Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Special Leave Petition (civil) 12078 of 2002
PETITIONER:
M/S CONTINENTAL CONSTRUCTION LTD.
Vs.
RESPONDENT:
TEHRI HYDRO DEVELOPMENT CORPORATION LTD. & ANR.
DATE OF JUDGMENT: 05/09/2002
BENCH:
S. RAJENDRA BABU & P. VENKATARAMA REDDI.
JUDGMENT:
J U D G M E N T
RAJENDRA BABU, J. :
This petition is directed against an order made by the High Court
of Delhi in a writ petition wherein the petitioner prayed for quashing the
decision of the first respondent that the second respondent has the pre-
qualification for the construction of Koteshwar Dam Spillway and Power
House Civil work of Koteshwar Hydro Electric Project pursuant to the
tender specification No. THDC/RKSH/CD/197/PQ/99. The pre-
qualification document under clause 10.2 provided as follows :-
"10.2. The minimum pre-qualification criteria for the work
of construction of "Koteshwar Dam, Spillway & Power House
Works" would be as under :
(i) The bidder should have minimum annual turnover of
Rs. 50 crores in anyone of the last five years.
(ii) The bidder should have successfully completed the
construction of at least one concrete dam/barrage
involving placement of minimum 2.5 lac cubic meters
of all grades of concrete against a single contract in a
Hydro Electric/Irrigation Project."
[Only relevant part extracted]
The challenge to the pre-qualification of the second respondent was met
by the first respondent on the following basis :-
1. "Amongst the 7 parties, recommended to be pre-
qualified for the subject work, one of the parties
recommended was M/s Progressive Construction Limited,
in Joint Venture with the Consortium of Intertech
:Lenhydro, Russia (named as respondent no. 2 in the writ
petition). In the Pre-qualification bid documents
submitted by M/s Progressive Construction Limited in
Joint Venture with the Consortium of Intertect Lenhydro,
Russia the party had, inter-alia, provided Memorandum of
Understanding (MOU), purporting to be an agreement
between M/s Progressive Construction Limited, with its
Head Officer at Hyderabad (India) and the Consortium of
Intertech Service (Head office at Saint Petersberg, Russia)
and Institute Lenhydro Project, (Head Office at Saint
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
Petersberg, Russia), formed to submit the pre-qualification
bids to the THDC in response to the subject tender. The
MOU had described the Intertech Lenhydro Consortium
having experience, skill and specialized experience in
construction of dams, underground tunnels, ports etc.
Further, the said MOU had laid down the detailed
obligations, responsibilities and working arrangements for
submission of bids and undertaking the subject works in
the event, the contract was awarded to the Joint Venture.
Alongwith the documents, the Joint Venture had also
provided details concerning experience and financial
status of all the respective Joint Venture partners.
2. As per information provided by the Joint Venture of
Progressive Construction Limited and Consortium of
Intertech Services: Institute Lenhydro Project, it was
disclosed that M/s Progressive Construction Limited would
be the Joint Venture lead partner. It was further indicated
in the submitted documents that Institute Lenhydro
Project, one of the Joint Venture partners, had
successfully completed Bureya Hydroelectric Project on
Bureya River, Far East of Russia, which was a 140 m. high
concrete dam. It was further stated that this massive
gravity dam contains 3.5 million cum. Concrete about 30%
of which being dry RCC which is placed into downstream
part of the dam. This experience detail was supported by
an Affidavit dated July 31, 1999, signed for and on behalf
of Institute Lenhydro Project, by their Chief Engineer and
authorised signatory declaring that Institute Lenhydro
Project had executed the Bureya Hydroelectric Project, as
per details given in the foregoing. It was also indicated in
the affidavit that the work was done for Government of
Russia.
3. The answering respondent vide letter no
THDC/RKSH/CD-197/2607 dated 18.11.99 intimated to
Progressive Construction Limited who were disclosed to be
the leader of Joint Venture, that the claim of meeting the
PQ requirements of having completed construction of Dam
involving 2.5 lac cum concrete based on the credential of
their Joint Venture partner, Lenhydro Project, had been
laid on the self certification made by Lenhydro Project to
the effect that they have placed 3.5 million cum concrete
in Bureya HEP. Similarly, the claim of having achieved
more than 20,000 cum concrete placement in a single
month was also laid on self certification through an
affidavit furnished by Institute Lenhydro Project. They
were required vide this communication dated 18.11.99 to
arrange to furnish a certificate in support of meeting the
above PQ requirements.
4. In response to this, Progressive Construction Ltd. vide
their letter dated 24.11.99 addressed to Sr. Manager
(Contracts) furnished the certificate issued by Bureya HPP,
an open joint stock company "UES of Russia" under
Ministry of Fuel and Power Engineering of Russia. While
forwarding the said certificate by Bureya HEP, it was
intimated by Progressive Construction Ltd. that the
certificate was in support of the successful completion of
the Project as well as also the total quantities of
concrete/peak month quantity of concrete executed by
their Joint Venture partners M/s Lenhydro Project. The
original letter of confirmation issued by the joint stock
company Bureya HPP under Ministry of Fuel & Power
Engineering of Russia was later forwarded by Progressive
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
Construction Ltd. vide letter No. PCL/ND/Koteshwar/2206
dated 29.11.99 by their letter also it was intimated that
the said letter of confirmation certifies total works of
concreting having been done by their Joint Venture
partners M/s Lenhydro Project for Bureya HPP in Russia.
5. The Standing Committee on pre-qualification, on
detailed examination of bids submitted by various parties,
had noted in regard to PCL-Intertech : Lenhydro
Consortium based on information/documents furnished
by them, that the annual turnover of M/s Progressive
during the year 1998-99 has been Rs. 158.11 crores. The
joint venture partners, M/s Institute Lenhydro Project,
Russia have successfully completed 140 M. high concrete
gravity dam on Bureya river for Bureya Hydroelectric
Project, Russia involving 35 Lac cum of concrete
placement. The peak rate of concrete placed by the party
in a single month on this project was more than the
required rat eof 20,000 cum. It was also noted that M/s
Progressive achieved a monthly rate of 2,50,307 cum for
earth and rock excavation in the month of June, 1994 for
Srisailam Right bank Canal work. M/s Institute Lenhydro
Project, having worked on Bureya HEP, Russia, have
adequate experience in Reinforced Cement Concrete
Technology. Based on the information provided, and
documents submitted by this Joint Venture in response to
the pre-qualification tenders, the Standing Committee
recommended pre-qualification of PCL-Intertech :
Lenhydro Consortium Joint Venture. It was intimated to
the applicant that since the pre-qualifying requirements
relating to concreting were being met by the consortium of
Intertech : Lenhydro Project, Intertech : Lenhydro
Consortium needs to be nominated as the leader of the
Joint Venture. This was accepted and confirmed by the
applicant vide letter No. PCL/ND/THDC/2000/2275 dated
22nd May, 2000.
6. Based on the recommendations of the Standing
Committee, the answering respondent, THDC, pre-
qualified seven parties in June, 2001, including the Joint
Venture of M/s Progressive Construction Limited and
Consortium of Intertech-Lenhydro, Russia, for submission
of bids for the civil construction works of Koteshwar
Hydroelectric Project."
In view of these pleadings, the High Court held that "on consideration
of the rival submissions and pleading on record, it is abundantly clear
that respondent No. 2 is fully qualified and eligible to carry out the
contract" and the writ petitioner did not, before the bids were opened,
raise any objection regarding the experience and financial capacity of
respondent No. 2. The High Court, therefore, dismissed the writ
petition filed by the writ petitioner.
In this case the respondents had entered caveats. We asked
them, even at the stage of preliminary hearing before issuing notice, to
address the arguments on the merits of the matter. Having heard the
parties in the case, we have passed this order.
In the writ petition filed before the High Court the petitioner
contended (i) that one of the constituents of the second respondent
Lenhydro Project is not a company engaged in actual physical
execution/construction of works; rather, it was only a design firm; (ii)
the Intertech Services is not a Construction Company engaged/having
experience in actual execution/construction of concrete Dam, Spillway
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
and Power House Works; (iii) The statement made by the authorised
signatory of the Lenhydro Project that the said constituent has executed
the Bureya Hydro-electric Project, far east Russia is not correct as in
fact the said project has been built by JSC Buguchangesstroy as turn
key contractor.
In support of this contention, the learned counsel for petitioner
relied upon a letter issued by the SHC Institute Hydro Projects and
letter dated May 25, 2002 by the Chamber of Commerce and Industry of
the Russian Federation which stated that "LENGIBROPROYEKT" is a
specialized design engineering company in the field of hydro-electric
projects where it enjoys good standing as a design firm. This firm does
not involve itself in executing projects nor is it known to associate or act
as a turn-key contractor"; that letter dated 22.11.1999 [Annexure P/12]
issued by the Bureya Hydro Power Project is ambiguous inasmuch as it
only refers to successful completion of the contract by the Russian
constituent of the second respondent without any details thereto; that
the Bureya Hydro Power Project on Bureya River was, in fact,
constructed by Boguchangesstroy as a turn-key contractor as per the
information obtained from the Reference list of the Project built by the
JSC Boguchangesstroy for the years 1997-2000. It is also contended
that during the period from 1993 to 1997 the "Lenhydroproject" merely
got executed construction work project at the Bureya Hydro Power
Station even as per certificate dated 15th July, 2002 issued by the Chief
Engineer of the Parent Company of the Russian Constituent of the 2nd
respondent. On this basis it is contended that the second respondent
had not placed any satisfactory material to show that it had necessary
experience as required under the pre-qualification documents.
The letters issued by the SHC Institute Hydro Projects and the
Chamber of Commerce and Industry of the Russian Federation do not
specifically deal with whether the 2nd respondent had in fact executed the
construction work of Bureya Hydro-Power Station project but makes
general reference. The Reference List obtained from the Internet gives
information from 1997 onwards and not for the earlier period. Therefore,
these three documents are not helpful to the petitioner. The stand of the
respondents is that Bureya Hydro-Power Station project is a multi-stage
project; that during period 1993-1997, the Russian Constituent of the
2nd respondent was entrusted with the construction, technical support
and quality control of Bureya Hydro-Power Station project and they were
providing construction machinery, material, manpower etc. during the
execution of works. Certificate issued on 1.8.2002 in this regard by the
parent company is made available by the 2nd respondent. Another
certificate dated June 11, 2002 was relied upon along with the letter
dated 22.11.1999 issued in this regard. Next stage of project from 1998
onwards was executed by a sub-contractor JSC Boguchangesstroy and
Boguchangesstroy had not figured for the earlier period prior to 1998.
This project has nothing to do with the earlier project. The clear stand of
the respondents on the basis of these documents is that apart from
general designing work they were also engaged in actual construction of
the project. If upon the material made available to the 1st respondent by
the 2nd respondent its pre-qualification has been decided, the High Court
is justified in not interfering under Article 226 of the Constitution.
In the light of this position, we find no merit in this petition and
the same stands dismissed. No costs.