Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 4465 of 2007
PETITIONER:
U.P. Power Corporation Ltd. & Ors.
RESPONDENT:
M/s Bonds & Beyonds (India) (P) Ltd.
DATE OF JUDGMENT: 24/09/2007
BENCH:
Dr. ARIJIT PASAYAT & P. SATHASIVAM
JUDGMENT:
J U D G M E N T
CIVIL APPEAL NO. 4465 OF 2007
(Arising out of S.L.P. (C) No.17051 of 2001)
Dr. ARIJIT PASAYAT, J.
1. Leave granted.
2. Challenge in this appeal is to the order passed by a
Division Bench of the Allahabad High Court holding that the
demand raised by the appellant-Corporation through various
bills purporting to realize penalty for violation of peak hour
restrictions cannot be maintained. The question was whether
one Meter Reading Inspection Report (in short ’MRI’) should be
construed as single violation of the commercial restrictions
irrespective of the fact that a number of contraventions might
have been made by consumers during the period covered by
the said report.
3. The State Government of Uttar Pradesh issued a
notification under Section 22-B of the Electricity Act, 1910
(hereinafter to be referred to as "the Act of 1910") known as
the U.P. Electricity (Regulation of Supply, Distribution,
Consumption and Use) Order, 1977 which was published in
the Official Gazette. This order was amended on 30-4-1984,
known as the U.P. Electricity (Regulation of Supply,
Distribution, Consumption and Use) (1st Amendment) Order,
1984 by which clause 9 of the 1977 Order was amended and it
was substituted by the following:
"9. (1) Without prejudice to the provisions
contained in Section 42 of the Indian
Electricity Act, 1910, all Chief Zonal
Engineers, Superintending Engineers,
Executive Engineers, Assistant Executive
Engineers and Assistant Engineers of the
Uttar Pradesh State Electricity Board, the
Chief Electrical Inspector, all Deputy
Electrical Inspectors and all Assistant
Electrical Inspectors to the State
Government are authorised to disconnect
the supply summarily without notice in
relation to such installation as are found
upon inspection made by them to have
contravened the provisions of this Order.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
The supply shall remain disconnected for
the period specified below\027
(a) Contravention first in point of time \027
5 days
(b) Contravention second in point of time
\027 10 days
(c) Contravention third in point of time \027
20 days
(d) Contravention beyond third point of
time \027 Permanently:
Provided that for the purposes of this
clause any contravention prior to 1-5-
1984 shall not be taken into account.
(2) In addition to above, such consumers
shall be liable to pay the penalty for each
contravention as follows:
(a) Consumers having contracted load up
to 100 kVA, at Rs 50 per kVA on their
contracted load.
(b) Consumers having contracted load
above 100 kVA and up to 500 kVA at
Rs.30 per kVA on their contracted load
subject to minimum of Rs 5000.
(c) Consumers having contracted load
above 500 kVA at the rate of Rs 20 per
kVA on their contracted load subject to
minimum of Rs 15,000.
The reconnection shall only be done after
payment of penalty and expiry of the
above specified disconnection period
whichever is later."
4. The amended Order of 1984 was initially applied from
1-5-1984 to 21-5-1984. The State Government again issued
another order known as the U.P. Electricity (Regulation of
Supply, Distribution, Consumption and Use) (Second
Amendment) Order, 1984 on 21-5-1984 and it was made
applicable with effect from 1-5-1984. By this, clause III of the
First Amendment Order was substituted and the same was
made applicable with effect from 1-5-1984 and was to remain
in force until withdrawn. It is alleged that the said Order was
not withdrawn by the State Government and is still in force.
The Corporation in order to check the malpractice by the
consumers installed electronic meters which are computerised
and can be downloaded for 35 days which will show the details
of consumption including any violation of peak hours
restriction in the last 35 days. Thereafter, the Board issued a
circular on 15-10-1998 to the effect that penalty for peak
hours restrictions will be imposed as per the meter reading
inspection report. However, it was pointed out by the
communication dated 7-4-1999 that for violation of restriction
of peak hours on the basis of meter reading inspection report
for the first time, one penalty for one month may be imposed
on the bill. However, for the second bill and thereafter, the
procedure for penalty will remain the same as mentioned in
the circular dated 15-10-1998. In this factual matrix, the
Division Bench of the Allahabad High Court after reading
these two circulars dated 15-10-1998 and 7-4-1999 took the
view that in view of the order dated 7-4-1999, the consumer
cannot be levied with penalty for each alleged contravention
but once only on the basis of alleged meter reading report,
meaning thereby that each such report will be treated as one
contravention. One meter reading inspection report which
stores data for 35 days, shall be treated as one contravention
irrespective of the fact that in the report a number of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
contraventions might have been made of peak hour restriction
but one meter reading inspection report shall be construed as
one contravention. Aggrieved against this order dated
25.5.2001 passed by the Division Bench of the Allahabad High
Court in Civil Miscellaneous Writ Petition No.4214 of 2001, the
appeal has been filed by grant of special leave.
5. A perusal of both these notifications makes it very clear
that by communication dated 7-4-1999 the relief was given
only for one time and it was not meant to be operated in
future. For violation of restrictions of peak hours on the basis
of MRI report for the first time, one penalty for one month
could be imposed. For second bill and subsequent bills, the
procedure of penalty will remain the same as mentioned in the
circular dated 15-10-1998. Therefore, according to the circular
dated 15-10-1998, whenever MRI computer print is taken, the
number of violations by a consumer shall be taken to be as
many times as indicated in MRI and it was clearly mentioned
that there will be no relaxation nor the violations will be
considered to be as one violation and will be treated
separately. It was also mentioned that the SDO, Junior
Engineer and Lineman in whose area the violation has been
committed by the consumers should be considered to be
penalised at the Chief Engineer level because of their failure to
stop the violation. The circular also further clarified that
whenever MRI has not been got done in time, the temporary
disconnection, on the basis of situation of the case can be
considered. But at least 5 days’ disconnection penalty will be
imposed for the first disobedience. Therefore, reading of these
two circulars makes it very clear that for violation of
restrictions of peak hours on the basis of MRI report for the
first time, one penalty for one month was to be imposed in the
bill. Therefore, by the circular dated 7-4-1999 one-time
concession was given to the consumers but it was not meant
to be for all times to come. Both these circulars clearly
contemplate that for each contravention penalty will be levied
and not simply because the violations have been recorded in
one MRI report, therefore, the same will be considered to be as
one violation. Hence, the view taken by the Division Bench of
the Allahabad High Court is clearly, unsuitable, and cannot be
sustained.
6. A similar issue was considered in U.P. Power Corpn. Ltd.
and Another v. Lohia Brass (P) Ltd.and Ors. (2006 (7) SCC
220) and it was held that High Court’s view is unsustainable.
7. The appeal is accordingly allowed with no order as to
costs.