REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6978 of 2016
(ARISING OUT OF SLP (CIVIL) NO.5695 OF 2016)
BAKSHI SECURITY AND PERSONNEL
SERVICES PVT. LTD. …APPELLANT
VERSUS
DEVKISHAN COMPUTED PVT. LTD.
AND ORS. …RESPONDENTS
J U D G M E N T
R.F. Nariman, J.
1. Leave granted.
JUDGMENT
2. On 20.11.2014, the Commissioner of Transport,
Government of Gujarat, floated a tender seeking bids for
services inter alia of supervisors, computer programmers, data
entry operators, and electrician staff at 11 RTO check-posts. A
few material clauses of the tender are set out hereinbelow:-
1
Page 1
“2.5.5 Commercials
| The Commercial Bids should strictly conform to the | |
|---|
| formats provided in Annexure 2 of this tender document. | | |
2.5.6 Fixed Price
| Prices quoted by the Bidder shall be fixed and no | |
| variation will be allowed under any circumstances during the | | |
| entire period of the project. | | No open-ended Bid shall be |
| entertained and the same is liable to be rejected | | |
| straightaway | | |
2.8.3 Rejection of Bid
| The hard-bound copy of T | echnical Bid Document shall be | |
| submitted in the form of printed | | document. Bids submitted by | |
| Telex, fax or email shall not | | be entertained. Any bid not | |
| secured in accordance with Cla | | use 2.8 mentioned above, shall | |
| be rejected by COT without a | | ny further correspondence, as | |
| non-responsive. A bid that does not meet all pre-qualification | | | |
| criteria or is not responsive or not fulfilling technical evaluation | | | |
| shall be rejected by COT, and may not subsequently be made | | | |
| responsive by correction or withdrawal of the non-conforming | | | |
| JUDGME<br>deviation or reservation by the Bidder. | | | NT |
| It shall be the responsibility of the Bidder to abide by the | |
| provisions of the labour welfare legislations, like The Payment | | |
| of Wages Act, 1936, The Payment of Bonus Act, 1965, The | | |
| Minimum Wages Act, 1948, The Equal Remuneration Act, 1976, | | |
| The Payment of Gratuity Act, 1972, The Employees’ State | | |
| Insurance Act, 1948, Contract Labor Act, 1970, The Workmen’s | | |
| Compensation Act, 1923 and other similar legislations, rules, | | |
| and orders as issued from time to time. | | |
2
Page 2
Annexure – 2 (Financial Bid)
Format for Financial Bid
| Price Bid: (Financial/Commercial Bid submitted in physical form<br>shall be liable for rejection. It should be submitted online only at<br>https://www.nprocure.com)<br>Please provide price bid for supply of Man Power to be deployed at<br>different Check-posts/CMC. | | | | |
| Sr.<br>No. | Particulars Qty | | Cost<br>per<br>person<br>per<br>month<br>without<br>tax | Total cost<br>for 24<br>months<br>without tax |
| 1 | Data Entry 12<br>operator | 0 | | |
| 2 | Computer 02<br>Engineer | | | |
| 3 | Electrician 12 | | | |
| 4 | Supervisor 12 | | | |
| Total | | | |
| Additional Service Tax % | | | | |
| GJranUd TDotalGMENT | | | | |
| Price Bid: (Financial/Commercial Bid submitted in physical form | |
| shall be liable for rejection. It should be submitted online only at | | |
| https://www.nprocure.com | | ) |
| Salary paid to the deployed manpower should not be less than | |
| the minimum wages published as per the notification issued by | |
| state govt. labour department or other statutory benefits | |
| applicable. In case of revision of minimum wages/DA by the | |
| labour department, agency would be entitled to get the revised | |
| rates from Commissioner of transport. | |
| 2. | | Break-up of salary for each category of employee should be | |
| | provided indicating clearly the wages, DA, other mandatory | |
| | statutory benefits & the service charges. | |
3. If the component of salary quoted is less than the minimum
wages prescribed or the components of mandatory statutory
3
Page 3
| benefits are not included in the break-up, the bid is liable to be | |
|---|
| rejected. | |
| The quantity of manpower required may vary and the supplier | |
| may be asked to supply upto 25% extra manpower at the rate | |
| quoted above. | |
| 5. L1 will be decided on grand total.<br>Signature: Date:<br>Designation: Seal:” | | | |
| 3. | | The financial bids were opened on 10.12.2014. 9 bidders | |
| | | |
| gave financial bids of which only three were qualified. The | | | |
| | | |
| Appellant bid for a total amount of Rs.2,92,93,944/-; | | | |
| Respondent No.1 bid for Rs. | | | 2,77,68,000/-, and one Airan |
| | | for Rs.3,03,83,184/-. |
| Consultants Pvt. Ltd. made a bid | | | for Rs.3,03,83,184/-. |
| | | |
| 4. | | On 26.2.2015, the Technical Evaluation Committee, after | |
| | | |
| taking into account the opinion of the Labour Department, | | | |
| Signature: | | | | | | | | |
|---|
| Designation: | | | | | | | | Seal:” |
JUDGMENT
arrived at a minimum wage figure of Rs.3,00,92,346/-.
Inasmuch as both the Appellant as well as Respondent No.1
gave bids which were below this figure, (which would, therefore,
be less than the amount required as minimum wages, in
accordance with the tender conditions read with the Annexure 2
thereof), both the Appellant as well as Respondent No.1 were
held to be ineligible. A decision was, therefore, taken to award
4
Page 4
the tender to the third bidder, namely, M/s Airan Consultants
Pvt. Ltd. Respondent No.1 approached the Gujarat High Court
in a writ petition challenging the aforesaid decision. By its
| |
| judgment dated 11.8.2015, the High Court ultimately came to | |
| |
| the conclusion that the tender in favour of M/s Airan | |
| |
| Consultants Pvt. Ltd. ought to be quashed and set aside with | |
| |
| the further direction that the Government of Gujarat shall give | |
| |
| an opportunity to all three tenderers to resubmit their bids after | |
| |
| being appraised of the minimum wage figure given by the | |
| Labour Department. This was | done as the High Court was of |
| |
| the opinion that all the bidders | ought to have been given an |
| |
| opportunity to revise their bills | subsequent to the minimum |
| wage calculated by the Labour Department. | |
| wage calculated by the Labour Department. | |
| 5. | | JUDGMENT<br>In pursuance of the aforesaid judgment, the Transport |
|---|
Department of the Government of Gujarat furnished to all the
competing bidders the Labour Department’s calculation that
minimum wages plus bonus payable for the contract was
Rs.3,00,92,346/-.
| 6. | | In response to the above, the Appellant wrote a letter |
|---|
dated 2.11.2015 sticking to the original bid figure of
5
Page 5
Rs.2,92,93,944/-. On 3.9.2015, Respondent No.1, in response
to the minimum wage figure disclosed, wrote to the Government
of Gujarat, as follows:-
| “ | (6.3) | Thus, it can be seen that according to the | |
|---|
| calculation, Minimum Wages and other statutory | | | |
| benefits payable to the employees for 730 days [2 | | | |
| years of contract] comes to Rs.3,00,92,346 [without | | | |
| service tax]. The price at which I am ready to work | | | |
| is Rs.2,77,68,000 [without service tax]. Thus, | | | |
| against payment of wages and all statutory benefits | | | |
| of Rs.3,00,92,346/- and service tax thereon, am | | | |
| ready and willing to accept Rs.2,77,68,000 [plus | | | |
| service tax] from the Government. This would<br>enable the Government to save Rs.23,24,346.00 | | | |
| and service tax there | | | on, and the ultimate |
| beneficiary would be publi | | | c exchequer. |
| (6.4) I have undertaken i | n past in writing that I am |
|---|
| ready to incur loss as well | . The price I have offered |
| shall have no impediment on wages and statutory | |
| benefits to be paid to the employees as calculated | |
| by the Technical Evaluation Committee based on | |
| the report/ opinion of the Labour Commissioner. | |
| JUDGMENT<br>The tender document itself binds the contractor to | |
| abide by all labour welfare legislation, and therefore, | |
| there is no question of resiling from performing that | |
| part of contract from my e | |
| (6.5) | | Even in my previous letters also, I have |
|---|
| undertaken that I shall conform to all labour welfare | | |
| legislations even after accepting Rs.2,77,68,000 + | | |
| Service Tax from the Government. I have also | | |
| undertaken that I shall bear the burden of loss | | |
| incurred on account of the margin between my bid | | |
| and the amount of minimum wages and statutory | | |
| benefits payable to my employees. The margin | | |
| between the two shall not be hindrance in quality of | | |
6
Page 6
| services I would offer through my employees on | |
|---|
| these check-posts. | |
| (6.6) Without prejudice to above, I am to state that I<br>am ready to accept even Rs.3,00,92,346.00 +<br>Service Tax, being the bare minimum wages<br>payable to the employees during the life of the<br>contract from the Government as calculated by the<br>Technical Evaluation Committee based on the<br>report of the Labour Commissioner, such offer will<br>result into ‘No Profit No Loss’ business for me, but<br>at the same time, it would create a burden of<br>Rs.23,24,346.00 on the State Funds.” | | | |
| 7. | | On 12.10.2015, the Labour Department gave a second | |
| opinion that though Data Entry Operators are ordinarily to be | | | |
| | | |
| treated as “skilled workers”, f | | | or the purpose of the present |
| | | |
| tender they should be treated a | | | s “semi skilled workers”. In view |
| | | |
| of this decision, the Government, on 30.10.2015, arrived at a | | | |
| | | |
| (6.6) | | Without prejudice to above, I am to state that I | |
|---|
| am ready to accept even Rs.3,00,92,346.00 + | | | |
| Service Tax, being the bare minimum wages | | | |
| payable to the employee | | | s during the life of the |
| contract from the Government as calculated by the | | | |
| Technical Evaluation Committee based on the | | | |
| report of the Labour Commissioner, such offer will | | | |
| result into ‘No Profit No Loss’ business for me, but | | | |
| at the same time, it would create a burden of | | | |
| Rs.23,24,346.00 on the State Funds.” | | | |
decision that the actual minimum wage plus bonus worked out
JUDGMENT
to Rs.2,91,00,000/-, and thus revised their earlier figure of
Rs.3,00,92,346/-. In the judgment under appeal, the High Court
has stated, and it is not controverted before us, that this figure
was not disclosed to either party.
| 8. | | On 2.11.2015, Respondent No.1 again knocked at the |
|---|
doors of the High Court in a second writ petition filed by it. By
7
Page 7
the impugned judgment dated 22.2.2016, the High Court
allowed Respondent no.1’s petition in the following terms:-
| “8. Under the circumstances, the decision of the<br>authorities to shortlist respondent No.3 for awarding<br>the contract is set aside. The offer of the petitioner<br>shall be treated as matching with the revised<br>minimum wage calculation. The petitioner shall give<br>such offer in clear writing and undertaking to the<br>authorities latest by 25.2.2016. The respondent<br>authorities, unless there is any other disqualification<br>of the petitioner to carry out the contract, being the<br>lower, shall accept the same.<br>9. Petition is disposed of.” | | | | |
|---|
| 9. | | | Being aggrieved by the af | oresaid judgment, the Appellant |
| is before us. | | | | |
| 10. | | | Shri Harin Raval, learned senior advocate appearing on | |
| “ | 8. | | Under the circumstances, the decision of the | |
|---|
| authorities to shortlist resp | | | | ondent No.3 for awarding |
| the contract is set aside. The offer of the petitioner | | | | |
| shall be treated as matching with the revised | | | | |
| minimum wage calculation. The petitioner shall give | | | | |
| such offer in clear writing and undertaking to the | | | | |
| authorities latest by 25.2.2016. The respondent | | | | |
| authorities, unless there is any other disqualification | | | | |
| of the petitioner to carry out the contract, being the | | | | |
| lower, shall accept the sam | | | | |
behalf of the Appellant, has pointedly referred to the tender
JUDGMENT
conditions and has argued before us that Respondent No.1’s
writ petition was not at all maintainable in view of the fact that
Respondent No.1 stuck to its earlier offer of Rs.2,77,68,000/-
which was lower than the figure of Rs.3,00,92,346/- as well as
the figure of Rs.2,91,00,000/- fixed by the Government upon
advice given by the Labour Department, of minimum wage plus
bonus. According to him, the without prejudice offer of
8
Page 8
Rs.3,00,92,346/- flew in the face of the tender conditions and,
therefore, the writ petition being not maintainable, ought to have
been dismissed both on the ground that the figure quoted by
| | | |
| Respondent No.1 was below the minimum wage fixed as also | | | |
| | | |
| on the ground that no open ended bid is liable to be | | | |
| | | |
| entertained. He further argued that the Court cannot make a | | | |
| | | |
| contract between the parties by treating the offer of the | | | |
| | | |
| Respondent No.1 as matched with the revised minimum wage | | | |
| | | |
| calculation. He further argued that a Mandamus cannot be | | | |
| issued to straightaway award th | | | e tender to a person who does |
| | | ditions of the tender. |
| not conform to the essential con | | | |
| | | |
| 11. | | Countering these submissions, Shri Shyam Divan, | |
| | | |
learned senior counsel appearing on behalf of Respondent
JUDGMENT
No.1, has argued that it is an admitted fact that the revised
figure of minimum wage was never disclosed to either of the
parties and this being so, the judgment under appeal is correct.
He also stated that though the High Court did not find
malafides, yet it went out of its way to comment on the secret
manner in which the Labour Department re-fixed the minimum
wage at Rs.2,91,00,000/-, which is only one lakh above the
9
Page 9
Appellant’s figure of Rs.2,92,00,000/- and that, therefore, the
said non-transparent process rendered the decision of the
Government to award the tender to the Appellant as bad in law.
| |
| He further argued that if the offer of the Respondent No.1 was | |
| |
| treated as matching with the revised minimum wage calculation, | |
| |
| the State will benefit by an amount of Rs.1 lakh and that this | |
| |
| was well within the discretion of the High Court while exercising | |
| jurisdiction under Article 226 of the Constitution.<br>12. Having heard learned counsel for the parties, we agree | |
| |
| with Shri Raval’s contention th | at Respondent No.1’s bid was |
| |
| contrary to the terms of the tend | |
| 13. | | First and foremost, under tender condition 2.5.5, |
|---|
commercial bids have to strictly conform to the format provided
JUDGMENT
in Annexure 2 of the tender document. Annexure 2 which
contains the format for the price bid makes it clear that the
salary paid to deployed manpower should not be less than the
minimum wage. It further goes on to state in paragraph 3
thereof that if the component of salary quoted is less than the
minimum wage prescribed, the bid is liable to be rejected. On
this ground alone, Respondent No.1‘s bid is liable to be
10
Page 10
rejected inasmuch as, vide its letter dated 3.9.2015,
Respondent No.1 stuck to its original figure of Rs.2,77,68,000/-
which is way below the minimum wage fixed by the
| |
| Government. Secondly, Shri Raval is also right in stating that | |
| |
| the without prejudice offer of Rs.3,00,92,346/- is an offer which | |
| |
| is not fixed, but open ended. This is clear from the fact that it | |
| |
| was up to the Government then to pick up either figure by way | |
| |
| of acceptance. This is clearly interdicted by clause 2.5.6 of the | |
| |
| tender which states that prices quoted by the bidder have to be | |
| fixed, and no open ended bid | can be entertained, the same |
| |
| being liable to be rejected st | raightaway. Such condition is |
| |
| obviously an essential condition | of the tender which goes to the |
| eligibility of persons who make offers under the tender. | |
| eligibility of persons who make offers under the tender. | |
| 14. | | JUDGMENT<br>Unfortunately, even though the High Court noticed the |
|---|
open ended nature of Respondent No.1’s bid, it went on to add
that the offer of Respondent No.1 shall be treated as matching
with the revised minimum wage calculation and that it is
nowhere envisaged by the tender conditions that rejection of an
offer which may have the potential of causing loss to the
tenderer is present. It is not for the High Court to revisit a
11
Page 11
condition contained in Annexure 2 read with 2.5.5 of the tender
in the manner aforesaid. Once the tender condition states that
the tender must strictly conform to the format provided in
| | | | |
| Annexure 2, and Annexure 2 in turn | | | | clearly states that if the |
| | | | |
| component of salary quoted is less than the minimum wage | | | | |
| | | | |
| prescribed, the bid is liable to be rejected, and the High Court | | | | |
| | | | |
| cannot hold otherwise. The High Court’s further finding that | | | | |
| | | | |
| Respondent No.1’s offer was “clear” is wholly incorrect. It was | | | | |
| | | | |
| a without prejudice offer which muddied the waters and | | | | |
| rendered the price quoted by t | | | he bidder as variable and not | |
| fixed. | | | | |
| 15. | | The law is settled that an essential condition of a tender | | |
| | | | |
| has to be strictly complied with. In | Poddar Steel Corpn. v. |
|---|
| JUDG<br>Ganesh Engineering Works, | MENT<br>(1991) 3 SCC 273, this Court |
|---|
held as under:-
“… The requirements in a tender notice can be
classified into two categories — those which lay
down the essential conditions of eligibility and the
others which are merely ancillary or subsidiary with
the main object to be achieved by the condition. In
the first case the authority issuing the tender may
be required to enforce them rigidly. In the other
cases it must be open to the authority to deviate
from and not to insist upon the strict literal
12
Page 12
compliance of the condition in appropriate cases….”
[para 6]
16. Similarly in B.S.N. Joshi & Sons Ltd. v. Nair Coal
“…( i ) if there are essential conditions, the same
must be adhered to;
( ii ) if there is no power of general relaxation,
ordinarily the same shall not be exercised and the
principle of strict compliance would be applied
where it is possible for all the parties to comply with
all such conditions fully;
( iii ) if, however, a deviation is made in relation to all
the parties in regard to any of such conditions,
ordinarily again a power of relaxation may be held
to be existing;
( iv ) the parties who have taken the benefit of such
relaxation should not ordinarily be allowed to take a
different stand in relation to compliance with another
part of tender contract, particularly when the was
also not in a position to comply with all the
conditions of tender fully, unless the court otherwise
finds relaxation of a condition which being essential
in nature could not be relaxed and thus the same
was wholly illegal and without jurisdiction;
JUDGMENT
( v ) when a decision is taken by the appropriate
authority upon due consideration of the tender
document submitted by all the tenderers on their
own merits and if it is ultimately found that
successful bidders had in fact substantially
complied with the purport and object for which
essential conditions were laid down, the same may
not ordinarily be interfered with; …” [para 66]
13
Page 13
| 17. | | We also agree with the contention of Shri Raval that the |
|---|
writ jurisdiction cannot be utilized to make a fresh bargain
between parties.
| | |
| 18. In General Assurance Society Ltd. V. Chandmull<br>Jain, (1996) 3 SCR 500, this Court, in a slightly different<br>context, stated: | | |
| “In other respects there is no difference between a<br>contract of insurance and any other contract except<br>that in a contract of insurance there is a requirement<br>of uberrima fides i.e. good faith on the part of the<br>assured and the contract is likely to be<br>construed contra proferentem that is against the<br>company in case of ambiguity or doubt. A contract is<br>formed when there is an unqualified acceptance of<br>the proposal. Acceptance may be expressed in<br>writing or it may even be implied if the insurer<br>accepts the premium and retains it. In the case of<br>the assured, a positive act on his part by which he<br>recognises or seeks to enforce the policy amounts<br>to an affirmation of it. This position was clearly<br>JUDGMENT<br>recognised by the assured himself, because he<br>wrote, close upon the expiry of the time of the cover<br>notes that either a policy should be issued to him<br>before that period had expired or the cover note<br>extended in time. In interpreting documents relating<br>to a contract of insurance, the duty of the court is to<br>interpret the words in which the contract is<br>expressed by the parties, because it is not for the<br>court to make a new contract, however reasonable,<br>if the parties have not made it themselves. Looking<br>at the proposal, the letter of acceptance and the<br>cover notes, it is clear that a contract of insurance | |
14
Page 14
under the standard policy for fire and extended to
cover flood, cyclone etc. had come into being.”
| 19. | | In the light of the aforesaid judgment, the High Court was |
|---|
| not correct in treating Respondent No.1’s offer as matching with | | | | |
|---|
| | | | |
| the revised minimum wage calculation, as that would make a | | | | |
| | | | |
| new contract between the parties that the parties have not | | | | |
| made themselves. | | | | |
| 20. | | It is also well to remember the admonition given by this | |
| Court in Michigan Rubber (India) Limited v. State of | | | | |
| Karnataka and Others, (2012 | | | | ) 8 SCC 216 in cases like the |
| present, as under:-<br>“In Jagdish Mandal v. State of Orissa, [(2007) 14<br>SCC 517], the following conclusion is relevant: | | | | |
“ 22 . Judicial review of administrative action
is intended to prevent arbitrariness,
irrationality, unreasonableness, bias and
mala fides. Its purpose is to check whether
choice or decision is made ‘lawfully’ and not
to check whether choice or decision is
‘sound’. When the power of judicial review is
invoked in matters relating to tenders or
award of contracts, certain special features
should be borne in mind. A contract is a
commercial transaction. Evaluating tenders
and awarding contracts are essentially
commercial functions. Principles of equity
and natural justice stay at a distance. If the
JUDGMENT
15
Page 15
| decision relating to award of contract is bona<br>fide and is in public interest, courts will not,<br>in exercise of power of judicial review,<br>interfere even if a procedural aberration or<br>error in assessment or prejudice to a<br>tenderer, is made out. The power of judicial<br>review will not be permitted to be invoked to<br>protect private interest at the cost of public<br>interest, or to decide contractual disputes.<br>The tenderer or contractor with a grievance<br>can always seek damages in a civil court.<br>Attempts by unsuccessful tenderers with<br>imaginary grievances, wounded pride and<br>business rivalry, to make mountains out of<br>molehills of some technical/procedural<br>violation or some prejudice to self, and<br>persuade courts to interfere by exercising<br>power of judicial review, should be resisted.<br>Such interferences, either interim or final,<br>may hold up public works for years, or delay<br>relief and succour to thousands and millions<br>and may increase the project cost manifold.<br>Therefore, a court before interfering in<br>tender or contractual matters in exercise of<br>power of judicial review, should pose to itself<br>the following questions: | |
|---|
| JUDGMENT<br>(i) Whether the process adopted or<br>decision made by the authority is mala fide<br>or intended to favour someone; | |
| OR | |
| Whether the process adopted or decision<br>made is so arbitrary and irrational that the<br>court can say: ‘the decision is such that no<br>responsible authority acting reasonably and<br>in accordance with relevant law could have<br>reached’; | |
| (ii) Whether public interest is affected. | |
16
Page 16
| | | | If the answers are in the negative, there<br>should be no interference under Article 226.<br>Cases involving blacklisting or imposition of<br>penal consequences on a tenderer/<br>contractor or distribution of State largesse<br>(allotment of sites/shops, grant of licences,<br>dealerships and franchises) stand on a<br>different footing as they may require a higher<br>degree of fairness in action.”[Para 21] | | | |
|---|
| | | | | | | |
| | | | | | | |
| 21. | | We have seen that the present tender has not gotten off | | | | |
| | | | | | | |
| the ground since May 2015, and one year’s precious time has | | | | | | |
| | | | | | | |
| been wasted due to litigation between the parties. We must | | | | | | |
| hasten to add that the Government of Gujarat is partly to blame | | | | | | |
| | | | | | | |
| for this inasmuch as it arrived at | | | | a minimum wage figure and did | | |
| | | | | | | |
| not disclose the same to the te | | | | ndering parties twice. Even in | | |
| | | | | | | |
| the second round of litigation, the Government did not disclose | | | | | | |
| | | | | | | |
the newly arrived at minimum wage figure of Rs.2,91,00,000/-
JUDGMENT
to the two persons in the fray before us. Ordinarily, therefore,
we would have asked the Government to disclose the second
figure of minimum wage and restart the tendering process.
However, we do not think that the justice of the case requires
us to do so, for two reasons. First and foremost, Respondent
No.1 before us has clearly violated the strict terms of the tender
condition on every occasion and hence cannot be given relief.
17
Page 17
And, secondly, we already find that due to litigation the present
tender has not taken off for over one year. In the absence of
malafides, and indeed the High Court judgment has found that
| |
| malafides did not vitiate the calculation of minimum wage by the | |
| |
| Labour Department, we cannot accept Shri Divan’s submission | |
| |
| that the figure of Rs.2,91,00,000/- was tailor made to suit the | |
| |
| bid offered by the Appellant herein. We, therefore, set aside the | |
| |
| decision of the Gujarat High Court and allow the Government to | |
| |
| proceed further in finalizing the tender in favour of the Appellant | |
| herein. The appeal is, accordin | gly, allowed with no order as to |
| costs. | |
JUDGMENT
……………………J.
New Delhi; (R.F. Nariman)
July 26, 2016