then the measure under Section
79(1) has to be in conformity with such
regulation under Section 178. This principle
flows from various judgments of this Court
which we have discussed hereinafter. For
example, under Section 79(1)( g ) the Central
Commission is required to levy fees for the
purpose of the 2003 Act. An order imposing
regulatory fees could be passed even in the
absence of a regulation under Section 178. If
the levy is unreasonable, it could be the
subject-matter of challenge before the
appellate authority under Section 111 as the
levy is imposed by an order/decision-making
process. Making of a regulation under Section
178 is not a precondition to passing of an
order levying a regulatory fee under Section
79(1)( g ). However, if there is a regulation
under Section 178 in that regard then the
order levying fees under Section 79(1)( g ) has
to be in consonance with such regulation.”
(95)
We are unable to see how the said judgment can
advance the case of the first respondent. The
question which fell for consideration and the
opinion which has been rendered do not in any way
detract from the view which we have taken.
Substantially, it was held that the making of
regulation was not a pre condition for levying a
regulatory fee under Section 79(1)(g). It is no
doubt true that Commission has an adjudicatory
function. It is also empowered to give opinions.
112
CIVIL APPEAL NO. 11826 OF 2018 etc.
Power to frame regulations indicates that it also
has legislative powers. The point is that since in
this case we are concerned with the adjudicatory
function of the Commission, we are concerned with
the trammels to which it is subject in the form of
the express terms of the contract. All that we are
holding is that in a case where the matter is
governed by express terms of the contract, it may
not be open to the Commission even donning the garb
of a regulatory body to go beyond the express terms
of the contract. It is apposite that we notice para
58 reads as follows:
“58. One must understand the reason why a
regulation has been made in the matter of
capping the trading margin under Section 178
of the Act. Instead of fixing a trading
margin (including capping) on a case-to-case
basis, the Central Commission thought it fit
to make a regulation which has a general
application to the entire trading activity
which has been recognised, for the first
time, under the 2003 Act. Further, it is
important to bear in mind that making of a
regulation under Section 178 became necessary
because a regulation made under Section 178
has the effect of interfering and overriding
the existing contractual relationship between
the regulated entities. A regulation under
Section 178 is in the nature of a subordinate
legislation. Such subordinate legislation can
even override the existing contracts
113
CIVIL APPEAL NO. 11826 OF 2018 etc.
including power purchase agreements which
have got to be aligned with the regulations
under Section 178 and which could not have
been done across the board by an order of the
Central Commission under Section 79(1)( j ).”
(96) While it may be open as indicated therein for a
regulation to extricate a party from its contractual
obligations, in the course of its adjudicatory power
it may not be open to the Commission by using the
nomenclature regulation to usurp this power to
disregard the terms of the contract.
(97) Another argument which has been raised on
behalf of the first respondent is that the
guidelines were framed on 19.01.2005. Clauses 4.7
and 5.17 came to be, however, modified before the
PPA was entered into and even prior to the RFP and
therefore, the PPA and Article 17.3 therein has been
cast in the widest terms.
(98)
We have already perused Article 17.3.1.
Article 17.3 to begin with, speaks of specific
instances which can trigger the dispute resolution
mechanism. A case in point and close to facts is a
dispute arising from a change in law, after a claim
114
CIVIL APPEAL NO. 11826 OF 2018 etc.
is denied and a resolution through settlement not
being arrived at. There are other specific clauses
which are part of the PPA which are adverted to in
the later part of Article 17.3.1. Therefore, the
argument is raised on behalf of the first respondent
that the opening words of Article 17.3.1 are
designedly broad to cater to situations such as are
represented by the facts of this case. In other
words, even irrespective of a situation being not
governed by Article 13.1 in order that the
restitutionary principle or the principle of an
incomplete contract leading to a lifelong regulation
assuring a fair return to the seller is observed,
the power of revisiting of the rates is what is
contemplated in the amended guideline which finds
enshrinement in Article 17.3.1., it is contended.
(99) In fact, when we notice the PPA, we find that
apart from matters which are expressly referred to
in Article 17.3.1, viz., Articles 4.7.1, Article
13.2, Article 18.1 or clause 10.1.3 of Schedule 17,
there are other Articles in the PPA with which
Article 17.3.1 can bear nexus with. They include
115
CIVIL APPEAL NO. 11826 OF 2018 etc.
apparently, Articles 4.5.2, 11.6.6 and 11.6.7. This
is besides 12.7(e) which relates to enforcement of
claims under Force Majeure . Therefore, it is not as
if Article 17.3.1 is not to be understood without
reference to the other parts of the contract. No
Court should attempt to read a part of the contract
in isolation. The draftsman of a contract of the
nature we are dealing with would have not left any
stone unturned in making the contract one to be
construed with a great sense of harmony and care.
Therefore, we do not accept the contention of the
first respondent that the Commission, Tribunal and
this Court must pour in meaning into the opening
words of Article 17.3.1 so that in the facts, the
first respondent can claim compensation on the basis
that it has incurred expenditure acting on the first
WAPCOS report.
(100) Here, we must notice finally, that
substantially, the claim in regard to the water
intake system was founded on the reliance placed on
the first WAPCOS report and on the strength of the
second WAPCOS report.
116
CIVIL APPEAL NO. 11826 OF 2018 etc.
(101)
We also find reinforcement in our view from the
following clauses 1.2.12:
“1.2.12 Different parts of this Agreement are
to be taken as mutually explanatory and
supplementary to each other and if there is
any inconsistency between or among the parts
of this Agreement, they shall be interpreted
in a harmonious manner so as to give effect
to each part.”
(Emphasis supplied)
(102) An argument was raised by Shri Amit Kapur that
the contract in the case calls for the application
of the principle of contra proferentem rule.
(103) We are of the view that the principle of contra
proferentem is ordinarily utilised in contracts of
insurance and standard form contracts.
(104) The principle of contra proferentem apparently
in substance is that in case of any doubt in its
terms, the doubt should be resolved against the
party who drafted the contract. We would not think
in the facts of this case that the first respondent
has been able to plant any serious doubt in regard
to the clauses with which we are concerned with on a
true understanding of the same.
117
CIVIL APPEAL NO. 11826 OF 2018 etc.
(105)
The second complaint- The Office Memorandum
dated 17.06.2011.
As far as the question relating to the OM dated
17.06.2011 providing the premise for change in
law claim is concerned, we are of the view that
the claim may not have merit in it. It is true
that Article 13.1.1 inter alia provides that a
change can be brought about by the issuance of
a notification by an Indian Governmental
authority. Also a change in interpretation of
any law by an Indian Governmental
instrumentality inter alia provided that it is
final authority under law for such
interpretation would constitute a change in
law.
Indian Governmental Instrumentality is defined
as follow: -
“Indian Governmental Instrumentality” means
the GOI, Government of States where the
Procurers and Project are located and any
ministry or department of or board, agency
or other regulatory or quasi-judicial
authority controlled by GOI or Government
of States where the Procurers and Project
are located and includes the Appropriate
118
CIVIL APPEAL NO. 11826 OF 2018 etc.
Commission;”
(106) Law as defined in the PPA is as follows:
“Law” means, in relation to this Agreement,
all laws including Electricity Laws in
force in India and any statute, ordinance,
regulation, notification or code, rule, or
any interpretation of any of them by any
Indian Governmental Instrumentality and
having force of law and shall further
include all applicable rules, regulations,
orders, notifications by an Indian
Govermental Instrumentatlity pursuant to or
under any of them and shall include all
rules, regulations, decisions and orders of
the Appropriate Commission;
(107) While the word ‘competent Court’ which can also
be the source of a change in interpretation of any
law is expressly defined in Article 13.1.1., when it
comes to the Indian Governmental instrumentality
which is the final authority, is concerned, there is
no definition in the PPA. The controversy is this.
(108) The first respondent allegedly imported goods
for the purpose of construction of the captive
mining plant. It is its case that the goods so
imported were being used for construction of the
mining plant which was in turn was utilised for the
119
CIVIL APPEAL NO. 11826 OF 2018 etc.
construction and operation of the ultra mega power
plant project. Such goods according to the first
respondent was expressly exempted from customs duty
by virtue of the notification holding the field.
The notifications holding the field it must be
understood were the notifications holding the field
before the cut off date. The cut off date
admittedly is 21.07.2007. In other words, the said
date is the date which is seven days before the bid
deadline. The OM which is the premise for the
argument has been issued by the Director no doubt
with the approval of the Joint Secretary in the
Ministry of Power. It reads as follows:
“No. 12/20/2009-UMPP
Government of India
Ministry of Power
Shram Shakti Bhawan, Rafi marg,
New Delhi, the 17th June, 2011
OFFICE MEMORANDUM
Sub: 3960 MW Sasan Ultra Mega Power Project, Distt.
Singrauli - Exemption from Custom Duty under project
Import - reg.
The undersigned is directed to refer to Govt. of
Madhya Pradesh's letter No. 4468/13/2011/01 dated
24.05.2011 on the subject mentioned above and to say
120
CIVIL APPEAL NO. 11826 OF 2018 etc.
that under Mega Power Policy, the Custom/Excise Duty
exemption is given in respect of power equipment
only.
This issues with the approval of JS (Thermal),
Ministry of Power
(A.A. Tazir)
Director
Shri Mohd. Suleman
Secretary (Energy)
Govt. of Madhya Pradesh,
Bhopal”
(109) It is the contention of the first respondent
that when it imported the goods it had to pay
customs duty on the same and it constituted a change
in law as the OM issued by the Joint Secretary
placing the interpretation constituted a change in
interpretation.
(110) In other words, in contrast with the law as it
stood before the cut off date, by the issuance of
the OM by the Joint Secretary in the Ministry of
Power, a change in interpretation of the law is
brought about. This sufficed to found a claim of
change in law within the meaning of Article 13.1.1
121
CIVIL APPEAL NO. 11826 OF 2018 etc.
(111)
The argument of the procurers, on the other
hand, is as we have noticed is that the OM cannot be
found to be issued by a Governmental instrumentality
which can be treated as the final authority under
law for such interpretation. It is for the reason
that the notification granting exemption has been
issued by the authority under the Customs Act and
the Joint Secretary in the Ministry of Power is not
such an authority. Secondly, it is the contention
of the procurers that the matter should have been
taken before the appropriate forum by the first
respondent on the basis that in law, actually, the
import of goods was exempt if it was exempt and it
was not open to the first respondent to pass on the
burden without taking recourse to law. Thirdly, it
is contended that the fact of the matter is that the
position even before the cut off date was that goods
in question were not exempt.
(112) Since we are dealing with the notifications, we
notice that the authority on Advance Ruling has gone
into the history of the notifications and dealt with
the same though in the context of the right to
122
CIVIL APPEAL NO. 11826 OF 2018 etc.
exemption in a mega power plant but not for an ultra
mega power project. But we are of the view that as
far as the history of the notifications go, it would
continue to be relevant:
“7.1 The Entry corresponding to the present
Entry was introduced for the first time in
1999. As pointed out by the learned Sr. counsel
for the applicant, the introduction of this
Entry in the Customs notification seems to be a
follow up to the policy decision taken by the
Central Government as set out in the
communication dated 10.11.1995 addressed by the
Secretary, Ministry of Power, Government of
India and the revised policy/guidelines
relating to Mega power projects issued in 1998.
The policy formulated in 1995 was in relation
to the “setting up of power plants of capacity
of 1000 MW or more supplying power to more than
one state”. In that policy document, it is
stated that the “project of capacity of 1000 MW
and more and catering power to more than one
state should be considered as a mega project.
Projects which cater power to a single State,
irrespective of size, would not come under this
category”. In the policy which has been recast
in 1998, it was decided that inter-state and
inter-regional mega power projects were to be
set up both in the public and private sectors.
The re-organization of the public sector
corporations was also envisaged by the policy.
The policy contemplates the beneficiary States
constituting Regulatory Commissions with powers
to fix tariff. Paragraph 5 of the guidelines is
important. It says “the import of capital
equipment would be free of custom duty for
these projects”. In order to ensure that
domestic bidders were not adversely affected,
certain safeguards were spelt out.”
123
CIVIL APPEAL NO. 11826 OF 2018 etc.
7.2 Entry/ Sl.No. 288A of Ch. 98.01 inserted by
Notification No. 63/1999 substantially gives
effect to the 1995 policy read with revised
policy of 1998. The same concept of mega power
project is to be found in that Entry. The Entry
reads:
| SL.<br>No. | Chapter/<br>heading/su<br>b-head no. | Descripti<br>on of<br>goods | Standa<br>rd<br>Rate | Addition<br>al Duty<br>rate | Conditi<br>on No. |
|---|---|---|---|---|---|
| 288<br>A | 9801 | Goods<br>required<br>for<br>setting<br>up of any<br>Mega<br>Power<br>Project<br>specified<br>in<br>List33,<br>if such<br>Mega<br>Power<br>Project<br>is-<br>a. an<br>inter-<br>state<br>thermal<br>power<br>plant of<br>a<br>capacity<br>of 1500MW<br>or more;<br>or<br>b. an<br>inter-<br>State<br>hydel<br>power<br>plant of<br>a<br>capacity<br>of 500MW<br>or<br>more……… | Nil | Nil | 82 |
124
CIVIL APPEAL NO. 11826 OF 2018 etc.
Condition No. 82 is as follows: -
82. (a) If an officer not below the rank of a
Joint Secretary to the Government of India in
the Ministry of Power certifies that-
(i) the power purchasing state undertakes, in
principle, to privatize distribution in all
cities, in that State, each of which having a
population of more than one million within a
period to be fixed by the Ministry of Power;
and
(ii) In the case of imports by a Central Public
Sector Undertaking, the quantity, total value,
description and specifications of the imported
goods are certified by the Chairman and
Managing Director of the said Central Public
Sector Undertaking; and
(c) In the case of imports by a Private Sector
Project, the quantity, total value, description
and specifications of the imported goods are
certified by the Chief Executive Officer of
such project”.
“7.3 List 33 specifies by name the thermal
projects and hydel projects in respect of which
exemption is made applicable. Then, under
Customs Notification No. 100 of 99 dated
28/7/99, the capacity of thermal power project
specified in the earlier notification was
altered from 1500 to 1000 MW. As a result of
this notification, 7 more thermal projects were
added to the list.”
“7.4 Then, the next notifications in succession
are Customs Notification No. 16 of 2000 and 17
of 2001 which are substantially the same
excepting that the number of thermal and hydel
projects specified in List 33 has gone down.”
“7.5 Then comes the Customs Notification No. 21
of 2002 dated 01.03.2002 which is material for
125
CIVIL APPEAL NO. 11826 OF 2018 etc.
our purpose. It reads as follows: -
| SL<br>.<br>No<br>. | Chapter/<br>heading/su<br>b-head no. | Descripti<br>on of<br>goods | Standar<br>d Rate | Addition<br>al Duty<br>rate | Conditio<br>n No. |
|---|---|---|---|---|---|
| 40<br>0 | 9801 | Goods<br>required<br>for<br>setting<br>up of any<br>Mega<br>Power<br>Project<br>specified<br>in<br>List42,<br>if such<br>Mega<br>Power<br>Project<br>is-<br>a. an<br>inter-<br>state<br>thermal<br>power<br>plant of<br>a<br>capacity<br>of 1000MW<br>or more;<br>or<br>b. an<br>inter-<br>State<br>hydel<br>power<br>plant of<br>a<br>capacity<br>of 500MW<br>or<br>more………<br>as<br>certified<br>by an<br>officer<br>not below | Nil | Nil | 86 |
126
CIVIL APPEAL NO. 11826 OF 2018 etc.
| the rank<br>of a<br>Joint<br>Secretary<br>to the<br>Governmen<br>t of<br>India in<br>the<br>Ministry<br>of Power |
|---|
“7.6 Entry 400 was amended by the Notification
No. 26/2003. The said amendment was
necessitated by reason of the policy decision
taken by the Government as reflected in the
Union budget speech of 203-04. The following
extract from the budged speech is relevant:
“Simultaneous to the emphasis on improvement in
power distribution, our attention on capacity
addition remains. The Government had earlier,
in 1999, notified 18 power projected as mega
projects, conferring upon them various duty and
licensing benefits. The Government now proposes
to liberalise the mega power project policy
further by extending all these benefits to any
power project that fulfills the conditions
already prescribed for mega power projects”.
Pursuant to the above policy, Notification No.
26/2003-Cus. Was issued amending the
notification no. 21/2002-Cus. Entry 400 as
amended reads:
400 9801 Goods required for
setting up of any
Mega Power Project
that is to say -
Nil Nil 86
a. an inter-state
thermal power
plant of a
capacity of 1000MW
127
CIVIL APPEAL NO. 11826 OF 2018 etc.
or more; or
b. an inter-State
hydel power plant
of a capacity of
500MW or more………
as certified by an
officer not below
the rank of a
Joint Secretary to
the Government of
India in the
Ministry of Power”
“7.7 The amended notification no. 21 of 2002
is almost in the same language as it stands
now (vide para 3 supra). Thus, w.e.f.
1/4/2003, the list of specified power projects
has been deleted in tune with the liberalized
policy of the Government. Further, it is to be
mentioned that Entry 400 of notification no.21
of 2002 was further amended keeping in view
the revised policy guidelines issued in order
to cater to the special requirements of power
projects in Jammu and Kashmir and NE States.
Entry 399 substantially remained the same from
1999 onwards excepting that there was change
in the Sl. No. and the rate.”
(113) The order of the Advance Ruling Authority is
dated 19.12.2008. No doubt, it is after the cut off
date. The case of the first respondent is not based
on the order of the Advance Ruling Authority. The
case of the first respondent is specifically based
only on the OM issued by the Joint Secretary in the
Ministry of Power. We may notice that Joint
128
CIVIL APPEAL NO. 11826 OF 2018 etc.
Secretary in the Ministry of Power has a role in
terms of the notification. The role assigned to him
is contained in condition 82 to the notification
63/1999 and this condition has continued thereafter
also. The condition as we have noticed is that it
is stated that an officer not below the rank of a
Joint Secretary is to certify the aspects which are
mentioned in condition 82.
(114) It is difficult, in fact, to describe the Joint
Secretary in the Ministry of Power as the
Governmental authority which is the final authority
under the law. The final authority under the law
would be the authority under the Customs Act which
issues the exemption notification. But we would not
wish to rest our findings on the said basis as we
feel that the objection of the procurers can rest on
surer foundations. The first respondent also relies
upon no doubt, the notification dated 26.05.2006
wherein it is indicated as follows:
“Notification No.49/2006-Customs
In exercise of the poowers conferred by sub-
section (1) of Section 25 of the Customs Act,
129
CIVIL APPEAL NO. 11826 OF 2018 etc.
1962 (52 of 1962), the Central Government, on
being satisfied that it is necessary in the
public interest to do so, hereby makes the
following further amendments in the
notification of the Government of India in the
Ministry of finance (Department of Revenue)
No.21/2002- Customs, dated the 1st March, 2002,
which was published in the Gazette of India,
Extraordinary vide number G.S.R. 118(E), dated
the 1st March, 2002, namely:-
(I) in the Table, against S.No.400, for
the entry in column (3), the following
entry shall be substituted,namely:-
“Goods required for setting up of any
Mega Power Project, so certified by an
officer not below the rank of Joint
Secretary to the Government of India in
the Ministry of Power, that is to say-
(a) an inter-state thermal power plant of
a capacit of 700MW or more, located in
the States of Jammu and Kashmir, Sikkim,
Arunachal Pradesh, Assam, Meghalaya,
Manipur, Mizoram, Nagaland and Tripura,or
(b) an inter-state thermal power plant of
a capacity of 1000MW or more, located in
States other than those specified in
clause(a) above; or
(c) an inter-state hydel power plant of a
capacity of 350MW or more, located in the
States of Jammu and Kashmir, Sikkim,
Arunachal Pradesh, Assam, Meghalaya,
Manipur, Mizoram, Nagaland and Tripura,or
(d) an inter-state hydel power plant of a
capacity of 500MW or more, located in
States other than those specified in
Clause(C) above”,
(II) in the Annexure, in Condition No.86,
for sub-clauses (ii) and (iii) of
clause(A), the following shall be
substituted, namely:-
“(ii) the power purchasing State
130
CIVIL APPEAL NO. 11826 OF 2018 etc.
undertakes, in principle, privatize
distribution in all cities, in that
State, each of which has a population of
more than one million, within a period to
be fixed by the Ministry of Power.”
(115) The Tribunal has, in fact, proceeded on the
basis that the goods in question would fall under
Entry 400 relating to power projects and therefore,
they were exempted. The Tribunal proceeded further
on the basis that the notification dated 17.06.2011
issued by the Joint Secretary amounted to an
interpretation which constitutes a change in law.
(116)
We are of the view that the approach of the
Tribunal cannot be upheld. There is no material,
whatsoever, apart from the notifications to indicate
that the goods in question were being treated as
exempt before the cut off date. In other words, it
was incumbent upon the first respondent to produce
incontestable material establishing that the goods
were exempt and were being treated so before the cut
off date. The best material would have been
examples of similar cases where goods were being
treated as exempt. Even though, it is pointed out
131
CIVIL APPEAL NO. 11826 OF 2018 etc.
that the first respondent was the only ultra mega
power plant, even then power plants including mega
power plants were operational. It is difficult to
conceive that there would not be a single case where
similar inputs by way of examples of other power
projects even if it is not ultra mega power projects
would not have operated for the first respondent to
draw from.
(117) The word law has been defined as we have
noticed. While the expression ‘Indian Governmental
Instrumentality’ is used in the definition of the
word law in Article 13.1.1, the change in
interpretation of any law by an Indian governmental
authority must be the final authority under the law
for such interpretation. It may be difficult to
attribute to the Joint Secretary in the Ministry of
Power the position of an Indian Governmental
Authority who has the final authority under the law.
But as we have indicated this must not be treated as
the basis on which we disagree with the Tribunal.
(118) The perusal of the OM does not advance the case
of the first respondent for yet another good reason.
132
CIVIL APPEAL NO. 11826 OF 2018 etc.
He does not in the OM indicate that the goods in
question had been exempted before the cut off date
and that the goods becoming exigible to duty on the
date after the cut off date. The Authority for
Advance Ruling has categorically affirmed that the
goods of the type with which we are concerned may
not qualify for exemption. The appellants have a
case that, in fact, the Joint Secretary was
essentially following the Advance Ruling. While it
is true that the Advance Ruling may not bind the
first respondent as it is not a party, and the
respondent could not have sought a ruling under the
law, it is undoubtedly an aspect which otherwise
adds strength to the case of the appellants. There
may be cases where placing the notification holding
the field before the cut off date side by side to
the subsequent notification or an interpretation
issued after the said cut off date, the Commission
or a Tribunal could find that there is change in
law, which added to the cost to the seller. On the
other hand, when the case of the first respondent
involves interpretation of the terms of the
133
CIVIL APPEAL NO. 11826 OF 2018 etc.
notification then particularly when two views are
fairly competing for acceptance before the body, at
best, we would think that the Tribunal has hazarded
taking a perilous route in venturing to find that
the OM issued by the Joint Secretary constituted the
change in law. Though reliance has been placed on
the judgment of this Court reported in Manohar Lal
Sharma v. Principal Secretary & Ors. (2014) 9 SCC
516 and Manohar Lal Sharma v. Principal Secretary &
Ors. (2014) 9 SCC 614 which decisions purported to
exempt the mining leases which were captive leases
operating for the purpose of the power projects
including the power projects specifically in
question from the purview of its decision, we do not
think that that by itself can determine the question
as to whether the goods which were imported for the
purpose of the captive mining plant was ever exempt.
What was exempt has been goods imported for the
purpose of the Power project. In other words, as to
whether the goods in question were goods which fell
within one entry or the other is in this case a
matter which is highly disputed and the premise of
134
CIVIL APPEAL NO. 11826 OF 2018 etc.
the first respondent viz., the OM of the Joint
Secretary cannot be treated as being a sound
foundation for making such a claim.
(119) The parties indeed contemplated a project to be
constructed and operated. The word ‘project’ we
find has been used in many clauses in the contract.
The word ‘project’ has been defined as follows:
““Project” means the Power Station and the
Captive Coal Mine(s) undertaken for design,
financing, engineering, procurement,
construction, operation, maintenance, repair,
refurbishment, development and insurance by
the Seller in accordance with the terms and
conditions of this Agreement;”
(120) Since the word ‘power station’ has been used
in word ‘project’, it is apposite that we advert to
the definition of the words ‘power station’:
“Power Station” means the:
(a) coal fired power generation facility
comprising of any or all the Units;
(b) any associated fuel handling, treatment or
storage facilities of the power generation
facility referred to above;
(c) any water supply, treatment or storage
facilities required for the operation of the
power generation facility referred to above;
(d) the ash disposal system including ash
dyke;
135
CIVIL APPEAL NO. 11826 OF 2018 etc.
(e) township area for the staff colony; and
(f) bay/s for transmission system in the
switchyard of the power station,
(g) all the other assets,
buildings/structures, equipments, plant and
machinery, facilities and related assets
require for the efficient and economic
operation of the power generation facility;
whether completed or at any stage of
development and construction or intended to be
developed and constructed as per the
provisions of this Agreement.”
(121) Since the word ‘captive coal mine’ has also
been referred to as part of the definition of the
word ‘project’, it is only right that we advert to
the definition:
“Captive Coal Mine(s) means the captive coal
mines as described in Schedule 1A and
associated fuel transport system up to the
Power Station;”
(122) ‘Project Documents” again has been defined. We
may also notice the definition of the words ‘Prudent
Utility Practices’:
“Project documents Mean
a) Construction Contracts;
b) Fuel mining agreements, including the Fuel
Transportation Agreement, if any;
c) O&M contracts;
136
CIVIL APPEAL NO. 11826 OF 2018 etc.
d) RFP and RFP Project Documents; and
e) any other agreements designated in writing
as such, from time to time, jointly by the
Procurers and the Seller;
“Prudent Utility Practices means the
practices, methods and standards that are
generally accepted internationally from time
to time by electric utilities or coal mining
entities for the purpose of ensuring the safe,
efficient and economic design, construction,
commissioning, operation and maintenance of
coal mines and power generation equipment and
mine of the type specified in this Agreement
and which practices, methods and standards
shall be adjusted as necessary, to take
account of:
a) operation and maintenance guidelines
recommended by the manufacturers of the plant
and equipment to be incorporated in the
Project;
b) the requirements of Indian Law; and
c) the physical conditions at the Site;”
(123) We have set out the history of the
notifications relating to grant of exemption for
power projects. All of it began with the policy
issued in the year 1995. The exemptions had their
origin with the notification issued in the year
1999. Thereafter there is Notification 21/2002 which
was issued on 01.03.2002. Entry 400 in the said
notification reads as follows:
137
CIVIL APPEAL NO. 11826 OF 2018 etc.
| S.N<br>o. | Chapte<br>r or<br>Headin<br>g or<br>Sub-<br>Headin<br>g | Description<br>of Goods | Stand<br>ard<br>rate | Additi<br>onal<br>Duty<br>Rate | Condi<br>tion<br>no. |
|---|---|---|---|---|---|
| 400 | 98.01 | “Goods<br>required for<br>setting up of<br>any Mega<br>Power<br>Project, so<br>certified by<br>an officer<br>not below the<br>rank of a<br>Joint<br>Secretary to<br>the<br>Government of<br>India in the<br>Ministry of<br>Power, that<br>is to say-<br>a) an inter-<br>state thermal<br>power plant<br>of a capacity<br>of 700 MW or<br>more, located<br>in the States<br>of Jammu and<br>Kashmir,<br>Sikkim,<br>Arunachal<br>Pradesh,<br>Assam,<br>Meghalaya,<br>Manipur,<br>Mizoram,<br>Nagaland and<br>Tripura; or<br>b an inter-<br>state thermal<br>power plant<br>of a capacity<br>of 1000 MW or<br>more, located | Nil | Nil | 86 |
138
CIVIL APPEAL NO. 11826 OF 2018 etc.
| in States<br>other than<br>those<br>specified in<br>clause (a)<br>above; or<br>c an inter-<br>state hydel<br>power plant<br>of a capacity<br>of 350 MW or<br>more, located<br>in the States<br>of Jammu and<br>Kashmir,<br>Sikkim,<br>Arunachal<br>Pradesh,<br>Assam,<br>Meghalaya,<br>Manipur,<br>Mizoram,<br>Nagaland and<br>Tripura; or<br>d an inter-<br>state hydel<br>power plant<br>of a capacity<br>of 500 MW or<br>more, located<br>in States<br>other than<br>those<br>specified in<br>clause (c)<br>above”; |
|---|
(124) Thereafter another notification namely
Notification No. 26/03 which has given a final shape
to it came to be issued which has been noticed also
by the Authority of Advance Ruling. It reads as
follows:
139
CIVIL APPEAL NO. 11826 OF 2018 etc.
400 9801 Goods required for
setting up of any
Mega Power Project
that is to say -
Nil Nil 86
a. an inter-state
thermal power
plant of a
capacity of 1000MW
or more; or
b. an inter-State
hydel power plant
of a capacity of
500MW or more………
as certified by an
officer not below
the rank of a
Joint Secretary to
the Government of
India in the
Ministry of Power
(Emphasis supplied)
(125)
We may notice that with the issuance of the
said notification what stands out is the following:
(126) While in the opening words of the Entry, there
is reference to power project, it is conditioned by
the words ‘that is to say’. We can quite safely
proceed on the basis that Entry 400 in the
Notification No. 21/2002 which came into effect on
01.03.2002 as amended by Notification No. 46/2008 is
the Entry which must be treated as holding the field
as on the cut off date. It is thereafter, no doubt,
that the first respondent has invoked the change in
140
CIVIL APPEAL NO. 11826 OF 2018 etc.
law clause by seeking to draw inspiration from the
OM issued on 17.06.2011.
(127) Change in law clause is sought to be invoked
apparently contending that there has been a change
in interpretation by Indian Governmental Authority
which has the final say in terms of the law. The
question which looms large before the Court is
whether there has been a change in law in terms of
‘change in interpretation’ placed by the
Governmental authority with reference to the
position obtaining under the notifications issued
under the Customs Act. Even the clauses in the PPA
which we have referred to maintain a distinction
between a power plant and a captive mine. A power
plant cannot be treated as the same as captive mine.
In fact, Schedule 1A which defines the site refers
to the captive mines in terms of the coal blocks
which are allotted. The definition of captive mine
also indicates that it is the coal mines as
described in Schedule 1A and the associated fuel
transport system up to the power station. No doubt,
the word ‘site’ has also been defined as the land
141
CIVIL APPEAL NO. 11826 OF 2018 etc.
over which the Project will be developed as provided
in Annexure 1A.
(128) Undoubtedly, in view of the very purpose of
having a coal mine which is to supply the requisite
fuel for the operation of the power plant, there
would be a certain measure of geographical
contiguity. But the question for the consideration
before this Court is whether that would decide the
fate of the contents of a notification issued under
the Customs Act.
(129) We must notice that it is not as if the first
respondent is the only person which had a right to
claim the benefit of exemption on the basis that the
goods which have been imported for the purpose of
their captive mine must be treated as goods used in
the power project. As the history of the
notifications as captured in order of the Advance
Ruling Authority would show over a period of time,
there have been a number of power plants which have
sprung up. All of them would also be using captive
mines for the purpose of generating power. It is not
as if there would be a dearth of examples of
142
CIVIL APPEAL NO. 11826 OF 2018 etc.
exemption being extended to imports made by them and
claiming the benefit of exemption under the
notification. Not a single instance of an exemption
granted to any other project where goods imported
for use in the captive mine has been produced before
the Commission, the Tribunal or even this Court.
This goes a long way to negate the claim of the
first respondent that what was once exempt has
ceased to be exempt only by virtue of the issuance
of the OM dated 17.06.2011.
(130) There is another very important circumstance
which strikes us. The material which appeals to us
is to be found undoubtedly in the order of the
Advance Ruling Authority relied upon by the
appellant. The application, no doubt, is filed in
the year 2008. What impresses the Court the most is
the stand of the customs authorities before the
Advance Ruling Authority. We cannot proceed on the
basis that the controversy which led to the seeking
of the ruling and far more importantly the
persistent stand of the customs authority before the
Advance Ruling Authority would not shed light on how
143
CIVIL APPEAL NO. 11826 OF 2018 etc.
the Department viewed the matter. This is important
as it is the customs department which has issued the
exemption notification. Being the authors of the
notification, they would be best placed to
understand the width and purport of a notification
granting exemption. They have stoutly opposed the
application and laid out various grounds which, no
doubt, has appealed also to the Advance Ruling
Authority. This is an aspect which goes a long way
to show that the view of the customs authority which
in a manner of speaking can also be viewed as
forming contemporanea expositio should not be
ignored by this Court.
(131)
The first respondent also sought considerable
reliance in this regard from the Mega Power
Projects: Revised Policy Guidelines. The relevant
portions reads as follows:
“MEGA POWER PROJECTS: REVISED POLICY
GUIDELINES
The following conditions are required to be
fulfilled by the developer for grant of mega
project status:-
a) an inter-state thermal power plant of a
capacity of 700 MW or more, located in the
144
CIVIL APPEAL NO. 11826 OF 2018 etc.
States of Jammu and Kashmir, Sikkim, Arunachal
Pradesh, Assam, Meghalaya, Manipur, Mizoram,
Nagaland and Tripura; or
b) an inter-state thermal power plant of a
capacity of 1000 MW or more, located in States
other than those specified in clause (a)
above; or
c) an inter-state hydel power plant of a
capacity of 350 MW or more. located in the
States of Jammu and Kashmir. Sikkim, Arunachal
Pradesh, Assam, Meghalaya. Manipur, Mizoram,
Nagaland and Tripura: or
d) an inter-state hydel power plant of a
capacity of 500 MW or more, located in States
other than those specified in clause (c)
above'
Fiscal concessions/benefits available to the
Mega Power Projects
Zero Customs Duty: In terms of the
notification of the Government of India in the
Ministry of Finance(Department of Revenue) No.
21/2002-Customs dated 18 March, 2002 read
together with No. 49/2006-Customs dated 26
May, 2006. the import of capital equipment
would be free of customs duty for these
projects.”
(132) The understanding of the Authority for Advance
Ruling appears to be that as far as the entitlement
to exemption under the notification is concerned a
mega power project has to be understood as confined
to what follows after the words ‘that is to say’. In
145
CIVIL APPEAL NO. 11826 OF 2018 etc.
other words, though the use of the words power
project in entry 400 would appear to suggest that it
is capable of embracing within its scope a captive
mine from which the fuel is generated to run the
power plant, when it came to the actual beneficiary
of entry 400, the maker of the notification has
confined the exemption to the goods for the purpose
of the power plant. In other words, the word power
project has been conflated with the power plant.
This appears to be the soul of the reasoning of the
Advance Ruling Authority. While we are aware that
the first respondent is not bound by the said Ruling
as it is not a party, we do not find it erroneous on
our part in finding merit in the logic of the same
or adopting the same for the purpose of deciding the
question which squarely arises before this Court
viz., whether there is a change in law.
(133) There is also merit in the contention of the
appellant that for article 13.1.1 to be successfully
invoked by the seller, it must demonstrate that
there was an interpretation earlier to or as on the
date of the cut off date which was advantageous to
146
CIVIL APPEAL NO. 11826 OF 2018 etc.
the seller and there has been a change in the said
interpretation after the cut off date.
(134) In other words, the OM issued with the
approval of the Joint Secretary in the Ministry of
Power does not indicate that it is a case of a
change in interpretation. He does not say that the
position adumbrated in the OM represents a shift or
a change from what the position was prior to the cut
off date. This is apart from any material being
available to show that there was an interpretation
in favour of the first respondent prior to the cut
off date.
(135)
We reiterate that no instance of exemption to
goods of similar nature being imported by any person
for the captive mine as part of a power project be
it mega or ultra mega plant is placed before the
Commission. It is one thing to say that in a
popular sense and it could be urged and it may be
true that the word project has been defined in the
PPA as power plant and the captive coal mine, but as
we have noticed this is a matter to be determined on
what was intended by the author of the notification
147
CIVIL APPEAL NO. 11826 OF 2018 etc.
under Section 25 of the Customs Act and the matter
is to be further determined with reference to the
express terms of the Notification. Even more
importantly, the question must fall to be decided
with reference to the interpretation available prior
to the cut off date and after cut off date. The
communication, which is the OM dated 17.06.2011
relied upon by the first respondent appears to have
been issued on the basis of the request made by the
first respondent to the State of Madhya Pradesh.
(136) Shri Amit Kapur, learned counsel on behalf of
the first respondent drew our attention to Entry 78
of notification No. 21/02 dated 1.3.2002. Entry 78
reads as follows:
| Sr.<br>No. | Chapter<br>or<br>Heading<br>or sub-<br>heading | Descriptio<br>n of goods | Standard<br>rate | Additional<br>rate | Condition<br>No. |
|---|---|---|---|---|---|
| 78. | 2714.90 | All goods,<br>for the<br>purpose of<br>power<br>generation | - | Nil | - |
148
CIVIL APPEAL NO. 11826 OF 2018 etc.
(137)
Shri Ramchandran, learned senior counsel,
would point out that the said Entry relates to
inputs for power generation. The case of the first
respondent is also that Entry 399 actually
specifically deals with the goods required for coal
mining project under which the first respondent has
been visited with customs duty.
(138) The argument of Shri Amit Kapur is that first
of all, Entry 78 if contrasted with Entry 400 would
show that all goods needed for a power project
understood in a larger sense as including a captive
coal mine would also come within four walls of Entry
400.
(139) Shri Amit Kapur, learned counsel, would point
out that captive coal mine envisaged as such is one
where the entire production of coal is to be
utilised for the power plant in question which also
would indicate that it is part of the power project.
It is not in dispute that whatever may be the
distinction which may exist between a mega power
project, an ultra mega power project (we are
concerned with latter), there is no separate
149
CIVIL APPEAL NO. 11826 OF 2018 etc.
notification under the Customs Act which deals with
ultra mega power project.
(140) The upshot of the above discussion is that we
are of the view that the first respondent has not
been able to demonstrate that there was a change in
law as contemplated in Article 13.1.1 by issuance of
the OM dated 17.06.2011.
RELIEF
(141) The three procurers who were respondents before
the Tribunal have not chosen to file appearance
before this Court. The lead procurer has filed an
appeal before this Court. Further, there is only
one PPA. Ironically, decisions relating to Order
XLI Rule 21 and Rule 33 have been placed before this
Court by the first respondent reminding this Court
of the power available to it. No doubt, they placed
this position in an attempt at salvaging the
situation arising from no appeal have been filed by
it challenging the finding relating to there being
no change in law in regard to the water intake
system.
150
CIVIL APPEAL NO. 11826 OF 2018 etc.
(142)
In the facts of this case, we also notice that
the three non-filing parties are respondents in the
appeals filed by the appellants. We also cannot be
unmindful of the argument of Shri P. Chidambaram and
others that if the first respondent had a case that
they were entitled to an exemption under the
situation extant prior to the cut off date then
proper remedy would be to seek refund on the basis
that they have been illegally visited with customs
duty.
(143) In the facts of this case, we feel that the
interest of justice do require that the impugned
order be set aside not only as against the
appellants but also as against the three non-
appellants. In the nature of the litigation, we
would think that the benefit of this order should be
vouchsafed to the three respondents also, viz., (1)
respondent No. 12(BSES Rajdhani Power Limited); (2)
respondent No. 13 (BSES Yamuna Power Limited); and
(3) respondent No. 15(Uttarakhand Power Corporation
Limited). Apparently, these respondents have not
contested the appeals.
151
CIVIL APPEAL NO. 11826 OF 2018 etc.
(144)
As we have noticed in the beginning as a sequel
to the impugned order, the Commission has passed
orders allowing the claim relating to the water
intake system whereas it has rejected the prayer
relating to change in law flowing from OM dated
17.06.2011. The affected parties have carried the
matter to the Tribunal in appeals. It is brought to
our notice that this Court passed an order of stay
dated 25.11.2019. Since the appellants have
challenged the order of the Tribunal, the subsequent
order by the Commission can only be treated as a
consequential order and therefore, it may not have
any independent legs to stand on. The appellants
must be given the fruits of the decision which
ultimately is rendered in their favour, as we are
rendering this judgment.
(145) Accordingly, the appeals are allowed. The
impugned order is set aside. The order will enure
to the benefit also of the three respondents also,
viz., (1) respondent No. 12(BSES Rajdhani Power
Limited); (2) respondent No. 13 (BSES Yamuna Power
Limited); and (3) respondent No. 15(Uttrakhand Power
152
CIVIL APPEAL NO. 11826 OF 2018 etc.
Corporation Limited). Equally, the order passed by
the Commission consequent upon the remand under the
impugned order cannot survive. The appeals filed
will also lose their force and it is for the
appellants to do the needful to bring it to an end
in the light of this judgment.
The parties will suffer their own costs.
………………………………………………………., J.
[ K.M. JOSEPH ]
………………………………………………………., J.
[ B.V. NAGARATHNA ]
New Delhi;
April 06, 2023.
153