Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
CASE NO.:
Appeal (civil) 11031 of 1996
PETITIONER:
MANOCHA CONSTRUCTION COMPANY (NOW DISSOLVED)
Vs.
RESPONDENT:
VS.
DATE OF JUDGMENT: 16/02/2001
BENCH:
S. Rajendra Babu & K.G. Balakrishnan.
JUDGMENT:
K.G. BALAKRISHNAN, J.
L...I...T.......T.......T.......T.......T.......T.......T..J
This appeal is directed against the judgment and order
passed by the Division Bench of the High Court of Madhya
Pradesh at Jabalpur in Civil Revision No. 296 of 1992 on
30th January, 1996. By the impugned judgment, the Division
Bench dismissed the said Civil Revision filed by the
appellant under Section 19 of the Madhya Pradesh Madhyastham
Adhikaran Adhiniyam, 1982, challenging the award dated
16.3.1992 passed by the M.P. Arbitration Tribunal, Bhopal
in Reference Case No. 11/1987.
The appellant, a construction company, entered into an
agreement on 18.3.1982 with the respondent State of Madhya
Pradesh, for the construction of a Dam in Barchar Tank
Project, in the Sidhi district. The total cost of the
construction was Rs.1,22,19,779/-. As per the work order
given to the appellant, the appellant was to complete the
work within a period of 15 months. The appellant was,
however, given several extensions and the last of such
extension was to expire on 30.6.1987. Payments were made to
the appellant during the course of the progress of the work.
The total quantity of the earth work to be done was 5,02,929
Cubic Meters. As per the contract, the appellant was also
bound to do an additional 10% of the agreed earth work at
the rate given under the agreement. According to the
appellant, more than 10% of the agreed quantity of the earth
work was carried out and for the additional quantity of the
earth work done, a claim was made by him @ Rs.34.50 per
Cubic Meter. The agreed rate for the earth work was Rs.15/-
per Cubic Meter. Dispute arose between the parties as to
the rate payable for the additional quantity of the earth
work carried out and the matter was referred to the
Arbitration Tribunal. The Tribunal passed an award on
14.7.1988 and by this award the rate of Rs.22/- per Cubic
Meter was fixed for the additional earth work done by the
appellant. Aggrieved by this award, the appellant preferred
a Civil Revision (Registered as C.R.No. 459 of 1988) before
the High Court of Madhya Pradesh. The respondent State of
Madhya Pradesh also filed Civil Revision No. 512 of 1988
against the said award of the Tribunal. Whereas the Civil
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
Revision filed by the State was dismissed, the Revision
filed by the appellant was remitted to the Tribunal with a
specific direction, which is to the following effect :
"For the aforesaid reasons, the award of compensation
for this extra work at Rs.22/- per cubic metre is hereby set
aside and to that extent Civil Revision No. 459 of 1988 is
allowed. Civil Revision No. 512 of 1988, filed by the
State Government of M.P. and others is hereby dismissed.
The matter shall go back to the Arbitration Tribunal, which
shall, after giving due opportunity to the parties,
determine the amount of compensation payable to the
contractor, i.e., M/s Manocha Construction Co., for the
additional work done, in accordance with the provisions of
clause 4.3.13.3 of the agreement. We affirm the finding of
the Tribunal as to the contractor’s entitlement to the
compensation for this additional work done."
Pursuant to the above Revisional order, the matter was
again considered by the Arbitration Tribunal and a fresh
award was passed on 16.3.1992. The Tribunal held that the
work relating to the additional quantity of the earth was in
respect of a temporary ’bund’ and the construction of the
same was completed by November/December, 1985. Therefore,
in view of sub-clause (d) of Clause 4.3.13.3, the rate had
to be fixed on the basis of the then prevailing market rate.
On that basis the claim of the appellant was considered and
it was held that the appellant was entitled to get at the
rate of Rs.15.70 per Cubic Meter. The award thus passed by
the Tribunal was challenged by the appellant before the High
Court, but the Division Bench by its order and judgment as
aforesaid, declined to interfere with the same. Hence this
appeal .
We heard the learned Senior Counsel, Mr. S.B. Sanyal,
for the appellant and also the counsel for the respondents,
Mr. Krishnan Venugopal. Learned counsel for the appellant
contended that the Tribunal had committed a serious error in
appreciating the evidence and wrongly held that the
additional earth work was completed in November/December,
1985 and thus adopted inappropriate criteria for fixing the
total amount due to the appellant. It was argued that the
series of correspondence between the appellant and the
respondent would show that the officers of the respondent
State Govt. had agreed to pay @ Rs.25.25 per Cubic Meter
while the appellant had all along been insisting for payment
@ Rs.34.50 per Cubic Meter for the additional earth work
done by him. Therefore, it is argued that the Tribunal
passed a wrong award and thereby failed to exercise the
jurisdiction vested in it and the High Court should have
interfered by virtue of the powers conferred on it under
Section 19 of the Madhya Pradesh Madhyastham Adhikaran
Adhiniyam, 1982, to correct the material irregularity
committed by the Tribunal by improper appreciation of the
evidence.
The learned counsel for the respondent State, on the
other hand, contended that the direction relating to the
construction of a temporary ’bund’ was carried out by the
appellant in 1985 and the rate of Rs.25.25 per Cubic Meter
agreed to be paid to the appellant for the additional earth
work was in respect of the main Dam work. He argued that
the appellant had been paid at a higher rate than the
contract rate.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
It is evident from the pleadings that the additional
earth work, for which the appellant had been bargaining for
a higher rate, related to the construction of the temporary
’bund’ in question. This temporary ’bund’ was constructed
for stopping the flow of the river to enable the department
to clear the Dam area. In paragraph 2 of the letter written
by the appellant to the Superintending Engineer of the
respondent State on 25.12.1986, it is stated as under :
"The agreemented quantity of earth work was given as
502929 Cums in Schedule ’G’ of the contract document.
During the course of execution, we were instructed to
construct the temporary bundh for stopping the flow of river
to enable the department to clear the dam seat of Nalla
portion. The work was taken up by us in the month of
October 1985 and the same was completed in the month of
November 1985. We were paid the rate of Rs.15/- per Cum
(tendered rate) for this item of work for the total of
48651.67 Cums in our running bills No. 20 dated 15.3.86 and
21 dated 4.5.86."
[Emphasis supplied]
The dispute referred to the Arbitration Tribunal related
to the rate payable for this work. In its first award dated
14.7.1988, the Arbitration Tribunal had considered that the
additional work related to the temporary ’bund’ constructed
by the appellant and the total earth work done by him was
49027.64 Cubic Meters. Therefore, there cannot be any
dispute that the additional work related to the construction
of the temporary ’bund’. It is also not possible for the
appellant to contend that this work was carried out in May,
1986 after the receipt of Exh. P-12 letter dated 5.4.1986
from the Superintending Engineer. The contention of the
appellant (I) that there was correspondence between the
appellant and the Executive Engineer in charge of the
construction work regarding the rate payable to the
appellant; (ii) that the appellant by letter dated 6.4.1986
had only provisionally agreed for the rate of Rs.25.25 per
Cubic Meter; and (iii) that he had been claiming the rate
of Rs.34.50 per Cubic Meter is incorrect. Reference was
made to the letter dated 5.4.1986 of the Executive Engineer
and the appellant’s letter dated 6.4.1986 addressed to the
Superintending Engineer. It is clear that these letters and
some other similar correspondence referred to by the
appellant, related to the additional earth work, if any,
done by the appellant in excess of the quantity of the earth
work agreed to by him in respect of the main Dam. In the
letter dated 31.10.1986 written by the appellant to the
Executive Engineer, the appellant had made a reference to
the construction of a temporary ’bund’ and it was stated
therein that he had undertaken that work under instructions
of the Executive Engineer and the payment for the same was
agreed at the rates of earthen dam. The respondent on the
other hand contended that this work itself was an
unauthorised work. We need not, however, dilate on that
aspect as the Division Bench in its earlier order had stated
that the appellant was entitled to get payment for the work
relating to temporary ’bund’.
The learned counsel for the appellant contended that the
Superintending Engineer, by his letter dated 5.4.1986 (Exh.
P-12) had agreed to pay at the rate of Rs.25.25 per Cubic
Meter and in the face of this admission it was not correct
on the part of the Arbitration Tribunal to fix the rate at
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
Rs.15.75 per Cubic Meter. This letter referred to by the
appellant is certainly not in respect of the temporary
’bund’ constructed by the appellant in 1985. It seems that
there was a dispute with regard to the rate payable for the
additional work in respect of the main Dam. Though the
appellant claimed Rs.34.50 per Cubic Meter, the
Superintending Engineer by his letter dated 5.4.1986 agreed
to pay Rs.25.25 per Cubic Meter. For this additional
quantity of the work, the appellant was paid in excess of
the contract rate.
However, the dispute before the Arbitration Tribunal was
with regard to the temporary ’bund’ and its work was
completed by November/December, 1985 and the total earth
work was 49027.64 Cubic Meters. The Tribunal went into this
question and fixed the rate having due regard to sub-clause
(d) of Clause 4.3.13.3 of the agreement which is to the
following effect :
"If the rates for the altered, additional or substituted
work cannot be determined in the manner specified in the
Sub- clause (a), (b), (c) above, the S.E. shall determine
the rate or rates and fix the same on the basis of
prevailing market rates to include prime cost of material
and labour charges (inclusive of hourlywise rates as
determined by the department for machinery and equipments if
used) plus 15% extra to cover the sundry, overhead charges
and profits etc. of the contractor."
On the basis of the above clause, the Tribunal
considered the prevailing market rates, including the cost
of material and labour charges and an additional 15% was
added to cover the sundry charges to arrive at the rate.
The details are given in the award. Learned counsel for the
appellant could not point out any defect or illegality
committed by the Tribunal in fixing the rate payable for the
additional work. When it was proved that the additional
earth work was completed in November/December, 1985, there
was nothing wrong in fixing the amount based on the rate
prevalent at that time.
The learned counsel for the appellant lastly contended
that by its earlier award dated 14.7.1988 the Arbitration
Tribunal had fixed the rate of Rs.22/- per Cubic Meter for
the earth work and that the Civil Revision filed by the
respondent State Govt. against that award had been
dismissed. Therefore, it was argued that at least the
appellant should be entitled to get the rate of Rs.22/- per
Cubic Meter. We do not find any substance in this
contention. In the order passed by the Division Bench of
the High Court on 26.7.1990, it was specifically stated that
the rate for the additional earth work is to be refixed in
accordance with the provisions of Clause 4.3.13.3 of the
agreement and it was accordingly done by the Tribunal. When
a fresh award has been passed by the Tribunal, whatever
award passed by it earlier loses its significance.
We are of the view that the appellant failed to
establish that there was any error of jurisdiction,
illegality or material irregularity warranting interference
by the Revisional court. The appeal has no merit and is
dismissed accordingly, however, without any order as to
costs.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5