Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO…9732../2016
(arising out of S.L.P.(Civil) No.11876/2013)
Mahanadi Coalfields Ltd. & Ors. …Appellants
Vs.
M/s. Dhansar Engineering Co. Pvt.Ltd & Anr. .....Respondents
J U D G M E N T
A.M.KHANWILKAR,J.
Leave granted.
2. This appeal challenges the judgment of the Division Bench of
JUDGMENT
th
the High Court of Orissa at Cuttack dated 7 November 2012 in
Writ Petition (Civil) No. 1093/2006.
nd
3. Briefly stated, on 2 December 2002 the appellants issued
notice inviting tenders for the work of extraction and transfer of
Coal/Coal Measure Strata (CMS) by deploying “Surface Miners” on
hiring basis at various Open Cast Projects, inter-alia, at Lakhanpur.
Page 1
2
The respondents were declared the lowest bidder having quoted
Rs.17/- per cubic meter for the stated contract. A letter of intent
th
was issued in favour of the respondents on 4 April, 2003 which
| pondents | on 14th |
|---|
rd
was issued in favour of the respondents on 23 April, 2003 and a
th
formal agreement was executed between the parties on 26 May
2003. The relevant clauses of the agreement are clauses 2 to 5
which read as under:
“2) Time shall be considered as one of the essence of
the contract and the time for the completion of the contract
shall be counted from 16.04.2003 of from the date of issue
of L.O.I. to which terms the contractor agreed at the time
when his tender was accepted and the contract shall be
completed by 15.04.2004 provided, sufficient face is
provided by the management.
3) The work order has already been issued for a period
of one year for a quantity of 49,50,000 Cum. At the rate of
Rs. 17.00/Cum. for an amount of Rs. 8,41,50,000.00.
JUDGMENT
4) The contractor shall re-deploy the Surface Miner in
other OCPs as per direction of the Company.
5) The tendered quantity may be reduced or increased
by +/- 30%. No claim shall lie on the company for such
variation in quantity whether increase or decrease. The
tenderer must be in a position to increase the machine
capacity upon 30% extra daily quantity within 45 days
notice. ”
(emphasis supplied)
Page 2
3
4. As the agreement refers to the terms and conditions of the
tender document, we may usefully refer to the relevant clauses
therein.
| “11.0 VARIATION IN SCHEDULED QUANTITY EXTENT AND<br>RATE<br>The quantity given in the “Schedule of Quantity’s provisional<br>and is meant to indicate the extent of the work and to provide<br>a uniform basis for tendering and any variation either by<br>addition or omission shall not vitiate the contract.<br>The tendered quantity may be reduced or increased by 30%.<br>No claim shall be on the company for such variation in<br>quantity whether increase or decrease. Tenderer must be in a<br>position to increase the machine capacity within 45 days<br>notice to achieve the extra increased quantity.<br>If the additional altered or substituted work includes any item<br>of work for which no “rate is specified in the contract, “rate”<br>for such item shall be determined by the Company<br>Headquarters in the following manner:- | ANTITY EXT | ENT AND |
item of work awarded in the Company, or
b) The rate shall be derived from contractor’s rate claimed for such
JUDGMENT
item of work supported by analysis of the rate claimed by the
contractor. The rate to be determined by the Company
Headquarters as may be considered reasonable taking into
account percentage of profit and overhead not exceeding ten
percent or on the basis of market rate, if any prevailing at the
time when work was done.
However, the Engineer-in-charge shall be at liberty to cancel
the instruction by giving notice in writing and to arrange to
carry out the work in such manner as he considers advisable
under the circumstances. The contractor shall under no
circumstances suspend the work in the plea of non-settlement
of rates.
Page 3
4
The time of completion of the originally contracted work shall
be extended/reduced by the Company in the proportion that
the additional/reduced work (in value) bears to the original
contracted work (in value), as may be assessed and certified
by the Engineer-in-charge.
| through<br>behalf of<br>f the work | its Engin<br>the compa<br>for any |
|---|
In the event of any deviation being ordered which in the
opinion of the contractor changes radically the original scope
and nature of the contract, the contractor shall under no
circumstances suspend the work, either original or altered or
substituted and the dispute/disagreement as to the nature of
deviation or the rate to be paid therefore shall be resolved
separately with the company.
13. TIME FOR COMPLETION OF CONTRACT
Time is the essence of the contract.
The contractual period of work shall be as
specified in NIT/LOI Agreement. The work shall be deemed to
have commenced within 60 days of the issue of Letter of
Intent at all the places and should be able to execute 100% of
the daily awarded quantity from 61th day from the date of
issue of LOI.
JUDGMENT
Agreement should be executed before the release
st
of 1 , on A/c. bill.
th
For failure to reach the desired quantity from 61
day of issue of LOI, contractor shall be liable for penalty @
20% of amount for shortfall quantity i.e. (shortfall quantity x
awarded rate x 20%).
The contractor must be prepared to work
continuously for three shifts a day and all the working days
in a year.
Page 4
5
| giving 1 | 5 days n |
|---|---|
| eit the Ear<br>ontract. | nest Mone |
14.0 EXTENSION OF DATE OF COMPLETION
On happening of any event causing delay as stated
hereunder, the contractor shall apply for time extension to the
CGM/GM of the Area.
a) Abnormally bad weather
b) Serous loss or damage by fire
c) Civil Commotion, strike or lockout affecting execution of
work
d) Non-availability of working force or site which is the
responsibility of the company to supply.
e) Any other cause which, at the sole discretion of the
company, is beyond the control of the contractor.
The contractor may request the company in writing for
extension of time within 14 days of happening of such event
ceasing delay stating the period for which extension is
desired. The company may, considering the eligibility of the
request, give a fair and reasonable extension of time of
completion of the work. Such extension shall be
communicated to the contractor, in writing, by the company
through the Engineer-in-charge within 1 month of the date of
receipt of such request.
……………………
JUDGMENT
30.0 DEFAULT AND PENALTY
30.1 LOSS OR DAMAGE
Any loss or any expenditure for damages incurred by
company will be recoverable from the contractor whether fully
or partly if such expenditure for damages have been caused
either directly or indirectly due to any negligence or failure on
the part of the contractor.
Page 5
6
30.2. SHORTFALL PENALTY IN MECHANICAL EXCAVATION
AND LOADING
The average daily quantity of the quarter shall be worked out
by dividing the mutually agreed quarterly allotted quantity by
th th
the working days of the quarter, ending on 30 June, 30
| December<br>rter must<br>ctual perio | & 31<br>conform to<br>d. |
|---|
In the event of the Contractors failure to comply with the rate
of rate of progress as per the agreed progress chart the
contractor shall be liable to pay a penalty on the quantity by
which the contractor has fallen short from the allotted
quarterly quantity at the rate of 20% of the awarded rate.
For failure of produce size coal as per NIT (-100 mm size), the
contactor shall also be liable for penalty at the rate of 20% of
the awarded rate for such over size quantity.
The shortfall penalty will be recovered concurrently from the
running bill which will be adjusted annually subject to that
the total penalty is limited to 20% of (Annual Shortfall
Quantity x Rate).
30.3 WAIVAL OF PENALTY
The company may at its sole discretion waive the payment of
penalty in full or in part in request received from the
contractor depending the merit of the case if the entire work is
completed within the date as specified in the contract or
within extended period approved without imposing penalty.
JUDGMENT
31.0. SETTLEMENT OF DISPUTE
Except where otherwise provided for in the contract, all
questions and disputes relating to meaning of the scope,
specification and instructions herein before mentioned and as
to any other question, claim right matter or thing whatsoever
in any way arising out of or relating to the contract,
instructions, orders or these conditions or otherwise
concerning the works or the execution or failure to execute the
same whether arising during the progress of the work or after
the completion or abandonment thereof, shall be referred to
Page 6
7
the Chairman-Cum-Managing Director of the Company or any
other person authorized by him.
| ent or of<br>lier, the c<br>been waive | the date<br>laim of th<br>d and ab |
|---|
(emphasis supplied)
5. The respondents commenced the work of surface miners at
Lakhanpur and completed around 70% of the awarded quantity by
the end of February 2004. Due to financial problems faced by the
th
respondents vide letter dated 13 February 2004, they requested
the appellants to allow them to close the contract by invoking power
to reduce the quantity by 30% of awarded quantity, under clause
JUDGMENT
11 of the general terms and conditions of the NIT; and to issue fresh
tender for the remaining work. The appellants did not accede to the
th
said request and informed the respondents vide letter dated 16
February 2004, stating that the agreement is for performing the
contract upto 100% of awarded value and provision of executing
extra 30% quantity on the same terms and conditions. The
th
respondents requested the appellants vide letter dated 9 May 2004
Page 7
8
to extend the time frame for completion of the remaining contract
th th
upto 15 July 2004 as the contract period was only till 15 April,
2004. The said letter reads thus:
ANNEXURE-P8
DHANSAR ENGINEERING CO. PVT. LTD.,
SITE
P.O. Dhansar P.O. Jorabaga
Dhanbad – 828106 (Jharkhand) Via Belpahar
Ph: 0326 – 307161/7074. Dist.: Jharsuguda (Orissa)
Fax: 0326 303294 Ph.: 06645 -233222
E-mail – decopl@dte.vsnl.net.in
Ref: No. DECO/NIT 276/2004 Date: 09.05.2004
To
The chief General Manager
Lakhanpur Area
Mahanadi Coalfields Ltd.,
(Through proper channel)
Sub: WORK OF EXTRACTION AND TRANSFER OF
COAL/COAL MEASURE STRATA BY DEPLOYING SURFACE
MINER ON HIRING AT LAKHANPUR OCP OF LAKHANPUR
AREA (NIT – 276) VIDE WORK ORDER NO. MCL/CGM/LKPA/
SO(M)/SUR. MINER/2003-04/001 DATED 23.04.2003.
JUDGMENT
Dear Sir,
Management is fully aware that tender rate of
Rs. 17/- per Cum for the work is all time low and wholly
unworkable. We are working at this rate at a colossal loss.
We started the work almost at the approach of
monsoon on 16.04.2003 and we could not also speed up
progress because of transportation restriction between 11.00
A.M. & 4.00 P.M. against heat wave alert and thereafter
on-set of heavy rains consequenting upon bad, water-logged
& slippery road followed by short supply of rakes. With all
these operational hazards beyond our control, we could
accomplish 34.74 Lakhs Cum upto 31.03.2004.
Page 8
9
As our financial loss was soaring day by day, we
had requested for foreclosure of the work after we have
completed 70% of the work but this was not agreed to by
GM(TC) vide his letter No. 1251 dated 26.03.2004.
| and woul<br>d with the<br>e ill-afford | d request<br>completion<br>to bear fu |
|---|
Thanking You,
Yours faithfully,
Sd/-
For Dhansar Engineering Co. Pvt. Ltd.”
6. This request of the respondents was considered by the
th
appellants in its 68 Meeting of the Board. Extension of three
months time was granted while reserving the right to impose
penalty. The respondents were informed accordingly vide letter
th
dated 5 June 2004. As a result of this decision, the contract
th
period was extended until 15 July 2004 on the same terms and
JUDGMENT
conditions agreed upon. As the contract period was subsisting till
th
15 July 2004, the appellants issued an approval order dated
th
11 June 2004 to increase of 30% extra quantity i.e. 14.8 Lakh
cubic meter at the existing rate of next tender rate or whichever
is lower, amounting to Rs. 252.42 Lakh. The respondents by
th
letter dated 11 June 2004, however, reiterated that the contract
Page 9
10
be treated as closed - as they were on the verge of completing the
th
quantity specified in the contract by 15 June 2004. The said
letter reads thus:
SITE
P.O. Dhansar P.O. Jorabaga
Dhanbad – 828106 (Jharkhand) Via Belpahar
Ph: 0326 – 307161/7074. Dist.: Jharsuguda (Orissa)
Fax: 0326 303294 Ph.: 06645 -233222
E-mail – decopl@dte.vsnl.net.in
Ref: No. DECO/NIT 276/2004 Date: 11.06.2004
To
The chief General Manager
Lakhanpur Area
Mahanadi Coalfields Ltd.,
Sub: NIT NO. 276 – EXTRACTION AND TRANSFER OF
COAL/COAL MEASURE STRATA BY DEPLOYING SURFACE
MINER ON HRING BASIS AT LAKHANPUR OCP OF MCL
Dear Sir,
We would like to inform you that the order
quantity of 49.50 lakh Cum is in the verge of completion, and
is expected that this quantity will be fully completed by
15.06.2004.
JUDGMENT
In this connection kindly refer to our letter No.
DECO/NIT – 276/2004 dated 09.05.2004 under which we
had requested your good-self to treat the contract as closed
with the completion of the quantity of 49.50 lakh Cum. In
reiterating our request we would inform you that we may be
forced to stop the machine as it is giving trouble and we are
not able to repair the machine for dire scarcity of fund.
Thanking You,
Yours faithfully,
Sd/-
For Dhansar Engineering Co. Pvt. Ltd.
Page 10
11
Copy to: 1) The Director (Technical) MCL, Burla,
2) The General Manager, Lakhanpur Area.”
| another<br>o financia | letter da<br>l hardsh |
|---|
withdrawing their operations. The appellants, however, by letter
th
dated 7 July 2004 called upon the respondents to continue with
the remaining work assigned under the contract which was still
subsisting; and also noted that the respondents had by then
completed only 105% of the contract work out of 130%. The said
communication reads thus:
“ ANNEXURE –P12
“UNDER JURISDICTION OF SAMBALPUR COURT ONLY”
MAHANADI COALFIELDS LIMITED
(A SUBSDIARY OF COAL INDIA LIMITED)
JUDGMENT
Corporate Office Office of the Chief General
Manager
M.C.L. Complex LAKHANPUR AREA
Jagriti Vihar P.O. bandhabahal – Via:
Belpahar
Burla – 768018 Dist.: Jharsuguda, Pin 768217
Dist: Sambalpur (Orissa) phone: 33202, STD CODE: 06645
Ref: No. MCL/CGM/LKPA/SO(M)/932 Date: 07.07.2004
To
M/s Dhansar Engineering Co. pvt. Ltd.
Page 11
12
Site Office: P.O. Jorabaga, Via – Belpahar,
Dist: Jharsuguda (Orissa)
Pin: 768217.
| basis at La | khanpur |
|---|
No. 276)
Dear Sir,
Kindly refer to your letter No. DECO/NIT-276/2004 dated
6.07.2004 on the above subject.
This is to bring to your notice that as per clause No.2 of
the work order forming part of the agreement the tendered
quantity can be increased by 30% and no claim shall lie on
the company for such variation till date only 105% (approx.) of
the awarded quantity has been executed by you. There is no
communication from MCL-HQ for finalization of new contract
for the above work till date.
In such condition you are requested to continue
your operation of surface miner at Lakhanpur OCP till
completion of 30% extra quantity. Withdrawal of operations of
Surface Miner at this stage will seriously affect dispatch of
coal to our Pit head customer (OPGC) and other linkage
customers earning a bad name to the company.
JUDGMENT
Thanking You,
Yours faithfully,
SD/-
GENERAL MANAGER
LAKHANPUR AREA
Copy to:
The Chairman-cum-Managing Director, MCL Buria
The Director (T), MCL, Burla
The General Manager (TC), MCL HQ, Burla
The Staff Officer (Mining) LKPA”
Page 12
13
8. The respondents, however, renewed their request to the
th
appellants to allow them to close the contract vide letters dated 8
th
July 2004 and 12 July 2004. The respondents finally wrote to the
| 004 whic | h reads t |
|---|
“ ANNEXURE – P15
DHANSAR ENGINEERING CO. PVT. LTD.,
SITE
P.O. Dhansar P.O. Jorabaga
Dhanbad – 828106 (Jharkhand) Via Belpahar
Ph: 0326 – 307161/7074. Dist.: Jharsuguda (Orissa)
Fax: 0326 303294 Ph.: 06645 -233222
E-mail –
decopl@dte.vsnl.net.in
Ref: No. DECO/NIT 276/2004 Date:
15.07.2004
To
The General Manager,
Lakhanpur Area, MCL,
JUDGMENT
Sub: Closing Down of work of Surface Miner at lakhanpur OCP
under NIT No. 276
Dear Sir,
A copy of our letter No. DECO/NIT/2004 dated
12.07.2004 addressed to CMD MCL Burla with copies to D(T)
and GM(TC), MCL HQ is enclosed herewith for your
information.
As notified this is to inform you that we are stopping
the work and withdrawing from operations at Lakhanpur
OCP with effect from 16.07.2004 (FN). It is not out of place
to mention that we had been expressing out intention to
Page 13
14
abandon execution after completing 100% of the work on
account of our un-economical plight out has been continuing
wit the execution to cooperate with the management to
arrange next recourse, so as to ensure that the production
schedule of Lakhanpur OCP does not suffer any set back.
| pathetic d<br>the con | ecision fr<br>tract per |
|---|
In view of the above situation we have no other
alternative but to withdraw from operation after working the
full period of the contract.
You are therefore requested to kindly take up final
measurement as on 15.07.2004 and finalise the contract.
Thanking you and assuring you of our best
cooperation to all time come.
Yours faithfully,
Sd/-
For Dhansar Engineering Co. Pvt. Ltd.
Copy to:
1. The CMD, MCL, Burla Fax No. 0663
-2432066/2542366
2. The D(T), MCL, Burla, Fax No. 0663 – 2542509
3. The GM (TC), MCL, Burla, Fax No. 0663 – 2542629.”
JUDGMENT
9. As the respondents had already informed the appellants of
their intention to withdraw from operation after the full contract
period, a fresh tender process was commenced by the appellants
which culminated with a letter of intent in favour of third party
Page 14
15
(Sainik Mining and Allied Services) but at a higher rate of Rs.31.50
per cubic meter.
| d 26th M | ay 2003 |
|---|
nd
Board of the appellants in its 72 meeting. The decision taken in
the said meeting was communicated to the respondents by letter
th
dated 8 December 2014 which reads thus:
“ANNEXURE R/9
MAHANADI COALFIELDS LIMITED
(A subsidiary of Coal India Limited)
P.O. – Jagruti Vihar, Burla, Distt. Sambalpur-768020
(Orissa)
Gram : SAMBCOAL,: Fax : (0663) 2542770
Phone : PBX :- (0663) 2542461 to 2542469
Ref. No. MCL/SBP/GM(TC)/2004/1047 Dt. 08.12.2004
To,
JUDGMENT
General Manager,
Lakhanpur Area
Dear Sir,
Enclosed herewith please find a copy of Extract
nd
from the Draft Minutes of the 72 meeting of the Board of
th
Directors of MCL held on 27 November, 2004 at Kolkata in
respect of imposing penalty by way of forfeiture of Earnest
Money Deposit of Rs. 20.00 lakhs to M/s. Dhansar
Engineering (P) Ltd., for non-performance of 130% of the
total contracted quantity under NIT – 276. The relevant
extract is appended below:-
“The Board deliberated on the subject in detail
and in consideration of the facts and circumstances
Page 15
16
| osed in the<br>16 – (Forfe | Agenda N<br>iture of E |
|---|
- 130% of Contract Quantity – 63,70,000.00 Cu.m.
- Final quantity executed – 53,49,437.55 Cu.m.
- Balance quantity to be executed – 10,20,562.45 Cu.m.
- Working rate - Rs. 17.00 per Cu.m.
- 20% of working rate Rs. 3.40 per Cu.m.
- Payable penalty for not executing
Upto 130% quantity Rs. 34,69,911.00
These penalties may be imposed individually or
collectively depending on the decision taken by the
Management. The imposition of penalty may be decided on
the background that the contractor working at a very low
rate has executed 108.47% in spite of incurring heavy losses
and withdrew only when the new contract was finished
ensuring that there is no loss of production.
JUDGMENT
Yours faithfully
Sd/- Illegible
General Manager (TC)
Encl : As above”
Page 16
17
th
11. The Board of the appellants in its 78 Meeting decided to
impose penalty for non-execution of the balance contract work by
the respondents and including the financial loss incurred by the
| ion of th | at work |
|---|
rate. In terms of that decision, an approval order for recovery of
rd
penalty was issued by the appellants on 3 November 2005 which
reads thus:
“ANNEXURE -19
MAHANADI COALFIELDS LIMITED
(A subsidiary of Coal India Limited)
P.O. – Jagriti Vihar
Burla – 768018
Distt: Sambalpur-768020 (Orissa)
Gram : SAMBCOAL,: Fax : (0663) 2542770
Phone : PBX :- 2542461 to 2542470
Ref: No. MCL/SBP/GM(TC)/2005/1100 Date:
03.11.2005
JUDGMENT
APPROVAL ORDER
Sub: Imposition of penalty to M/s Dhansar Engineering
Company Pvt. Ltd., under NIT-276 (Dt; 01.12.2002) for the
work of “Extraction and Transfer of Coal/Coal Measure Strata
by deploying “Surface Miners” on hiring basis at lakhanpur
OCP, Lakhanpur Area.
On recommendation of the committee to examine
the issue on imposition of penalty under NIT – 276 dated
02.12.2002 to M/s Dhansar Engineering Company Pvt. Ltd.,
for the work of “Extraction and Transfer of Coal/Coal
Measure Strata by deploying “Surface Miners” on hiring basis
at Lakhanpur OCP, Lakhanpur Area, the same has been
Page 17
18
| 57,40,655.<br>usand Six | 22 (Rupee<br>Hundred |
|---|
Sd/- General Manager (TC)
Distribution:
1. GM Lakhanpur Area
2. CGM(F) MCL, HQ
3. TS to CMD, MCL
4. TS to D(T), MCL
5. Secy. To D(F), MCL
6. Sanction Order file”
12. Aggrieved, the respondents filed Writ Petition under Article
226 of the Constitution of India and prayed as follows:
JUDGMENT
“ PRAYER
In the circumstances, it is therefore prayed that Your
Lordships be graciously pleased to issue a Rule NISI in the
nature of certiorari calling upon the Opposite Parties, to show
cause as why the impugned letter dated 08.12.2004 vide
Annexure-22 issued by the General Manager (TC), Mahanadi
Coal Fields Limited, Opposite party No.2 imposing penalty
shall not be quashed and if the Opposite Parties fail to show
cause or show insufficient cause make the said Rule absolute.
AND
Issue a Writ in the nature of mandamus directing the Opposite
parties to pay a sum of Rs. 79,01,434.60 to the Petitioner
Page 18
19
No.1 Company, which has been illegally withholding by the
Opposite parties.
| 4.60 of | Petitioner |
|---|
And for this act of Kindness the Petitioner shall as in duty
bound ever pray.”
13. The Writ Petition was opposed by the appellants by filing reply
affidavit. The appellants raised preliminary objection about the
maintainability of the Writ Petition. On merits, the appellants
asserted that the demand raised against the respondents was in
accord with the terms and conditions of the contract and if the
JUDGMENT
respondents were aggrieved by the same they were free to resort to
the procedure for settlement under clause 31 of the agreement. The
Division Bench of the High Court, however, allowed the Writ
Petition preferred by the respondents on the finding that it was not
permissible for the appellants to allot extra work to the respondents
at the fag end of the contract period in terms of clause 5 of the
contract which envisaged giving 45 clear days notice for variation of
Page 19
20
the quantity under the contract. That notice was given to the
th
respondents only on 11 June 2004 even though the extended
th
contract period was to expire on 15 July 2004. The Court held
| xtending | the con |
|---|
th
2004, within six days on 11 June 2004 the appellants decided to
enhance the contract quantity by 30%. That was not a bonafide act
and was unacceptable. The Court also held that the appellants had
not offered any explanation as to in what circumstances decision to
impose penalty was taken by the Board of Directors. The Court
further noted that the respondents had executed the contract upto
108.47% at a very low rate, and incurred heavy losses in that
regard. Further, a new contract for Lakhanpur OCP was already
awarded and there was no loss of production caused to the
JUDGMENT
appellants. On these basis, the Division Bench allowed the Writ
Petition in the following terms:
“16. Accordingly, the letter dated 8.12.2004 of the General
Manager (T.C) Mahanadi Coalfields Limited under
Annexure-22 proposing to levy shortfall penalty as well as, its
Approval Order dated 03.11.2005 under Annexure-A to the
counter affidavit are hereby quashed. The outstanding dues
payable to the petitioner be released in its favour within the
period of thirty days along with simple interest @ 8% per
Page 20
21
| etition is a | llowed wi |
|---|
14. Aggrieved, the appellants have filed the present appeal. This
th
Court passed an interim order on 12 April, 2013, directing to
maintain status quo as it existed on that date until further orders.
15. According to the appellants the High Court has committed
manifest error in entertaining the Writ Petition. Firstly, in respect
of a purely contractual matter and moreso when efficacious remedy
under clause 31 of the contract was available to the respondents for
redressal of their grievance. Secondly, on merits the High Court
JUDGMENT
has misconstrued and misapplied the contractual terms and in
particular clause 5 of the contract. However, if the terms and
conditions of the contract are read as a whole, it leaves no manner
of doubt that the appellants had the discretion to extend the
original contract period; and having done so at the request of the
respondents, the respondents were bound by the terms of the
th
contract till 15 July 2004. Further, before that date at any point of
Page 21
22
time, it was open to the appellants to reduce or increase the
contract quantity upto 30%. The sole plea of the respondents for
their inability to perform the contract was founded on financial
| of furth | er loss d |
|---|
That can be no consideration for walking out of the contract.
Moreso, after the extra quantity was allocated the respondents
could have asked for further time for completing the extra work, if
they were not in a position to complete the same within the contract
period. That request could have been considered by the appellants
appropriately. The respondents did not do so. Instead, they insisted
to withdraw from operation merely because the rate of contract was
not affordable to them. Resultantly, the appellants had to allot the
extra quantity of unfinished work by the respondents, to third party
JUDGMENT
at a higher rate. The fact that the appellants did not suffer any loss
of production, it does not follow that no financial loss was suffered
by the appellants due to higher rate paid for the unfinished extra
work. The appellants were, therefore, justified in recovering the
difference of rate in respect of unfinished extra work and penalty
therefor. That was a legitimate demand under the terms and
conditions of the contract between the parties.
Page 22
23
16. The respondents, on the other hand, contend that it was
unfair on the part of the appellants not to allow the respondents to
close the contract as per the original contract and within the
| d i.e. up | to 15th |
|---|
respondents cannot be made liable for the unfinished extra quantity
th
of work as that was allotted only on 11 June 2004, leaving very
little time for the respondents to complete the same for which the
appellants should blame themselves. According to the respondents,
the High Court was right in concluding that clause 5 of the
agreement did not permit the appellants to allot an extra quantity of
work to the extent of 30% at the fag end of the extended contract
period, absent 45 clear days notice mandated therein. Further, the
High Court has passed an equitable order also keeping in mind that
JUDGMENT
the respondents had already executed 108.47% of the contract work
by suffering heavy losses, which fact is substantiated from the
execution of new contract at the rate of Rs.31.50 per cubic meter as
against the rate of Rs.17/- per cubic meter payable to the
respondents. It is also contended that the demand for penalty
amount is unilateral and without any just cause. The same is
Page 23
24
illegal. Hence, contends the learned counsel, the appeal be
dismissed.
| he plea o | f the ap |
|---|
the Writ Petition filed by the respondents was limited to the letter
th
dated 8 December 2004, issued by the General Manager of the
appellants. The respondents had not challenged the extension of
th th
contract period till 15 July 2004 vide letter dated 5 June 2004,
the decision of the appellants to allot an extra quantity of 30% work
and much less the decision of the Board to impose penalty taken on
th
27 October, 2005 and communicated to the respondents vide
rd
Approval Order dated 3 November 2005. The High Court, however,
th
has not only set aside the letter dated 8 December 2004 but also
JUDGMENT
rd
the Approval Order dated 3 November 2005.
18. For doing so, the High Court has taken support from clause 5
of the Contract. That clause cannot be read in isolation. The other
terms and conditions of the contract must be read as a whole.
th
Clause 5 of the agreement dated 26 May 2003 posits authority in
the appellants to reduce or increase the tendered quantity by +/–
Page 24
25
30%, whilst the contract is subsisting. Indisputably, the original
th
contract period was upto 15 April, 2004. At the instance of these
th
respondents, the same stood extended till 15 July 2004. The extra
| the resp | ondents |
|---|
th
expiry of the extended contract period i.e. 15 July 2004. As the
contract period was extended and that decision was allowed to
attain finality, it inevitably obliged the respondents to fulfill all the
contractual stipulations under the original agreement including to
complete the assigned quantity of work - be it original quantity or
th
extra quantity - before 15 July 2004. The fact that they had to
suffer financial loss due to low contract rate could not be cited as
an excuse to extricate from that contractual obligation.
19. Failure to comply with the contractual obligation of executing
JUDGMENT
the original quantity of work or the extra work, as the case may be,
must visit the respondents with liability to compensate the
appellants in terms of other express clauses of the contract to the
extent of unfinished work and in particular the financial loss
suffered by the appellants for getting the same work executed
through a third agency at a higher rate. The fact that the
Page 25
26
th
respondents executed 108.47% of work before 15 July 2004, could
be no justification to relieve them of their obligation to compensate
the appellants with suitable amount for the unfinished contract
work (out of 130%).
20. Presumably to get over this position, the respondents relying
on clause 5 of the agreement would contend that the extra quantity
of work could not be allotted to them, absent 45 clear days notice
that too at the fag end of the contract period. This argument, in our
opinion, is a complete misreading of the said clause. It is one thing
to say that the contractor should be given sufficient time to
complete the extra work commensurate with the extra quantity
required to be executed by him. However, in law, it is not open to
contend that even though the contract period is still subsisting, the
JUDGMENT
principal (appellants) could not have exercised its option to increase
the quantity of work to the extent permissible under that clause, to
be executed by the contractor within the contract period. The
principal (appellants) could be asked to exercise their option to
th
extend the contract period beyond 15 July, 2004, to enable the
respondents to complete the unfinished extra work. If such request
Page 26
27
were to be made by the respondents, there would have been
corresponding obligation on the appellants to extend the contact
period commensurate with the increased quantity of work in terms
| ment. Th | e respo |
|---|
walk out of the contract for the sole reason that the contract rate
agreed by them was very low and was causing financial loss to
them. That can be no just reason to not fulfill their contractual
obligation.
21. Relying on the third sentence (last sentence) in clause 5, it was
contended that the employer could not have increased the tendered
quantity in absence of 45 clear days notice. We agree with the
appellants that the said stipulation would come into play only if the
respondents were also called upon to increase the machine capacity
JUDGMENT
by upto 30% extra “daily” quantity. In the present case, the
appellants merely allotted extra 30% quantity without requiring the
respondents to increase the daily quantity. There is marked
difference between increasing the extra quantity during the contract
period and that of increasing the extra “daily” quantity. In the case
of latter, the contractor would be required to step up the machine
Page 27
28
capacity for which giving of 45 clear days notice to him is
necessary. Suffice it to observe that the stipulation in the third
sentence of clause 5 providing for 45 clear days notice was not an
| llants to | allot ext |
|---|
30%, whilst the contract period was subsisting.
22. The respondents had then relied on the notings of the Project
th
Officer dated 26 January 2005 to contend that assigning of extra
work to the respondents at the fag end of the contract period was
doubted even by the said officer. The observations of the Project
Officer cannot be the basis to construe the scope of Clause 5 of the
contract. Besides, it was only an inter-departmental communication
which was duly considered at different level in the office of the
appellants, but finally it is the decision of the Board of Directors of
JUDGMENT
the appellants that must prevail. As a matter of fact, Clause 5 of the
agreement empowers the appellants to increase or reduce the
quantity of work upto permissible limit whilst the contract was
subsisting. That power having been exercised, the obligation of the
contractor to complete the extra work in terms of the subject
contract within the contract period or extended contract period was
Page 28
29
imperative. The respondents are not right in contending that the
appellants-Company had no authority to grant extension of time to
complete the enhanced quantity. This contention deserves to be
| ping in | mind the |
|---|
such as Clause 11.0 - providing for variation in the scheduled
quantity, extent and rate; Clause 13 - time for completion of
contract and more particularly Clause 14.0 - for extension of date of
completion. Clause 14.0 (e) was available and ought to have been
invoked by the respondents in this situation. It postulates that for
any other cause not specifically provided in sub-clauses (a) to (d) of
the same Clause, at the sole discretion of the appellants, the date of
completion could be extended, if it was found to be necessary
because of situation beyond the control of the contractor. That
JUDGMENT
clause could be invoked for the situation in which the respondents
were placed due to extra work allocated to them at the fag end of
the contract (extended) period.
23. In our opinion, clause 5 did not prohibit the principal
(appellants) to allot upto extra 30% quantity of work, for want of 45
clear days of subsisting contract period. Whereas, that option could
Page 29
30
be exercised by the appellants at any time until the contract period
th
was subsisting, which in this case was until 15 July 2004. In the
present case, such notice regarding increase of work upto 30%
| e 5 of th | e agree |
|---|
June 2004. On this finding, it must follow that the respondents
committed breach of their contractual obligation, in not completing
the balance work out of 130% of work (i.e. 130 - 108.47%). To that
extent the respondents became liable to compensate the appellants
including by way of penalty and in particular towards the financial
loss caused to the appellants due to assigning the unfinished work
to a third agency (contractor) at a higher rate. The amount
demanded by the appellants includes the difference of contractual
rate and the actual loss suffered by the appellants for completing
JUDGMENT
the unfinished work through a third agency (contractor) at a higher
th
rate, as is noticed from the communication dated 8 December
2004 sent to the respondents.
24. The respondents, would then contend that, the appellants
without giving any opportunity to the respondents unilaterally
imposed penalty and despite the noting of the General Manager that
Page 30
31
there was no loss of production to the appellants. Similarly, a doubt
was expressed by the Project Officer regarding giving extra work to
the respondents at the fag end of the contract period. The
| n the de | cision of |
|---|
1
vs. Union of India , in which it has been held that “where a sum is
named in the contract in the nature of a penalty, where loss in
terms of money can be determined, the party claiming
compensation must prove the loss suffered by it.” It is, however,
indisputable that financial loss was suffered by the appellants on
account of assigning the unfinished work to a third agency
(contractor) at a higher rate. In that, the contract rate for the same
work to be done by the respondents would have been at Rs. 17/-
per cubic meter, which the appellants were required to get it
JUDGMENT
executed at the rate of Rs. 31.50 per cubic meter through a third
agency. The fact that no loss of production was suffered by the
appellants cannot relieve the respondents of that liability. It is a
different matter that the respondents were not put to notice before
the final decision was taken by the appellants to recover the
financial loss along with penalty. The respondents could have
1 (1969) 2 SCC 554
Page 31
32
approached the appellants for reconsideration of their demand
towards penalty, in terms of Clause 30.3 of the contract; and
persuade the appellants to waive the penalty amount to be
| The r | esponde |
|---|
straightway approach the High Court by way of Writ Petition.
Notably, the High Court has not set aside the penalty amount as
such, but the entire demand being impermissible. Since we have
reversed the findings and conclusion of the High Court and even if
this appeal succeeds, the respondents can be granted an
opportunity to make a representation to the Appellants - company,
who in turn can deal with the same in accordance with law. If the
appellants accept the claim of the respondents about the
unjustness of penalty or quantum thereof, they would be free to
JUDGMENT
withdraw or modify their claim for recovery of penalty amount, if so
advised. In the event, the appellants reject the representation, they
will be free to recover the amount as demanded towards penalty
along with interest accrued thereon, as may be permissible in law.
However, that would not absolve the respondents from the financial
liability arising due to difference of rate of contract and the actual
cost incurred by the appellants to complete the unfinished work out
Page 32
33
of 130% of the contract quantity, through a third agency at a higher
rate. That can be recovered by the appellants from the respondents
along with interest accrued thereon at such rate, as may be
| en if th | e repre |
|---|
respondents for recall or modification of the penalty amount is
pending consideration. Considering the above, it is not necessary
for us to burden this judgment with the contention of the
respondents that the penalty imposed without any notice or hearing
to the respondents is vitiated; as also the decisions relied in support
of that contention in the case of Gorkha Security Services vs.
2
Government (NCT of Delhi) & Ors. and Kumari Shrilekha
3
Vidyarthi & Ors vs. State of U.P.
25. Similarly, it is not necessary for us to burden this judgment
JUDGMENT
with the decisions relied on by the respondents, to contend that
existence of alternative remedy is no bar to entertain a Writ Petition
under Article 226 of the Constitution of India, as held in the cases
4
of Popcorn Enterainment vs. City Development Corporation ,
2 (2014) 9 SCC 105
3 (1991) 1 SCC 212
4 (2007) 9 SCC 593
Page 33
34
Harbanslal Sahnia & Anr. vs. Indian Oil Corporation Ltd. &
5 6
Ors. , Union of India & Ors. vs. Tantia Construction Pvt. Ltd. ,
M.P. State Agro Industries Development Corpn. & Anr. Vs.
| hirlpool | Corpor |
|---|
8
Trade Marks, Mumbai . For, we have already examined the merits
of the controversy and more so granted liberty to the respondents to
make representation to the appellants on the question of justness of
the demand towards penalty or the quantum thereof. It will be
open to the respondents to pursue remedy in that behalf, as may be
permissible in law. We are not expressing any opinion one way or
the other on the issue of penalty amount. All questions in that
behalf are left open.
26. Accordingly, we partly allow this appeal. The judgment of the
JUDGMENT
th
Division Bench dated 7 November 2012 is set aside. The reliefs
claimed by the respondents in the Writ Petition are disposed of in
the above terms.
5 (2003) 2 SCC 107
6 (2011)5 SCC 697
7 (2007) 10 SCC 88
8 (1998) 8 SCC 1
Page 34
35
27. The appeal is partly allowed in the above terms with no order
as to costs.
………………………………….CJI
(T.S. Thakur)
…………………………………..J.
(A.M.Khanwilkar)
New Delhi,
September 27, 2016
JUDGMENT
Page 35