Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
PETITIONER:
U.P. STATE SUGAR CORPORATION
Vs.
RESPONDENT:
M/S. SUMAC INTERNATIONAL LTD.
DATE OF JUDGMENT: 04/12/1996
BENCH:
M.M. PUNCHHI, SUJATA V. MANOHAR
ACT:
HEADNOTE:
JUDGMENT:
THE 4TH DAY OF DECEMBER, 1996
Present:
Hon’ble Mr. Justice M.M. Punchhi
Hon’ble Mrs. Justice Sujata V. Manohar
Dushyant Dave, Sr. Adv., and Pradeep Misra, Adv. with
him for the appellant
V.C. Mahajan, Sr. Adv., Anil Dr. Sangal, Adv. with him
for the Respondent
J U D G M E N T
The following Judgment of the Court was delivered:
J U D G M E N T
Mrs. Sujata V. Manohar, J.
Leave granted.
The appellant, U.P. State Sugar Corporation entered
into an agreement dated 2nd of August, 1989 with the
respondent, M/s Sumac International Pvt. Ltd. under which
the respondent agreed to design, to prepare an engineering
lay-out and to manufacture or procure and supply to the
appellant the machinery and equipment for a complete sugar
plant for extension and modernisation of the appellant’s
existing sugar plant at Rohana Kalan, District
Muzaffarnagar, U.P. The respondent was required to set up a
new plant of 2500 TCD at a new site or an adjoining site
close to the existing sugar plant of the appellant. The
total contract price was fixed under Clause 2.1 of the
contract at Rs. 1780 lacs.
Under the terms of the agreement the respondent was
required to set up the plant and make it ready for
commercial production by 30th of November, 1990. The
agreement stated that in this regard time was of the essence
of the contract and if the respondent failed to do so the
consequences were also spelt out in the contract. Under
clause 3 of the contract a month-wise progressive delivery
report was to be submitted by the respondent and a PERT/CPM
chart had to be submitted and adhered to. Clause 4 which
dealt with delivery required the respondent to complete all
supplies by 15th of November, 1990 so that the plant could
be commissioned by 30.11.1990. Under Clause 11.1 the
respondent-seller was entitled to a reasonable extension of
time as decided by the purchaser if the purchase order was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
expressly suspended for no fault of the seller.
Under Clause 15 the respondent-seller was required to
furnish to the appellant five bank guarantees as specified
therein. These were:
1. A bank guarantee for timely delivery of plant and
machinery as provided in Clause 14.1 representing five
percent of the contract price referred to in Clause 2.1.
This was required to be furnished within 3-1/2 months of the
signing of the agreement.
2. The seller was required to furnish a bank guarantee in
respect of guaranteed performance of the plant and machinery
for an amount representing 5% of the contract price. This
guarantee was required to be furnished eight months before
the scheduled date of commissioning mentioned in Clause 4.1
or within six months from the date of the signing of the
agreement or after 2-1/2 months of the opening of the Letter
of Credit whichever of these dates was earlier.
3. Three bank guarantees in respect of advance payments to
be made by the appellant to the respondent under Clause
13.2(a) to 13.3(c) were required to be for Rs.89 lacs,
Rs.178 lacs and Rs.89 lacs respectively, representing 5%,
10% and 5% of the contract price respectively.
Under Clause 13.2 on receipt of the first of these bank
guarantees for Rs.89 lacs the first installment of advance
would be paid within a week from the date of signing of the
agreement. Or receipt of the second bank guarantee for
Rs.178 lacs the second advance would be paid by the
appellant to the respondent within 2-1/2 months of the
signing of the agreement subject to the respondent
furnishing various statements, certificates etc. as set out
in that clause. The third bank guarantee for Rs.89 lacs was
to be furnished against the advance to be paid by the
appellant to the respondent within 3-1/2 months from the
date of the signing of the agreement. These three bank
guarantees are thus in respect of the advance payments
required to be made by the appellant to the respondent.
Under Clause 15.5 all these bank guarantees are payable
on demand. It is expressly provided that it shall not be
open to the guarantor to know the reasons of or to
investigate or to go into the merits of the demand invoking
the bank guarantee or to question or challenge the demand or
to require the proof of the liability of the seller before
paying the amount demanded. It is further provided that the
invocation of the bank guarantee shall be binding on the
respondent and that the invocation of the bank guarantee
would not be affected in any manner by reason of the fact
that any dispute or disputes had been raised by the
respondent with regard to its liability. Nor would it be
affected by the fact that proceedings were pending before
any Tribunal, Arbitrator or Court with regard thereto.
Accordingly, the respondent furnished, inter alia, four
bank guarantees, one being a guarantee for due delivery and
the other three being the bank guarantees in respect of
advance payment of price. The total amount covered by the
bank guarantees securing advance payments is Rs.3.56 crores,
which amount was paid by the appellant to the respondent as
advance.
The contract was not carried out within the time
envisaged under the contract. Thereafter, at a meeting held
on 1.10.1991 between the appellant and the respondent, the
time for completion of this project was extended upto May
1992 and a detailed chart was drawn up for the completion of
the project by that date. No further extension of time has
been given by the appellant to the respondent thereafter.
The respondent, however, did not complete the said project
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
within the extended period.
By their letter dated 6th of September, 1995 the State
of U.P. through the Special Secretary, Govt. of U.P.
informed the Managing Director of the appellant that it had
been decided to transfer the Rohana Kalan (Muzaffarnagar
unit) of the appellant to the joint sector. As a result, the
expansion project of this unit should be cancelled and
appropriate action in accordance with law should be taken.
Thereupon the appellant cancelled the agreement by its
letter dated 7th of September, 1995 addressed to the
respondent. The appellant claimed a refund of the advance
payment of Rs. 3,14,78,093/- as unutilised and unadjusted
amount of advance payment. The appellant, by its four
letters all dated October 28, 1995 addressed to the
respondent invoked the three bank guarantees in respect of
advance payments after giving credit to the respondent for
material worth Rs.42 lacs which had been supplied till then.
The appellant also invoked the delivery guarantee for Rs.89
lacs. The bank guarantees so invoked are: Bank guarantee
no.9/47 dated 10.8.89 for Rs. 89 lacs. In this bank
guarantee credit for Rs.42 lacs has been given and the
invocation of the bank guarantee is only for the balance sum
of Rs.47 lacs. The second bank guarantee so invoked is
no.9/64 dated 20.11.89 for Rs.178 lacs. The third bank
guarantee is no.9/70 of 6.1.90 for Rs.89 lacs and the
fourth, delivery guarantee is no.12/88 dated 13.11.1990 for
Rs.89 lacs.
On 5.10.1995 the respondent filed a petition under
Section 20 of the Arbitration Act for appointment of an
arbitrator since the agreement between the parties provides
for arbitration. The respondent also filed two applications
for interim relief under Section 41(b) of the Arbitration
Act seeking interim stay against encashment of bank
guarantees. The Civil Judge, Senior Divisions, Muzaffarnagar
before whom these applications were filed, dismissed these
applications. In revision, however, these applications have
been allowed by the High Court and an injunction has been
granted restraining the appellant from enforcing these bank
guarantees. Hence, the appellants has come by way of the
present appeal.
These bank guarantees which are irrevocable in nature,
in terms, provide that they are payable by the guarantor to
the appellant on demand without demur. They further provide
that the appellant shall be the sole judge of whether and to
what extent the amount has become recoverable from the
respondent or whether the respondent has committed any
breach of the terms and conditions of the agreement. The
bank guarantees further provide that the right of the
purchaser to recover from the guarantor any amount shall not
be affected or suspended by reason of any disputes that may
have been raised by the respondent with regard to its
liability or on the ground that proceedings are pending
before any Tribunal, Arbitrator or Court with regard to such
dispute. The guarantor shall immediately pay the guaranteed
amount to the appellant-purchasers on demand.
The law relating to invocation of such bank guarantees
is by now well settled. When in the course of commercial
dealings an unconditional bank guarantee is given or
accepted, the beneficiary is entitled to realize such a bank
guarantee in terms thereof irrespective of any pending
disputes. The bank giving such a guarantee is bound to
honour it as per its terms irrespective of any dispute
raised by its customer. The very purpose of giving such a
bank guarantee would otherwise be defeated. The courts
should, therefore, be slow in granting an injunction to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
restrain the realization of such a bank guarantee. The
courts have carved out only two exceptions. A fraud in
connection with such a bank guarantee would vitiate the very
foundation of such a bank guarantee. Hence if there is such
a fraud of which the beneficiary seeks to take advantage, he
can be restrained from doing so. The second exception
relates to cases where allowing the encashment of an
unconditional bank guarantee would result in irretrievable
harm or injustice to one of the parties concerned. Since in
most cases payment of money under such a bank guarantee
would adversely affect the bank and its customer at whose
instance the guarantee is given, the harm or injustice
contemplated under this head must be of such an exceptional
and irretrievable nature as would override the terms of the
guarantee and the adverse effect of such an injunction on
commercial dealings in the country. The two grounds are not
necessarily connected, though both may co-exist in some
cases. In the case of U.P. Cooperative Federation Ltd. v.
Singh Consultants and Engineers (P) Ltd. (988 [1] SCC 174),
which was the case of works contract where the performance
guarantee given under the contract was sought to be invoked,
this Court, after referring extensively to English and
Indian cases on the subject, said that the guarantee must be
honoured in accordance with its terms. The bank which gives
the guarantee is not concerned in the least with the
relations between the supplier and the customer; nor with
the question whether the suppler has performed his
contractual obligation or not, nor with the question whether
the supplier is in default or not. The bank must pay
according to the tenor of its guarantee on demand without
proof or condition. There are only two exceptions to this
rule. The first exception is a case when there is a clear
fraud of which the bank has notice. The fraud must be of an
agregious nature such as to vitiate the entire underlying
transaction. Explaining the kind of fraud that may absolve a
bank from honouring its guarantee, this Court in the above
case quoted with approval the observations of Sir John
Donaldson, M.R. in Bolivinter Oil SA v. Chase Manhattan Bank
NA (1984 [1] AER 351 at 352): "The wholly exceptional case
where an injunction may be granted is where it is proved
that the bank knows that any demand for payment already made
or which may thereafter be made will clearly be fraudulent.
But the evidence must be clear both as to the fact of fraud
and as to the bank’s knowledge. It would certainly not
normally be sufficient that this rests on the uncorroborated
statement of the customer, for irreparable damage can be
done to a bank’s credit in the relatively brief time which
must elapse between the granting of such an injunction and
an application by the bank to have it charged". This Court
set aside an injunction granted by the High Court to
restrain the realisation of the bank guarantee.
The same question came up for consideration before this
Court in Svenska Handelsbanken v. M/s Indian Charge Chrome &
Ors. (1994 [1] SCC 502). The Court once again reiterated
that a confirmed bank guarantee/irrevocable letter of credit
cannot be interfered with unless there is established fraud
or irretrievable injustice involved in the case.
Irretrievable injury has to be of the nature noticed in the
case of Itek Corporation v. The First National Bank of
Boston etc. (566 Fed Supp. 1210). On the question of fraud
this Court confirmed the observations made in the case of
U.P. Cooperative Federation Ltd. (supra) and stated that the
fraud must be that of the beneficiary, and not the fraud of
anyone else.
On the question of irretrievable injury which is the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
second exception to the rule against granting of injunctions
when unconditional bank guarantees are sought to be realised
the court said in the above case that the irretrievable
injury must be of the kind which was the subject-matter of
the decision in the Itek Corporation case (supra). In that
case an exporter in the U.S.A. entered into an agreement
with the Imperial Government of Iran and sought an order
terminating its liability on stand by letters of credit
issued by an American bank in favour of an Iranian Bank as
part of the contract. The relief was sought on account of
the situation created after the Iranian revolution when the
American Government cancelled the export licences in
relation to Iran and the Iranian Government had forcibly
taken 52 American citizens as hostages. The U.S. Government
had blocked all Iranian assets under the jurisdiction of
United States and had cancelled the export contract. The
court upheld the contention of the exporter that any claim
for damages against the purchaser if decreed by the American
Courts would not be executable in Iran under these
circumstances and relisation of the bank guarantee/Letters
of credit would cause irreparable harm to the plaintiff.
This contention was upheld. To avail of this exception,
therefore, exceptional circumstances which make it
impossible for the guarantor to reimburse himself if the
ultimately succeeds, will have to be decisively established.
Clearly, a mere apprehension that the other party will not
be able to pay, is not enough. In the Itek case (supra)
there was a certainty on this issue. Secondly, there was
good reason, in that case for the court to be prima facie
satisfied that the guarantors i.e. the bank and its customer
would be found entitled to receive the amount paid under the
guarantee.
Our attention was invited to a number of decisions on
this issue -- among them, to Larsen & Turbro Ltd. v.
Maharashtra State Electricity Board & Ors. (1995 [6] SCC 58)
and Hindustan Steel Workers Construction Ltd. v. G.S. Atwal
& Co. (Engineers) Pvt. Ltd. (1995 [6] SCC 76) as also to
National Thermal Power Corporation Ltd. v. Flowmore Pvt.
Ltd. & Anr. (1995 [4] SCC 515). The latest decision is in
the case of State of Maharashtra & Anr. v. M/s National
Construction Company, Bombay & Anr. (JT 1996 [1] SC 156)
where this Court has summed up the position by stating, "The
rule is well established that a bank issuing a guarantee is
not concerned with the underlying contract between the
parties to the contract. The duty of the bank under a
performance guarantee is created by the document itself.
Once the documents are in order the bank giving the
guarantee must honour the same and make payment ordinarily
unless their is an allegation of fraud or the like. The
courts will not interfere directly or indirectly to withhold
payment, otherwise trust in commerce internal and
international would be irreparably damaged. But that does
not mean that the parties to the underlying contract cannot
settle the disputes with respect to allegations of breach by
resorting to litigation or arbitration as stipulated in the
contract. The remedy arising ex-contractu is not barred and
the cause of action for the same is independent of
enforcement of the guarantee." The other recent decision is
in Hindustan Steelworks Construction Ltd. v. Tarapore & Co.
& Anr. (JT 1996 [6] SC 295).
Clearly, therefore, the existence of any dispute
between the parties to the contract is not a ground for
issuing an injunction to restrain the enforcement of bank
guarantees. There must be a fraud in connection with the
bank guarantee. In the present case we fail to see any such
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
fraud. The High Court seems to have come to the conclusion
that the termination of the contract by the appellant and
his claim that the time was of the essence of the contract,
are not based on the terms of the contract and, therefore,
there is a fraud in the invocation of the bank guarantee.
This is an erroneous view. The disputes between the parties
relating to the termination of the contract cannot make
invocation of the bank guarantees fraudulent. The High Court
has also refereed to the conduct of the appellant in
invoking the bank guarantees on an earlier occasion on 12th
of April, 1992 and subsequently withdrawing such invocation.
The court has used this circumstance in aid of its view that
the time was not of the essence of the contract. We fail to
see how an earlier invocation of the bank guarantees and
subsequent withdrawal of this invocation make the bank
guarantees or their invocation tainted with fraud in any
manner. Under the terms of the contract it is stipulated
that the respondent is required to give unconditional bank
guarantees against advance payments as also a similar bank
guarantee for due delivery of the contracted plant within
the stipulated period. In the absence of any fraud the
appellant is entitled to realise the bank guarantees.
Before us, however, in the course of argument, learned
advocate for the respondent urged for the first time that in
this case there would be irretrievable injustice to the
respondent if the bank guarantees are allowed to be realised
because the appellant is a sick industrial company in
respect of which a referee is pending before the Board for
Industrial and Financial Reconstruction under The Sick
Industrial Companies (Special Provisions) Act, 1985. The
respondent contends that even if it succeeds before the
Arbitrator it will not be able to realise its claim from the
appellant. The mere fact that a reference under The Sick
Industrial Companies (Special Provisions) Act, 1985 is
pending before the Board, is, in our view, not sufficient to
bring the case in the ambit of the "irretrievable injustice"
exception. Under the scheme of the said Act the Board is
required to make such inquiry as it may deem fit for
determining whether any industrial company has become a sick
industrial company. Under Section 16(4) where the Board
deems it fit to make an inquiry or to cause and inquiry to
be made in this connection, it may appoint one or more
person to be special directors for safeguarding the
financial and other interests of the company or in the
public interest. Under Section 17 after making an inquiry,
if the Board is satisfied that a company has become a sick
industrial company, the Board may then decide, by an order
in writing, whether it is practicable for the company to
make its net worth exceed the accumulated losses within a
reasonable time. If this is practicable, then the Board
shall give such company the opportunity to make its net
worth exceed the accumulated losses. Under sub-section (3)
of Section 17 if the Board decides that this is not
practicable within a reasonable time, it may adopt measures
specified in Section 18 and provide for a scheme for
appropriate measures in relation to that company. There can,
therefore, be no presumption that the company will, in no
circumstance, be able to discharge its obligations.
Under Section 22 on which the respondent relies, where
in respect of an industrial company, an inquiry under
Section 16 is pending, or any scheme under Section 17 is
under preparation or a sanctioned scheme is under
implementation or when an appeal under Section 25 is
pending, then no proceedings for the winding up of the
industrial company or for execution, distress or the like
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
against any of the properties of the industrial company or
the appointment of a receiver in respect thereof can be
proceeded with; and no suit for the recovery of money or for
the enforcement of any security against the industrial
company shall lie or be proceeded with except with the
consent of the Board or, as the case may be, the Appellate
Authority. The respondent contends that its right to realise
its claim, if established, would be affected by reason of
Section 22 of the said Act. There is no material before us
to show that the appellant-company cannot make its net worth
positive. No scheme has been framed under the said Act so
far. Even under Section 22 there is no absolute bar against
any suit for the recovery of money. The suit cannot be
proceeded with except with the consent of the Board or the
Appellate Authority. Therefore, in an appropriate case, the
Board or the Appellate Authority is entitled to give its
consent to such a claim being proceeded with. This is not a
situation of the kind envisaged in the case of Itek
Corporation (supra) where there was no possibility
whatsoever of recovery of any amount from the purchaser. In
the present case, there is a good possibility of such
recovery. In any case, learned counsel for the appellant
has, on instructions, very fairly stated that the appellant-
company undertakes to earmark the amounts realised from the
bank guarantees in question for the purpose of recovery of
claims, if any, which the respondent may ultimately be found
to be entitled to recover from the appellant. Any scheme
which the Board may frame under the said Act will be subject
to this undertaking given by the appellant to set apart the
amounts realised under the bank guarantees in question for
meeting any validly adjudicated claims of the respondent
against the appellant under or arising from the said
contract. If any scheme is required to be framed, the Board
shall take into account this undertaking, while framing the
scheme.
Both sides are agreed that for a speedy resolution of
their disputes they are willing to refer all their disputes
under or arising from the said contract to the sole
arbitration of Justice R.M. Sahai (retd.), a retired Judge
of this Court. We accordingly refer all disputes between the
parties under or arising from the contract to the sole
arbitration of Justice R.M. Sahai (retd.). The arbitrator
may fix his remuneration in consultation with the parties.
The parties shall obtain appropriate directions from the
learned arbitrator in connection with the filing of claims,
replies etc. in accordance with law. The petition filed by
the respondent before the court of the Chief Judicial
Magistrate/Civil Judge, Muzaffarnagar under Section 20 of
the Arbitration Act is disposed of accordingly.
The appeal is allowed and the impugned judgment and
order of the High Court is set aside and the injunction
granted by the High Court is vacated. Parties will bear
their own costs.