Full Judgment Text
REPORTABLE
2024 INSC 431
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1496 OF 2023
United India Insurance Co. Ltd. ...Appellant(s)
Versus
M/s Hyundai Engineering & Construction
Co. Ltd. & Ors. …Respondent(s)
J U D G M E N T
PAMIDIGHANTAM SRI NARASIMHA, J.
1. The appellant, United India Insurance Co. Ltd., an insurance
company, challenges the decision by the National Consumer
Disputes Redressal Commission (hereinafter ‘the NCDRC’), which
by its impugned order dated 16.01.2023 allowed the Consumer
Complaint No.160 of 2019 and directed the appellant to release
and pay an insurance claim of Rs. 39,09,92,828/-.
2. Facts : The National Highway Authority of India (‘NHAI’),
respondent no. 3 herein, awarded a contract for the design,
construction and maintenance of a cable-stayed bridge across the
Signature Not Verified
Digitally signed by
Indu Marwah
Date: 2024.05.16
15:44:34 IST
Reason:
river Chambal on NH-76 at Kota, Rajasthan to a joint venture
company comprising of respondent no. 1 and respondent no. 2.
1
The value of the project under the contract was Rs.
213,58,76,000/-. The contract provided that the construction
work was to be completed within 40 months and the joint venture
was thereafter assigned the task of maintaining the said bridge for
a period of 6 years, of which, 2 years was the ‘defect-notification
period’. NHAI also assigned consultancy services for design,
construction and maintenance of the bridge to another joint
venture of M/s Louis Berger Group Inc. (USA) and M/s COWI A/S
(Denmark).
3. The appellant issued a Contractor’s All Risk Insurance Policy
covering the interest of NHAI as principal, and M/s Hyundai
Engineering Infrastructure Co. Ltd. along with M/s Gammon India
as JV Contractor under the policy bearing No.
011900/44/07/03/60000001 for the period from 05.12.2007 to
04.12.2011 for a total amount of Rs. 213,58,76,000/-. The
relevant clauses of the policy are extracted as follows:
“ SECTION I - MATERIAL DAMAGE:
1. The Company hereby agrees with the Insured
(subject to the exclusions and conditions contained
herein or endorsed hereon) that if, at anytime
during the period of insurance stated in the
Schedule, or during any further period of extension
thereof the property (except packing materials of
any kind) or any part thereof described in the
2
Schedule be lost, damaged or destroyed by any
cause, other than those specifically excluded
hereunder, in a manner necessitating replacement
or repair, the Company will pay or make good all
such loss or damage upto an amount not exceeding
in respect of each of the items specified in the
Schedule the sum set opposite thereto and not
exceeding in the whole the total Sum Insured
hereby.
The Company will also reimburse the Insured for
the cost of clearance and removal of debris
following upon any event giving rise to an
admissible claim under this Policy but not
exceeding in all the sum (if any) set opposite thereto
in the Schedule. The term debris only of the Insured
property and the cost of clearance and removal of
debris pertaining to property not Insured by the
policy will not be payable .”
“ EXCLUSIONS TO SECTION - I
The Company, shall not, however, be liable for;
a) the first amount of the loss arising out of each
and every occurrence shown as Excess in the
Schedule;
b) loss discovered only at the time of taking an
inventory;
c) normal wear and tear, gradual deterioration due
to atmospheric conditions or lack of use or
obsolescence or otherwise, rust, scratching of
painted or polished surfaces or breakage of glass;
d) loss by damage due to faulty design;
e) the cost of replacement, repair or rectification of
defective material and/or workmanship, but this
exclusion shall be limited to the items immediately
affected and shall not be deemed to exclude loss of
or damage to correctly executed items resulting
from an accident due to such defective material
and/ or workmanship;
f) the cost necessary for rectification or correction of
any error during construction unless resulting in
physical loss or damage
3
g) loss of or damage to files, drawings, accounts,
bills, currency, stamps, deeds, evidence of debt,
notes, securities, cheques, packing materials such
as cases, boxes, crates;
h) any damage or penalties on account of the
Insured's non-fulfilment of the terms of delivery or
completion under this Contract of construction or of
any obligations assumed thereunder or lack of
performance including consequential loss of any
kind or description or for any aesthetic defects or
operational deficiencies;
i) loss of or damage to vehicles licensed for general
road use or waterborne vessels or
machinery/equipment mounted or operated or
fixed on floating vessels/craft/barges or aircraft. ”
4. The construction project commenced in December, 2007.
While the construction was in progress, a part of the constructed
bridge collapsed on 24.12.2009, resulting in the death of 48
workmen. On 26.12.2009, the Ministry of Road Transport and
Highways, Government of India constituted a Committee of
Experts (hereinafter, ‘Expert Committee’) under the chairmanship
of the Director General (Road Development) and Special Secretary,
Ministry of Road Transport and Highways. The task of this
committee was to investigate and report the cause of the collapse.
An FIR was also lodged against the respondents for offences under
Sections 304/308 of the Indian Penal Code, 1860. After
investigation, a final report dated 19.03.2010 was filed wherein the
officials of the respondent companies were charged under the said
4
provisions. It was found that they were liable for the loss of 48 lives
due to several defects at the stage of design, construction and
supervision.
5. The NHAI intimated the appellant about the incident on
29.12.2009 and requested the deputation of a surveyor to assess
the damage caused due to the accident and also sought
indemnification of the loss. A surveyor was appointed. He
commenced his work and by a letter dated 06.01.2010, he called
for certain details and clarifications from the respondents. While
furnishing the details, the respondents made a claim of Rs.
151,59,94,542/-.
6. The Committee of Experts constituted by the Government of
India submitted its report on 07.08.2010. Relevant parts of some
of the important findings of the Committee are as follows:
“ 8.2.2 Views of the Committee
8.2.2.1 The majority of failures in structures occur
during construction stages when they are most
vulnerable. The Chambal Bridge Accident was a
sudden and catastrophic structural failure. It may
be pointed out that the bridge was at one of its
critical stages at the time of the accident. […]
8.2.2.2 […] At this stage, as noted in para 5.8, the
stabilizing moment would become less than the
overturning moment. Uncontrolled rotation of the
pylon about the base would take place which
5
would result in its gaining momentum as it fell.
This is borne out by the fact that the catastrophic
failure involved a catapult action wherein the
span P3-P4 as a whole, (which was tied together
by prestressing cables) was thrown some 100 m
away.
8.2.2.3 The serious distress in span P3-P4
referred to para 8.2.2.2 could have been caused
by shortfall in design, poor workmanship,
unexpected load, sub-standard material or
distress in foundation P4 or a combination of some
of these. […]
8.2.2.4 It can be seen that had there been
additional stability devices in place (such as those
mentioned in para 8.2.2.1) the cycle involving
progressive loss of rotational restrain at the base
of the pylon and accentuation of distress in P3-P4
might not have been initiated and the collapse
might not have occurred .”
7. The final conclusions of the committee are relevant for this
case, and are as follows:
“ CONCLUSIONS
9.1 From all the information made available by
the various agencies as also the analysis and
evaluation made by the Committee, it is felt that
a combination of factors such as lack of stability
and robustness in the partially completed
structure, shortfalls in design and lack of quality
of workmanship in the construction of span P3-
P4 have contributed to the collapse of this bridge.
The trigger for initiation of the collapse appears
to have been unpredictable and sudden
additional loading due to failure of supporting
arrangement of the form traveller. ”
6
9.2 Since this is a design-build "Turnkey
Contract" which covers planning, investigation,
design, construction and maintenance of the
cable stayed bridge, the primary responsibility
for the collapse lies with the Contractor, M/s
Hyundai — Gammon (JV). The Contractors are
responsible for allowing the structure to reach a
vulnerable stage without taking adequate
precautions with respect to stability and
robustness of the partially completed structure
and the short fall in the design. They are also
responsible for deficiency in workmanship in the
construction of span P3-P4 .
9.3 The design for this bridge was prepared by
M/s SYSTRA, the Design Consultants of the
Contractor M/s Hyundai-Gammon (JV). Since
there have been shortfalls in design, the
responsibility for the same also lies with M/s
SYSTRA .
9.4 The Supervision Consultants for this Project
are M/s LBG-COWI whose duties include
construction supervision along with the proof-
checking of the design through M/s COWI While
carrying out the proof-checking work M/s COWI
have not highlighted the shortfalls in the design
which have been observed subsequently by the
Committee. Further, the Supervision Consultants
have not been sufficiently proactive in preventing
lapses in workmanship. They have also given
tacit approval for major changes during
construction without insisting on a proper review
of the design by the Contractors / Design
Consultants. As such, the Supervision
Consultants are responsible for these lapses.
9.5 M/s Freyssinet acted as specialist Agency to
M/s Hyundai for supply, installation and
operation of the form traveller equipment for
cantilever construction, post - tensioning work
and installation of stay cables. Since the trigger
7
for the collapse appears to be the failure of the
Freyssibar and / or the supporting arrangement
for the form traveller, the extent of their
responsibility may be examined keeping in view
the Contract Agreement between the concerned
agencies .
9.6 Apportioning of extent of responsibility to the
various agencies for the collapse of the structure
could be examined further by the Employer
(NHAI) keeping in view the contracts for this
Project entered into between various agencies
with each other and with NHAI . ”
8. On 06.12.2010, NHAI issued a show-cause notice to the
respondent nos. 1 and 2 calling upon them to justify as to why
they should not be debarred. The respondents replied to the show
cause notice, and after perusing the reply, the NHAI took a decision
to permit them to carry out the remaining part of the contract.
9. In the meanwhile, the surveyor appointed by the appellant
submitted its final report on 28.02.2011. While assessing the net
loss at Rs. 39,09,92,828/-, the surveyor recommended to the
appellant that the insurance claim must be rejected as the
respondents no. 1 and 2 had violated the conditions of the
insurance policy. Based on the surveyor’s report and also the
findings and conclusions of the Expert Committee, the appellant
repudiated the insurance claim in its letter dated 21.04.2011.
8
10. By their letter dated 17.06.2011, respondents nos. 1 and 2
requested the appellants to reconsider the decision of repudiation.
In support of their contentions, the respondents relied on certain
independent reports submitted by i) Mr. Jacques Combault; ii) M/s
SETRA/CETE (French Ministry of Transportation Technical
Department); iii) M/s Halcrow Group Ltd. and iv) AECOM Asia Co.
Ltd. Relying on these reports, the respondents urged stated that
there is no fault in the design of the bridge, and this is clearly
reiterated by technical experts, who are specialists in the field.
11. As the appellant agreed to reconsider the repudiation,
respondents no. 1 and 2 submitted various documents in support
of their claim. The appellant re-considered the claim, and by a
letter dated 17.04.2017 informed the respondents that the original
decision of repudiation is affirmed as they did not find any
justifiable reason for accepting the claim. The relevant portion of
the said communication dated 17.04.2017 is as follows:
“ We refer to your letter Ref: 17011/27/2006-
kota/CAR/RJ-05/3909, dt: 18.01.2017 and
Contractor letter Ref: HZ-6718, dt: 04.02.2017
and also the subsequent meeting held at our
office-Chennai. On perusal of the documents
provided, we find that no further points have
.
emerged in support of the claim
In view of the above we regret our inability
to reconsider the claim which was repudiated .”
9
12. In the meanwhile, respondents no. 1 and 2 completed the
work under the contract by 31.07.2017. The bridge was
inaugurated and put to public use from 29.08.2017, and it is said
to be operating since then.
13. Almost after 2 years of the rejection of the claim, on
24.01.2019, respondents no. 1 and 2 filed a Consumer Complaint
No. 160 of 2019 before the NCDRC alleging deficiency in the
appellant’s service and unfair trade practice adopted by it.
14. Decision of the NCDRC : At the outset, the NCDRC rejected
the preliminary objection of the appellant that the summary
jurisdiction under the Consumer Protection Act, 1986 (hereinafter,
‘the CPA’) is not appropriate for dealing with complicated questions
of law and fact. The objection relating to limitation in filing the
complaint was also dismissed by holding that the period for
calculating the limitation would commence from 17.04.2017 and
not from 21.04.2011.
14.1 On merits of the matter, the NCDRC held that the report of
the Committee of Experts was inconclusive as it could not identify
the precise reasons for the collapse of the bridge. On the other
hand, the NCDRC placed reliance on the reports of i) Mr. Jacques
10
Combault, ii) the Halcrow Group, iii) SETRA and iv) AECOM Asia
Co. Ltd., and came to the conclusion that there is no defect in the
design of the bridge and that the respondent nos. 1 and 2 are not
at fault.
14.2 Finally, the NCDRC relied on the decision of the NHAI
permitting the respondent nos. 1 and 2 to proceed with the
construction of the remaining part of the bridge and held that if
the NHAI found the respondents to be competent enough to
continue with the contract, it can safely be concluded that they
were not at fault.
14.3 In this view of the matter, the NCDRC directed the
appellant to pay the respondents no. 1 and 2 a sum of Rs.
39,09,92,828/- with an interest at 9% p.a. from the first date of
repudiation, i.e., 21.04.2011.
14.4 Strangely, while the judgment of the NCDRC was
pronounced on 16.01.2023, an addendum came to be added to the
judgment. This addendum is undated and seeks to amend
paragraphs 28 and 29 and directs payment of Rs. 151,59,94,542/-
instead of Rs. 39,09,92,828/-. The relevant portion of the
addendum is extracted here for ready reference:
11
“ 32. It will be relevant to mention here that though
the Complainant No.1, vide letter dated
27.02.2010 had submitted a detailed Claim
Statement of ₹ 93,67,17,876 to the Surveyor but it
was revised vide e-mail dated 07.03.2010 to the
tune of ₹ 149,87,44,914/-. It was again revised
vide letter dated 24.06.2010 (Serial No.2 of the
Claim Statement - ₹ 8,29,15,604 to ₹ 10,01,65,232)
to a final Claim of ₹ 151,59,94,542/-. The
Surveyor had, however, assessed the total loss at
₹ 39,09,92,828/- . Even though in the Written
Submissions filed by the Learned Counsel for the
Complainants they have claimed that at least a
net loss of ₹ 39,09,92,828/- be payable towards
the insurance claim but in my considered opinion
the Complainants are entitled for the payment of
entire loss of ₹ 151,59,94,542/- claimed by them.
33. Consequently, the Complaint is partly allowed
with a direction to the Insurance Company to pay
₹
a sum of 151,59,94,542/- to the Complainants
along with interest @9% p.a. from the date of
repudiation of the claim i.e. 21.04.2011 till the
actual realization, within a period of 8 weeks from
the date of passing of the order failing which the
amount shall attract interest @12% p.a. for the
said period. The Complainants shall also be
entitled for a costs of ₹ 50,000/-. ”
15. Mr. Dama Seshadri Naidu, learned senior counsel appearing
for the respondents has submitted that he is not in a position to
support the judgment amending the paragraphs 28 and 29 and
directing the payment of the revised amount of Rs.
151,59,94,542/-. It is unimaginable as to how the NCDRC could
unilaterally revise the claim from Rs. 39,09,92,828/- to Rs.
151,59,94,542/-, without hearing the parties and more
12
surprisingly when respondent nos. 1 and 2 have themselves filed
written submissions confining the claim to Rs. 39,09,92,828/-. Be
that as it may, in view of the submission of the learned counsel for
the respondent that he will confine the claim Rs. 39,09,92,828/-,
this issue need not detain us any further.
16. Analysis : Insurance is a contract of indemnification, being a
1 2
contract for a specific purpose , which is to cover defined losses .
The courts have to read the insurance contract strictly.
Essentially, the insurer cannot be asked to cover a loss that is not
mentioned. Exclusion clauses in insurance contracts are
interpreted strictly and against the insurer as they have the effect
3
of completely exempting the insurer of its liabilities.
17. In Texco Marketing P. Ltd. v. TATA AIG General Insurance
4
Company Ltd. , while dealing with an exclusion clause, this Court
has held that the burden of proving the applicability of an
exclusionary clause lies on the insurer. At the same time, it was
stated that such a clause cannot be interpreted so that it conflicts
| Oriental Insurance Co. Ltd. v. Samayanallur Primary Agricultural Coop. Bank, | |
| (1999) 8 SCC 543. |
13
with the main intention of the insurance. It is, therefore, the duty
of the insurer to plead and lead cogent evidence to establish the
5
application of such a clause . The evidence must unequivocally
establish that the event sought to be excluded is specifically
6
covered by the exclusionary clause. The judicial positions on the
nature of an insurance contract, and how an exclusion clause is
to be proved, shall anchor our reasoning in the following
paragraphs.
18. Seeking to justify their repudiation, the appellant relied on
the affidavit of evidence by Mr. S. Anantha Padmanabhan,
examined as RW 2. He produced the surveyor’s report as well as
the Expert Committee’s report as Ex. RW 2/2. On the other hand,
the reports of the independent experts relied upon by the
respondents no. 1 and 2 were not marked as exhibits. They were
not adduced in evidence as none of these experts was examined as
a witness. Under these circumstances, we have no hesitation in
coming to a conclusion that the appellants have discharged the
burden as enunciated in Texco (supra).
5
National Insurance Company Ltd. v. Vedic Resorts and Hotels Pvt. Ltd ., 2023
SCC OnLine SC 648.
6
National Insurance Co. Ltd. v. Ishar Das Madan Lal , 2007 (4) SCC 105.
14
19. The Expert Committee was constituted by the Ministry of
Road Transport and Highways (‘MORTH’), Government of India. It
was chaired by the Director General (Road Development) and
Special Secretary, MORTH. The other members of the Committee
were Mr. Ninan Koshi DG (RD) & AS (Retd.), Prof. Mahesh Tandon,
Bridge Specialist, and Prof. A.K. Nagpal, Dept. of Civil Engineering,
IIT Delhi. We have referred to the constitution as well as the
expertise of the Committee only to assure ourselves that it
comprised of experts in the field of civil engineering. It is also
indicative of the fact that the members were independent and well-
qualified to examine and submit a report. We would, therefore, be
justified in relying on the findings of the Expert Committee. In fact,
the NCDRC’s opinion about the Expert Committee is not about
lack of credibility, or lack of expertise, rather its opinion was only
that the Committee was not conclusive in its findings.
20. The proof of the pudding is in its eating - we will straight away
refer to the relevant portions of the Expert Committee’s report.
Referring to the variations introduced on-site without any approval
by the design checker, the Committee held as follows:
“
5.1.2 Since this is a Design Build Contract, the
Contractors M/s Hyundai-Gammon (JV) had
appointed M/s SYSTRA of France as their Design
15
Consultant. The designs prepared by M/s
SYSTRA were proof checked by M/s COWI, the
Proof Check Consultant. During the course of
presentations and discussions with various
agencies, there were some contradictions in the
stand taken by M/s SYSTRA and M/s COWI as
regards the extent of proof checking of designs by
the Proof Check Consultant. In fact, M/s COWI in
their submission dated 28th May, 2010 (Annexure
L-21) have stated as follows: “The Design Checker
verified the Final Design prior to start of
construction. The variations introduced on site
were introduced by the BOT Contractor. We expect
that all variations were subject to verification and
approval of the Designer. The Design Checker was
not requested to review any design verification
following variations on site from the Final Design.
[…]”
( emphasis supplied )
20.1 The Committee noted that each lateral span of the bridge
was supposed to be a monolithic structure. A lateral span is the
structure between two support pillars. However, the collapsed
lateral span was cast in multiple parts, as noted in the following
paragraph:
“ 5.3.3 M/s SYSTRA have expressed vide their
submission dated 17th April, 2010 (Annexure
H-11, page 3) that they have envisaged “one go”
(i.e. monolithic construction) for each lateral span
during the development of the design. However,
during actual construction the lateral span P3-P4
was cast in seven parts. The lower part of the box
girder (U-shaped section comprising bottom slab
and webs upto about mid height) was concreted
in four different stages with three vertical
construction joints. The upper part of the box
girder (comprising deck slab and top half of the
16
webs) was later concreted in three stages (with
two vertical construction joints). It has been
informed by M/s Hyundai-Gammon JV vide their
letter HN-1656 dated 1st September, 2009
(Annexure L-18, page 3) that M/s SYSTRA, the
designer of the main bridge including lateral
spans, were aware of this. In fact, Mr. J. Mirailles
of M/s SYSTRA had visited the site in the month
of July 2009 and stayed there for a couple of
weeks to inspect the ongoing construction. The
construction of lateral span P3- P4 in parts was
being carried out at that time …”
“ 5.3.5 The query of the Committee regarding
position of M/s LBG-COWI in respect of
applicability of Clauses of AASHTO relating to
“Segmentally Constructed Bridges” to the design
of lateral span P3-P4, was discussed with Mr.
Nielsen of M/s COWI on 23rd June, 2010. Mr.
Nielsen mentioned that as per his understanding,
it was a case of segmental construction . […]”
( emphasis supplied )
20.2 The Committee noted that the point at which the cable was
going to be suspended with the pylon was crucial. It observed that
the height at which the suspension took place was 77 metres,
whereas, it was supposed to be 40 metres. The relevant paragraph
is as follows:
“ 6.2 The drawing No.A104-DWG-MB-FD-1301
REV. 1 dated 28th May, 2009 [Annexure H-01(ii)]
shows that the lateral spans P3-P4 as well as P2-
P3, should have been completed and external
tendons tensioned before the first stay cable was
installed. The steel box for anchoring the first stay
cable was to be placed in the pylon at the height
of 33.30m. Also, the first cantilever segment
towards the river side from P4 was to be
17
constructed only after the lateral spans P3-P4 and
P2-P3 had been completed and fully prestressed.
It is seen that this sequence was changed in the
actual construction. Further, drawing No.A104-
DWG-MB-FD-846 REV. 2(c) dated (??)/07/09
[Annexure H-01(ii)] specifically mentions that
“tendons tensioning on span P2-P3 must be
performed before pouring segment S10”. This
requirement was also changed during actual
construction. […]
6.3 …This implies that the height of the pylon
should have been about 40 m at the time of
tensioning of first stay cable at cantilever segment
S10. However, it is seen that at the time of casting
of segment S10, the free-standing pylon had
already been constructed to a height of 77 m .”
( emphasis supplied )
20.3 The other relevant portions cited to us from the Committee’s
Report include para 6.5, which speaks about the changes in the
sequence of construction without consulting or informing the
design consultants of the project. Para 6.8 was relied on to
highlight further discrepancies between the approved drawing
plans and the actual construction. Concrete batching plants
involved were of a lower capacity, leading to delays in construction
of the lateral spans. Para 8.1.2 (iii) was also brought to our notice,
as it spoke about the changes which were brought about without a
proper technical review. The conclusions of the committee have
already been quoted by us in paragraph 7 above, and it was found
that:
18
a) a combination of factors such as lack of stability and
robustness in the structure, shortfall in design, lack of
quality workmanship have all contributed to the
collapse;
b) the primary responsibility lies with the contractor, M/s
Hyundai and Gammon (JV) who are responsible for
allowing the structure to reach a vulnerable stage
without taking adequate precautions and there is a
shortfall in the design;
c) there were shortcomings in the design for the bridge
prepared by M/s SYSTRA and the responsibility for the
design lies with M/s SYSTRA;
d) M/S COWI, the supervision consultants have not
highlighted the shortfall in the design. M/s COWI has
not been sufficiently proactive in preventing lapses in
workmanship. They have given tacit approvals for
major changes without insisting on a proper review of
the design;
e) The trigger for the collapse appears to be the failure of
M/s Freyssinet. Their responsibility must be examined
in detail.
19
21. We are inclined to accept the appellant’s submission that
there is sufficient evidence to justify repudiation of the claim on
the basis of the exclusion clause. On the other hand, there is
absolutely no evidence on behalf of the respondents. His argument
is only that the Surveyor/Committee report is not clinching, it is
open ended and does not hold that the respondents no. 1 and 2
are responsible for the negligence.
22. We will now refer to the surveyor’s report, the findings of
which are as follows:
“ C) After a detailed study of the Insured’s
submission vide their letter dt;27.02.2010 and
several rounds of face to face interactions with the
Insured’s Engineers at site, we derived the
following inferences;
1). The junction at Pylon P4, was the most critical
and vulnerable in the entire construction and had
to be handled with due care and diligence.
2). It was clear and obvious, that, an unstable
equilibrium has been created at this junction,
(where, the over turning moment was in excess of
resisting moment), due to the shearing of the slab
in lateral span P3 -P4 at about 15 mts from the P4
junction, which has caused the tilting of the Pylon,
dragging with it, spans P3-P4, P3-P2 and Piers P4,
P3. The shearing of the slab is purely a Design
aspect.
3). The restraints imposed on the movement of the
Bearings at P4 were released by the Insured prior
to completion of the main spans, which facilitated
20
movement of Pylon along with Lateral spans and
this is one of the most significant factors,
contributing to this massive failure.
4). The sequence of operations in the construction
of the Bridge were changed in actual construction
to make up for the time lost and this has adversely
affected the stability of the P4 joint.
5). Raising Pylon P4 to an abnormal height of 77
mts (out of 80 mts) without any lateral anchorage
in the form of stringers, had left the Pylon P4
exposed to heavy wind pressure and in a state of
unstable equilibrium, ready to collapse at any
time, with the application of a little external force
in excess.
6). We were informed that, the concreting of
Lateral span P3-P4 was done in 7 stages,
whereas, it should have been done at ONE GO.
This leaves vertical joints which are vulnerable.
We also noted that, the Insured had to resort to
concreting in stages, due to insufficient Batching
Plants.
7). Change in allocation of works amongst the
Joint Venture Partners also played a key role in
the quality of workmanship. At several places,
M/s.Gammon had to carryout the jobs, supposed
to have been carried out by M.s,Hyundai. Even in
the affected location of P4, the construction of Pier
P4 was the responsibility of M/s. Hyundai,
whereas, it was carried out by M/s Gammon.
8). Lack of co-ordination and planning between
proof checking consultant and design consultants
could have been streamlined.
[…]
21
11). The sequence of concreting carried out on the
date of failure, as informed to us, was different
from the versions of the Insured. […]”
23. It is important to note that the surveyor was examined as
RW-1 and his evidence remained unrebutted. In
National Insurance Company Ltd. v. Hareshwar
7
Enterprises (P) Ltd . and National Insurance Company Ltd. v. Vedic
8
Resorts and Hotels Pvt. Ltd ., this court has held that the
surveyor’s report is a credible evidence and the court may rely on
it until a more reliable evidence is brought on record. In the
present case, the surveyor’s report was the evidence tendered by
the insurance company, and it has not been treated as unreliable
by the NCDRC.
24. Mr. Naidu, appearing on behalf of the respondents,
commenced his submission by referring to certain portions of the
judgment of this court in Texco (supra) to emphasise that
exclusionary clauses place extraordinary burden on the insurance
company. We have already answered this question by referring to
the evidence adduced by the appellant, which we consider to be a
sufficient discharge of the burden. On the Expert Committee’s
7
(2021) SCC Online SC 628.
8
2023 SCC OnLine SC 648.
22
report, Mr. Naidu has re-iterated the finding of the NCDRC that it
is inconclusive apart from being a mere opinion. Even this
submission stands answered by extracting specific and categorical
findings of the Committee as well as the surveyor’s report.
25. Mr. Naidu sought to draw support from the reports of
independent experts on the issue of design to establish that the
respondents are not at fault. Mr. Naidu sought to rely on reports
by (i) Mr. Jacques Combault; (ii) M/s SETRA/CETE (French
Ministry of Transportation Technical Department); (iii) M/s
Halcrow Group Ltd.; and (iv) AECOM Asia Co. Ltd.
26. At the outset, the concerned experts were never examined
before the NCDRC. Further, these reports were not based on site-
inspection. They are all theoretical in nature. For example, the
report Mr. Jacques Combault is based on:
“ The analysis reported in the following pages is
based on:
- The description of Bridge Concept as proposed
by Systra
- The Main characteristics of the Structural
Concept as proposed by Systra
-
The State of the Art in the field of prestressed
concrete cable stayed bridges
- Examples of similar bridges successfully
achieved in the past ”
23
After a theoretical analysis, the following conclusion is drawn:
“ The structural concept of the Chambal Bridge as
proposed by Systra is: -
- perfectly fitting the site-conditions
- conforming to the state of the art in the field of
cable stayed bridges
The construction methods, as proposed by Systra,
are simple and proven processes well adapted to
the structural concept .”
27. A similar approach was adopted by the other experts. On the
other hand, the surveyor has examined himself and adduced
documents. Further, there is sufficient evidence to indicate that
the surveyor has made site-visits and the proof of that was part of
the pleadings filed before us.
28. The submission that NHAI continuing the contract with
respondent nos. 1 and 2 and they have, in fact, completed the
contract does not impress us. The continuation of work by
respondent nos. 1 and 2 could be due to various reasons. Even if
the NHAI’s decision to continue is taken to be a valid economic
decision, that by itself cannot be a reason for not applying the
applicable clause of the contract if such applicability is otherwise
proved by cogent evidence.
29. For the reasons stated above, we are of the opinion that the
NCDRC fell into a clear error of law and fact in allowing the
24
consumer complaint for multiple reasons. As we have not agreed
with the preliminary objection of the appellant to reject the
complaint and relegate the respondents to civil court, we made
extra efforts to examine the facts in detail. It is for this reason that
the evidentiary value of the reports, their scope and ambit, and
their contents were examined by us in some detail.
30. For the reasons stated above, we allow the appeal and set-
aside the impugned order dated 16.01.2023 passed by the NCDRC
in Consumer Complaint No. 160 of 2019.
31. Pending applications, if any, shall be disposed of.
32. There shall be no order as to costs.
………………………………. J.
[PAMIDIGHANTAM SRI NARASIMHA]
………………………………. J.
[ARAVIND KUMAR]
NEW DELHI;
May 16, 2024
25