Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
K. P. POULOSE
Vs.
RESPONDENT:
STATE OF KERALA & ANR.
DATE OF JUDGMENT21/04/1975
BENCH:
GOSWAMI, P.K.
BENCH:
GOSWAMI, P.K.
ALAGIRISWAMI, A.
BHAGWATI, P.N.
CITATION:
1975 AIR 1259 1975 SCR 214
1975 SCC (2) 236
CITATOR INFO :
D 1989 SC 606 (8)
ACT:
Arbitration Act, s. 30 (a)-Scope of.
HEADNOTE:
For the construction of three overhead reservoirs tenders
were invited. The appellant was the successful tenderer for
the work. The notification inviting tender,., gave a
description of the soils at the places of constructions.
Sometime later, however, the Research Institute of the State
Government recommended a different mode of foundation in
respect of one reservoir and the department accordingly gave
instruction to the appellant to adopt the process
recommended by the Research Institute. The appellant
executed the work in accordance with the recommendations of
the Research Institute and claimed a higher payment on the
ground that the work done by him was not included in the
original design because when he submitted his tender he
assumed the site conditions to be as represented in the
Schedule to the notification. The Department, having
refused the claim. the dispute was referred to Arbitration
under cl. 34 of the tender notification. The Chief Engineer
who was the, sole Arbitrator gave a speaking order based on
an examination of the documents.
The High Court set aside the judgment of the Subordinate
Judge and restored the order of the Arbitrator.
On appeal to this Court it was contended that the Arbitrator
was, guilty of legal misconduct in conducting the
proceedings in that the material documents were absolutely
ignored by the Arbitrator, resulting in miscarriage of
justice.
Allowing the appeal.
HELD : Under s. 30(a) of the Arbitration Act an award can be
set aside when an Arbitrator has misconducted himself or the
proceedings. Misconduct under s. 30(a) has not a
connotation of moral lapse. It Comprises legal misconduct
which is complete if the Arbitrator on the face of the award
arrives at an inconsistent conclusion even on his own
finding or arrives at a decision by ignoring very material
documents which throw abundant light on the controversy to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
help a just and fair decision. It is in this sense that the
Arbitrator has misconducted the proceedings in this case.
In the instant case the two documents which the Arbitrator
failed to consider were material documents to arrive at a
just and fair decision to resolve the controversy between
the Department and the appellant. In the background of the
controversy in this case even if the Department did not
produce these documents before the Arbitrator it was
incumbent upon him to get hold of all the relevant documents
including those two documents for the purpose of a just
decision. The award, therefore, suffers from a manifest
error apparent ex facie. [218ABC]
JUDGMENT:
CIVIL APPELLATE JURISDICTION CIVIL APPEAL No. 1485 OF 1974
Appeal by special leave from the judgment and decree dated
29-1-73 of the Kerala High Court in A.S. No. 357 of 1972.
S.V. Gupte, C. J. Balakrishnan and A. S. Nambiar, for
the appellant.
215
T. S. Krishnamurthy Iyer anti K. R. Nambiar, for the
respondents.
The Judgment of the Court was delivered by
GOSWAMI, J.--This is an appeal by special leave against the
judgment of the Kerala High Court setting aside the judgment
of the Subordinate Judge, Ernakulam and restoring the award
of the Arbitrator who had earlier refused the claim of the
appellant.
The appellant (briefly the contractor) was a successful
tenderer for construction of three zonal R.C.C. Overhead
Reservoirs, two in Matencherry and one in Cochin, in
connection with the Ernakulam Mattencherry Water Supply
Scheme. In the schedule annexed to the notification
inviting tenders under the heading ’Site’, it was stated
that "the soil at the site for Reservoir No. 1 and Reservoir
No. 2 is loose clay and for Reservoir No. 3, sandy". The
tenderer was to execute an agreement on a stamped paper
before commencing work. It appears later on the Kerala
Engineering Research Institute, Poochi. Soil Mechanics and
Foundation Division (briefly the Research Institute) submit-
ted a report (Ext. P. 10 dated September 14, 1965) that the
sub-soil at the three places chosen as sites for the
reservoirs upto 16 in showed that the top soil was sand, the
middle layer clay, and the bottom layer, silty sand or sand.
It was stated that the clay found at the three places was of
a highly compressible nature and hence pile foundation was
preferable and that as the top strata was sandy, jetting had
to be resorted to for driving the piles through this strata.
After receipt of the opinion of the Research Institute,
respondent No. 2 (hereinafter to be described as the
Department) gave instructions to the contractor to adopt the
process of jetting for driving piles for the tank at
Thoppumpady which is alone in dispute in this case. On
October 7, 1965, the Chief Engineer after scrutinising the
pile design of the contractor wrote to him, inter alia, as
follows :
"The piles as per design submitted with raft
like cap may be adapoted for tank at
Thoppumpady where the length of pile suggested
by the research division is in the region of
30 ft................ Jetting has to be
resorted to in the top strata where sandy
layer is met with.... Your statement that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
piles of more than 30 ft. length is very
difficult to be driven in Ernakulam is not
quite convincing to the Department.
Any how a decision will be taken on this only
after ascertaining the details regarding the
practical difficulties if any from agencies
actually engaged in such type of works in the
locality.
Meanwhile you may please execute the agreement
and start the work on the Reservoir at
Thoppumpady receiving further instructions
from Executive Engineer, Public Health,
Alwaye" (Ext. P. 1).
On February 21, 1966, the contractor wrote to the Executive
Engineer informing him that as per instructions of the
Research Institute and
10 SC/75-15.
216
site conditions he provided jetting arrangements for driving
the piles although the process of jetting was not included
in his tender. He enclosed the details of expenditure on
that account and mentioned that for the pile casting he used
extra reinforcement for additionally strengthening the head
of piles due to the site, condition. He pointed out that
this was not included in his original design. The sum and
substance of the contractor’s grievance was that he assumed
the site condition to be as represented in the schedule to
the notification inviting tenders and submitted his original
design on that basis and since, however, the site condition
was found to be different and on the advice of the Research
Institute jetting had to be resorted to involving extra
expenditure he was entitled to claim additional amount for
the work of jetting. The Department, however, refused the
claim which led to the arbitration under; clause 34 of the
tender notification. The Arbitrator was the Chief Engineer.
It appears the award was based on examination of documents
and after hearing arguments of the parties.
The award with which we are concerned is a speaking one and
gives the reasons for the decision against the contractor.
Mr. Gupte, the learned counsel for the appellant submits
that the Arbitrator was guilty of legal misconduct in
conducting the proceedings. He submitted that two very
material documents, Exts., P. 11 and P. 16, were absolutely
ignored by the Arbitrator resulting in miscarriage of
justice. On the other hand Mr. Krishnamurthy Iyer submitted
that these documents were not even marked before the
Arbitrator; they were marked only before the Subordinate
Judge. According to him, therefore, there is no foundation
for the grievance.
We have been taken through all the relevant documents by the
learned counsel for both sides and we are satisfied that
Ext. P. 11 and Ext. P. 16 are material documents to arrive
at a just and fair decision to resolve the controversy
between the Department and the contractor. In the
background of the controversy in this case even if the
Department did not produce these documents before the
Arbitrator it was incumbent upon him to get hold of all the
relevant documents including Exts. P. 11 and P. 16 for the
purpose of a just decision. Ext. P. 1 1 dated September 8,
1966, is a communication from the Superintending Engineer to
the Chief Engineer with regard to the objections raised by
Audit in connection with the construction of the reservoirs.
The following extract will explain the position then taken
by the Department:-
"The contention of the Accountant General that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
jetting was resorted to by the contractor to
facilitate the driving of the piles is not
correct. Had it not been for jetting, it
would not have been possible for the piles to
reach the required depth of 30’, passing
through sandy strata and we would have been
constrained to stop with a smaller depth viz.,
upto the point of refusal for penetration of
the pile by hammering. It was, therefore, in
the interest
217
of the work that jetting was insisted upon by
the Department for pile driving. The
contractor had to resort to jetting under
instructions from the Department.
The Accountant General has stated that the
department is not bound to pay extra for
adopting the method of jetting for pile
driving. This does not appear correct since
the method of jetting was adopted in the
interest of the department in view of the
sandy stratum obtaining at the site as against
the indication given by the department that
the soil is clayey upto a depth of nearly 200
ft. No doubt, the contractor was asked to
ascertain the nature of the soil; but this
does not imply that he was to conduct
exploratory borings to confirm the
classification given by the department in the
tender within the short span of time available
for submitting tenders".
Earlier also on July 25, 1966, as per Ext. P. 16 the
Executive Engineer had written to the Chief Engineer
wherefrom paragraph 4 is revealing
"Even though while inviting tenders for the
work there was a condition that the tenderer
should examine the soil condition it was not
expected, of them to do soil testing in detail
within the period available to them to tender
for the work. A clear indication regarding
the nature of the strata that is likely to be
met with was also furnished at the time of
inviting tenders. After complete ,oil
investigation the strata was found to be
different from that furnished by the
department and so in my opinion technical
specification has changed. In the
circumstances jetting clone by the contractor
can be considered as an extra item".
We now come to the Award. Although the Arbitrator has held
that "jetting, however, is not an authorised extra covered
by the agreement", he has made the following significant
observation which is inconsistent with his conclusion that
the contractor has no right for extra payment for the
jetting :
"The Chief Engineer has rejected the claims of
the ’contractor on grounds of non-inclusion of
this (jetting) in the agreement which was
executed subsequent to the direction issued by
the department to adopt jetting. The Chief
Engineer’s decision totally ignores the next
sentence in that letter ’Meanwhile you may
execute the agreement’. By this sentence the
issue of extra payment for jetting is left
open even after the execution of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
agreement".
If the above is the conclusion of the Arbitrator, rejection
of the claim on the ground that "jetting, however, is not an
authorised extra covered by the agreement" cannot be
anything but rationally inconsistent. The award, therefore,
suffers from a manifest error apparent ex facie.
218
Under section 30(a) of the Arbitration Act an award can be
set aside when an Arbitrator has misconducted himself or the
proceedings. Misconduct under section 30(a) has not a
connotation of moral lapse. It comprises legal misconduct
which is complete if the Arbitrator on the face of the award
arrives at an inconsistent conclusion even on. his own
finding or arrives at a decision by ignoring very material
documents which throw abundant light on the controversy to
help a just and fair decision. It is in this sense that the
Arbitrator has misconducted the proceedings in this case.
We have, therefore, no hesitation in setting aside such an
award. In the result the judgment of the High Court is set
aside and that of the Subordinate Judge is restored. The
award of the Arbitrator thus stands quashed. The Arbitrator
will complete the proceedings after considering all the
relevant documents including Ext. P. 11 and Ext. P. 16
after giving opportunity to the parties. The appeal is
allowed with costs.
P.B.R. Appeal allowed.