Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
2023INSC850
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1968 OF 2012
BATLIBOI ENVIRONMENTAL ENGINEERS
LIMITED
.....
APPELLANT
VERSUS
HINDUSTAN PETROLEUM CORPORATION
LIMITED AND ANOTHER
.....
RESPONDENTS
J U D G M E N T
SANJIV KHANNA, J.
This appeal by way of special leave by Batliboi Environmental
1
Engineers Limited takes exception to the judgment dated
02.11.2007, whereby the Division Bench of the High Court of
2
Judicature at Bombay allowed the appeal filed by Hindustan
3
Petroleum Corporation Limited under Section 37 of the Arbitration
4
and Conciliation Act, 1996 , and thereby has set aside the arbitral
award dated 23.03.1999.
Signature Not Verified
1
For short, BEEL.
2
Appeal No. 227 of 2001 in Arbitration Petition No. 280 of 1999.
3
For short, HPCL.
4
For short, A&C Act.
Digitally signed by
SWETA BALODI
Date: 2023.09.21
17:25:51 IST
Reason:
C.A. No. 1968 of 2012 Page 1 of 50
2. On acceptance of tender and in terms of the letter of intent dated
27.02.1992, HPCL had awarded to BEEL the turnkey contract for
detailed engineering including civil and structural design, supply
and erection, testing and commissioning of 23 MLD capacity
Sewage Water Reclamation Plant in Mahul Refinery area. The
contract value was Rs.574.35 lakhs. The contract period was 18
months from the date of letter of intent, and accordingly the work
was to be completed by 28.08.1993. There was delay in
completion. On written requests/applications made by BEEL, the
time for completion was extended on two occasions. Three
revisions were also issued by HPCL. The last revision dated
20.09.1994 had extended the period for completion from
26.09.1994 by 10 months beginning from the date on which
approval of electrical items was accorded by HPCL. BEEL carried
on the work till 30.03.1996. Thereafter, BEEL abandoned the work.
It is an accepted position that as on 30.03.1996, 80% of the work
was complete.
3. On 04.07.1996, BEEL made a formal claim to HPCL for breach of
contract on account of delay in execution, causing extra expenses
and losses. By the letter dated 16.05.1997, BEEL sought an
advance payment of Rs.50 lakhs to enable them to resume work,
C.A. No. 1968 of 2012 Page 2 of 50
and simultaneously expressed its desire to resolve the dispute
through conciliation. BEEL by the same letter also invoked the
arbitration clause in the contract, if the proposal as given by BEEL
was unacceptable to HPCL. HPCL by the letter dated 05.05.1997
refused to make payment, and relying on the terms of the contract
had impressed upon BEEL to resume and complete the remaining
work, even if the matter was to proceed for arbitration. BEEL did
not agree and resume work.
4. The General Manager (Project), Mahul Refinery, HPCL, appointed
Mr. K. Narayanan as the sole arbitrator to adjudicate upon the
disputes and differences in the execution of the contract. Claim was
filed by BEEL and reply/counter claim was filed by HPCL, to which
rejoinder with supporting documents and sur-rejoinders were filed.
In all about 14 hearings were held before the arbitral tribunal
between the period 12.03.1998 and 07.01.1999 and oral arguments
were addressed. Ocular evidence was not led. The learned
arbitrator had conducted a site inspection on 24.12.1997.
5. The arbitral award dated 23.03.1999, substantially allows the
Claims Nos. 1,2, and 4 of the BEEL. The relevant portion of the
award dealing with the claims of the BEEL, reads:
C.A. No. 1968 of 2012 Page 3 of 50
“ A. Claims of the Claimants:
Claim No.1 – Compensation for loss of
Overhead and profit and also profitability:
Rs.3,38,38,460.00
The claim is forwards loss of Overheads and
profit/profitability calculated on the basis of 48
months delay as of 27.08.1997. The Claimants
have considered 10% of the Contract value
towards Overheads and another 10% towards
profit/profitability to arrive at the above figure, after
taking into account the same percentages from the
payments already received by them.
My finding is that the Owner Respondents are fully
responsible for the huge delay that occurred by not
taking proper and timely action in removing the
various impediments and obstacles that stood in
the way of completing the project in the given span
of 18 months. The party had been tied down to a
project, which was allowed to drift aimlessly, with
the owner-respondents showing hardly any
interest in completing it in time.
Even the basic approval for the Electrical scheme,
with numerous revisions was kept pending, till the
end without any decision. The Claimants could not
have expected to complete the project without
these clearances. The Respondents have thus
evaded their own responsibilities and committed
breach of contractual obligations.
As admitted by the Respondents, even the
arrangement with MCGB for the supply of Sewage
water for purification has not yet been finalised.
This, as advised by the Respondents, is awaiting
the intervention of the Chief Minister. It is any
body’s guess when this arrangement will be firmed
up the necessary pumping station and
underground pipelines etc. will be ready so that
C.A. No. 1968 of 2012 Page 4 of 50
sewage water will flow to the plant being built for
purification by the claimant. This is proof that the
Respondents were not serious enough in
implementing the project.
For reasons given above, I consider that the
claimants are legitimately entitled for
compensation towards both loss of Overheads
and profit/profitability. In arriving at the
compensation, the period upto 30.03.1996, when
the claimants discontinued the work is being
considered. The total period works out to 49
months. The original contract period being 18
months, the extended period comes to 31 months.
The claimants had stated in their claim statement
that they had provided for 22 months overheads in
their estimate. I am allowing 3 months for internal
administrative process of the Owner-Respondents
and for unforeseen delays such as strike, red
alerts etc. I also consider 10% of contract value
towards loss of overheads and 10% towards loss
of profit/profitability as reasonable. On these (sic)
basis, the Compensation works out to
Rs.78,68,833.00 towards loss of overheads and
an equal amount of Rs.78,68,833.00 towards loss
of profit/profitability, the total being
Rs.1,57,37,666.00 after taking into account the
same percentage from payments already received
by them for the work done. I award this amount to
the Claimants.
While awarding the above compensation, the
existence of the means to mitigate the loss has
been considered. According to me, the only means
available to the claimants, was to work on
Sundays and Holidays, to make up for the lost time
to some extent, which was denied by the
Respondents except for a brief period at the very
end. This brief relaxation was not of much
significance in determining the compensation
payable to the claimants.
C.A. No. 1968 of 2012 Page 5 of 50
| (i) | Transportation of excavated earth | Rs.12,05,000.00 |
|---|---|---|
| (ii) | Dewatering charges incurred during<br>delayed period | Rs.5,62,570.00 |
| (iii) | Shifting charges for material | Rs.1,01,405.00 |
| (iv) | Shifting charges for Filter media | Rs.31,250.00 |
C.A. No. 1968 of 2012 Page 6 of 50
| Item No.I | Rs.1,20,000.00 towards transportation of excavated earth<br>dumped by other contractors in the work site, prior to<br>award of contract but after submission of the offer. |
|---|---|
| Item No.II | Nil amount |
| Item No. III | Rs.50,000.00 towards shifting of materials manually<br>because of non-availability of approach to site for vehicle. |
| Item No.IV | Rs.25,000.00 towards charges for shifting the Filter Media<br>Several times for paucity of space. |
for liquidated damages of Rs.57.40 lakhs, on the ground that the
C.A. No. 1968 of 2012 Page 7 of 50
delay was caused by omissions and commissions of HPCL. Claims
by HPCL for rectification/rehabilitation cost of Rs.102.05 lakhs,
costs of balance work of Rs.160 lakhs and de-watering cost of Rs.9
lakhs were denied on the ground that they relate to future works
and therefore, would not fall within the ambit of arbitration in
question.
7. We have intentionally quoted the entire findings and reasoning
accorded by the learned arbitrator, while allowing the Claim Nos.
1,2 and 4 of BEEL. The first egregious and obvious flaw in the
award is, the omnibus finding and conclusion that HPCL (referred
to as the owner and the respondent in the quoted portion of the
award) was fully responsible for the inordinate delay that had
occurred by not taking proper and timely action in removal of
various impediments and obstacles that stood in the way of
completing the project within the stipulated period of 18 months.
This finding, in our opinion, is bereft of analysis and examination of
facts and contentions. The relevant and material facts and the
respective stances of the parties are neither decipherable nor
evaluated and no reason has been given for arriving at the
conclusion. A conclusion without any discussion and reasons, is
non-compliant and violates the mandate of sub - section (3) of
C.A. No. 1968 of 2012 Page 8 of 50
5
Section 31 of the A& C Act , an aspect we would examine
subsequently.
8. The second patent error relates to the computation and award of
10% of the contract value towards loss of overheads and another
10% towards loss of profits/profitability. The two amounts have
been quantified at Rs.78,68,833/- each. Thus, Rs.1,57,37,666/- has
been awarded and held as payable by HPCL to BEEL. The award
is deficient being completely silent as to the method and the manner
in which the arbitral tribunal has computed the figures. Therefore, it
leaves us and the parties to wonder the basis for awarding and
computing the amounts. We are not commenting or examining the
merits of the computation, but complete absence of any justification
and reason to allow the claim and quantification of the sum
awarded. We would subsequently examine the chart furnished by
BEEL in support of the said computation, albeit at this stage we
would like to highlight the apparent contradiction in the award,
which is the third ground to uphold the decision of the Division
Bench of the High Court.
9. We begin our substantiation of the third ground, by referring to the
5
Section 31 - Form and contents of arbitral award - (3) The arbitral award shall state the reasons upon
which it is based, unless—
(a) the parties have agreed that no reasons are to be given, or
(b) the award is an arbitral award on agreed terms under section 30.
C.A. No. 1968 of 2012 Page 9 of 50
first paragraph of the award quoted above, under the heading
‘Claim No. 1 - Compensation for loss of overhead and profit and
also profitability’. BEEL had based Claim No.1 for loss on account
of overheads and profits/profitability upon 48 months delay as on
27.08.1997. BEEL for computation had considered 10% of the
contract value towards overheads and other 10% towards
profits/profitability for arriving at the figure of Rs. 3,38,38,460/-, after
taking into “account the same percentages from the payments
already received by them”. In the subsequent portion of the award,
dealing with Claim No. 1, the learned arbitrator has held that the
total contract period was 49 months. The original contract period
being 18 months, the extended period being 31 months. However,
BEEL in the claim statement had accepted that it had provided for
22 months towards overheads in the estimates. Further, the learned
arbitrator has allowed additional 3 months for internal administrative
process, and for unforeseen delays, such as strikes, red alerts, and
as force majeure events. In other words, the learned arbitrator, for
the purpose of default, had excluded the period of 18 months, i.e.,
the original contract period, plus 4 months as provided by BEEL,
and another 3 months on account of internal administrative process
and force majeure events. Thus, the default period for which BEEL
as per the award is entitled to claim damages/compensation
C.A. No. 1968 of 2012 Page 10 of 50
towards overheads and loss of profits/profitability is 24 months.
10. BEEL had, as observed above, accepts the position that the loss
towards overheads and profits/profitability has to be arrived at by
applying the percentage formula, variant with the execution of the
work. Thus, in our opinion, the loss towards overheads and
profits/profitability is to be computed on the payments due for the
un-executed work, and should exclude the payments
received/receivable for the work executed. In other words, based
on the value of the work executed by BEEL, the proportionate
amount has to be reduced for computing the
damage/compensation as a percentage of expenditure on
overheads, and damages for loss of profit/profitability. Damages
towards expenditure on overheads and loss of profit are
proportionate, and not payable for the work done and paid/payable.
Delay in payment on execution of the work has to be compensated
separately.
11. It is an accepted position and specifically recorded in the award that
the total value of the contract was Rs. 5,74,35,213.00p. In an earlier
paragraph of the award, which has been not reproduced, the
learned arbitrator has referred to R.A. Bill No.4 dated 31.08.1993,
as per which BEEL had completed work of Rs.1,21,95,859.68p. It
is also an accepted and admitted position that as on 30.03.1996,
C.A. No. 1968 of 2012 Page 11 of 50
the date on which the work stopped, as per R.A. Bill No. 37, work
valued at Rs. 2,92,07,619.13p had been executed. In other words,
BEEL had executed and received payments of Rs. 2,92,07,619.13/-
from HPCL from time to time, between the period 01.09.1993 and
30.03.1996. Eighty percent of the work was complete. BEEL has
received total payment of Rs.4,14,03,478.81p in terms of running
account bills till R.A. No. 37. The balance work was Rs.
1,14,87,042.00p. Twenty percent of Rs.1,14,03,478.81 is
Rs.22,97,408.40p. In addition, BEEL is entitled to compensation for
the delay in execution of the work of Rs.2,92,07,619.13/- till the date
payments were made, albeit , the award directs payment of Rs. 18%
interest per annum on all claims awarded effective from
16.05.1997.
12. The award also reduces the performance bank guarantee amount
by 50%, without any discussion, elucidation and reason.
13. In order to justify the computation made in the award and also the
principle or the method adopted by the arbitral tribunal, BEEL has
referred to the Hudson’s formula and relied upon judgments of this
Court in McDermott International Inc. v. Burn Standard
6
Company Limited and Others. , and Associate Builders v. Delhi
6
(2006) 11 SCC 181 (for short, McDermott International Inc.).
C.A. No. 1968 of 2012 Page 12 of 50
7
Development Authority , in addition to an earlier decision of this
8
Court in A.T Brij Paul Singh and Others v. State of Gujarat , and
a few judgments of the High Courts.
14. In McDermott International Inc. this Court has referred to various
methods of computation of damages in paragraphs 102 to 107. In
particular, reference has been made to Hudson’s formula, Emden’s
formula, and Eichleay’s formula in the following terms:
“ Method for computation of damages
102 . [Ed.: Para 102 corrected vide Official
Corrigendum No. F.3/Ed.B.J./52/2006 dated 31-7-
2006] . What should, however, be the method of
computation of damages is a question which now
arises for consideration. Before we advert to the
rival contentions of the parties in this behalf, we
may notice that in M.N. Gangappa v. Atmakur
Nagabhushanam Setty & Co. [(1973) 3 SCC 406]
this Court held that the method used for
computation of damages will depend upon the
facts and circumstances of each case.
102-A . In the assessment of damages, the court
must consider only strict legal obligations, and not
the expectations, however reasonable, of one
contractor that the other will do something that he
has assumed no legal obligation to do.
(See Lavarack v. Woods of Colchester
Ltd. [(1967) 1 QB 278 : (1966) 3 All ER 683 :
(1966) 3 WLR 706 (CA)] , All ER p. 690 G.)
7
(2015) 3 SCC 49 (for short, Associate Builders).
8
(1984) 4 SCC 59.
C.A. No. 1968 of 2012 Page 13 of 50
103 . The arbitrator quantified the claim by taking
recourse to the Emden Formula. The learned
arbitrator also referred to other formulae, but, as
noticed hereinbefore, opined that the Emden
Formula is a widely accepted one.
104 . It is not in dispute that MII had examined one
Mr D.J. Parson to prove the said claim. The said
witness calculated the increased overheads and
loss of profit on the basis of the formula laid down
in a manual published by the Mechanical
Contractors Association of America entitled
“Change Orders, Overtime, Productivity”
commonly known as the Emden Formula. The said
formula is said to be widely accepted in
construction contracts for computing increased
overheads and loss of profit. Mr D.J. Parson is said
to have brought out the additional project
management cost at US$ 1,109,500. We may at
this juncture notice the different formulas
applicable in this behalf.
(a) Hudson Formula: In Hudson's Building and
Engineering Contracts, Hudson Formula is stated
in the following terms:
“Contract head
office overhead and
profit percentage
× Contract
sum
Contract
period
× Period
of
delay”
In the Hudson Formula, the head office overhead
percentage is taken from the contract. Although
the Hudson Formula has received judicial support
in many cases, it has been criticised principally
because it adopts the head office overhead
percentage from the contract as the factor for
calculating the costs, and this may bear little or no
relation to the actual head office costs of the
contractor.
(b) Emden Formula: In Emden's Building
Contracts and Practice, the Emden Formula is
stated in the following terms:
C.A. No. 1968 of 2012 Page 14 of 50
“Head office
overhead and
profit
× Contract
sum
× Period of
delay”
100
Contract
period
Using the Emden Formula, the head office
overhead percentage is arrived at by dividing the
total overhead cost and profit of the contractor's
organisation as a whole by the total turnover. This
formula has the advantage of using the
contractor's actual head office overhead and profit
percentage rather than those contained in the
contract. This formula has been widely applied and
has received judicial support in a number of cases
including Norwest Holst Construction
Ltd. v. Coop. Wholesale Society Ltd. [ Decided on
17-2-1998, [1998] EWHC Technology 339]
, Beechwood Development Co. (Scotland)
Ltd. v. Mitchell [ Decided on 21-2-2001, (2001)
CILL 1727] and Harvey Shopfitters Ltd. v. Adi
Ltd. [ Decided on 6-3-2003, (2004) 2 All ER 982 :
[2003] EWCA Civ 1757] .
(c) Eichleay Formula: The Eichleay Formula was
evolved in America and derives its name from a
case heard by the Armed Services Board of
Contract Appeals, Eichleay Corporation. It is
applied in the following manner:
Step 1
Contract
billings
× Total
overhead for
contract
period
= Overhead
allocable to
the contract
Total
billings for
contract
period
Step 2
Allocable overhead = Daily overhead rate
Total days of contract
Step 3
C.A. No. 1968 of 2012 Page 15 of 50
Daily
contract
overhead
rate
× Number of
days of
delay
= Amount of
unabsorbed
overhead”
This formula is used where it is not possible to
prove loss of opportunity and the claim is based on
actual cost. It can be seen from the formula that
the total head office overhead during the contract
period is first determined by comparing the value
of work carried out in the contract period for the
project with the value of work carried out by the
contractor as a whole for the contract period. A
share of head office overheads for the contractor
is allocated in the same ratio and expressed as a
lump sum to the particular contract. The amount of
head office overhead allocated to the particular
contract is then expressed as a weekly amount by
dividing it by the contract period. The period of
delay is then multiplied by the weekly amount to
give the total sum claimed. The Eichleay Formula
is regarded by the Federal Circuit Courts of
America as the exclusive means for compensating
a contractor for overhead expenses.
105 . Before us several American decisions have
been referred to by Mr Dipankar Gupta in aid of his
submission that the Emden Formula has since
been widely accepted by the American courts
being Nicon Inc. v. United States [ Decided on 10-
6-2003 (USCA Fed Cir), 331 F. 3d 878 (Fed. Cir.
2003)] , Gladwynne Construction Co. v. Mayor
and City Council of Baltimore [ Decided on 25-9-
2002, 807 A. 2d 1141 (2002) : 147 Md. App. 149]
and Charles G. William Construction
Inc. v. White [ 271 F 3d 1055 (Fed. Cir. 2001)] .
106 . We do not intend to delve deep into the
matter as it is an accepted position that different
formulae can be applied in different circumstances
and the question as to whether damages should
be computed by taking recourse to one or the
C.A. No. 1968 of 2012 Page 16 of 50
other formula, having regard to the facts and
circumstances of a particular case, would
eminently fall within the domain of the arbitrator.
107 . If the learned arbitrator, therefore, applied the
Emden Formula in assessing the amount of
damages, he cannot be said to have committed an
error warranting interference by this Court.”
9 10
15. McDermott International Inc . refers to Sections 55 and 73 of the
11
Indian Contract Act, 1872 , which deal with the effect of failure to
perform at fixed time in contracts where time is of essence, and
computation of damages caused by breach of contract,
respectively, and states that these Sections neither lay down the
9
Section 55 - Effect of failure to perform at fixed time, in contract in which time is essential - When a
party to a contract promises to do a certain thing at or before a specified time, or certain things at or
before specified times, and fails to do any such thing at or before the specified time, the contract, or
so much of it as has not been performed, becomes voidable at the option of the promisee, if the
intention of the parties was that time should be of the essence of the contract.
Effect of such failure when time is not essential.—If it was not the intention of the parties that time
should be of the essence of the contract, the contract does not become voidable by the failure to do
such thing at or before the specified time; but the promisee is entitled to compensation from the
promisor for any loss occasioned to him by such failure.
Effect of acceptance of performance at time other than that agreed upon.—If, in case of a contract
voidable on account of the promisor’s failure to perform his promise at the time agreed, the promisee
accepts performance of such promise at any time other than that agreed, the promisee cannot claim
compensation for any loss occasioned by the non-performance of the promise at the time agreed,
unless, at the time of such acceptance, he gives notice to the promisor of his intention to do so.
10
Section 73 - Compensation for loss or damage caused by breach of contract. - When a contract has
been broken, the party who suffers by such breach is entitled to receive, from the party who has broken
the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the
usual course of things from such breach, or which the parties knew, when they made the contract, to
be likely to result from the breach of it.
Such compensation is not to be given for any remote and indirect loss or damage sustained by reason
of the breach.
Compensation for failure to discharge obligation resembling those created by contract. When an
obligation resembling those created by contract has been incurred and has not been discharged, any
person injured by the failure to discharge it is entitled to receive the same compensation from the party
in default, as if such person had contracted to discharge it and had broken his contract.
Explanation - In estimating the loss or damage arising from a breach of contract, the means which
existed of remedying the inconvenience caused by the non-performance of the contract must be taken
into account.
11
For short, Contract Act.
C.A. No. 1968 of 2012 Page 17 of 50
mode nor how and in what manner computation of damages for
compensation has to be made. As computation depends upon
attendant facts and circumstances and methods to compute
damages, how the quantum thereof should be determined is a
matter which would fall within the domain and decision of the
arbitrator.
16. This is without doubt, a sound legal and correct proposition.
However, the computation of damages should not be whimsical and
absurd resulting in a windfall and bounty for one party at the
expense of the other. The computation of damages should not be
disingenuous. The damages should commensurate with the loss
sustained. In a claim for loss on account of delay in work attributable
to the employer, the contractor is entitled to the loss sustained by
the breach of contract to the extent and so far as money can
compensate. The party should to be placed in the same situation,
with the damages, as if the contract had been performed. The
principle is that the sum of money awarded to the party who has
suffered the injury, should be the same quantum as s/he would
have earned or made, if s/he had not sustained the wrong for which
12
s/he is getting compensated.
12
See - Robinson v. Harman (1848) 1 Ex 850 at 855 and Livingstone v. Rawyards Coal Co (1879-80)
L.R. 5880 cases 25
C.A. No. 1968 of 2012 Page 18 of 50
17. We shall subsequently catechise the Hudson’s formula, suffice at
this stage is to notice that the learned arbitrator does not specifically
refer to any formula or the method, and the figures to compute
damages under the head of loss on account of overheads and
profits/profitability. The award, as quoted above, does refer to
Sections 55 and 73 of the Contract Act.
18. Having examined the award and the contents, we would now like to
refer to the chart produced by BEEL by way of additional or new
material, which it is claimed, is drawn on the basis of the statement
of claims filed in the arbitration proceedings, to which the column
with the heading “explanation” has been added for the benefit of the
court. The chart is as under:
| Sr. | Particulars | Amount (Rs.) | Explanation | ||
|---|---|---|---|---|---|
| No. | |||||
| 1. | Contract Sum | 5,74,35,213.00 | Total Contract Value | ||
| 2. | Overheads (10%) and<br>profits (10%) included in<br>the above sum | 1,14,87,042.00 | 20% of Rs.5,74,35,213.00<br>(1) i.e. contract value | ||
| 3. | Time limit for completion<br>of the work | 22 Months | Though the contract was<br>for 18 Months, Petitioner<br>estimated that the site<br>would have to be<br>maintained for 22 Months<br>i.e. 4 months over and<br>above contract term. | ||
| 4. | Overheads and Profits<br>per month [(2) divided<br>by (3)] | 5,22,138.27 Per<br>month | Total Overheads and<br>Profits divided by months<br>of work (22 Months) |
C.A. No. 1968 of 2012 Page 19 of 50
| Sr. | Particulars | Amount (Rs.) | Explanation | ||
|---|---|---|---|---|---|
| No. | |||||
| 5. | Value of work done till<br>R.A. Bill No.4 dated<br>31.08.1993 | 1,21,95,859.68 | Contract period was up to<br>31.08.1993 i.e. 18 months<br>from 22 February 1992 | ||
| 6. | Pro-rata overheads and<br>profits received till<br>31.08.1993 | 24,39,171.00 | 20% of (5). Since the<br>Petitioner received<br>payment of bill at (5), the<br>overheads and profits for<br>the work done covered by<br>bill at (5) have been<br>deducted by the Arbitrator<br>in (7). | ||
| 7. | Net loss suffered as on<br>01.09.1993 [(2) – (6)] | 90,47,871.00 | As above, for 22 months<br>of work, the Petitioner<br>was to get Rs.<br>1,14,87,042.00/- (2)<br>towards overheads and<br>profits. However, out of<br>this, the Petitioner<br>received Rs.<br>24,39,171.00/- (6), the<br>same has been deducted.<br>Rs.90,47,871.00/- is the<br>outstanding receivable by<br>the Petitioner towards<br>overheads and profits for<br>the contract period. | ||
| 8. | Delay in months | 24 months | Total time spent was 49<br>Months (Pg.56 of SLP)<br>(22 February 1992 to 31<br>March 1996).<br>Out of this, since 22<br>months were<br>contemplated by the<br>Petitioner for the work, the<br>same have been<br>deducted from 49 months<br>by the Arbitrator. (Pg.56<br>of SLP). |
C.A. No. 1968 of 2012 Page 20 of 50
| Sr. | Particulars | Amount (Rs.) | Explanation | ||
|---|---|---|---|---|---|
| No. | |||||
| A further period of 3<br>months on account of<br>Force Majeure has been<br>deducted by the<br>Arbitrator.<br>Thus 49 – 22 – 3 = 24<br>Months extra work.<br>(Pg.56 of SLP). | |||||
| 9. | Overheads and profit<br>expected during the<br>extra period [(8) * (4)] | 1,25,31,318.48 | This is the amount for the<br>extra time spent i.e. 24<br>Months.<br>244 Months multiplied by<br>per month overhead and<br>profit.<br>24 * Rs.5,22,138.27 =<br>Rs. 1,25,31,318.48 | ||
| 10. | Value of work executed<br>during the extended<br>period upto 30.03.1996<br>(R.A. Bill No.37) | 2,92,07,619.13 | This is the amount<br>received for the work<br>done during extended<br>period i.e. August 1993 to<br>March 1996. | ||
| 11. | Pro-rata overheads and<br>profits received during<br>the extended period. | 58,41,523.80 | This is 20% of<br>2,92,07,619.13 (10).<br>Since the petitioner<br>received payment of bill at<br>(10), the overheads and<br>profits for the work done<br>covered by bill at (10),<br>have been deducted by<br>the Arbitrator in (11) | ||
| 12. | Net loss suffered till<br>27.08.1997 [(9) – (11)] | 66,89,791.68 | This is loss of overhead<br>and profits for the extra<br>period of 24 Months.<br>As stated in (9),<br>overheads and profits for |
C.A. No. 1968 of 2012 Page 21 of 50
| Sr. | Particulars | Amount (Rs.) | Explanation | ||
|---|---|---|---|---|---|
| No. | |||||
| extra time of 24 months<br>was Rs.1,25,31,318.48.<br>Since, the Petitioner<br>received a sum of<br>Rs.58,41,523.80 (11), the<br>same has been deducted<br>by the Arbitrator. | |||||
| 13. | Total loss on overheads<br>and profit on this count<br>till 27.08.1997 [(7) –<br>(12)] | 1,57,37,665.68 | This amount is the sum of<br>overhead and profits due<br>during contract period<br>plus the overhead and<br>profits for the extra period<br>of 24 Months.<br>Awarded by the Arbitrator<br>(Pg.56 of SLP) |
afterthought and futile finagle to work backwards to somehow justify
the computation and award of damages. These explanations are ex
facie irrational and eristic for the following reasons:
(i) S.No.7 computes the net loss suffered by BEEL as
Rs.90,47,871/-as on 01.09.1993, that is for the period of 18
months. The computation ignores and does not add the
period of 4 months as mentioned by BEEL in the claim
statement. Further, the arbitrator had added another period of
3 months for internal administrative process and force
majeure events. Thus, the date 01.09.1993 referred to in
S.No.7 is incorrect and not the basis of the computation made
C.A. No. 1968 of 2012 Page 22 of 50
in the award. S.No.7 fails to taken into consideration the
seven-month period, which as per the award has to be added.
(ii) The figure of Rs.90,47,871/- would have been relevant, in
absence of work done and in fact payments post 01.09.1993.
However, it is an accepted and admitted position that
payment of Rs.2,92,07,619.13p was made on different dates
between 01.09.1993 till 30.03.1996 upon completion of the
proportionate value of the work. Claim on account of loss of
profits/profitability and overheads, as has been explained
above and also elucidated herein-after with reference to
several judgments and treatise, is payable if and when there
is an increase in cost of off-site and on-site overheads due to
delay in completion of work post the agreed or contractual
13
period which is caused by the employer. Further, loss on
account of profit earning capacity is paid when the
contractor’s profit earning capacity is affected due to it being
retained longer in the contract in question, without
corresponding increase in the monetary benefit earned and
13
In this case, as noticed, the contract bars claims for compensation for losses due to
enhancement/escalation of costs etc. We make no comments in this regard. Interpretation and validity
of such clauses is not subject matter of this appeal. When such clauses, which are apparently one-
sided and absolve breach with immunity, are subjected to judicial scrutiny, the courts/tribunals
invariably tend to interpret the clauses in a restrictive manner to grant just and fair relief. Courts should
be slow to interfere, unless the award falls within the ambit of the parameters set out in Section 34 of
the A&C Act.
C.A. No. 1968 of 2012 Page 23 of 50
without being free to move elsewhere to earn profit which it
might otherwise be able to do. It is not the case of BEEL that
they are entitled to enhance or increase in cost on account of
delay in execution of the work. Pertinently, Claim No. 3 for
compensation of losses incurred due to increase in cost of
material and labour has been specifically rejected, as
escalation in prices/costs are barred by the terms of the
contract.
(iii) The computation of loss under S.No.7 of Rs.90,47,871/- is,
therefore, unsustainable and cannot be justified by any
calculation and in terms of the Contract Act.
(iv) As per the chart, in addition to Rs.90,47,871/-, the arbitrator
has awarded at S.No.12, a further amount of
Rs.66,89,794.68p. on account of loss of overheads and
profits for the extra period of 24 months, that is, till
27.08.1997. The figure as per S.No.12 is arrived at after
reducing pro rata overheads and profits during the extended
period as mentioned in S.No.9. The computation belies and
defies logic. It clearly amounts to double payment towards
compensation and damages, as it fails to notice that the sum
mentioned in S.No.7 of Rs. 90,47,871/- is on account of
compensation towards overheads and profits/profitability.
C.A. No. 1968 of 2012 Page 24 of 50
Therefore, 20% of the value of the unfinished work had
already been included in the computation and awarded under
S.No.7. The date 27.08.1997 is at best, an assumption of
BEEL and not mentioned anywhere or decipherable from the
award.
20. We have briefly referred to the principle applicable for computing
the claim for compensation/damages in case of partial prevention,
i.e., where the breach by the employer is not fundamental and does
not entitle the builder/contractor to cease the work, or, being
fundamental, is not treated as repudiation by the builder/contractor.
Measure of compensation/damages in such cases is the loss of
profit arising from reduced profitability or added expense of the
14
work carried out. In a given case, where there is a fundamental
breach by the employer, albeit, the builder/contractor does not
immediately elect to treat the contract as repudiated, he may still be
entitled to raise a claim for loss of profit on the uncompleted work.
Offsite expenses or overheads are all administrative or executive
costs incidental to the management supervision or capital outlay as
distinguished from operating charges. These charges cannot be
fairly charged to one stream of work or job, and rather be distributed
14 th
See Hudson’s Building Contracts (10 edn) pp 450, 596.
C.A. No. 1968 of 2012 Page 25 of 50
as they relate to the general business or the work of the
contractor/builder being undertaken or to be undertaken, as the
overheads are relatable to the builder/contractor’s business in
entirety.
21. The usage of formulae such as Hudson’s, Emden’s, or Eichleay’s
formulae to ascertain the loss of overheads and profits has been
judicially approved in the English cases of Peak Construction
15
(Liverpool) Ltd v. McKinney Foundations Limited , Whittal
16
Builders v. Chesterle-Street District Council , and JF Finnegan
17
Ltd v. Sheffield City Council and in the Canadian case of Ellis-
18
Don v. Parking Authority of Toronto . The three formulae deal
with theoretical mathematical equations, but are based on factual
assumptions, and therefore can produce three different and
unrelated compensation/damages. Therefore, while applying a
particular equation or method, the assumptions should be
examined, and the satisfaction of the assumption(s) ascertained in
the facts and circumstances.
th
22. The formula suggested by Hudson in his 10 edition of the book
Building and Engineering Contracts for the computation of
15
(1970) 1 BLR 114.
16
(1987) 40 BLR 82.
17
(1988) 43 BLR 124.
18
(1978) 28 BLR 98.
C.A. No. 1968 of 2012 Page 26 of 50
damages takes the head office and profit percentage as a
proportion of the contract value. The formula assumes that the profit
judged by the builder/contractor is in fact capable of being earned
by her/him elsewhere had the builder/contractor been free to leave
the contract at the proper time. The formula is couched on three
assumptions. First, that the contractor is not habitually or otherwise
underestimating the cost when pricing; secondly the profit element
was realistic at that time; and lastly, there was no fluctuation in the
market conditions and the work of the same general level of
profitability would be available to her/him at the end of the contract
period. Satisfaction of these assumptions should be ascertained
when we apply Hudson’s formula for computing the damages.
Material should be furnished by the claimant to justify and assure
that the assumptions for applying Hudson’s formula are met.
23. Ordinarily, when the completion of a contract is delayed and the
contractor claims that s/he has suffered a loss arising from
depletion of her/his income from the job and hence turnover of
her/his business, and also for the overheads in the form of
workforce expenses which could have been deployed in other
contracts, the claims to bear any persuasion before the arbitrator or
a court of law, the builder/contractor has to prove that there was
other work available that he would have secured if not for the delay,
C.A. No. 1968 of 2012 Page 27 of 50
by producing invitations to tender which was declined due to
insufficient capacity to undertake other work. The same may also
be proven from the books of accounts to demonstrate a drop in
turnover and establish that this result is from the particular delay
rather than from extraneous causes. If loss of turnover resulting
from delay is not established, it is merely a delay in receipt of
money, and as such, the builder/ contractor is only entitled to
interest on the capital employed and not the profit, which should be
paid. The High Court of Justice Queen’s Bench Division in the case
of Property and Land Contractors Ltd v. Alfred McAlpine
19
Homes North Ltd. succinctly points the in-exactitude of Hudson’s
formulae, by observing:
“Furthermore the Emden formula, in common with
the Hudson formula (see Hudson on Building
Contracts, (11th edn, 1995) paras 8–182 et seq)
and with its American counterpart the Eichleay
formula, is dependent on various assumptions
which are not always present and which, if not
present, will not justify the use of a formula. For
example the Hudson formula makes it clear that
an element of constraint is required (see Hudson
para 8.185) ie in relation to profit, that there was
profit capable of being earned elsewhere and
there was no change in the market thereafter
affecting profitability of the work. It must also be
established that the contractor was unable to
deploy resources elsewhere and had no possibility
of recovering cost of the overheads from other
sources, eg from an increased volume of the work.
19
(1995) 76 BLR 59.
C.A. No. 1968 of 2012 Page 28 of 50
Thus such formulae are likely only to be of value if
the event causing delay is (or has the
characteristics of) a breach of contract.”
th
24. As mentioned in McDermott International Inc., Hudson’s 11
Edition has referred to Eichleay formula, which gives the resultant
figures with greater precision and accuracy. This formula, which
20
emerged in 1960s , is far more nuanced and rigorous, as it requires
the builder/contractor to itemise and quantify the total fixed
overheads during the contract period. It takes into consideration all
the contracts of the contractor/builder during the contract period
with those of the individually delayed contract to determine the
proportionate faction of the total fixed overheads. However, in both
Hudson’s and Eichleay's formulae, the amount to be recovered is
determined weekly or monthly, which the delay in the contract
completion is expected to earn.
25. Hudson’s formula might result in double recovery as the profit being
added to the profit is already subsumed within the ‘contract sum’.
To avert this double-recovery, it has been suggested that the
formula should be modified to ‘contract sum less overhead and
21
profit’ . Any increase in the value of the final account for extra works
20
The formula borrows the name from the Armed Services Board of Contract Appeals decision in
Eichleay Corporation case, ASBCA No. 5183, 60-2 BCA.
21
Ibid.
C.A. No. 1968 of 2012 Page 29 of 50
such as variations contain their own element of overheads and
profits. Therefore, Hudson’s formula like other formulae, which are
only rough approximations of the cost impact of unabsorbed
overhead, should be applied with great care and caution to ensure
22
fair and just computation.
th
26. Hudson in his 14 Edition refers to claim for management or
overheads during the period of delay. The author has referred to
Hudson’s formula as well as Eichleay’s formula, and observes that
recently limitations of Hudson’s approach have received greater
emphasis as the English courts have become more generous in
their approach and assessment of claims for time management.
The authors accept what has been highlighted above, and the need
to take care in delay cases to avoid any double recovery, overlap
with other claims, or when payments are obtained by the contractor
on account of variation(s), or any damages for breach have to be
concluded by using contract price. “Thickening”, by adding
unreasonable expenses, should not be accepted. It is observed that
in the total cost method, there is difficulty in linking cause and effect
convincingly, albeit is more precise and factually accurate. Thus,
Hudson’s method should be taken as the basis for computation with
22
Claims for head office overheads - alternatives to formulae, John W. Pettet, 1999.
C.A. No. 1968 of 2012 Page 30 of 50
caution and as a last resort, where no other way to compute
damages is feasible or mathematically accurate. Inaccuracies in
Hudson’s computation should not be overlooked, and should be
accounted and neutralized. Hudson’s formula when applied should
be with full care and caution not to over-award the damages.
27. Arbitral tribunal in the present case has given complete go by to
these principles well in place, overlooked care and caution required
and taken a one-sided view grossly and abnormally inflated the
damages. The figures quoted in paragraph 11 supra show the over-
statement and aggrandizement in awarding Rs. 1,57,37,666/-,
towards loss of overheads and loss of profits/profitability, in a
contract of Rs. 5,74,35,213/-. Rs.1,21,95,859.68/- was paid for the
work done within the term. Rs. 2,92,07,619.13 was paid for the work
done post the term. Thus, Rs. 4,14,03,478.81/- was paid for 80% of
the work. The balance was Rs.1,14,87,042.00/. The amount
awarded towards loss of overheads and profits/profitability is
Rs.1,57,37,666/-. No justification for computation of the loss is
elucidated or can be expounded. Even if one were to rely upon the
chart given by the BEEL, and ignore the contradictions in findings,
the amount awarded is highly disproportionate and exorbitant. It is
clearly a case of overlapping or at least a part doubling of the
loss/damages.
C.A. No. 1968 of 2012 Page 31 of 50
28. The arbitral tribunal has accepted that principle of mitigation is
applicable but observes that the only way BEEL could have abased
the loss, was to work on Sundays or holidays. This reasoning is
again ex facie fallacious and wrong. The principle of mitigation with
regard to overhead expenses does not mandate working on
Sundays or holidays.
29. We would like to refer to Claim No.2 for idle machinery and
equipment. This was on account of extended period of contract.
This claim of more than Rs.84,00,000/- has been accepted for
Rs.12,00,000/-, by simply stating that the learned arbitrator had
inspected the site and, in his opinion, there is substance in the
claim. Inspection of the site was post the appointment of the
arbitrator after August 1997, whereas BEEL had abandoned the
contract more than a year ago in March 1996. The amount awarded
is merely on ipsi dixit without giving any reasons and basis for
awarding the amount.
30. The scope and ambit of the court’s power to review the awards
under Section 34 of the A&C Act has been contentious viz., on the
interpretation to the expression ‘in conflict with the public policy of
India’. There have been legislative interventions as well as judicial
pronouncements. In the context of the present case, we are
C.A. No. 1968 of 2012 Page 32 of 50
required to interpret the provisions as they existed on the date on
which the objections to the award were filed i.e., on 21.06.1999.
Accordingly, the amendment introduced to Section 34 of the A&C
Act vide Act No. 3 of 2016 with retrospective effect from 23.10.2015
and the judgments of this Court examining the amended Section 34
of the A&C Act need not be examined.
31. Post award interference and the extent of the second look by the
courts under Section 34 of the A&C Act has been a subject matter
of perennial parley. The foundation of arbitration is party autonomy.
Parties have the freedom to enter into an agreement to settle their
disputes/claims by an arbitral tribunal, whose decision is binding on
23
the parties. It is argued that the purpose of arbitration is fast and
quick one-stop adjudication as an alternative to court adjudication,
and therefore, post award interference by the courts is un-
warranted, and an anathema that undermines the fundamental
edifice of arbitration, which is consensual and voluntary departure
from the right of a party to have its claim or dispute adjudicated by
24
the judiciary. The process is informal, and need not be legalistic .
Per contra , it is argued that party autonomy should not be treated
23
See Vidya Drolia and Others v. Durga Trading Corporation and Others , (2021) 2 SCC 1, which
examines arbitrability and non-arbitrability of subject matters and claims, which aspect will not be
examined in this case.
24
The expression “judicially”, does not equate arbitration with formal/court proceedings, and would
include a just and fair decision.
C.A. No. 1968 of 2012 Page 33 of 50
as an absolute defence, as a party despite agreeing to refer the
disputes/claims to a private tribunal consensually, does not barter
away the constitutional and basic human right to have a fair and
just resolution of the disputes. The court must exercise its powers
when the award is unfair, arbitrary, perverse, or otherwise infirm in
law. While arbitration is a private form of dispute resolution, the
conduct of arbitral proceedings must meet the juristic requirements
of due process and procedural fairness and reasonableness, to
achieve a ‘judicially’ sound and objective outcome. If these
requirements, which are equally fundamental to all forms of
adjudication including arbitration, are not sufficiently
accommodated in the arbitral proceedings and the outcome is
marred, then the award should invite intervention by the court.
32. To disentangle and balance the competing principles, the degree
and scope of intervention of courts when an award is challenged by
one or both parties needs to be stated. Reconciliation as a
statement of law and in particular application in a particular case
has not been an easy exercise. We begin by first referring to the
views expressed by this Court in interpreting the width and scope
of the post award interference by the courts under Section 34 of the
A&C Act.
C.A. No. 1968 of 2012 Page 34 of 50
33. Section 34 of the A&C Act, prior to amendment effected vide Act
No. 3 of 2016 with retrospective effect from 23.10.2015, reads as
under:
“34. Application for setting aside arbitral award.—
(1) Recourse to a court against an arbitral award
may be made only by an application for setting
aside such award in accordance with sub-section
(2) and sub-section (3).
(2) An arbitral award may be set aside by the court
only if—
(a) the party making the application furnishes proof
that—
(i) a party was under some incapacity; or
(ii) the arbitration agreement is not valid under the
law to which the parties have subjected it or, failing
any indication thereon, under the law for the time
being in force; or
(iii) the party making the application was not given
proper notice of the appointment of an arbitrator or
of the arbitral proceedings or was otherwise
unable to present his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of
the submission to arbitration, or it contains
decisions on matters beyond the scope of the
submission to arbitration:
Provided that, if the decisions on matters
submitted to arbitration can be separated from
those not so submitted, only that part of the arbitral
award which contains decisions on matters not
submitted to arbitration may be set aside; or
(v) the composition of the Arbitral Tribunal or the
arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement
was in conflict with a provision of this Part from
which the parties cannot derogate, or, failing such
agreement, was not in accordance with this Part;
or
C.A. No. 1968 of 2012 Page 35 of 50
(b) the court finds that—
(i) the subject-matter of the dispute is not capable
of settlement by arbitration under the law for the
time being in force, or
(ii) the arbitral award is in conflict with the public
policy of India.
Explanation.—Without prejudice to the generality
of sub-clause (ii), it is hereby declared, for the
avoidance of any doubt, that an award is in conflict
with the public policy of India if the making of the
award was induced or affected by fraud or
corruption or was in violation of Section 75 or
Section 81.
(3) An application for setting aside may not be
made after three months have elapsed from the
date on which the party making that application
had received the arbitral award or, if a request had
been made under Section 33, from the date on
which that request had been disposed of by the
Arbitral Tribunal:
Provided that if the court is satisfied that the
applicant was prevented by sufficient cause from
making the application within the said period of
three months it may entertain the application within
a further period of thirty days, but not thereafter.
(4) On receipt of an application under sub-section
(1), the court may, where it is appropriate and it is
so requested by a party, adjourn the proceedings
for a period of time determined by it in order to give
the Arbitral Tribunal an opportunity to resume the
arbitral proceedings or to take such other action as
in the opinion of Arbitral Tribunal will eliminate the
grounds for setting aside the arbitral award.”
34. Sub-section (1) to Section 34 of the A&C Act requires that the
recourse to a court against an arbitral award is to be made by a
party filing an application for setting aside of an award in
C.A. No. 1968 of 2012 Page 36 of 50
accordance with sub-sections (2) and (3) of Section 34. Sub-section
(2) to Section 34 of the A&C Act stipulates seven grounds on which
a court may set aside an arbitral award. Sub-section (2) consists of
two clauses, (a) and (b). Clause (b) consists of two sub-clauses,
namely, sub-clause (i) which states that when the subject matter of
the dispute is not capable of settlement by arbitration under the law
for the time being in force, and sub-clause (ii), which states that the
court can set aside an arbitral award when the award is ‘in conflict
with public policy of India’. We shall subsequently examine the
decisions of this Court interpreting ‘in conflict with public policy of
India’ and the explanation.
35. Under sub-clause (a) to sub-section (2) to Section 34 of the A&C
Act, a court can set aside an award on the grounds in sub-clauses
(i) to (v) namely, when a party being under some incapacity;
arbitration agreement is not valid under the law for the time being
in force; when the party making an application under Section 34 is
not given a proper notice of appointment of the arbitrator or the
arbitration proceedings, or was unable to present its case; and
when the composition of the arbitral tribunal or the arbitral
procedure was not in accordance with the agreement between the
parties, unless such agreement was in conflict with the mandatory
and binding non-derogable provision, or was not in accordance with
C.A. No. 1968 of 2012 Page 37 of 50
Part I of the A&C Act. Sub-clause (iv) states that the arbitral award
can be set aside when it deals with a dispute not contemplated by,
or not falling within the terms of submission of arbitration, or it
contains a decision on matters beyond the scope of submission to
arbitration. However, the proviso states that the decision in the
matters submitted to arbitration can be separated from those not
submitted, then that part of the arbitral award which contains the
decision on the matter not submitted to arbitration can be set aside.
In the present case, we are not required to examine sub-clauses to
clause (a) to sub-section (2) to Section 34 of the A&C Act in detail.
Hence, this decision should not be read as making any observation,
even as obiter dicta on the said clauses.
36. Explanation to sub-clause (ii) to clause (b) to Section 34(2) of the
A&C Act, as quoted above and before its substitution by Act No.3
of 2016, had postulated and declared for avoidance of doubt that
an award is 'in conflict with the public policy of India', if the making
of the award is induced or affected by fraud or corruption, or was in
violation of Sections 75 or 81 of the A&C Act. Both Sections 75 and
81 of the A&C Act fall under Part III of the A&C Act, which deal with
conciliation proceedings. Section 75 of the A&C Act relates to
confidentiality of the settlement proceedings and Section 81 deals
with admissibility of evidence in conciliation proceedings. Suffice it
C.A. No. 1968 of 2012 Page 38 of 50
is to note at this stage that while ‘fraud’ and ‘corruption’ are two
specific grounds under ‘public policy’, these are not the sole and
only grounds on which an award can be set aside on the ground of
‘public policy’.
37. Act No. 3 of 2016 with retrospective effect from 23.10.2015 has
substituted the explanation referred to above, by two new
25
explanations that are differently worded. Sub-section (2-A) to
Section 34 of the A&C Act, which was instituted by Act No. 3 of
2016 with retrospective effect from 23.10.2015, states that the
arbitral award arising out of arbitrations other than international
commercial arbitrations can be set aside by the court, if it is vitiated
by patent illegality appearing on the face of the award. The proviso
to sub-section (2-A) to Section 34 of the A&C Act also states that
the award shall not be set aside merely on the ground of erroneous
25
Explanations 1 and 2 to sub-clause (ii) to clause (b) to Section 34(2) of the A&C Act substituted vide
Act No. 3 of 2016 read as under:
Explanation 1.—For the avoidance of any doubt, it is clarified that an award is in conflict with the public
policy of India, only if,—
(i) the making of the award was induced or affected by fraud or corruption or was in violation of Section
75 or Section 81; or
(ii) it is in contravention with the fundamental policy of Indian law; or
(iii) it is in conflict with the most basic notions of morality or justice.
Explanation 2.—For the avoidance of doubt, the test as to whether there is a contravention with the
fundamental policy of Indian law shall not entail a review on the merits of the dispute.
Sub-section 2A to Section 34(2) of the A&C Act inserted vide Act No. 3 of 2016 reads as under:
(2-A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may
also be set aside by the court, if the court finds that the award is vitiated by patent illegality appearing
on the face of the award:
Provided that an award shall not be set aside merely on the ground of an erroneous application of the
law or by reappreciation of evidence.
C.A. No. 1968 of 2012 Page 39 of 50
application of law or by reappreciation of evidence. The aforesaid
sub-section need not be examined in the facts of the present case,
as we are not required to interpret and apply the substituted
explanations to (ii) to sub-clause (b) to 34(2) of the A & C Act in the
present case.
38. The expression ‘public policy’ under Section 34 of the A&C Act is
capable of both wide and narrow interpretation. Taking a broader
interpretation, this Court in ONGC Limited. v. Saw Pipes
26
Limited ., held that the legislative intent was not to uphold an
award if it is in contravention of provisions of an enactment, since it
would be contrary to the basic concept of justice. The concept of
‘public policy’ connotes a matter which concerns public good and
public interest. An award which is patently in violation of statutory
provisions cannot be held to be in public interest. Thus, expanding
on the scope and expanse of the jurisdiction of the court under
Section 34 of the A&C Act, it was held that an award can be set
aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
26
(2003) 5 SCC 705 (for short, Saw Pipes Limited).
C.A. No. 1968 of 2012 Page 40 of 50
(d) in addition, if it is patently illegal.
Nevertheless, the decision holds that mere error of fact or law in
reaching the conclusion on the disputed question will not give
jurisdiction to the court to interfere. However, this will depend on
three aspects: (a) whether the reference was made in general terms
for deciding the contractual dispute, in which case the award can
be set aside if the award is based upon erroneous legal position;
(b) this proposition will also hold good in case of a reasoned award,
which on the face of it is erroneous on the legal proposition of law
and/or its application; and (c) where a specific question of law is
submitted to an arbitrator, erroneous decision on the point of law
does not make the award bad, unless the court is satisfied that
arbitrator had proceeded illegally. In the said case, the court set
aside the award on the ground that the award had not taken into
consideration the terms of the contract before arriving at the
conclusion as to whether the party claiming the damages is entitled
to the same. Reference was made to the provisions of Sections 73
and 74 of the Contract Act, which relate to liquidated damages,
general damages and penalty stipulations. This view had held the
field for a long time and was applied in subsequent judgments of
this Court in Hindustan Zinc Ltd. v. Friends Coal
C.A. No. 1968 of 2012 Page 41 of 50
27
Carbonisation , Centrotrade Minerals and Metals Inc. v.
28
Hindustan Copper Limited , Delhi Development Authority v.
29
R.S. Sharma and Co ., J.G. Engineers (P) Ltd . v. Union of India
30 31
and Another , and Union of India v. L.S.N. Murthy .
39. In 2006, this Court in McDermott International Inc. despite
following the ratio of Saw Pipes Limited , made succinct
observations regarding the restrictive role of courts in the post-
award interference. In addition to the three grounds introduced in
32
Renusagar Power Co. Limited v. General Electric Co , as
noticed above, an additional ground of ‘patent illegality’ was
introduced Saw Pipes Limited , for exercise of the court’s
jurisdiction in setting aside an arbitral award. This Court, in
McDermott International Inc, held that patent illegality, must be
such which goes to the root of the matter. The public policy violation
should be so unfair and unreasonable as to shock the conscience
of the court. Arbitrator where s/he acts contrary to or beyond the
express law of contract or grants relief, such awards fall within the
purview of Section 34 of the A&C Act. Further, what would
27
(2006) 4 SCC 445.
28
(2006) 11 SCC 245.
29
(2008) 13 SCC 80.
30
(2011) 5 SCC 758.
31
(2012) 1 SCC 718.
32
1994 Supp (1) SCC 644.
C.A. No. 1968 of 2012 Page 42 of 50
constitute public policy is a matter dependent upon the nature of
transaction and the statute. Pleadings of the party and material
brought before the court would be relevant to enable the court to
judge what is in public good or public interest, or what would
otherwise be injurious to public good and interest at a relevant
point. So, this must be distinguished from public policy of a
particular government.
40. A similar view was expressed in Rashtriya Ispat Nigam Ltd. v.
33
Dewan Chand Ram Saran with the clarification that where a term
of the contract is capable of two interpretations and the view taken
by the arbitrator is a plausible one, it cannot be said that the
arbitrator travelled outside the jurisdiction or the view taken the
arbitrator is against the terms of the contract. The court cannot
interfere with the award and substitute its view with the award and
interpretation accepted by the arbitrator, the reason being the court
does not sit in appeal over the findings and decision of the
arbitrator, while deciding an application under Section 34 of the
A&C Act. The arbitrator is legitimately entitled to take a view after
considering the material before him/her and interpret the
agreement. The judgment should be accepted as final and binding.
33
(2012) 5 SCC 306.
C.A. No. 1968 of 2012 Page 43 of 50
41. Subsequently, in ONGC Ltd . v. Western Geco International
34
Ltd ., a three Judge Bench of this Court observed that the Court,
in Saw Pipes Ltd. , did not examine what would constitute
‘fundamental policy of Indian law’. The expression ‘fundamental
policy of Indian law’ in the opinion of this Court includes all
fundamental principles providing as basis for administration of
justice and enforcement of law in this country. There were three
distinct and fundamental juristic principles which form a part and
parcel of ‘fundamental policy of Indian law’. The first and the
foremost principle is that in every determination by a court or an
authority that affects rights of a citizen or leads to civil
consequences, the court or authority must adopt a judicial
approach. Fidelity to judicial approach entails that the court or
authority should not act in an arbitrary, capricious or whimsical
manner. The court or authority should act in a bona fide manner
and deal with the subject in a fair, reasonable and objective
manner. Decision should not be actuated by extraneous
considerations. Secondly, the principles of natural justice should be
followed. This would include the requirement that the arbitral
tribunal must apply its mind to the attending facts and
34
(2014) 9 SCC 263, (for short, Western Geco)
C.A. No. 1968 of 2012 Page 44 of 50
circumstances while taking the view one way or the other. Non-
application of mind is a defect that is fatal to any adjudication.
Application of mind is best done by recording reasons in support of
35
the decision. As noticed above, Section 31(3)(a) of the A&C states
that the arbitral award shall state the reasons on which it is based,
unless the parties have agreed that no reasons are to be given.
Sub-clauses (i) and (iii) to Section 34(2) also refer to different facets
of natural justice. In a given case sub-clause to Section 34(2) and
sub-clause (ii) to clause (b) to Section 34(2) may equally apply.
Lastly, is the need to ensure that the decision is not perverse or
irrational that no reasonable person would have arrived at the same
or be sustained in a court of law. Perversity or irrationality of a
decision is tested on the touchstone of Wednesbury principle of
36
reasonableness . At the same time, it was cautioned that this Court
was not attempting an exhaustive enumeration of what would
constitute ‘fundamental policy of Indian law’, as a straightjacket
definition is not possible. If on facts proved before them, the
arbitrators fail to draw an inference which ought to have been drawn
or if they have drawn an inference which on the face of it, is
untenable resulting in injustice, the adjudication made by an arbitral
35
Supra footnote 5.
36
As expounded in the case of Associated Provincial Picture Houses Ltd . v. Wednesbury
Corporation ., (1948) 1 KB 223: (1947) 2 All ER 680 (CA).
C.A. No. 1968 of 2012 Page 45 of 50
tribunal that enjoys considerable latitude and play at the joints in
making awards, may be challenged and set aside.
42. The decision of this Court in Associate Builders elaborately
examined the question of public policy in the context of Section 34
of the A&C Act, specifically under the head ‘fundamental policy of
Indian law’. It was firstly held that the principle of judicial approach
demands a decision to be fair, reasonable and objective. On the
obverse side, anything arbitrary and whimsical would not satisfy the
said requirement.
43. Referring to the third principle in Western Geco , it was explained
that the decision would be irrational and perverse if (a) it is based
on no evidence; (b) if the arbitral tribunal takes into account
something irrelevant to the decision which it arrives at; or (c) ignores
vital evidence in arriving at its decision. The standards prescribed
in Excise and Taxation Officer-cum-Assessing Authority v.
37
Gopi Nath & Sons and Kuldeep Singh v. Commissioner of
38
Police should be applied and relied upon, as good working tests
of perversity. In Gopi Nath & Sons it has been held that apart from
the cases where a finding of fact is arrived at by ignoring or
37
1992 Supp (2) SCC 312, (for short, Gopi Nath & Sons).
38
(1999) 2 SCC 10.
C.A. No. 1968 of 2012 Page 46 of 50
excluding relevant materials or taking into consideration irrelevant
material, the finding is perverse and infirm in law when it
outrageously defies logic as to suffer from vice of irrationality.
Kuldeep Singh clarifies that a finding is perverse when it is based
on no evidence or evidence which is thoroughly unreliable and no
reasonable person would act upon it. If there is some evidence
which can be acted and can be relied upon, however compendious
it may be, the conclusion should not be treated as perverse. This
Court in Associate Builders emphasised that the public policy test
to an arbitral award does not give jurisdiction to the court to act as
a court of appeal and consequently errors of fact cannot be
corrected. Arbitral tribunal is the ultimate master of quality and
quantity of evidence. An award based on little evidence or no
evidence, which does not measure up in quality to a trained legal
mind would not be held to be invalid on this score. Every arbitrator
need not necessarily be a person trained in law as a Judge. At
times, decisions are taken acting on equity and such decisions can
be just and fair should not be overturned under Section 34 of the
A&C Act on the ground that the arbitrator’s approach was arbitrary
or capricious. Referring to the third ground of public policy, justice
or morality, it is observed that these are two different concepts. An
award is against justice when it shocks the conscience of the court,
C.A. No. 1968 of 2012 Page 47 of 50
as in an example where the claimant has restricted his claim but
the arbitral tribunal has awarded a higher amount without any
reasonable ground of justification. Morality would necessarily cover
agreements that are illegal and also those which cannot be
enforced given the prevailing mores of the day. Here again
interference would be only if something shocks the court’s
conscience. Further, ‘patent illegality’ refers to three sub-heads: (a)
contravention of substantive law of India, which must be restricted
and limited such that the illegality must go to the root of the matter
and should not be of a trivial nature. Reference in this regard was
made to clause (a) to Section 28(1) of the A&C Act, which states
that the dispute submitted to arbitration under Part I shall be in
accordance with the substantive law for the time being in force. The
second sub-head would be when the arbitrator gives no reasons in
the award in contravention with Section 31(3) of the A&C Act. The
third sub-head deals with contravention of Section 28(3) of the A&C
Act which states that the arbitral tribunal shall decide all cases in
accordance with the terms of the contract and shall take into
account the usage of the trade applicable to the transaction. This
last sub-head should be understood with a caveat that the arbitrator
has the right to construe and interpret the terms of the contract in a
reasonable manner. Such interpretation should not be a ground to
C.A. No. 1968 of 2012 Page 48 of 50
set aside the award, as the construction of the terms of the contract
is finally for the arbitrator to decide. The award can be only set aside
under this sub-head if the arbitrator construes the award in a way
that no fair-minded or reasonable person would do.
44. As observed previously, we need not examine the amendment
made to the A&C Act vide Act No. 3 of 2016 with retrospective effect
from 23.10.2015 and the judgments that deal with the amended
Section 34 of the A&C Act. Pertinently, the amendment to Section
34 of the A&C Act was effected, pursuant to the observations of the
Supplementary Report to Report No. 246 on Amendments to
Arbitration and Conciliation Act, 1996 by the Law Commission of
India, titled ‘ Public Policy – Developments post-Report No. 246 ’
published in February 2015. This Supplementary Report observed
that the power to review an arbitral award on merits under Section
34 of the A&C Act, as elucidated in the case of Western Geco ,
subsequently followed in Associate Builders , is contrary to the
object of the A&C Act and international practice on minimization of
judicial intervention. A reference can also be conveniently made to
39
MMTC Ltd. v. Vedanta Ltd ., and Ssangyong Engg. &
40
Construction Co. Ltd . v. National Highways Authority of India ,
39
(2019) 4 SCC 163 (for short, MMTC Ltd.).
40
(2019) 15 SCC 131(for short, Ssangyong Engg).
C.A. No. 1968 of 2012 Page 49 of 50
which examine the scope of intervention of courts under Section 34
of the A&C Act as amended by Act No. 3 of 2016. MMTC Ltd. and
Ssangyong Engg., and other judgments which deal with the
amended Section 34 of the A&C Act that are not applicable in the
present case.
45. We have extensively analysed the award, its patent flaws and
illegalities which emanate from it, like the manifest lack of reasoning
in arriving at the conclusions and the calculation of amounts
awarded, which, in fact, amount to double or part-double payments,
besides being contradictory etc. In view of our aforesaid reasoning,
the award has been rightly held to be unsustainable and set aside
by the division bench of the High Court exercising power and
jurisdiction under Section 37 read with Section 34 of the A & C Act.
46. In view of the aforesaid discussion, the appeal is dismissed without
any order as to costs.
......................................J.
(SANJIV KHANNA)
......................................J.
(M.M. SUNDRESH)
NEW DELHI;
SEPTEMBER 21, 2023.
C.A. No. 1968 of 2012 Page 50 of 50