Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
THE HINDUSTAN VIDYUT PRODUCTS LTD.
Vs.
RESPONDENT:
STATE OF RAJASTHAN & ORS.
DATE OF JUDGMENT: 24/03/1999
BENCH:
S.R.Babu, S.N.Phukan
JUDGMENT:
RAJENDRA BABU, J. :
The District Judge, Jaipur City, appointed a sole
arbitrator to adjudicate upon the disputes that had arisen
between the parties to these appeals in relation to a
transaction by which the appellant had agreed to supply 3290
k.ms. of PANTHER Conductor to the respondent. The
appellant filed a detailed statement of claims and we may
summarise the same as follows :- i) Outstanding bills
5,21,143.30
ii) Steel price variation 13,23,661.93
iii) Amount of Bank Guarantee 15,67,278.54
------------------------ 34,12,023.77
LESS
i) Raw Material - 11,38,800.48
ii) Cash advance - 3,29,348.83
- 14,68,149.31
----------------------- Rs. 19,68,149.31
----------------------
The respondents also made claims which are as follows
:-
i) Damages on account of 28,65,555.17 risk purchase
ii) Balance 20% cash advance 3,29,581.00
iii) Interest @ 18% on 1,14,030.50 Rs. 3,29,581.00
iv) Interest charges @ 18% 3,15,134.23 on 11,28,018
v) Recovery on account of 3,93,321.35 excess payment @
144/- on 2652 km. ----------------------- 40,51,433.08
-----------------------
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
The respondent further stated that the appellant would
be given adjustment on return of the following raw material
failing which should be ordered to pay a sum of Rs.
47,27,771.20 :- i) Aluminium steel in the form of 3/8 size
Aluminium wire rods 288.957 MT
ii) H.T.G. Steel wire 3.0 mm size 186.400 MT
The arbitrator awarded the claims of the parties in
the following terms :- Claim of claimant - petitioner Claim
No. Amount awarded
1) 5,21,143.30 3,29,806.89
2) 13,23,661.93 Nil
3) 6,99,816.20 Nil
4) 10,00,000.00 (damages) Nil
Claim of Respondent Amount claimed Amount awarded
1) 3,29,581.00 3,29,348.83
2) 1,14,030.00 Nil
3) 3,93,321.35 Nil
Damages for the purchase of 478 km from market -
33,93,800-40
Being the contract price of 478 km. - 19,39,932-60
-------------------- Balance payable by Company
14,53,932.60 -------------------- Finally, the arbitrator
gave the following amount :-
Company Respondent
3,29,806.89 3,29,348.83
14,53,932.60 -------------------- 17,82,781.43
(-) 3,29,806.89 -------------------- Net payable by
Company 14,53,474.54 ------------------- It was further
directed that since the Government has already recovered Rs.
15,67,278.54, therefore, after adjusting Rs. 14,53,474.54
the Company is entitled to receive Rs. 1,13,804/- plus
interest @ 16%. A letter was sent by the advocate for the
respondent on the date when the award was made known to the
parties pointing out that certain amount of adjusting the
cost of raw material had not been awarded in favour of the
respondent and it is stated therein that this apparent error
should be corrected in the award. The arbitrator
acknowledged the objection having been raised and a letter
being sent to him but he expressed his helplessness to
consider the same as after pronouncement of the award he had
become functus officio. The respondent filed an application
in Suit No. 122 of 1979 before the District Judge, Jaipur
city, under Sections 15 and 16 of the Arbitration Act, 1940
for correcting the award. The learned Judge rejected the
claim made by the respondent and made the award the rule of
the court. Against that order an appeal was filed in the
High Court and the High Court allowed the appeal and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
modified the award directing the appellant to pay a further
sum of Rs. 11,38,800.48 to the company as the cost of raw
material which is stated to have been admitted by the
company in the statement of claim. Hence this appeal by
special leave.
After referring to the decisions of this Court in
Hindustan Construction Company Limited v. State of J & K,
1992(4) SCC 217; State of Bihar v. Hanuman Mal Jain, 1997
(11) SCC 40; M.C.D. v. Jagannath Ashok Kumar, 1987 (4)
SCC 497 and Naraindar Lilaram Adnani v. Narsingdas
Naraindas Adnani & Ors., 1995 Supp. (1) SCC 312, it is
submitted that the finding of the High Court that the
arbitrator has failed by over-sight to consider the claim of
the respondent for a sum of Rs. 11,38,800.48 is not
permissible at all and that the award needed modification is
not correct and the scope for interference in such matter is
very much limited. The learned counsel for the respondents
urged that the High Court had correctly given effect to what
was obvious from the pleadings and no dispute regarding the
same had arisen for adjudication. The arbitrator set out
the claims of both the parties and made an award without
setting out reasons for making such an award. One of the
claims made by the appellant has been referred to by us
earlier in the course of this order which excludes one of
the amounts, i.e., Rs. 11,38,800.48 thus making a claim
after deducting this amount for a sum of Rs. 9,68,149.31
and the respondents had claimed return of left over
quantities of aluminium products as its equivalent in money
is a sum of Rs. 47,27,771.20. The arbitrator considered
this aspect of matter as follows :- On merits I hold an
consideration of the entire evidence including accounts
relating to bills sent by the company to the Government that
the company refused to supply the remaining 478 kms. of
conducts in December 1973 and this refusal had no
justification. Thus the company committed breach of
contract in December 1973. I compute damages for this
breach in December 1973 at Rs. 33,93,800. The Government
in its statement of claim and the learned counsel for both
the parties during arguments stated that Rs. 19,39,867.40
should be deducted as contract price of 478 kms. of
conductor from Rs. 33,93,800 to arrive at the amount of
damages payable by the company. Thus the company is liable
to pay Rs. 14,53,932.60 as damage to the Government.
As a result of the above mentioned decisions the
company is entitled to receive Rs. 3,29,806.89 while it has
to pay Rs. 3,29,348.83 plus Rs. 14,53,932.60 to he
Government.
Thus the Government is entitled to recover Rs.
14,53,474.54 from the company.
However, the Government on 15.11.75 had recovered Rs.
15,67,278.54 from the company by encashing bank guarantee
under orders of the Supreme Court. Therefore, now the
Government has to refund Rs. 1,13,804/- to the company.
The Supreme Court in its order had also directed that if the
Government has to refund any sum from the amount recovered
under its order, then the Government will refund the same
with interest at the rate that the company paid to its
Bankers. The Dena Bank, New Delhi, has certified that it
has been charging interest at the rate of 16% per annum from
the company since April 1975. The correctness of this rate
has not been challenged on behalf of the Government.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
Therefore, the Government is liable to pay interest @ 16%
per annum from 15.11.75 on Rs. 1,13,804.00 till its
payment.
No other point was argued before us.
Accordingly I hold after final adjustment that the
company is entitled to recover as refund from the Government
Rs. 1,13,804.00 with interest @ 16% per annum from 15.11.75
till realisation.
The Government claims return of certain amount of
aluminium and steel wire quantities specified in its
statement of claims. Its claim is that the Government
imported aluminium and purchase steel wire through the
company exclusively for manufacture of 3130 kms. of Panthar
conductor. The company failed to supply 478 kms. of
Panthan conductor and the said material to that extent is
with the company. Accordingly, the company is liable to
return the left over quantities or to pay its equivalent
amounting to Rs. 47,27,771.20. I fail to see any force in
this claim and I reject it.
When the claim either for return of the raw material
or for its price had been rejected, we fail to see as to how
the respondent becomes entitled for adjustment of the amount
regarding raw material supplied and it cannot be termed as
an inadvertent error of a clerical or arithmetical nature
which can be corrected under Section 15 of the Arbitration
Act. The High Court has exceeded its jurisdiction in
interfering with the award particularly when the award was a
non- speaking award and the claims made by the parties have
been borne in mind by the arbitrator in passing the award
and the arbitrator had not omitted any claim made by any of
the parties. Therefore, we think the High Court was not
justified in interfering with the award which was made the
rule of the court by the District Judge, Jaipur city.
We allow this appeal, set aside the order made by the
High Court allowing the claim of Rs. 11,38,800.48 on
account of raw material supplied by the respondent. If any
amount has been paid by the appellant or deposited in the
court pursuant to an interim order made by this Court the
same shall be refunded and the security furnished thereto
shall stand discharged.