Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 13
PETITIONER:
ASSOCIATED ENGINEERING CO.
Vs.
RESPONDENT:
GOVERNMENT OF ANDHRA PRADESH AND ANR.
DATE OF JUDGMENT15/07/1991
BENCH:
THOMMEN, T.K. (J)
BENCH:
THOMMEN, T.K. (J)
SAHAI, R.M. (J)
CITATION:
1992 AIR 232 1991 SCR (2) 924
1991 SCC (4) 93 JT 1991 (3) 123
1991 SCALE (2)50
ACT:
Arbitration Act, 1948: Sections 10, 14, 17, 33-
Arbitrator-Jurisdiction-dispute of-Not within the award-To
be decided outside the award-Ambiguity of such award-To be
resolved by admitting extrinsic evidence-Jurisdiction cannot
be widened by Arbitrator-He is bound by the recital in the
contract-Conscious disregard of law or provisions of
contract-Whether amounts to mala fide action and vitiates
the award.
HEADNOTE:
Some disputes arose between the Respondent State and
the Contractor in respect of the Cement concrete lining
under an agreement in connection with the construction of
Nagarjunasagar Dam. Arbitrator Umpire was appointed and the
parties filed their pleading and documents before him.
There were 15 claims apart from the general claim for cost
and interest. The award made by the Umpire was filed before
the Civil Court. The Civil Court made the award a rule of
Court and passed a decree in terms of the award together
with interest at 12% per annum from the date of the decree.
On appeal, the High Court set aside the decree in
respect of three claims on the ground that the claims were
not supported by the agreement between the parties and that
the arbitrator had gone beyond the contract in awarding the
claims, and confirmed the decree in respect of three other
claims.
Aggrieved by the High Court’s Judgment, both the
Contractor and the State Government preferred appeals by
special leave.
On behalf of the Contractor it was contended that since
the Umpire made a non-speaking award and did not incorporate
any document as part of the award except his reference to
the contract, law did not permit interference by the Court
with the award, and that the High Court exceeded its
jurisdiction in interfering with a non-speaking award.
On behalf of the State Government it was contended that
notwith-
925
standing the brevity of his reasoning, the arbitrator had
given a speaking award, but with errors of law and fact
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 13
apparent on the face of it; and that he acted contrary to
the contract, thereby exceeding his jurisdiction.
Dismissing the appeal of the Contractor and partly
allowing the appeal of the State Government, this Court,
HELD: 1. The arbitrator cannot act arbitrarily,
irrationally capriciously or independently of the contract.
His sole function is to arbitrate in terms of the contract.
He has no power apart from what the parties have given him
under the contract. If he has travelled outside the bounds
of the contract, he has acted without jurisdiction. But if
he has remained inside the parameters of the contract and
has construed the provisions of the contract, his award
cannot be interfered with unless he has given reasons for
the award disclosing an error apparent on the face of it.
[938A-B]
2. An arbitrator who acts in manifest disregard of the
contract acts without jurisdiction. His authority is
derived from the contract and is governed by the Arbitration
Act which embodies principles derived from a specialised
branch of the law of agency. He commits misconduct if by
his award he decides matters excluded by the agreement. A
deliberate departure from contract amounts to not only
manifest disregard of his authority or a misconduct on his
part, but it may tantamount to a mala fide action. A
conscious disregard of the law or the provisions of the
contract from which he has derived his authority vitiates
the award. [938C-E]
Mustill & Boyd’s Commercial Arbitration, Second
Edition, p. 64; Halsbury’s Laws of England, Volume II, 4th
Edn., para 622, referred to.
3. A dispute as to the jurisdiction of the arbitrator
is not a dispute within the award, but one which has to be
decided outside the award. An Umpire or arbitrator cannot
widen his jurisdiction by deciding a question not referred
to him by the parties or by deciding a question otherwise
than in accordance with the contract. He cannot say that he
does not care what the contract says. He is bound by it.
It must bear his decision. He cannot travel outside its
bounds. If he exceeded his jurisdiction by doing so, his
award would be liable to be set aside. [938E-F]
Attorney General for Manitoba v. Kelly & Others, [1922]
1 AC 268, referred to.
926
4.1 Evidence of matters not appearing on the face of
the award would be admissible to decide whether the
arbitrator travelled outside the bounds of the contract and
thus exceeded his jurisdiction. In order to see what the
jurisdiction of the arbitrator is, it is open to the Court
to see what dispute was submitted to him. If that is not
clear from the award, it is open to the Court to have
recourse to outside sources. The Court can look at the
affidavits and pleadings of parties; the Court can look at
the agreement itself. [939A-B]
Bunge & Co. v. Dewar & Webb, [1921] 8 LI. L.Rep.
436(K.B.), referred to.
4.2. If the arbitrator commits an error in the
construction of the contract, that is an error within his
jurisdiction. But if he wanders outside the contract and
deals with matters not allotted to him, he commits a
jurisdictional error. Such error going to his jurisdiction
can be established by looking into material outside the
award. Extrinsic evidence is admissible in such cases
because the dispute is not something which arises under to
the contract or dependent on the construction of the
contract or to be determined within the award. The dispute
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 13
as to jurisdiction is a matter which is outside the award or
outside whatever may be said about it in the award. The
ambiguity of the award can, in such cases, be resolved by
admitting extrinsic evidence. The nature of the dispute is
something which has to be determined outside and independent
of what appears in the award. Such jurisdictional error
needs to be proved by evidence extrinsic to the award.
[939C-F]
M/s. Alopi Parshad & Sons Ltd. v. The Union of India,
[1960] 2 SCR 793; Union of India v. Kishori Lal, AIR 1959 SC
1362; Renusagar Power Co. Ltd. v. General Electric Company,
[1984] 4 SCC 679; Jivarajbhai v. Chintamanrao, AIR 1965 SC
214; Gobardhan Das v. Lachhmi Ram, AIR 1954 SC 689 and
Thawardas v. Union of India, AIR 1955 SC 468, relied on.
Bunge & Co. v. Dewar & Webb, [1921] 8 LI. L. Rep. 436
(K.B.); Christopher Brown Ltd. v. Genossenschaft
Oesterreichischer, [1954] 1 QB 8; Rex v. fulham, [1951] 2
K.B. 1; Falkingham v. Victorian Railways Commission, [1900]
A.C. 452; Rex v. All Saints, Southampton, [1828] 7 B. & C.
785; Laing, Son & Co. Ltd. v. Eastcheap Dried Fruit Co.,
[1961] 1 LI. L. Rep. 142, 145 (Q.B.); Dalmia Dairy
Industries Ltd. v. National Bank of Pakistan, [1978] 2 LI.
L. Rep. 223 (C.A.); Heyman v. Darwins Ltd., [1942] A.C.
356; Omanhene v. Chief Obeng, AIR 1934 P.C. 185; F.R.
Absalom Ltd. v. Great Western (London) Garden
927
Village Society, Limited, [1933] AC 592 (HL) and M. Golodetz
v. Schrier & Anr., [1947] 80 LI. L.Rep. 647, referred to.
5. In the instant case, the umpire decided matters
strikingly outside his jurisdiction. He outstepped the
confines of the contract. He wandered far outside the
designated area. He diagressed far away from the allotted
task. His error arose not by misreading or misconstruing or
misunderstanding the contract, but by acting in excess of
what was agreed. It was an error going to the root of his
jurisdiction because he asked himself the wrong question,
disregarded the contract and awarded in excess of his
authority. In many respects, the award flew in the face of
provisions of the contract to the contrary. The umpire
acted unreasonable, irrationally and capriciously in
ignoring the limits and the clear provisions of the
contract. In awarding claims which are totally opposed to
the provisions of the contract to which he made specific
reference in allowing them, he has misdirected and
misconducted himself by manifestly disregarding the limits
of his jurisdiction and the bounds of the contract from
which he derived his authority thereby acting ultra fines
compromissi. [940A-D]
M.L. Sethi v. R.P. Kapur, AIR 1972 SC 2379; The
managing Director, J. and K. Handicrafts v. M/s. Good Luck
Carpets, AIR 1990 SC 864 and State of Andhra Pradesh & Anr.
v. R.V. Rayanim, AIR 1990 SC 626, relied on.
Anisminic Ltd. v. Foreign Compensation Commission,
[1969] 2 AC 147; Pearlman v. Keepers and Governors of Harrow
School, [1979] 1 Q.B. 56 and Lee v. Showmen’s Guild of Great
Britain, [1952] 2 Q.B. 329, referred to.
Mustill & Boyd’s Commercial Arbitration, Second
Edition, p. 641 and Halsbury’s Laws of England, 4th Edn.,
Vol. 2, para 622, referred to.
6.1. In the instant case, the contract did not
postulate-in fact it prohibited-payment of any escalation
under Claim No. III for napaslabs or Claim No. VI for extra
lead of water or Claim No. IC for flattening of canal slopes
or Claim No. II for escalation in labour charges otherwise
than in terms of the formula prescribed by the contract.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 13
The umpire travelled totally outside the permissible
territory and thus exceeded his jurisdiction in making the
award under those claims. This is an error going to the
root of his jurisdiction. As such, the High Court was right
in holding that the arbitrator acted outside the contract
928
in awarding the abovesaid claims. However, the High Court
went wrong in confirming the decree in respect of Claim No.
II relating to escalation in labour charges since a specific
formula had been prescribed under Item 35, and the function
of the umpire was to make an award in accordance with the
formula; he had no jurisdiction to alter the same. [937C-D;
936F]
Jivarajbhai Ujamshi Sheth & Ors. v. Chintaman rao
Balaji & Ors., AIR 1965 SC 214, relied on.
6.2. Claim No. IV relating to ‘Refund of Excess hire
charges of machinery and payment towards losses suffered as
a result of poor performance of department machinery and
also direction for the future’ was rightly allowed by the
arbitrator and his decision was rightly upheld by the High
Court. The Government was, in terms of the contract, bound
to compensate the contractor for the excess higher charges
paid as a result of the poor performance of the machinery
supplied by the Government. [937E-F]
6.3. As regards Claim No. VII(4) relating to ‘Sand
Conveyance’ the arbitrator was right in stating that the
diesel oil requirement should be taken as 0.35 lit for item
No. 5 of statement (A) at page 59 of Agreement as indicated
in the original tender and not as O.035 and price adjustment
made accordingly. The High Court Court rightly upheld this
claim. [937G-H; 938A]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 338-339
of 1991.
From the Judgment and Order dated 28.12.85 of the
Hyderabad High Court in OMA No. 456 of 1984 and CRP No. 2743
of 1984.
WITH
Civil Appeal Nos. 2692-930F 1991.
K.R. Choudhary for the Appellant.
K. Madhava Reddy, G. Prabhakar, T.V.S.N. Chari (N.P.)
for the Respondents.
The Judgment of the Court was delivered by
THOMMEN. J. Leave granted in S.L.P. (C) Nos. 7071-72 of
1986.
These appeals are brought against the common judgment
of the
929
Andhra Pradesh High Court in O.M.A. No. 456 of 1984 and
C.R.P. No. 2743 of 1984. The High Court set aside in part
the common judgment of the Ist Additional Chief Judge, Civil
Court at Hyderabad, in Original Suit No. 174 of 1983 and
O.P. No. 49 of 1983 whereby he made the award of the umpire
(hereinafter referred to as the ‘umpire’ or ‘arbitrator’) a
rule of court and passed a decree in terms of the award
together with interest on the principal amount awarded at
the rate of 12 per cent per annum from the date of the
decree. The High Court set aside the decree in respect of
Claim Nos. III, Vi and IX and affirmed the decree for the
other claims. The main appeal Nos. 338 & 339 of 1991
arising from S.L.P. (C) Nos. 1573 & 1574 of 1986 are by the
Associated Engineering Co. (hereinafter referred to as ‘the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 13
Contractor’). It challenges the judgment of the High Court
setting aside the decree of the Civil Court in respect of
Claim Nos. III, VI and IX. The other appeals arising from
S.L.P. (C) Nos. 7071 & 7072 of 1986 are by the Government of
Andhra Pradesh and they are against the judgment of the High
Court confirming the decree of the Civil Court in respect of
Claim Nos. II, IV and VII(4).
The High Court set aside Claim Nos. III, VI and IX on
the ground that those claims were not supported by the
agreement between parties and that the arbitrator travelled
outside the contract in awarding those claims. While that
portion of the judgment of the High Court is supported by
the Government, the Contractor submits that the High Court
exceeded its jurisdiction in interfering with non-speaking
award. The Government challenges the judgment of the High
Court in so far as it affirmed the findings of the Civil
Court in respect of Claim Nos. II IV and VII(4) on the
ground that the arbitrator awarded those claims totally
unsupported by the contract.
Mr. A.B. Dewan, appearing for the Contractor, submits
that the umpire made a non-speaking award. He did not
incorporate any document as a part of the award,
notwithstanding his reference to the contract. In the
circumstances, counsel submits, the law does not permit
interference by the Court with such an award.
Mr. K. Madhava Reddy, appearing for the Government, on
the other hand, submits that the umpire made a speaking
award with reference to the claims and he gave reasons for
awarding those claims. It is true, counsel says, that the
umpire made only brief reference to the provisions of the
contract and his reasons for making the award. But
notwithstanding the brevity of his reasoning, he has spoken
sufficiently clearly as a result of which errors of law and
fact have become
930
apparent on the face of the award disclosing that the umpire
acted contrary to, and unsupported by, contract, thereby
exceeding his jurisdiction. He says that the umpire has
referred to the contract not merely for the purpose of
reciting or narrating his authority to hear the matter and
resolve the dispute, but for incorporating it as a part of
the award. In doing so, he exceeded the contract, not
merely by misinterpreting it, but by travelling totally
outside it, and by making an award without regard to and
independent of the contract. A number of decision have been
cited on either side in support of the respective
contentions.
The award was made in respect of disputes which arose
between the Government and the Contractor for the cement
concrete lining under Agreement dated 20.1.1981 (as
supplemented subsequently) in connection with the
construction of Nagarjunasagar Dam. The parties filed their
pleadings and documents before the arbitrator/umpire. There
were 15 claims apart from the general claim for cost and
interest. As stated earlier, we are concerned only with
Claim Nos. III, VI and IX which are claims awarded by the
umpire and decreed by the Civil Court, but set aside by the
High Court, and with Claim Nos. II, IV and VII(4) which were
awarded by the umpire and decreed by the Civil Court as well
as by the High Court. The first set of claims respectively,
are: ‘Escalation on Napa Slabs’; ‘Payment of Extra Lead for
water; and, ‘Extra Expenditure incurred due to flattening of
canal slopes and consequent reduction in top width of banks
used as roadway’. The other set of claims relate
respectively to ‘Labour Escalation’; ‘Refund of excess Hire
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 13
Charges of Machinery’; and’ ‘Stand conveyance’.
The umpire after reciting the background of the dispute
which led to his entering upon reference on 16.12.82 to
decide the dispute and the relevant agreement between the
parties deals with the claims seriatim. As regards Claim
No. III, he says:
"I hereby declare and award and direct the
respondent to compensate the claimants towards
escalation in the cost of napaslabs calculated at
Rs.4.25 (Rupees four and paise twenty five) per Sq.
Met. of napa slab lining, under item 11 of schedule
A of the agreement for the entire work and make
payments accordingly".
The main criticism levelled by the Government against
this award is that there was no provision in the contract
for escalation of
931
the cost or price of napa-slabs. The escalation provision
in the contract related to labour, diesel oil, tyres and
tubes, as provided in Item 35 thereof. There was no
escalation provision in the contract as far as napa-slabs
were concerned. The price for these slabs had been
determined in the contract at Rs. 4.25 Per Sq. Met. and
there was no provision for increase or decrease of that
price. Both the parties to the contract were bound by that
price and the arbitrator, therefore, had no jurisdiction to
award any escalation in the price of napa-slabs. In the
absence of any provision in the contract, the arbitrator had
no jurisdiction to make an award for escalation. This
contention of the Government was accepted by the High Court.
Mr. Dewan, appearing for the Contractor, is not in a
position to refer to any provision of the contract allowing
escalation for napa-slabs. All that he is in a position to
refer to is Item 35 of the contract which refers to price
adjustment for increase or decrease inthe cost. That item,
as stated earlier, refers to various matters such as, diesel
oil, labour, etc., but not to napa-slabs. On the other
hand, at the end of that item, it is specifically stated ‘no
claims for price adjustment other than those provided
herein, shall be entertained’. Furthermore, it is
specifically provided in the contract ‘the contractor shall
have to make his own arrangements to obtain the napa-slabs
as per standard specifications. The Department does not
accept any responsibility either in handing over the
quarries or procuring the napa-slabs or any other
facilities. The contractor will not be entitled for any
extra rate due to change in selection of quarries as above’.
There is thus a specific prohibition against price
adjustment or award for escalated cost in respect of any
matter falling outside Item 35.
Mr. Dewan, however, submits that being a non-speaking
award, the Court cannot examine the reasons. Mr. Madhava
Reddy, appearing for the Government, submits that the award
is not silent on the point. It speaks eloquently, though
briefly. It is not merely in the recital or narrative
portion of the award that the agreement is referred to, but
in making the award under Claim No. III the agreement is
specifically incorporated by directing payment for
escalation on napa-slabs under Item 11 of Schedule A of the
Agreement at the rate of Rs.4.25. The agreement is thus
bodily incorporated into the award thereby disclosing an
error apparent on its face and the total lack of the
arbitrator’s jurisdiction by reason of his going totally
outside and opposed to the contract. This, counsel says, is
revealed not by a construction of the contractual
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 13
provisions, but by merely looking at the matters covered by
the contract.
932
Claim No. VI-Payment of Extra Lead for water.
This is what the arbitrator says:
"I hereby declare and award and direct the
Respondent to pay extra towards additional lead for
water i.e. 3 K. Ms. over the specified lead of 2
K.Ms. in the agreement for items 4, 5, 6, 10 and 11
of Schedule A".
As regards this claim, Mr. Dewan reiterates his contention
that the award is silent as to the reasons and, therefore,
the Court should not interfere. Mr. Madhava Reddy on the
other hand submits that the award speaks as to the reasons
for allowing the claim for extra amount towards additional
lead for water i.e. for 3 K.Ms. over and above the specified
lead of 2 K.Ms. But counsel says, the agreement provides for
no payment at all for any lead and much less for any
additional lead. He refers to the specific provision of the
agreement regarding water. He says that the Contractor had
to make its own arrangements for supply of water at work
site for all purposes including quarry. There is no
provision in the contract for making any payment to the
Contractor for the water brought by it to the site. In the
absence of any such provision, counsel says, it is
preposterous that the arbitrator should have awarded extra
amount for additional lead for water. The contract
specifically stated that it was the responsibility of the
Contractor to make its on arrangements for the supply of
water. The Government gave no assurance to the Contractor
regarding the availability of water or the prices payable
therefor. The umpire, therefore, had no jurisdiction to
allow Claim No. VI. The High Court accepting the contention
of the State reversed the Civil Court’s decree as regards
that claim and held" .........In view of unequivocal
agreement that the contractor should make his own
arrangements for supply of water for the purpose of curing,
the award of compensation is outside the purview of the
agreement and is vitiated".
Claim No. IX-Extra expenditure incurred due to
flattening of canal slopes and consequent reduction
in top width of banks used as roadway.
Referring to this claim, this is what the award says:
"I hereby declare and award and direct the
respondent to pay the claimant for 50% of the work
done on the napa slab lining on the left side slope
of Canal at the extra rate of Rs.4.00 per Sq. Met
of lining work".
933
Rejecting the contentions of the Contractor and
accepting those of the Government, the High Court held that
the contract did not provide for any payment whatever for
the maintenance of canal slopes and consequent deduction in
top width of banks used as roadway. The High Court found
that it was the responsibility of the Contractor to repair
the banks and the contract contained no provision for
payment of any amount towards the decrease in the width or
otherwise. The High Court says ‘....the acceptance of claim
on this score is beyond the purview of the agreement and as
such vitiated’.
While counsel for the Contractor repeats his
contentions regarding the award being silent as to reasons,
Mr. Madhava Reddy submits that the contract provides for no
payment whatever under Claim No. IX. On the other hand, it
specifically states-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 13
"8(A) SITE FACILITIES-
Haul roads from batching plant site to the
work site in the first instance will be formed by
the Department as per site surveys per each
batching plant site. These haul roads are fair
weather roads only with hard passages at stream
crossings. Formation of haul roads within the
batching plant area, maintenance of all haul roads
including those formed by the Department shall be
the responsibility of the contractors. Existing
roads and roads under the control of N.S. Project
can be made use of by the Contractor. Any other
haul roads required by the Contractor and not
specified in plan shall be carried out by the
Contractor at his cost.
8.(A) 1. WIDENING OF BANKS
The canal banks will be widened to 5 meters and 3
meters width respectively by the Department for
right and left banks to facilitate transport of
materials. The contractor however has to maintain
the haul roads".
In the absence of any provision to pay for extra
expenditure and in the light of the specific provision
placing the sole responsibility for the maintenance of the
haul roads on the Contractor, the arbitrator had no
jurisdiction to award 50% at extra rate of Rs. 4 per Sq.
Meter. The contract contains no provision for payment of
any amount outside what is strictly specified under the
clause. In the circumstances, Mr.
934
Madhava Reddy says, the High Court was perfectly justified
in coming to the conclusion, which it did, as regards the
arbitrator acting outside his jurisdiction.
We shall now deal with the other set of claims, namely,
Claim Nos. II, IV and VII(4) which had been awarded and
decreed by both the courts below.
The arbitrator deals with Claim No. II as follows:
"The claim is admitted.
I hereby declare and award and direct the
Respondents that due to the statutory revision of
Minimum rates of wages payable to various
categories of workers, the claimant is to be paid
compensation as per the following formula:
P1 (WSI-WSO)0.10+ (WSSI-WSSO)0.10- (WUSI-WUSO)0.8
V2-- X R ---- ------ ----- - --- --------
100 WSO WSSO WUSO
Where Vs- Compensation payable due to statutory
increase in Min. Wages of labour
notified by the Government of A.P.
after 22.10.1980 under the Min. Wages
Act., 1948.
P-1. Percentage Labour component of each item
of Work as per Appendix 9 at page 139 of
Agreement.
R- Value of work done under each item of
work during the period under review.
WSO- 11.15 (Daily Minimum wage in force on the
date of Tender for skilled labour).
WSSO- 8.50 (Daily Minimum wage in force on the
date of Tender for semiskilled labour).
WUSO- 5.65 (Daily Minimum wage in force on the
date of Tender for unskilled labour).
WSI- Revised daily Min. wage as fixed by Govt.
A.P. for skilled labour applicable for
the period under review.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 13
935
WSSI- Revised daily Min. wage as fixed by Govt.
of A.P. for semiskilled labour applicable
for the period under review.
WUSI- Revised daily Min. wage as fixed by Govt.
of A.P. for semiskilled labour applicable
for the period under review.
WUSI- Revised daily Min. Wages as fixed by
Government of A.P. for unskilled labour
applicable for the period under review.
The above compensation is payable to the
claimant for the work done after 23.12.80, the date
of publication of G.O. No. 835 dated 18.12.80, till
the completion of the work".
It is not seriously disputed that the observation "The
claim is admitted" is only a reference to the arbitrator’s
decision to allow the claim and not as a concession or
admission on the part of the Government. In fact from the
pleadings it is quite clear that the Government had opposed
every claim and there was no concession on its part.
Claim No. II had been, as seen above, elaborately dealt
with by the arbitrator. On account of the statutory
revision of minimum rates of wages payable to various
categories of workers, the arbitrator made the award in
respect of labour escalation. Escalation under this item is
in fact, as stated above, provided for under the contract,
but in terms thereof. The grievance of the Government is
not because the umpire awarded escalation for labour, but
because he allowed escalation otherwise than as provided
under the contract. The contract under Item 35 provides-
‘Increase or decrease in the cost due to labour
shall be calculated quarterly in accordance with
the following formula:
V1 = 0.75 P1 X R(i-i)
---- -----
100 10
V1 = increase or decrease in the cost of work
during the quarter under consideration
due to changes in rates for labour.
R = the value of the work done in Rupees
during the quarter under consideration
936
1 = the average consumer price index for
industrial workers (wholesale prices) for
the quarter in which tenders were opened
(as published in Nalgonda District by the
Director of Bureau of Economics and
Statistics, Andhra Pradesh).
P1 = Percentage of labour components
(specified in schedule in appendix-9 of
the item).
i = the average consumer price index for
industrial workers (wholesale prices) for
the quarter under consideration.
Price adjustment clause shall be
applicable only for the work that is
carried out within the stipulated time or
extensions thereof as are not
attributable to the contractor. No
claims for price adjustment other than
those provided herein, shall be
entertained".
The contention of the Government is that the two
formulae are totally different from each other as a result
of which the arbitrator awarded very much more than what is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 13
warranted under the agreed formula. Mr. Madhava Reddy
submits that it is true that the contractor was bound to pay
minimum wages according to the relevant statutory
provisions. In fact the contract contains a provision
making it necessary for the Contractor to conform to all
laws, regulations, bye-laws, ordinances, regulations, etc.
But the fact that the Contractor necessarily had to pay
enhanced rates of wages did not entitle it to claim any
amount from the Government in excess of what had been
strictly provided under the contract. A specific formula
had been prescribed under Item 35, as seen above, and the
function of the umpire was to make an award in accordance
with that formula. He had no jurisdiction to alter the
formula, which he has done, as seen from the award.
It is not disputed on behalf of the Contractor that the
formula followed by the arbitrator, as seen from the award
under Claim No. II, is different from the formula prescribed
under the contract. But Mr. K.R. Chowdhury, one of the
counsel appearing for the Contractor, points out that the
contract provided for payment of all wages according to the
current rates and, therefore, the arbitrator was well within
his jurisdiction to make an award by adopting a formula in
keeping with the enhanced rates of wages, and the High
Court, he contends,
937
rightly decreed the amounts under that claim in terms of the
award.
We shall deal with Claim Nos. IV and VII(4)
separately. But as regards Claim Nos. III, VI and IX, we
are of the view that the High Court was right in stating
that the arbitrator acted outside the contract in awarding
those claims. For the very same reason we are of the view
that the High Court was wrong in coming to the conclusion,
which it did, regarding Claim No. II. We say so because
there is no justification whatsoever for the arbitrator to
act outside the contract.
These four claims are not payable under the contract.
The contract does not postulate-in fact it prohibits payment
of any escalation under Claim No. III for napa-slabs or
Claim No. VI for extra lead of water or Claim No. IX for
flattening of canal slopes or Claim No. II for escalation in
labour charges otherwise than in terms of the formula
prescribed by the contract. The conclusion is reached not
by construction of the contract but by merely looking at the
contract. The umpire travelled totally outside the
permissible territory and thus exceeded his jurisdiction in
making the award under those claims. This is an error going
to the root of his jurisdiction: See Jivarajbhai Ujamshi
Sheth & Ors. v. Chintamanrao Balaji & Ors., AIR 1965 SC 214.
We are in complete agreement with Mr. Madhava Reddy’s
submissions on the point.
As regards Claim Novs. IV and VII(4), we see no merit
in Mr. Madhava Reddy’s contentions. Claim No. IV relates to
‘Refund of excess hire charges of machinery and payment
towards losses suffered as a result of poor performance of
department machinery and also direction for the future’.
This claim, was rightly allowed by the arbitrator and his
decision was rightly upheld by High Court. The Government
was, in terms of the contract, bound to compensate the
Contractor for the excess higher charges paid as a result of
the poor performance of the machinery supplied by the
Government.
Claim No. VII(4) is as regards ‘Sand Conveyance’. The
arbitrator says-
"The diesel oil requirement shall be taken as 0.35
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 13
lit for item No. 5 of statement (A) at page 59 of
Agreement as indicated in the original tender and
not as 0.035 and price adjustment made
accordingly".
The arbitrator was, in our view, right in so stating and the
High Court,
938
in our view, rightly upheld this claim.
The arbitrator cannot act arbitrarily, irrationally,
capriciously or independently of the contract. His sole
function is to arbitrate in terms of the contract. He has
no power apart from what the parties have given him under
the contract. If he has travelled outside the bounds of the
contract, he has acted without jurisdiction. But if he has
remained inside the parameters of the contract and has
construed the provisions of the contract; his award cannot
be interfered with unless he has given reasons for the award
disclosing an error apparent on the face of it.
An arbitrator who acts in manifest disregard of the
contract acts without jurisdiction. His authority is
derived from the contract and is governed by the Arbitration
Act which embodies principles derived from a specialised
branch of the law of agency (see Mustill & Boyd’s Commercial
Arbitration, Second Edition, p. 641). He commits misconduct
if by his award he decides matters excluded by the agreement
(see Halsbury’s Laws of England, Volume II, Fourth Edition,
Para 622). A deliberate departure from contract amounts to
not only manifest disregard of his authority or a misconduct
on his part, but it may tantamount to a mala fide action. A
conscious disregard of the law or the provisions of the
contract from which he has derived his authority vitiates
the award.
A dispute as to the jurisdiction of the arbitrator is
not a dispute within the award, but one which has to be
decided outside the award. An umpire or arbitrator cannot
widen his jurisdiction by deciding a question not referred
to him by the parties or by deciding a question otherwise
than in accordance with the contract. He cannot say that he
does not care what the contract says. He is bound by it.
It must bear his decision. He cannot travel outside its
bounds. It he exceeded his jurisdiction by so doing, his
award would be liable to be set aside. As stated by Lord
Parmoor:
".......It would be impossible to allow an umpire
to arrogate to himself jurisdiction over a question
which on the true construction of the submission
was not referred to him. An umpire cannot widen
the area of his jurisdiction by holding, contrary
to the fact, that the matter which he affects to
decide is within the submission of the parties
.......".
939
Attorney-General for Manitoba v. Kelly &
Others, [1922] 1 AC 268, 276.
Evidence of matters not appearing on the face of the award
would be admissible to decide whether the arbitrator
travelled outside the bounds of the contract and thus
exceeded his jurisdiction. In order to see what the
jurisdiction of the arbitrator is, it is open to the Court
to see what dispute was submitted to him. If that is not
clear from the award, it is open to the Court to have
recourse to outside sources. The Court can look at the
affidavits and pleadings of parties; the Court can look at
the agreement itself. Bunge & Co. v. Dewar & Webb, [1921] 8
L1. L.Rep. 436(K.B.).
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 13
If the arbitrator commits an error in the construction
of the contract, that is an error within his jurisdiction.
But if he wanders Outside the contract and deals with
matters not allotted to him, he commits a jurisdictional
error. Such error going to his jurisdiction can he
established by looking into material outside the award.
Extrinsic evidence is admissible in such cases because the
dispute is something which arises under or in relation to
the contract or dependent on the construction of the
contract or to be determined within the award. The dispute
as to jurisdiction is a matter which is outside the award or
outside whatever may be said about it in the award. The
ambiguity of the award can, in such cases, be resolved by
admitting extrinsic evidence. The rationale of this rule is
the nature of the dispute is something which has to be
determined outside and independent of what appears in the
award. Such jurisdictional error needs to be proved by
evidence extrinsic to the award. See M/s. Alopi Parshad &
Sons. Ltd. v. The Union of India, [1960] 2 SCR 793; Bunge &
Co. v. Dewar & Webb., [1921] 8 L1. L. Rep. 436 (K.B.);
Christopher Brown Ld. v. Genossenschaft Oesterreichischer,
[1954] 1 QB 8; Rex v. Fulham, [1951] 2 K.B. 1; Falkingham v.
Victorian Railways Commission, [1900] A.C. 452; Rex v. All
Saints, Southampton, [1828] 7 B. & C. 785; Laing. Son & Ltd.
v. Eastcheap Dried Fruit Co., [961] 1 L1.L. Rep. 142, 145
(Q.B.); Dalmia Dairy Industries Ltd. v. National Bank of
Pakistan, [1978] 2 L1. L. Rep. 223 (C.A.); Heyman v. Darwing
Ld., [1942] A.C. 356’ Union of India v. kishorilal, AIR 1959
SC 1362; Renusager Power Co. Ltd. v. General Electric
Company, [1984] 4 SCC 679; Jivarajbhai v. Chintamanrao, AIR
1965 SC 214; Gobardhan Das v. Lachhmi Ram, AIR 1954 SC 689,
692; Thawardas v. Union of India., AIR 1955 SC 468; Omanhene
v. Chief Obeng, AIR 1934 P.C. 185, 188; F.R. Absalom. Ltd.
v. Great Western London Garden Village Society. Limited,
[1933] AC 592 (HL) and M. Golodetz
940
v. Schrier & Anr., [1947] 80 L1. L. Rep. 647.
In the instant case, the umpire decided matters
strikingly outside his jurisdiction. He outstepped the
confines of the contract. He wandered far outside the
designated area. He diagressed far away from the allotted
task. His error arose not by misreading or misconstruing or
misunderstanding the contract, but by acting in excess of
what was agreed. It was an error going to the root of his
jurisdiction because he asked himself the wrong question,
disregarded the contract and awarded in excess of his
authority. In many respects, the award flew in the face of
provisions of the contract to the contrary. See the
principles state in Anisminic Ltd. v. Foreign Compensation
Commission., [1969] 2 AC 147; Pearlman v. Keepers and
Governors of Harrow School, [1979] 1 Q.B. 56; Lee v.
Showmen’s Guild of Great Britain, [1952] 2 Q.B. 329; M.L.
Sethi v. R.P. Kapur, AIR 1972 SC 2379; The Managing
Director. J. and K. Handicrafts v. M/s. Good Luck Carpets,
AIR 1990 SC 864 and State of Andhra Pradesh & Anr. v. R.V.
Rayanim, AIR 1990 SC 626. See also Mustill & Boyd’s
Commercial Arbitration, Second Edition; Halsbury’s Laws of
England, Fourth Edition,Vol. 2.
The umpire, in our view, acted unreasonably,
irrationally and capriciously in ignoring the limits and th
clear provisions of the contract. In awarding claims which
are totally opposed to the provisions of the contract to
which he made specific reference in allowing them, he has
misdirected and misconducted himself by manifestly
disregarding the limits of his jurisdiction and the bounds
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 13
of the contract from which he derived his authority thereby
acting ultra fines compromissi.
In the circumstances, we affirm the judgment of the
High Court under appeals except in respect of Claim No. II.
Accordingly, the appeals of the contractor are dismissed;
and, the appeals of the Government are allowed in respect of
claim No. II. We do not, however make any order as to
costs.
G.N. Appeals dismissed.
941