Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 5665 of 2006
PETITIONER:
Rochem Separation Systems (I) Pvt. Ltd
RESPONDENT:
Mazagon Dock Ltd. and Ors
DATE OF JUDGMENT: 08/12/2006
BENCH:
Dr. AR. Lakshmanan & Tarun Chatterjee
JUDGMENT:
J U D G M E N T
(Arising out of SLP (C) No. 10826/2005)
Dr. AR. Lakshmanan, J.
Leave granted.
This appeal is directed against the judgment and final
order dated 21.04.2005 passed by the High Court of
Judicature at Bombay in Writ Petition No. 884 of 2005.
The appellant is a manufacturer of various membrane
technology systems and components using the Reverse
Osmosis Process (ROP) for desalination of sea water and
treatment of industrial effluents for converting them to
reusable water. The appellant also designs, manufactures and
services desalination plants. The appellant commenced its
operations in 1993 for manufacturing sea water, desalination
system using ROP and is also an ISO 900:2000 Company.
The appellant is also registered with the Ministry of Defence,
Director General of Quality Assurance and is the only Indian
company to have supplied plants for submarines of the Indian
Navy.
Respondent No.1 called for a tender for design,
manufacture, testing, supply, preservation, alignment,
installation, setting to work, commissioning and trials of the
complete supply of 4 units of 30 tonnes per day, self-
sustaining reverse osmosis plants per ship for 3 ships of P15A
class \026 destroyer of Indian Navy to be built by the 1st
respondent vide tender dated 20.06.2002, 04.07.2002 and
12.09.2002. The appellant submitted its original techno-
commercial and price bids as per the tender terms. The
appellant also submitted the clarification sought for by the
respondent No.1. Commercial discussions were also held
between the parties. The appellant submitted its
supplementary price bid dated 11.05. 2004 and the technical
bid dated 12.05.2004 as directed in the meeting dated
03.05.2004. The first respondent again sought technical
clarifications from the appellant subsequent to the submission
of supplementary price bid. The first respondent, by letter
dated 23.06.2004, set out certain comments of the 3rd
respondent on the revised technical offer submitted by the
appellant and sought further clarifications from the appellant.
The appellant submitted the technical clarifications as
required. The first respondent once again sought technical
clarification on 20.09.2004 and the appellant submitted the
clarification sought. The first respondent by a communication
acknowledged receipt of the appellant’s facsimile
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
communication dated 23.06.2004 and sought review and
advice. The first respondent once again wrote to the appellant
stating that it was in a position to open the price bids but that
additional time was required to complete the process of
obtaining internal approvals and, therefore, sought further
extension of the validity period of the price bids till
31.01.2005.
On 29.12.2004, the first respondent issued a letter to the
appellant stating that an un-priced price format had not been
submitted with the supplementary price bid of 12.05.2004,
which was neither an essential condition nor complained of
until then and hence it would not be considered and that a
new supplementary price bid in the format annexed for only
increase over the original technical specifications should be
submitted on or before 05.01.2005 though the decision as per
the meeting of 03.05.2004 was for submission of
increase/decrease over the original TSP. The appellant, by
letter dated 04.01.2005 addressed the first respondent to
extend the advantages of advancements in technology leading
to a reduction in price to respondent No.1. The appellant
submitted the supplementary price bid as per the new format.
The first respondent had opened the original offer and the
supplementary price bid in the new format but did not inform
the appellant about the opening of the price bids. The
appellant wrote to the first respondent enquiring about the
status of the opening of the tender price bids but did not
receive any reply. Several reminders were sent. The first
respondent stated that the Management approval was granted
on 18.02.2005 and that the letter of intent was given to
respondent No.4. The first respondent sent a belated reply to
the reminder of the appellant dated 09.02.2005 stating that
the supplementary price bid of 12.04.2004 was rejected as the
unpriced price format was not submitted and that it was not
confirmed in the bid that it was the increase/decrease over the
original technical specifications and that on opening of the
bids, it was found that the appellant was not L1 and hence it
was mandatory to initiate price negotiations with the other
bidder. The appellant questioned the action of the first
respondent as discriminatory. Thereafter, appellant filed writ
petition under Article 226 of the Constitution of India in the
High Court and questioned the discriminatory and biased
action of the first respondent in permitting respondent No.4 to
alter its original offer nearly 2 years later in the new format
given to the 4th respondent which was different from that
furnished to the appellant. By judgment and final order dated
21.04.2005, a Division Bench of the High Court rejected the
writ petition holding that it would not be proper to interfere at
that stage.
Being aggrieved by the above-mentioned judgment the
appellant has filed the above appeal in this Court.
The order passed by the High Court reads as follows:-
"1. Heard Mr. Dwarkadas in support of this petition, Mr.
Mandalik for Respondent No.1 and Mr. Chavan for
Respondent nos.2 & 3. The grievance made in this petition
is in respect of award of contract to Respondent No.4. Two
points are raised principally to challenge this award. Firstly
it is stated that in December, 2004 there was a variation in
the terms offered to Respondent No.4 which was a favourable
variation. The second submission is that the Petitioner was
ready to decrease the price offered earlier. The second
submission is basically to submit that there are mala fides
on the part of decision making authorities.
2. Respondent No.1 has filed reply and it has placed on
record that the Petitioner participated all throughout in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
decision making process. The terms which were given while
inviting the bids were common to both the parties. It is only
during the course of negotiations that the parties required
clarifications and that is how the letters were written to both
the parties in December, 2004. There is some variation in
them. That variation is related to the questions and queries
raised by the parties concerned.
3. In the circumstances, it would not be proper for us to
interfere at this stage. Petition, therefore, is rejected."
We heard Mr. R.F. Nariman, learned senior counsel for
the appellant and B. Datta, learned ASG for R-1 and Mr.
Upamanyu Hazarika and Mr. Swetank counsel for respondent
No.4. At the time of arguments, our attention was invited to
the various communications and letters which were exchanged
between the appellant, the first respondent and 4th
respondent.
On 11.05.2005, this Court ordered notice to the
respondents and also passed an order that any action taken in
regard to the disputed contract shall be subject to further
orders of this Court. Parties were asked to file counter
affidavit, rejoinder affidavit etc. On 03.08.2006, this Court
directed respondent No.1 to produce the original records
pertaining to the tender in question. The parties were
permitted to peruse the original records in the presence of the
Registrar (Judl.) and the representative of respondent No.1.
Additional affidavits were also filed after the inspection of the
files.
Mr. R.F. Nariman, learned senior counsel appearing for
the appellant made the following submissions:-
(a) The High Court has erred in holding that the
appellant had participated in the decision-
making process particularly in the 2nd
supplementary price bid submitted on January
5, 2005 as such participation by the appellant
was involuntary in the face of the two letters
sent by the appellant dated 04.01.2005 and
05.01.2005.
(b) The High Court has failed to notice that even
the letter dated 29.12.2004 discriminates
between the appellant and respondent No.4 as
it permits respondent No.4 to include
additions/deletions in the new supplementary
price bid including two additional items in the
form whilst the appellant was directed to
include only increase over the original offer
made by them despite the TNC/CNC meeting
dated 28.04.2004 and 03.05.2004 respectively
permitting the appellant to increase/decrease to
the original offer, which per se discriminates
against the appellant and which has caused
grave prejudice to the appellant. Several other
submissions were also made in regard to the
letter dated 29.12.2004. Many other factual
and legal contentions have also been raised in
the grounds of appeal.
(c) That the High Court has failed to consider that
whilst the first respondent has permitted
respondent No.4 to alter its original offer of
2002 contrary to tender conditions, it has
peremptorily rejected the offer of the appellant
to extend the benefit of lower price resulting
from technological advances, though it would
have accrued to the benefit of respondent No.1
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
despite the same is in accordance with tender
conditions 1.6.3 which according to Mr.
Nariman is patent discrimination and contrary
to public interest.
Mr. Datta, learned Additional Solicitor General, after
inviting our attention to the various documents and records
submitted that commercial discussions were held with the
appellant in which it was recorded:
"Based on TNC meeting the firm stated that they
agreed to execute the order as per MDL & Navy’s
requirement. After prolonged deliberations, the firm
stated that based on TNC meeting they will submit
their technical clarification and supplementary price
bid to the original offer, only for the increase/decrease
scope, over and above Tender’s TSP by 12.5.2004.
However, the Committee insisted to submit their
supplementary price bid in a sealed envelope by
12.5.2004 at 1200 hrs\005"
Identical decision was taken qua the respondent No.4.
On 12.5.2004, Supplementary bids were submitted by
the appellant and respondent No.4 in sealed envelope. These
bids were not accompanied by Proforma Price Scheme
Blanking the prices and indicated items quoted.
On 15.12.2004, offers made by the appellant and
respondent No.4 was declared to be technically acceptable.
The net result was that the appellant as also respondent
No.4, were required to provide certain additional items/satisfy
certain requirements over and above what was quoted by them
in their original offer submitted in October, 2002. Both in the
case of the appellant and respondent No.4, there was an
increase in scope over and above what was quoted by them in
October, 2002 and there was no decrease whatsoever on any
account. It was in respect of these additional requirements
that supplementary bids were called from the appellant and
respondent No.4. It was not permissible for either the
appellant or the respondent No.4 to revise their original bid
submitted in October, 2002 but instead only supplement the
same by quoting for the additional requirements.
On 29.12.2004 letters were sent to both the appellant
and respondent No.4 requesting them to submit their
supplementary bid only by indicating the change over the
original offer. A supplementary rate sheet was enclosed along
with the said letter setting out the additional
items/requirements in respect of which the parties were
required to quote. The parties were also told that the earlier
supplementary bid submitted on 12.05.2004 will not be
considered. This letter was necessitated since the parties had
not submitted any Proforma Price Schedule Banking the prices
and indicating items quoted/not quoted, as required under
Tender Condition IN-202.
On 04.01.2005, the appellant replied to the letter dated
29.12.2004 and sought permission to revise the original price
bid submitted in October, 2002 instead of just quoting for the
additional items. The said request was declined by the
respondent No.1 as the same would virtually amount to
starting the tender process de novo.
On 05.01.2005, the appellant submitted its
supplementary price bid in the prescribed format. Price bids
were opened on 17.01.2005 and respondent No.4 found to be
L1. PNC was conducted with respondent No.4 on 03.02.2005.
On 18.02.2005, LOI issued to respondent No.4. On
22.02.2005 purchase order placed on respondent No.4.
Thus, he submitted from the pleadings filed before this
Court, the following facts stand admitted by the appellant:-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
i) That the amount quoted by the appellant vide
its Bid dated 04.10.2002 was much higher
than that was quoted by respondent No.4
while the amount quoted by the appellant was
around Rs.11.92 crores, the amount quoted by
respondent No.4 was around Rs.8.57 crores.
ii) Even assuming that the original bid of
respondent No.4 did not include any quotation
for the Second Stage RO Plant, even if the
supplementary offer submitted by respondent
No.4 (which admittedly included the Second
Stage RO Plant) is added to its original offer,
even then the total amount quoted by
respondent No.4 is lower than the original
price quoted by the appellant.
The entire case of the appellant rests on the premise that
it should be allowed to retract from its original offer dated
04.10.2002 and be allowed to submit a "revised" price bid
instead of a "supplementary" price bid confined to "additional
items/requirements" not covered by the original offer dated
04.10.2002.
At no stage was it ever contemplated that the parties be
allowed to withdraw/retract from their original offer and
submit a fresh/revised offer. The understanding was always
clear that the parties would only give their supplementary bid
in respect of the additional items/requirements not covered by
their original offer. However, as it transpired before the High
Court, and now again before this Court that in the guise of
submitting its "supplementary bid" in May, 2004, the
appellant sought to completely revise its original bid, which is
not permissible. Vide letter dated 29.12.2004, the respondent
No.1 rightly asked both the appellant and the respondent No.4
to submit their supplementary price bids in the proper format.
The said request of the respondent No.1 was complied with by
the appellant on 5.1.2005. The writ petition was belatedly
filed on 28.03.2005 clearly as an afterthought. There is no
infirmity in the decision making process warranting any
interference from this Court.
Mr. Datta has also drawn our attention to the affidavit in
reply of respondent No.1.
Respondent No.4 also filed a detailed affidavit in reply to
the grounds of appeal. According to learned counsel for
respondent No.4 that he has complied with the formalities,
terms and conditions and in view thereof, the contract is
concluded between respondent No.4, and 1 and hence the
question of setting aside and or quashing the tender process
or any other reliefs as prayed for in the present appeal does
not arise. Respondent No.4 has also denied the averments
and allegations raised by the appellant in the present appeal
against the 4th respondent with regard to the tender in
question. Learned counsel took us through the said counter
affidavit. A rejoinder affidavit was filed by the appellant to the
affidavit in reply filed on behalf of respondent No.4. Our
attention was also drawn to the minutes regarding inspection
and the affidavit in rejoinder on behalf of the appellant to the
affidavit filed on behalf of respondent No.1. Voluminous
documents have been filed before us in this appeal. It was
specifically contended that the action of respondent No.1. in
rejecting the bids of the appellant was arbitrary, collusive and
contrary to the principles laid down by this Court in the
acceptance of tenders/bids by the government/its agencies. It
was also strenuously contended by Mr. Nariman that the
tender conditions would not permit respondent No.1 to
consider the bid of respondent No.4 which was admittedly not
complete at the time of its first submission and that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
respondent No.1 could not permit respondent No.4 from re-
submitting its bid with additions to the original offer on the
ground that the requirements were not understood at the time
of submitting the original offer.
The Court has, therefore, to see as to whether the action
of respondent No.1 in permitting respondent No.4 to include a
basic requirement of the original offer subsequently without
offering any such opportunity to others is discriminatory and
bias.
The Court also has to see as to whether the action of
respondent No.1 in permitting respondent No.4 to submit
supplementary price bid by indicating additions and deletions
while at the same time, calling upon the appellant to submit
supplementary price bid only by indicating increase over
original offer was not discriminatory, arbitrary and bias.
A careful perusal of the judgment of the High Court
impugned in this appeal would only go to show that the High
Court has failed to consider the real issues raised by the
appellant and proceeded merely on the basis of a reply filed by
appellant No.1 that does not address or touch upon such
issues as contended by Mr. Nariman.
It is seen from the order passed by the High Court that
the writ petition was dismissed at the admission stage. No
counter affidavit was filed by the 4th respondent and 4th
respondent to whom the approval was granted on 18.02.2005
and the letter of intent was given to them on the same day was
not heard at all. Learned counsel for respondents 1,2 and 3
alone were heard. Two points were raised principally to
challenge the award in favour of the 4th respondent by the
appellant. The first point was in respect of variation in terms
offered to respondent No.4 which according to the appellant
was a favourable variation. The second submission was that
the appellant was ready to decrease the price offered earlier.
The second submission was basically to submit that there are
malafides on the part of decision making authorities. The
High Court without considering the mala fides on the part of
the decision making authorities dismissed the writ petition
without considering the rival submissions and the documents
filed before it. The High Court though stated in its order that
there was some variation in the terms had not considered the
nature of variation at all.
The project in question and the work sought to be
undertaken by the tender process is one of national
importance. Learned ASG submitted that the tender process
is purely of commercial nature and no interference by this
Court is called for. The High Court, in our opinion, ought to
have heard respondent No.4 in whose favour the letter of
intent is now given. The High Court has not disposed of the
writ petition after affording opportunity to all the parties and
in particular the fourth respondent. In our opinion, the
matter requires deep and elaborate consideration in the nature
of pleadings filed by the appellant, respondent No.1 and
respondent No.4. We, therefore, set aside the order passed by
the High Court and remit the matter to the High Court with a
request to dispose of the writ petition on merits after affording
opportunity to all the parties. Since the project is of national
importance, the High Court is requested to dispose of the
same on priority basis and at any rate not later than 28th
February, 2007. Both the appellants and the other
respondents are at liberty to raise the grounds/contentions
that have been raised in this Court before the High Court by
way of additional pleadings. They are also at liberty to file the
civil appeal grounds, counter by all the parties and the
rejoinder and other documents and records before the High
Court for a fair and proper consideration of the same by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
High Court.
In the result, the appeal filed by the appellant is allowed
and the order of the High Court stands set aside and matter is
remitted back for fresh disposal. No costs.