Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 27
PETITIONER:
OM PRAKASH & ANR.
Vs.
RESPONDENT:
STATE OF U.P. & ORS.
DATE OF JUDGMENT: 15/07/1998
BENCH:
S.B. MAJMUDAR, A.P. MISRA
ACT:
HEADNOTE:
JUDGMENT:
WITH
CIVIL APPEAL NOS. 3264- 3268, 3262-3263 OF 1998
(Arising out of SLP (C) Nos. 21680-82, 21689, 21699 of 1995,
164 & 1874 of 1996)
AND
[ I.A. No. --------------- in S.L.P. (C) No. 164 of 1996
(for substitution)]
J U D G M E N T
S.B. MAJMUDAR, J:
Leave granted in all these special leave petitions.
I.A. filed in Civil Appeal arising out of S.L.P. (C)
No. 164 of 1996 for bringing on record legal representatives
of respondent no. 37 Mahipal is granted.
The title of the Civil Appeal concerned Shall be
corrected accordingly.
By consent learned senior advocates appearing for the
contesting parties, the appeals were finally heard and are
being disposed of by this judgment. These appeals arise out
of a common judgment rendered by a Division Bench of the
High Court of Judicature at Allahabad on 24th August 1995.
The High Court dismissed the writ petitions filed by the
appellants who were petitioners before the High Court
appellants who were petitioners before the High Court who
challenged the notification issued by the State of Uttar
Pradesh on 5th January 1991 under Section 4 (1) of Land
Acquisition Act, 1894 [ hereinafter referred to as ’the
Act’] and also the notification under Section 6 of the Act
whereby the writ petitioners’ lands situated at village
Chhalera banger then situated in District Ghaziabad in the
State of Utter Pradesh were sought to be acquired. The
impugned acquisition was for the planned industrial
development of District Ghaziabad through New Okhla
Industrial Development Authority (’NOIDA’ in short),
Ghaziabad. As the writ petitions raised a common challenge
on diverse grounds, they were all heard together and were
disposed of by the impugned common judgment of the High
Court. The High Court after considering the submissions
raised by the learned counsel for the writ petitioners for
challenging the acquisition proceedings, came to the
conclusion that the land acquisition proceedings were not
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 27
vitiated in law and consequently the writ petitions were
dismissed. That is how the original writ petitioners are
before us in these proceedings. They are now confined to the
appellants in these 8 Civil Appeals arising from Special
Leave Petitions filed by the original writ petitioners
concerned.
Before we deal with the main contentions canvassed by
learned senior counsel, Shri Shanti Bhushan, appearing for
appellants in some of the appeals, and Shri Uma Dutta,
learned counsel for appellants in other appeals, it will be
necessary to note a few background facts leading to these
proceedings.
Introductory Facts.
NOIDA is an authority entrusted with the task of
developing lands in the district of Ghaziabad in the Stat of
Uttar Pradesh. In the year 1976, NOIDA had acquired large
tracts of lands in the Ghaziabad district including lands of
village Chhalera Banger for the planned industrial
development of Ghaziabad district including lands of village
Chhalera Banger for the planned industrial development of
Ghaziabad. At that stage, the State of Uttar Pradesh, at the
instance of NOIDA had invoked the provisions of sub-sections
(1) and (4) of Section 17 of the Act as acquisitions for the
purposes of NOIDA was considered to be of an urgent nature.
Thereafter, again in the year 1987, further lands were
acquired from the same village for the purpose of NOIDA by
the State of Uttar Pradesh issuing notification under
Section 4 of the Act on 30th October, 1987. The said
notification was issued without invoking Section 17(4) of
the Act. After hearing the objections put forward against
the acquisition by the objectors concerned, ultimately the
State of Uttar Pradesh issued notification under Section 6
of the Act on 14th December, 1989. On that occasion, 353
acres of lands consisting of diverse survey numbers were
acquired from the occupants of the lands in village Chhalera
Banger. It was thereafter that NOIDA submitted a proposal to
acquire the lands under the present acquisition on 14th
June, 1988. It also made a written request in this
connection on 14th December, 1989 to the State authorities.
By a communication dated 14th December 1989 addressed by the
personnel officer, Noida to the Special Land Acquisition
officer, NOIDA, Ghaziabad, it was submitted that 494.26
acres of land of village chhalera Banger were urgently
required for the development of Sector No. 43 and other
sectors of NOIDA. Therefore, it was requested that necessary
notification under Section 4 read with Section 17 of the Act
may be got issued immediately. It was thereafter that on 5th
January, 1991, the impugned notification was issued by the
Government of Uttar Pradesh in exercise of powers under sub-
section (1) of Section 4 of the Act. It was stated therein
that the lands mentioned in the Schedule to the notification
were required for public interest, that is, for the planned
industrial development of district Ghaziabad through NOIDA.
It was recited in the said notification that the Governor
was of the opinion that sub-clauses of sub-section (1) of
Section 17 of the Act shall apply to the aforementioned land
because the said land was essentially urgently required for
the planned industrial development in District Ghaziabad
through NOIDA and in view of this urgency; and essential
requirement, it was also necessary that possible delay for
inspection under Section 5- A may be condoned . Therefore,
in exercise of powers under sub-section (4) of section 17 of
the Act, Governor also directed that provisions of Section
5-A of the said Act shall not be applicable and were
dispensed with. This notification was followed by another
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 27
notification dated 7th January, 1992 under Section 6 of the
Act. It was declared therein that the land mentioned in the
notification was required in public interest, i.e., for the
planned development of District Ghaziabad through NOIDA. It
was also stated that the Governor was satisfied that this
matter was to be disposed of urgently, therefore, in
exercise of power sunder sub-section (1) of Section 17 of
the Act he was also pleased to direct that though no
decision had been given under Section 11, the Collector of
Ghaziabad could take possession of the aforesaid land
mentioned in Schedule for public interest after 15 days of
the publication of the notice under sub-section (1) of
Section 9.
The aforesaid two notifications were brought in
challenge by the appellants herein, amongst others before
the High Court of Allahabad, as noted earlier. In these writ
petitions, the High Court by its order dated 31st march,
1992 directed that status quo may be maintained by the
parties to the writ petitions. The State of Uttar Pradesh as
well as NOIDA were the contesting respondents in the writ
petitions and in the present appeals also they are the main
contesting respondents.
Rival Contentions
Shri Shanti Bhushan, learned senior counsel for the
appellants in some of the appeals and Shri Uma Dutta,
learned counsel for the other appellants contended that the
impugned notification are null and void mainly on two
grounds - (i) that there was no relevant material before the
State authorities to enable them to invoke Section 17(4) of
the Act and to dispense with the inquiry under Section 5-A
of the Act; and that the grounds sought to be made out by
the State authorities in this connection were legally
unsustainable and, therefore, the direction contained in the
impugned notification under Section 4 invoking Section 17
sub-section (4) of the Act and in dispensing with inquiry
under Section 5-A was liable to be set aside and
consequently notification under Section 6 also was required
to be quashed. (ii) It was also contended that in any case
the lands occupied by the appellants which were sought to be
acquired in the present proceedings were having Abadi -
constructions occupied for residential and industrial
purposes by the appellants concerned and that a policy
decision was taken by the contesting respondents not to
acquire land covered by such Abadi. The acquisition
proceedings were, therefore, required to be set aside even
on that ground. Shri Shanti Bhushan, learned senior counsel
appearing for appellants in appeal arising from Special
leave Petition (c) No. 20905 of 1995 submitted that these
appellants had already filed a suit against NOIDA for
permanently restraining NOIDA from acquiring the appellants’
land which is covered by the present acquisition proceedings
on the ground that it was having Abadi thereon. That the
judgment of the Civil Court was rendered on 14th December,
1989 much prior to the issuance of the Section 4
notification in the present case wherein a clear finding was
reached by the Civil Court on evidence that there was
existing Abadi on the land dispute and the said decision was
confirmed by the District Court in Civil Appeal No. 46 of
1990 on 17th November, 1990. We are informed by learned
senior counsel, Shri Mohta, for respondent NOIDA that the
decision of the District Court has not become final and is
pending scrutiny in second Appeal before the High Court of
Allahabad. Shri Shanti Bhushan, learned senior counsel for
the appellants, in support of his submission that there was
an existing Abadi on the land sought to be acquired, invited
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 27
out attention to the relevant evidence on the record and
contended that in any view of the matter appellants’ land
having Abadi in the light of the policy consistently
followed by the contesting respondents could not have been
acquired. Learned counsel appearing in the other appeals,
Shri Uma Dutta also adopted these very contentions in
support of his appeals and submitted in addition that the
High Court had erred in taking the view that the subjective
satisfaction for invoking the provisions of Section 17(4) of
the Act was not independent of satisfaction for invoking
Section 17 sub-section (1) and that both these satisfactions
were really independent of each other and had to be arrived
at as such.
In support of the aforesaid contentions learned senior
counsel for the appellants placed before us certain
decisions of this Court to which we will refer at an
appropriate stage in the latter part of this judgment. It
was contended by learned counsel for the appellants that the
High Court had erred in taking the view that the State was
justified in involving the provisions of Section 17(4) of
the Act on the facts and circumstances of the cases. He,
however, fairly stated that if it is held that the State
authorities could not have dispensed with Section 5-A
inquiry and if the appellants are to be given an opportunity
to put forward their written objections before the acquiring
authority under Section 5-A of the Act then the second
question regarding Abadi lands immunity from being acquired
may not be decided at this stage. Hence this question may
also be permitted to be raised by the objectors in section
5-A proceedings.
Repelling these contentions, Shri Mohta, learned senior
counsel for NOIDA and Dr. N.M. Ghatate, learned senior
counsel appearing for the state of Uttar Pradesh contended
that no error was committed by the High Court in upholding
the applicability of Section 17 sub-section (4) to the
present proceedings as there was sufficient material before
the authorities to come to that decision. That the High
Court rightly held that for acquisition of the present type
wherein large acreage of lands had to be acquired for the
purpose of the planned industrial development of the area
undertaken by NOIDA, urgency clause could be legitimately
invoked. Urgent situation was implicitly in such acquisition
proceedings and if Section 5-A inquiry was not dispensed
with, years would have passed before Section 6 notification
could have been issued. It was also submitted by them that
the material relied upon by the State authorities for
dispensing with inquiry under Section 5-A of the Act was
quite relevant and this Court would not sit in appeal over
the subjective satisfaction of the authorities in this
connection as it is well settled that if such subjective
satisfaction for invoking section 17(4) of the Act is found
to be based on relevant material it cannot be challenged in
a court of law by requesting the court to re-appreciate such
evidence especially when there was no challenge to the
acquisition proceedings on the ground of mala ides. The High
Court’s decision in this connection, therefore, requires to
be upheld. It was also submitted that possession of the
lands in question was already taken by NOIDA on 30th March,
1992 prior to the date on which the High Court granted
status quo order. It was next contended that the appellants’
lands cannot be said to be having Abadi as mere stray
construction on agricultural lands cannot be termed Abadi.
That ’Abadi’ is a term of art which connotes construction
for residential purposes on village-site lands and it has
nothing to do with agricultural lands situate beyond village
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 27
sites. It was also submitted by Shri Mohta, learned senior
counsel for NOIDA, that the Civil Court’s judgment which is
not final till date had loosely treated lands having
construction as Abadi lands and consequently, it could not
be urged by the appellants that their lands having some
stray construction thereon could not have been acquired
under the Act in the light of the policy decision of the
State authorities of the contesting respondents not to
acquire lands having Abadi. In this connection, Shri Mohta
also submitted that the documentary material which is
furnished in the present proceedings by some of the
appellants to show that their lands were having Abadi
appears to be interpolated and such forged documents cannot
be permitted to be relied upon by the appellants. Dr.
Ghatate, learned senior counsel for State of U.P. submitted
that the state was not a party to the civil Court litigation
and hence was in no way bound by the finding arrived at by
the Civil Court regarding the abadi nature of the lands
under acquisition.
It was lastly contended placing reliance on some of the
judgments of this Court, to which we will make a reference
hereinafter, that acquisition for the planned development of
a township on a large scale would entitle the authorities to
invoke urgency provisions of Section 17(4) of the Act and
that the High Court has not erred in relying upon this legal
position. It was ultimately submitted that as almost 494
acres of lands were sought to be acquired by the impugned
notifications and only some of the persons whose lands were
being acquired had challenged the notifications in the High
Court and that challenge in the present proceedings gets
confined to about 40 acres in all, and as the planned
development of the sector is already underway and pipelines
and other infrastructure facilities are being made available
on spot, this court in exercise of its discretionary powers
under Article 136 of the Constitution of India may not
interfere in the peculiar facts of the case at such a late
stage. Learned senior counsel Shri Shanti Bhushan, repelling
these contentions, submitted that the material on which
contesting respondents relied upon for supporting such an
exercise and that there is no universal formula that
acquisition for planned development of a township
necessarily has to be treated to be of an urgent nature
without anything more. The applicability of section 17 (4)
of the Act in the peculiar facts of the present case should
be treated to be uncalled for. It was submitted that the
appellants, given an opportunity to have their written
objections under section 5-A of the Act, will fully co-
operate in the proceedings and will abide by the appropriate
directions regarding maintenance of time schedule for such
an inquiry as may be fixed by this Court. Shri Shanti
Bhushan further submitted that once it is shown that the
impugned notifications were liable to be set aside, on non-
compliance with Section 5-A of the Act, which was wrongly
excluded by the authorities, then this Court being a final
Constitution Court may not refuse appropriate relief to the
appellants by not interfering under Article 136 of the
Constitution of India. Shri Shanti Bhushan also sought to
distinguish judgments of this Court on which strong reliance
was placed by learned senior counsel for contesting
respondents.
In the light of the above rival contentions, the following
points arise for out determination :
1. Whether the State authorities were justified in
invoking Section 17(4) of the Act for dispensing with
inquiry under Section 5-A of the Act.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 27
2. In any case, whether the appellants’ lands have to be
treated as immune from acquisition proceedings on the
ground that they were having Abadi thereon and were,
therefore, governed by the policy decision of the State
of U.P. not to acquire such lands.
3. Whether this Court should refuse to exercise its
discretionary jurisdiction under Article 136 of the
Constitution of India in the facts and circumstances of
the case.
4. What final orders ?
What shall deal with these points seriatim.
Point No. 1
So far as the question of dispensing with inquiry under
Section 5-A is concerned, the scheme of the Land Acquisition
Act has to be kept in view. Sub-section (1) of Section 4 of
the Act lays down that whenever it appears to the
appropriate Government that land in locality is needed or is
likely to be needed for any public purpose or for a company,
a notification to that effect has to be published in the
official Gazette and also to proceed further according to
the mode laid down in the said provision. Then follows
section 5-A, Sub-section (1) thereof provides that any
persons interested in any land which has been notified under
section 4, sub-section (1), as being needed or is likely to
be needed for a public purpose may, within 30 days from the
date of publication of the notification, object to the
acquisition of the land or of any land in the locality, as
the case maybe. Sub-section (2) of Section 5-A of the Act
lays down the procedure in connection with such inquiry. The
objections under Section 5-a are to be lodged in writing
with the Collector and the Collector is required to give the
objector an opportunity of being heard in person or by any
persons authorised by him in this behalf or by pleader and
shall after hearing all such objections and after making
such further inquiry, if any, as he thinks necessary, either
make a report in respect of the land which has been notified
under Section 4 sub-section (1) , or make different reports
to the Government and in the light of the said report, the
appropriate government has to come to its own decision on
the objections and such decision is made final under the
Act. Then follows Section 6 sub-section (1) which lays down
that subject to the provisions of part vii of the Act, when
the appropriate Government is satisfied, after considering
the report, if any, made under Section 5-A, sub-section (2),
that any particular land is needed for a public purpose, or
for a company, a declaration can be made by the appropriate
Government for acquiring such lands. It is, therefor,
obvious that under the normal scheme of land acquisition
proceedings under the Act before any land can be acquired,
by issuing notification under Section 6, the gamut of
hearing of objections to such proposed acquisition as laid
down by Section 5-A has to be followed. It is in this light
that Section 17 of the Act which permits dispensing with
inquiry under Section 5-A in appropriate cases has to be
appreciated. Sub-sections (1) and (4) of Section 17 deserve
to be noted in extenso. They read as under:
" 17. Special powers in cases of
urgency. - (1) In cases of urgency,
whenever the appropriate Government
so directs, the Collector, though
no such award has been made, may,
on the expiration of fifteen days
from the publication of the notice
mentioned in Section 9, sub-section
(1), take possession of any land
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 27
needed for public purpose. such
land shall thereupon vest
absolutely in the Government, free
from all encumbrances.
(2) ............... ...... .....
(3) ............... ...... .....
(3-A) ............... ...... .....
(3-B) ............... ...... .....
(4) In the case of any land to
which, in the opinion of the
appropriate Government , the
provisions of sub-section (1) or
sub-section (2) are applicable, the
appropriate Government may direct
that the provisions of Section 5-A
shall not apply, and, if it does so
direct, a declaration may be made
under Section 6 in respect of the
land at any time after the date of
the publication of the notification
under Section 4, sub-section (1). "
It may be noted that prior to 1984, sub-section (1) of
section 17 could be invoked only in cases of lands which
were waste and arable and qua acquisition of such lands, if
there was any urgency Section 17 Sub-section (1) could b
invoked and accordingly even after issuance of notification
of Section 6 and before award is passed possession of such
lands could be taken on expiry of 15 days of the publication
of notice under Section 9 sub-section (1). But if the lands
were not waste or arable, neither section 17 sub-section (1)
nor section 17 sub-section (4) could have been invoked prior
to 1984 qua them as sub-section (4) of Section 17 has a
clear linkage with the lands to which provisions of sub-
section (1) are applicable. Consequently, prior to 1984, the
parent Act did not permit dispensing with inquiry under
Section 5-A or for taking possession prior to the award of
the acquired lands if the lands were not waste or arable
even though there might be any urgency centering round such
acquisition. The words ’Waste or arable’, however, were
deleted from the parent Act by Amending Act 68 of 1984 with
the result that now under the main Central Act for any type
of lands even if they may be waste or arable, or may not be
so, in cases of urgency, provisions of section 17 sub-
section (1) can be invoked and equally for any type of lands
sought to be acquired, in cases of urgency, the provisions
of section 17 sub-section (4) can be invoked, meaning
thereby, the intermediate procedure under Section 5-A
sandwiched between sections 4 and 6 can be legitimately
dispensed with and notification under Section 6 can follow
almost on the heels of section 4 notification in cases of
urgency , when appropriate direction under Section 17 sub-
section (4) is issued by the appropriate Government being
subjectively satisfied about the requisite requirement s
about invoking these provision. Even though under the
Central Act, no such power could have been invoked prior to
1984 for lands which were not waste or arable so far as
State of Uttar Pradesh was concerned, a special provision
was made by amending Section 17 of the Central Act by the
Land Acquisition (UP Amendment Act) XXII of 1954. Pursuant
to the said State amendment, a new sub-section (1-A) was
added to Section 17 of the parent Act in its application to
Uttar Pradesh to the following effect:
"The power to take possession under
sub-section (1) may also be
exercised in the case of other than
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 27
waste or arable land, where the
land is acquired for or in
connection with sanitary
improvements of any kind or planned
development "
Therefore, so far as the State of Uttar Pradesh in
concerned, any type of land after 19th November, 1954 even
though, not being waste or arable could be subjected to the
provisions of Section 17 sub-section (1). However, so far as
sub-section (4) of section 17 was concerned, no amendment
was made in the State of Uttar Pradesh till 26th April,
1974, when by the Land Acquisition (U.P. Amendment and
Validation) Act VIII of 1974, Section 17 sub-section (4) was
also amended by subsisting the words, brackets and figures
"sub-section (1), sub-section 1(A) or sub-section (2)" as
applicable to the State of Uttar Pradesh. The net result of
these two State amendments is that after 26th April, 1974,
if lands of any type, apart from being waste or arable, were
sought to be acquired under the Land Acquisition Act as
applicable to the State of Uttar Pradesh in case of urgency,
provisions of Section 5-A could be dispensed with provided
such lands were acquired for or in connection with sanitary
improvements of any kind or planned development. Thus, this
enabling provision was available to the appropriate
Government functioning in the State of Uttar Pradesh, If it
was satisfied that the situation was so urgent that Section
5-A inquiry was to be dispensed with in connection with
acquisitions of any type of lands for the planned
development of any are. However, still one basic requirement
remained for being satisfied before such power could be
exercised, namely, that there should be case of urgency.
Even if the acquisition was for the planned development of
any area and there was no material before the appropriate
Government for dispensing with inquiry under Section 5-A on
the touchstone of any urgency as found by the appropriate
Government, the provisions of Section 17 sub-section (4) as
amended by the Amending Act VIII of 1974 could not have been
invoked. However, the parent Act itself underwent an
amendment in 1984, as noted earlier, and the words ’waste or
arable’ were taken out from the sweep of section 17 sub-
section (1) read with sub-section (4) thereof The net result
is that after 1984, for acquisition of any type of lands if
the appropriate authority is satisfied about the existence
of urgency requiring acceleration of taking of possession as
per section 17(1) before award or acceleration of issuance
of notification under section 6 as per section 17(4) whether
such acquisition was for the planned development of any area
or for sanitary improvements in the area or for any other
public purpose or for a company.
As we are concerned only with the applicability of
Section 17 sub-section (4), it will be necessary to find out
whether there was any relevant material with the appropriate
Government, namely, respondent, State of UP herein, to
enable it to arrive at its subjective satisfaction about
dispensing with inquiry under Section 5-A in connection
with the present acquisition. Before we deal with the
judgments of this Court on the point, it will be necessary
to quickly glance through the factual backdrop leading to
the present proceedings. As we have noted earlier, NOIDA was
entrusted with the task of developing areas under its
jurisdication and that development could necessarily be a
planned development on a large scale. Such development could
not be confined only to a few pockets of the land but must
necessarily encompass in its fold schemes pertaining to
large tracts of lands which were lying undeveloped and which
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 27
had to be developed on a systematic basis. It is not in
dispute between the parties that initially in 1976 large
tracts of lands in Ghaziabad District in the State of Uttar
Pradesh were acquired from the very village from which the
present lands also are sought to be acquired. By a
notification dated 30th April, 1976, the State of Uttar
Pradesh exercising powers under sub-section 1 of section 4
issued a notification in the name of the Governor of Uttar
Pradesh to the effect that various plots of lands mentioned
in the notification were needed for public purpose, that is,
for the planned industrial development in the district which
was then known as Bullandshahr and the said acquisition was
through the NOIDA for that purpose. The said notification
showed that 121 and odd acres of lands were sought to be
acquired and at that stage, Section 5-A inquiry was
dispensed with by the State authorities by invoking powers
under Section 17 sub-section (4) thereof. This notification
worked itself out and was followed by Section 6 notification
and various chunks of land were acquired even from village
chhalera Banger amongst others. It appears that thereafter
necessary development was carried out on the acquired lands
by NOIDA and as a part and parcel of the comprehensive plant
for industrial development, further lands were sought to be
acquired by it by stages as development of any area of
township is a long drawn process spread over years. A
further notification under section 4(1) was issued by the
State of Uttar Pradesh on 30th October, 1987 acquiring
further lands for NOIDA from this very village. A number of
plots of land from this village were sought to be acquired
an they in all amounted to 353 acres of land. At this stage,
the state authorities did not think it fit to dispense with
inquiry under Section 5-A of the Act and invited parties
affected by the proposed acquisition of the lands by
submitting objections in writing to the Collector,
Ghaziabad. The purpose of acquisition was the same, namely,
for the planned industrial development in district Ghaziabad
through Noida. As by the time, district Bullandshahr was
renamed as Ghaziabad. It is, therefore, obvious that for
further development in the area, no urgency wad felt at that
stage for dispensing with the provisions of section 5-A of
the Act. It is not in dispute between the parties that the
further acquisition was for developing sector no. 42 in this
very Scheme run by NOIDA. The aforesaid notification under
Section 4 was followed by notification under section 6
dated 14th December, 1989, within two years of the issuance
of section 4 notification dated 30th October, 1987 after the
inquiry under section 5-A was over and the report was
submitted to the appropriate Government. It is interesting
to note that on the very day on which section 6 notification
was issued on 14th December 1989, acquiring these additional
lands, NOIDA proposed to the State Government that further
494.26 acres of land out of this very village Chhalera
Banger were urgently required for the development of Section
43 and other sectors of NOIDA. It was also requested that
necessary notification under Section 4 read with Section 17
of the Act with regard to the said lands may be issued
immediately. We were informed by senior counsel, Shri Mohta
for NOIDA that even though in the earlier acquisition of
1987, pursuant to section 4 notification inquiry under
Section 5-A was not dispensed with, by the time Section 6
notification came to be issued section 17(1) was resorted to
as urgency had developed at least by the end of December,
1989. If that is so, it was expected that pursuant to the
requisition of 14th December, 1989 by NOIDA invoking urgency
powers of the State Government, consequential notification
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 27
under Section 4(1) would have seen light of the day at the
earliest in connection with acquisition of proposed 494.26
acres of land for the development of Section 43 and other
sectors. But curiously enough, nothing happened urgently and
Section 4 notification which is impugned in the present case
was issued on 5th January, 1991. Thus despite the invocation
of urgency by NOIDA by its letter dated 14th December, 1989
it appears that the State did not think the said proposal to
be so urgent as to immediately respond and to issue
notification under Section 4 read with Section 17, sub-
section (4) till 5.1.91. more than one year elapsed in the
meantime. Why this delay took place and why the State did
not think it fit to urgency respond to the proposal of Noida
has remained a question mark for which there is no answer
furnished by the respondent authorities in the present cases
and nothing is brought on the record by them to explain this
delay. It has, therefore, necessarily to be presumed that
despite the emergency powers of the State Government being
invoked by NOIDA, the State authorities in their wisdom did
not think the matter to be so urgent as to immediately
respond the promptly issue section 4 notification read with
Section 17(4). The impugned notification of 5.1.91 recites
that for public interest, i.e., for the planned industrial
development through NOIDA, the lands mentioned in the
schedule to the notification were required to be acquired.
It was further recited in he notification that because the
lands were essentially required for the planned development
in District Ghaziabad through NOIDA, in exercise of powers
under sub-section (4) of Section 17, provisions of Section
5-A of the Act were dispensed with. The learned senior
counsel for the appellants vehemently submitted that in the
background of the aforesaid fact situation, it appeared that
when the State authorities invoked sub-section (4) of
section 17 on 5.1.91 in connection with present acquisition,
in fact, there was no urgency as even earlier in 1987, when
from this very village for the very purpose lands were
acquired, the State authorities in their wisdom did not
think it fit to apply urgency clause and to dispense the
inquiry under Section 5-A and in fact heard the objectors.
Even that apart, despite proposal to acquire this land was
moved by NOIDA, as early as on 14th June, 1988, and even
thereafter when the request was sent in this connection on
14th December, 1989, the State authorities did not think the
situation to be so urgent as to respond quickly and could
wait for more than one year. When the appellants in the writ
petitions before the High Court raised their grievances
regarding dispensing with inquiry under Section 5-A being
not backed up by relevant evidence and the subjective
satisfaction of the State in this connection was brought in
challenge, all that was stated by NOIDA in its counter in
para 26 was to the effect that the contents of paras 25 and
26 of the writ petition were denied and that the petitioners
were not able to point out any lacunae in the proceedings
under the Land Acquisition Act. Position was no better so
far as the counter of the State authorities was concerned.
In paragraph 24 of the counter before the High Court all
that was stated was that paragraphs 25 and 26 of the writ
petition were denied. When we turn to paragraphs 25 and 26
of the writ petition, we find averments to the effect that
the urgency of the acquisition was only for the purpose of
depriving the petitioners of their rights to file objections
under Section 5-A and their right to hold the possession
till they got compensation for which the respondents had
issued notification under Section 17(1) as well as
notification under Section 17(4) of the Act. But so far as
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 27
the process of the acquisition was concerned, the
respondents were taking their own time, which would be
evident from the fact that the notification under Section 4
read with Section 17(4) was issued on 5th January, 1991 but
was published in the newspaper on 30th March 1991, whereas
the declaration under Section 6 of the Act was made on 7th
January 1992 and that on the one hand respondents had
deprived the petitioners of filing their objections under
Section 5-A of the Act on the ground of urgency of
acquisition, but on the other hand, they themselves had
taken more than nine months in issuing the declaration under
section 6 of the said Act. This conduct of the respondents
falsified their claim of urgency of acquisition. These
averments in the writ petitions, to say the least, almost
went unchallenged and nothing concrete could be pointed out
by the respondents before the High Court to support their
stand as noticed from their counters referred to earlier.
thereafter, an additional model counter affidavit was filed
by the State authorities in the High Court for explaining
the reasons why section 5-A inquiry was dispensed with. In
paragraph 9 of the additional model counter affidavit it was
averred that it was necessary to bring material before the
date of notification under Section 4 for showing as to why
sub-section (4) of Section 17 was invoked. The additional
material which was produced before the High Court was by way
of Annexures - CA3, CA4 and CA 5. When we turn to these
annexures, we find that Annexure - CA 3 is a letter dated
21st April, 1990 written by the District Magistrate,
Ghaziabad, to the Joint Secretary, Industries, Government of
Uttar Pradesh. It recites that on examination, it was found
that the land was immediately required in public interest so
that the development work in the said land could be carried
out smoothly. What was the nature of urgency is not
mentioned in the said letter. Therefore, the position
remains as vague as it was earlier. When we turn to Annexure
- CA 4 which is dated 12th June, 1990, we find that the
District Magistrate, Ghaziabad wrote to the Joint Secretary,
Industries, State of U.P., that as to how many farmers were
going to be affected by the proposed acquisition. It does
not even whisper about the urgency of the situation which
requires dispensing with Section 5-A inquiry. The last
Annexure - CA 5 is the letter dated 14th December; 1989
written by NOIDA to the Land Acquisition Officer proposing
urgent acquisition of the lands in question. We have already
made a reference to the said letter. It recites that if
immediate action for acquisition of the aforesaid lands
adjacent to Sector 43 for development of which the
acquisition was to be resorted to was not taken them there
was possibility of encroachment over this area. That other
land adjacent to this sector was already being proposed for
the botanical garden. To say the least, possibility of
encroachment over t he area cannot by any stretch of
imagination be considered to be a germane ground for
invoking urgency powers for dispensing with Section 5-A
inquiry. Even if acquisition taken place urgently by
dispensing with inquiry under Section 5-A and the possession
is taken urgently after Section 6 notification within 15
days of issuance of notice under Section 9 sub-section (1),
even then there is no guarantee that the acquired land would
not be encroached upon by unruly persons. It is a law and
order problem which has nothing to do with the acquisition
and urgency for taking possession. Even that apart, it is
easy to visualise that if objectors are heard in connection
with Section 5-A inquiry and in the meantime, they remain in
possession of land sought to be acquired they would be the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 27
best persons to protect their properties against
encroachers. Consequently, the ground put forward by NOIDA
in its written requested dated 14-12-1989 for invoking
urgency powers must be held to be totally irrelevant. Even
that apart, if that was the urgency suggested by Noida on
14-12-1989, we fail to appreciate as to how the State
authorities did not respond to that proposal equally
urgently and why they issued notification under Section 4
read with Section 1794) after one year in January, 1991. On
this aspect no explanation whatsoever was furnished by the
respondent State authorities before the High Court. It is
also interesting to note that even after dispensing with
inquiry under Section 5-A pursuant to the exercise of powers
under Section 17(4) on 5th January, 1991, Section 6
notification saw the light of the day only on 7.1.1992. If
the urgency was of such a nature that it could not brook the
delay on account of Section 5-A proceedings, it is difficult
to appreciates as to why section 6 notification in the
present case could be issued only after one year from the
issuance of Section 4 notification. No explanation for this
delay is forthcoming on record. This also shows that
according to the State authorities, there was no real
urgency underlying dispensing with Section 5-A inquiry
despite NOIDA suggesting at the top of its voice about the
need for urgently acquiring the lands for the development of
sector no. 43 and other sectors.
So far as the present proceedings are concerned, the
situation was tried to be salvaged further in the counter-
affidavit filed on behalf of NOIDA. Its working secretary
Ram Shankar has filed a counter-affidavit in the present
proceedings explaining the necessity to apply emergency
provisions. It has been averred in para 9 of the counter to
the effect that what necessitated application of emergency
provisions was imminent possibility of unauthorised
construction and/or encroachment upon the suit land which
would have hammered the speedy and planned industrial
development of the area which was the purpose of acquisition
proceedings. This stand is in line with the earlier stand of
NOIDA in its written requisition dated 14th December, 1989.
We have already seen that the said stand reflects a ground
which is patently irrelevant for the purpose of arriving at
the relevant subjective satisfaction by the State
authorities about dispensing with Section 5-A inquiry. We
could have appreciated the stand of the State authorities
for invoking urgency clause under Section 17(4) of the Act
on the ground that when about 500 acres of land were to be
acquired for further planned development of Sector 43 and
other sectors of Noida, as mentioned in the impugned
notification, hearing of objectors who might have filed
written objections when there are large number of occupants
of these lands and who possess about 438 plots of land under
acquisition, would have indefinitely delayed the acquisition
proceedings and years would have rolled by before Section 6
notification could have been issued. Under these
circumstances, the entire further development of the area
would have, on the peculiar facts and circumstances of these
cases, come to a grinding halt. Such a stand would have
justified the subjective satisfaction of the authorities for
invoking Section 17 (4) of the Act. Such satisfaction then
could not have been gone behind by court of law. But
unfortunately for the respondents such was not their case
nor did they even whisper in these cases that these aspects
were kept in view while dispensing with Section 5-A inquiry.
The court cannot obviously, therefore, make out a new case
for them which is not pleaded in these proceedings to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 27
justify their action.
In the light of the aforesaid factual position emerging
on the record of the case it becomes clear that there was no
relevant material before the State authorities when it
invoked powers under sub-section (4) of section 17 for
dispensing with Section 5-A inquiry while issuing the
impugned notifications under Section 4 followed by Section 6
notification of 7.1.92.
It is in the background of the aforesaid fact situation
that we now turn to consider the relevant decisions of this
Court on which strong reliance was placed by either side
before us. We may note that the High Court while repelling
the contention centering round the question of dispensing
with inquiry under Section 5-A of the Act has placed strong
reliance on the two decisions of this Court having noted
that as large acres of lands were to be acquired, it was
necessary for the State to dispense with inquiry under
Section 5-A. In the case of State of U.P. etc. v. Smt. Pista
Devi and others [ (1986) 4 SCC 251], a Bench of two learned
Judges of this Court speaking through E. S. Venkataramiah,
J., (as he then was) had to consider the fact situation
existing in Meerut city which was densely populated part of
the State of Uttar Pradesh and was growing very fast. A
Development Authority was constituted under the provisions
of U.P. Urban Planning and Development Act, 1973 for the
purpose of tackling the problem of town planing and urban
development. 662 bighas 10 biswas and 2 biswanis of land
situate din the surrounding villages in the periphery of
Meerut town were sought to be acquired urgently by
dispensing with inquiry under Section 5-A. The High Court
before which the acquisition proceedings were challenged
took the view that because there was delay of one year
between Section 4 and Section 6 notifications, the urgency
clause under Section 17(4) was wrongly invoked. Upturning
the said decision of the High Court, this Court held that
the delay of one year was clearly explained on the facts of
the case as there was a corrigendum to be issued to Section
4 notification and when it was pointed out to the State
authorities by the Collector, the authorities issued the
corrigendum and simultaneously issued section 6
notification. Thus the delay of one year between Section 4
and Section 6 notifications was satisfactorily explained by
the authorities in that case. But even that apart, the
nature of the population pressure in the Meerut town and the
urgent need for providing for housing accommodation to those
residents in view of this Court’s directions in the
aforesaid decision, authorities were justified in invoking
powers under Section 17 (4) of the Act. it is no doubt true
that in the aforesaid decision, this Court referred to the
earlier three Judge Bench judgment of this Court in the case
of Narayan Govind Gavate and others etc. v. State of
Maharashtra and others etc. [(1977) 1 SCC 133] on which
strong reliance was placed by Shri Shanti Bhushan, learned
senior counsel for the appellants and observed that perhaps
at the time to which the said decision related situation
might have been that the schemes relating to development of
residential areas in the urban centres were not so urgent
and it was not necessary to eliminate the inquiry under
Section 5-A of the Act. The acquisition proceedings which
had been challenged in that case related to the year 1963.
During this period of nearly 23 years since then the
population of India has gone up by hundreds of millions and
it is no longer possible for the Court to take the view that
the schemes of development of residential areas do not
appear to demand such emergent action as to eliminate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 27
summary inquiry under Section 5-A of the Act. But even on
this basis it has to be shown by the authority invoking such
emergent action to satisfy the Court when challenge is
raised that the particular development of residential areas
concerning the acquired lands in the then existing fact
situation required dispensing with Section 5-A inquiry. In
the present case no such data was even whispered about by
the respondents either before the High Court or before us,
as we have seen earlier. Apart from that, as noted in the
said judgment, the delay between Section 4 and Section 6
notifications was adequately explained and that is how the
acquisition was upheld by this Court. With respect, the High
Court seems to have read much more in the said decision than
what was contemplated by this Court when it delivered the
said decision. In the case of Rajasthan Housing Board and
ors. vs. Shri Kisan and ors. [ (1993) 2 SCC 84], another
Bench of two learned Judges of this Court consisting of
Kuldip Singh and B.P. Jeevan Reddy, JJ., had to consider the
question of urgency requiring dispensing with Section 5-A
inquiry in connection with a housing scheme promulgated by
the Rajasthan Housing Board for settling Harijans who were
the weaker Sections of the Society. The Court in para 14 of
the Report noted that there was material before the
Government in the case upon which it could have acted when
it formed the requisite opinion that it was a case calling
for exercise of power under Section 17 sub-Section (4). The
material placed before the Court disclosed that the
Government found on due verification that there was an acute
scarcity of the land and there was heavy pressure for
construction of houses for weaker sections and middle income
group people; that Housing Board had obtained a loan of Rs.
16 Crores under a time bound programme to construct and
utilise the said amount by 31st march 1983; that in the
circumstances the Government was satisfied hat unless
possession was taken immediately and the Housing Board
permitted to proceed with the construction, the Board would
not be able to adhere to the time-bound programmed. It was
also noted that there was material on record to show that
the Housing Board had already appointed a large number of
engineers and other subordinate staff for carrying out the
said work and that holding an inquiry under Section 5-A
would have resulted in uncalled for delay endangering the
entire scheme and time schedule of the Housing Board. It was
also noted that satisfaction under Section 17 sub-section
(4) was a subjective one and that so long as there was
material upon which the Government could have formed the
said satisfaction fairly, the Court would not interfere nor
would it examine the material as an appellate authority. We
fail to appreciate as to how the said decision rendered in
the peculiar facts of the case before this Court could ever
be pressed in the service in the peculiar facts of the
present cases to which we have made a detailed reference
earlier. No such urgency based on any time bound scheme is
found in the present cases as was in the case of Rajasthan
Housing Board (supra). It is, of course, true that the High
Court has noted that large areas of lands are being acquired
for NOIDA and the activity carried out by it in the region
is very laudable and that NOIDA not only is an authority
constituted under the Act of 1976 but also caters to a well
developed locality which is situated in near proximity to
Delhi and the entire concentration of the State of Uttar
Pradesh is to develop it in such a fashion so as to attract
the biggest entrepreneurs from India and abroad. NOIDA is
the only jewel in the industrial crown of the State of UP
and, therefore, acquisition of land for the planned
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 27
industrial development in NOIDA is nothing but emergent. We
fail to appreciate as to how the High Court could persuade
itself to come to the aforesaid conclusion about emergency
when such was not the case pleaded either by the State or by
NOIDA before it. The only justification with which they came
forward was about the possibility of encroachers usurping
the land if it was not acquired urgently. That ground, as we
have noted earlier, to say the least, is totally irrelevant
one for basing any subjective satisfaction of the State
authorities for invoking powers under sub-section (4) of
Section 17.
It is time for us now to refer to a few other judgments
to which our attention was invited by learned senior counsel
for the respective parties.
In the case of Narayan Govind Gavate others etc. v.
State of Maharashtra & Ors. etc. [ (1977) 1 SCC 133], a
three-Judge Bench of this Court speaking through Beg, J. had
to consider the question whether invocation of powers under
Section 17 sub-section (4) of the Land Acquisition Act for
dispensing with the inquiry under Section 5-A in connection
with acquisition of land for development of industrial areas
and residential tenements could be justified on the facts of
that case. The following pertinent observations in
paragraphs 40, 41 & 42 of the Report were pressed in
service:
" 40. In the case before us, the
public purpose indicated is the
development of an area for
industrial and residential
purposes. This, in itself, on the
fact of it, does not call for any
such action, barring exceptional
circumstances, as to make immediate
possession, without holding even a
summary enquiry under Section 5A of
the Act, imperative. On the other
hand, such schemes generally take
sufficient period of time to enable
at least summary inquiries under
Section 5A of the Act to be
completed without any the scheme.
Therefore, the very statement of
the public purpose for which the
land was to be acquired indicated
the absence of such urgency, on the
apparent facts of the case, as to
require the elimination of an
enquiry under Section 5A of the
Act.
41. Again, the uniform and set
recital of a formula, like a ritual
of mantra, apparently applied
mechanically to every case, itself
indicated that the mind of the
Commissioner concerned was only
applied to the question whether the
land was waste or arable and
whether its acquisition is urgently
needed. Nothing beyond that seems
to have been considered. The
recital itself shows that the mind
of the Commissioner was not applied
at all to the question whether the
urgency is of such a nature as to
require elimination of the enquiry
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 27
under Section 5A of the Act. If it
was, at least the notifications
gave no inkling of it at all. on
the other hand, its literal meaning
was that nothing beyond matters
stated there were considered.
42. All schemes relating to
development of industrial and
residential areas must be urgent in
the context of the country’s need
for increased production and more
residential accommodation. yet, the
very nature of such schemes of
development does not appear to
demand such emergent action as to
eliminate summary enquiries under
Section 5A of the Act. There is no
indication whatsoever in the
affidavit filed on behalf of the
State that the mind of the
Commissioner was applied at all to
the question whether it was a case
necessitating the elimination of
the enquiry under Section 5A of the
Act. The recitals in the
notifications, on the other hand,
indicate that elimination of the
enquiry under Section 5A of the Act
was treated as an automatic
consequence of the opinion formed
on other matters. The recital does
not say at all that any opinion was
formed on the need to dispense with
the enquiry under Section 5A of the
Act. It is certainly a case in
which the recital was at least
defective. The burden, therefore,
rested upon the State to remove the
defect, if possible, by evidence to
show that some exceptional
circumstances which necessitated
the elimination of an enquiry under
Section 5A of the Act and that the
mind of the Commissioner was
applied to this essential question.
It seems to us that the High court
correctly applied the provisions of
Section 106 of the Evidence Act to
place the burden upon the State to
prove those special circumstances,
although it also appears to us that
the High Court was not quite
correct in stating its view in such
a manner as to make it appear that
some part of the initial burden of
the petitioners under Sections 101
and 102 of the Evidence Act had
been displaced by the failure of
the State to discharge its duty
under Section 106 of the Act. The
correct way of putting it would
have been to say that the failure
of the State to produce the
evidence of facts especially within
the knowledge of its officials,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 27
which rested upon it under section
101 of the Evidence Act, taken
together with the attendant facts
and circumstances, including the
contents of recitals, had enabled
the petitioners to discharge their
burden under Sections 101 and 102
of the Evidence Act."
It is no doubt true that the aforesaid decision of
three Judge Bench of this Court was explained by latter to
Judge Bench decision of this Court in State of U.P. v. Smt.
Pista Devi (supra) as being confined to the fact situation
in those days when it was rendered However, it is trite to
note that the latter Bench of two learned judges of this
court could not have laid down any legal proposition by way
of a ratio which was contrary to the earlier decision of
three Judge Bench in Narayan govind Gavate (supra). In fact,
both these decisions referred to the fact situations in the
light of which they were rendered.
Our attention was also invited by shri Shanti Bhushan,
learned senior counsel for the appellants to a decisions of
a two Judge Bench of this Court in the case of State of
Punjab and Anr. vs. Gurdial Singh and Ors. [(1980) 2 SCC
471] wherein Krishna Iyer, J. dealing with the question of
exercise of emergency powers under section 17 of the Act
observed in para 16 of the Report that save in real urgency
where public interest did not brook even the minimum time
needed to give a hearing land acquisition authorities should
not, having regard to Articles 14 and 19 burke an inquiry
under Section 17 of the Act. Thus, according to the
aforesaid decision of this Court, inquiry under Section 5-A
is not merely statutory but also has a flavour of
fundamental rights under Articles 14 and 19 of the
Constitution though right to property has now no longer
remained a fundamental right, at least observation regarding
Article 14, vis-a-vis, Section 5-A of the Land Acquisition
Act would remain apposite.
We may now refer to decision of a three judge Bench of
this Court in the case of Nandeshwar Prasad and Anr. vs. The
State of U.P. and Ors. [ (1964) 3 SCR 425] to which our
attention was invited by learned counsel, Shri Dutta
appearing for appellants in some of the appeals. Therein
Wanchoo J. speaking for the Court observed to the effect
that just as section 17(1) and 17(4) are independent of each
other, section 17(1A) and section 17(4) are independent of
each other and an order under section 17(1A) would not
necessarily mean that an order under section 17(4) must be
passed. There cannot be any dispute on this legal position.
however, the question with which we are concerned is
entirely different. It is to the effect whether on the facts
of these cases, there was any relevant material before the
State authorities to invoke powers under Section 17 sub-
section (4).
It is now time for us to refer to certain latter
decisions of this Court to which strong reliance was placed
by Shri Mohta, learned senior counsel for NOIDA. In the case
of A.P. Sareen and Others Vs. State of U.P. and Others [
(1997) 9 SCC 359], a two Judge Bench of this Court
consisting of Ramaswamy J. and G. T. Nanavati J, had to
consider the question whether the need for urgent possession
underlying acquisition proceedings could cease to exist only
because of bureaucratic inadvertence. It was held on the
facts of that case that urgency continued so long as the
scheme was not initiated, action taken and process
completed. It is, of course, true that while deciding this
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 27
question, it is observed that it is well settled legal
position that urgency can be said to exist when land
proposed to be acquired is needed for planned development of
the city or town, etc. The said observation clearly shows
that in appropriate cases when acquisition is needed for
planned development of city or town urgency provisions can
be invoked. This aspect is legislatively recognised by
enactment of Section 17(1A) by U.P. legislature. But the
said observations cannot be read to mean that in every case
of planned development of city or town necessarily and
almost automatically urgency clause has to be invoked and
inquiry under Section 5-A is to be dispensed with. It will
all depend upon the facts and circumstances of each case.
The aforesaid observations cannot be held to be laying down
nay absolute proposition that whenever any acquisition is to
take place for planned development of city or town, section
5-A should be treated to be almost otios or inoperative.
Such is not the ratio of the aforesaid decision and nothing
to that effect can even impliedly be read in the aforesaid
observation which is of general nature. It only suggests
that in appropriate cases, urgency clause can be invoked
when the land is proposed to be acquired for planned
development of city or town.
Another decision to which our attention was invited by
Shri Mohta, learned senior counsel for NOIDA is reported in
(1996) 2 SCC 365 [Ghaziabad Development Authority Vs. Jan
Kalyan Samiti, Sheopuri, ghaziabad and Anr.]. In that case,
a Bench of two learned Judges consisting of K. Ramaswamy and
G.B. Pattanaik. JJ examined an entirely different question
as to whether notification under Section 6 could be issued
simultaneously with the notification under Section 4 (1)
When Section 5-A was dispensed with under Section 17 sub-
section (4). This decision therefore, cannot be of any avail
to Shri Mohta. In the case of Jai Narain and Ors. vs. Union
of India and Ors. [(1996) 1 SCC 9 ], another bench of two
learned Judges consisting of Kuldip Singh and S. Saghir
Ahmad, JJ. had to examine the question whether invocation of
urgency provisions under Section 17 (4) for acquiring lands
for constructing a Sewage Treatment Plan (STP) in Okhla area
of this city could be said to be well justified. Upholding
the said exercise by the acquiring authorities, Kuldip
Singh, J in para 3 of the Report clearly noted the peculiar
fact situation under which Section 5-A inquiry was dispensed
with in that case. It was noted that this Court itself had
issued earlier time bound directions for procurement of land
for STP in various parts of Delhi. In the aforesaid
judgement, it was also observed in an earlier decision dated
24th march, 1995, this Court had observed that sewage
problems were of grave nature and so far as discharge of
effluent in Yamuna was concerned, the industries wee the
prime contributors apart from MCD and NDMC which were also
discharging Sewage directly into the river Yamuna and
thereafter on 21st April, 1995, this Court regarding the
construction of STP had observed that the treatment of
sewage was of utmost importance for health and for supply of
pure water to the citizens of Delhi. Any delay in this
respect was a health hazard and could not be tolerated. It
was also observed therein that this Court had earlier
directed to the authorities to take up the work of land
acquisition and sewage on war footing. In view of the
directions of this Court, therefore, the authorities were
bound to apply urgency clause and invoke urgency powers for
dispensing with Section 5-A inquiry so that the sewage
treatment plant could be established at the earliest and on
a war footing. We fail to appreciate as to how the aforesaid
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 27
fact situation and the direction to the State to move
quickly and urgently as issued by this Court which was
binding on the State authorities could be legitimately
pressed in service by Shri Mohta in the facts of this case
which stand on an entirely different footing, as noted
earlier.
In the light of the aforesaid discussion, therefore,
the conclusion becomes inevitable that the action of
dispensing with inquiry under Section 5-A of the Act in the
present cases was not based on any real and genuine
subjective satisfaction depending upon any relevant data
available to the State authorities at the time when they
issued the impugned notification under section 4(1) of the
Act and dispensed with Section 5-A inquiry by resorting to
Section 17 sub-section (4) thereof. The first point is,
therefore, answered in the negative, in favour of the
appellants and against the contesting respondents.
Point No. 2
So far as this point is concerned Shri Shanti Bhushan,
learned senior counsel for the appellants submitted that
much prior to the issuance of Section 4 notification and
after the earlier acquisition of 15 bighas of land from the
appellants’ own Survey No. 488, as the appellant was
apprehending further acquisition of a portion of land on
which his construction stood the appellant was constrained
to file a civil suit against NOIDA for a declaration that
the appellant was the owner and in possession of land
measuring 4 bigha 10 biswas comprising in Khasra No. 488
situated in village Chhalera Banger, and abadi stood therein
for about 5-6 years. The said suit was registered as Case
No. 46 of 1989 in the court of Munsif, Ghaziabad. After
hearing the plaintiff and NOIDA, the Civil court came to the
conclusion on evidence that there was abadi in the disputed
property. The Civil Court also noted the contention of NOIDA
which was defendant in that case that if disputed land was
abadi land of the plaintiff, then he could file objections
under Section 5-A of the Land Acquisition Act against the
proposed acquisition proceedings and if his abadi was
proved on the disputed land, then his abadi land could be
left out. Our attention was also invited to the further fact
that the said decision of the Civil Court dated 14th
December, 1989 was confirmed by the District Court dated 145
December, 1989 was confirmed by the District Court in appeal
on 17th November, 1990. Thus final court of facts came to
the conclusion that there was abadi of the appellant on the
land in question even prior to the date of Section 4
notification in the present case. It is, of course, true as
informed to us by Shri Mohta, learned senior counsel for
NOIDA, that the said decision of the District Court is not
final and second appeal against the said decision is pending
in the Allahabad High Court. Be that as it may, the
contention of Shri Shanti Bhushan, learned senior counsel
for the appellants, was that there was sufficient evidence
on the record of this case to show that the disputed land
under acquisition was having abadi since number of years and
that was prior to the issuance of section 4 notification
dated 05th January, 1991. he also invited our attention to
the further fact that pending the proceeding before the high
Court a site inspection report was prepared in connection
with diverse lands under acquisition and the appellant’s
Khasra No. 488 was one of them. This report dated 11th
March, 1996 was submitted by Officer on Special Duty, Land
Acquisition Department, Revenue Board, U.P. which clearly
shows that at the time when the inspection was made of
Khasra No. 488 belonging to the appellant, on the extend of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 27
4 acres and 10 bighas of land factory was located and the
property was being used also for residential purpose. There
was telephone number, there were three electric meters
installed, about 60 workers were found working in the
factory. Besides, 8 shops and 5 residential houses were
existing where families were living. It was also noted that
construction was very old and people were residing there for
long time and factory was also being run. Learned senior
counsel for NOIDA submitted that the aforesaid inspection
report was one-sided and it did not indicated whether NOIDA
authorities were also present at the time of the said
report. The learned counsel appearing for the appellants in
the remaining appeals also submitted that there was abadi on
the lands occupied by these appellants also. It is submitted
on behalf of the appellants by their learned counsel that
there is a policy followed by the State of Uttar Pradesh not
to acquire lands which are having abadi and consequently if
Section 5-A inquiry was held, the appellants could have
requested the appropriate authorities not to acquire these
lands.
Repelling the aforesaid contention, learned senior
counsel for NOIDA submitted that there is some misconception
about the concept of abadi. That abadi is a term which
refers to village site lands utilised for the residential
purposes. He, of course, stated tat it is true that there is
a policy adopted by the State of Uttar Pradesh not to
acquire lands on which there is abadi, namely, village site
lands having residential construction thereon. But according
to him, the Civil Court’s decree which has not become final
tries to equate construction with abadi but in the strict
sense of the term it would not be abadi which would be
covered by the State policy of not acquiring lands having
such abadi as any stray construction made on agricultural
lands outside the village sites reserved for putting up
construction of residential quarters in villages would not
be covered by the State policy of not acquiring such abadi
lands. He stated that whatever stand NOIDA authorities might
have taken as defendant in the suit cannot bind the state
authorities. Dr. Ghatate, learned senior counsel appearing
for the State of Uttar Pradesh, also submitted that the
State was not a party to the Civil Court litigation. He, of
course, stated that there is a State policy in existence as
on date under which genuine abadi lands on which abadi is
situated within the village sites may not be acquired but
only because there are some stray construction so
agricultural lands beyond the village sites they would not
be covered by such State policy. It was also submitted by
Shri Mohta, learned senior counsel for NOIDA and Dr.
Ghatate, learned senior counsel for State of U.P. that what
is necessary to be seen is whether there was any real abadi
on the lands under acquisition on the date of Section 4
notification dated 05th January, 1991 as any subsequent
construction put up thereafter by any of the occupants would
not create any equitable rights in their favour and any
subsequent construction and change of user of the land
covered by Section 4 notification cannot be of any avail.
In view of the aforesaid rival contentions, therefore,
it appears to us that in the present proceedings arising out
of petitions under Article 226 of the Constitution of India
it is not possible to come to a definite conclusion on these
highly disputed questions of fact, namely, whether the lands
in dispute were part of village site lands reserved for
construction of residential houses and whether they were
covered by the term ’abadi’ so as to subjected to any
policy decision of the State for excluding such abadi lands
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 27
from acquisition proceedings. Even the Civil Court
litigation which is still subjudice before the High Court
would by itself not bind the State authorities as State of
U.P. was not a party to these proceedings as rightly
contended by learned senior counsel Dr. Ghatate. Not only
that but the High Court in the impugned judgment has
referred to the set of evidence on record and has held that
there is no evidence showing the extent of construction on
the lands. On the other hand, there is a 17- point report by
the Tehsildar, Dadri, which is Annexure - 7 to the model
counter affidavit filed by the State in which he clearly
pointed out that the land sought to be acquired was
agricultural and that only boundary wall had been
constructed in 11 plots. The High Court has also observed
that in exercise of the powers under clause (d) of section
2 read with Section 3 of the U.P. Industrial Area
Development Act, 1976 the notification of 17th April, 1976
was published to declare the area comprising the villages
mentioned in the schedule annexed thereto, to be called the
New Okhla Industrial Development Area. The village chhalera
Banger, land of which is shown in Khasra entries is one of
the villages comprised in the schedule. The submission of
the learned standing Counsel is that this area was already
declared as industrial development area and after the
notification of 1976 was issued, such area could not have
been converted into Abadi. Therefore, a further disputed
question would arise as to whether the so-called abadi on
these lands sought to be acquired out of the agricultural
holdings of the occupants in village Chhalera Banger were
subjected to construction of abadi prior to 1976
notification or subsequent thereto. Consequently, no
direction can be issued to the State authorities
straightaway to release these lands from acquisition by
coming to a firm finding that there were existing old abadi
on these lands and which were squarely covered by any State
policy of not acquiring lands having abadi thereon.
We may also mention at this stage that apart from the
appellants in Civil Appeal arising out of S.L.P. (C) No.
20905 of 1995 in cases of other appellants no civil suits
were filed and, therefore, in their cases the question even
about construction, if any, is totally at large. That the
moot question is whether the lands under acquisition in the
present case were having abadi at the time of issuance of
Section 4(1) notification and whether such construction, if
any, could be said to be abadi as covered by a policy
decision of the State of U.P. not to acquire such lands. in
fairness to Shri Shanti Bhushan it was submitted by him that
we may not answer this question one way or the other if the
appellants are to be relegated to the remedy of filing
objections under Section 5-A of the Act. It is, of course
true as found by us on point No. 1 that Section 17 sub-
section (4) was not rightly invoked by the authorities in
the present cases. However, as will be seen hereafter, while
considering point No. 3, we are not inclined to give
opportunity under Section 5A to the appellants on the
peculiar facts of these cases. All that we can observe at
this stage is that the question whether the appellants’
lands are covered by any existing policy decision of the
State of U.P. for not acquiring lands having abadi thereon,
is required to be kept open for consideration of the proper
State authorities, as will be indicated by us hereinafter
while considering point Nos. 3 and 4. Point No. 2 is
answered accordingly.
Point NO. 3.
Now remains the vital question as to whether in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 27
light of our finding on point No. 1 the notification under
Section 4(1) so far as it dispenses with Section 5-A inquiry
by invoking powers under Section 17 (4) of the Act and the
consequential notification under Section 6 are required to
be set aside or not. We must keep in view that we are called
upon to exercise our jurisdiction under Article 136 of the
constitution of India. Such jurisdiction will necessarily
have to be exercised in the light of facts and circumstances
of these cases. Section 4 notification in the present cases
is dated 5th January 1991. It is followed by Section 6
notification dated 7th January 1992. In between the
appellants went to the High Court and got status quo order
since 31st March 1992.. Result is that till today even after
the expiry of 6 years and more, the land acquisition
proceedings qua the appellants’ lands have remained
stagnant. It is also to be kept in view that the impugned
notification under Section 6 of the Act was issued for the
purpose of planned development of District Ghaziabad through
NOIDA and by the said notification, 496 acres of land spread
over hundreds of plot numbers have ben acquired. Out of
494.26 acres of land under acquisition, only the present
appellants owning about 50 acres, making a grievance about
acquisition of their lands have gone to the court. Thus,
almost 9/10th of the acquired lands have stood validly
acquired under the land acquisition proceedings and only
dispute centers round 1/10th of these acquired lands owned
by the present appellants. It is a comprehensive project for
the further planned development in the district. We are
informed by learned senior counsel Shri Mohta for NOIDA,
that a lot of construction work has ben done on the
undisputed land under acquisition and pipelines and other
infrastructure have been put up. That the disputed lands
belonging to the appellants may have stray complex of lands
sought to be acquired. That if notification under Section
4(1) read with Section 17 (4) is set aside qua these pockets
of lands then the entire development activity in the complex
will come to a grinding halt and that would not be in the
interest of anyone. It was also contended by learned senior
counsel for the respondents that it was not the appellants’
contention that the proposed acquisition was not for public
purpose nor any mala fides were alleged to the behind such
acquisition. learned senior counsel, Shri Shanti Bhushan,
fairly stated that though the appellants might have mounted
a challenge on the ground of mala fides, they have not done
so before the High Court nor before this Court. Under these
circumstances, we find considerable force in the contention
of learned senior counsel for the respondent that it is
neither advisable nor feasible to interfere with the
acquisition of such large tracts of lands when the occupants
of 9/10th of the acquired lands have not thought it fit to
challenge these acquisition proceedings and the occupants of
only 1/10th of lands are agitating there grievance since
more than six years firstly before the High court and then
before this Court. The appellants’ main grievance centers
round the question whether their lands having alleged abadi
could be acquired in the light of the State policy for not
acquiring such lands. For such a contention, of course,
grievance could have been made under Section 5-A inquiry if
it was held. But that could have been urged years back
before Section 6 notification saw the light of the day in
1992. Now after a passage of more than six years, it would
not be feasible to put the clock back and permit the
appellants to agitate this contention which appears to be
the sole contention for opposing the acquisition proceedings
in the facts of the present cases by permitting them to urge
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 27
this grievance in Section 5-A inquiry which according to
them should be held at this stage. We will show presently
that this solitary grievance of the appellants could be
vindicated before the State authorities themselves by
relegating the appellants to proper remedy by way of
representation under Section 48 of the Act and when that
remedy is available to the appellants and when that is the
sold grievance of the appellants, at this stage no useful
purpose would be served by striking down the notification
under Section 4(1) qua the appellants so far as invocation
of Section 17 (4) is concerned and the consequent
notification under Section 6. That we cannot permit
upsetting the entire apple cart of acquisition of 500 acres
only at the behest of 1/10th of land owners whose lands are
sought to be acquired. We may also keep in view the further
alien fact that all the appellants have filed reference for
additional compensation under Section 18 of the Act. Shri
Shanti Bhushan, learned senior counsel, was right when he
contended that the appellants could not have taken the risk
of getting their reference applications time barred during
the pendency of these proceedings. Therefore, without
prejudice to their contentions in the present proceedings
they have filed such references. Be that as it may., that
shows that an award is also made and reference are pending.
Under these circumstances for enabling the appellants to
have their say regarding release of their lands on the
ground that they are having abadi and that the State Policy
helps them in this connection the appellants can be
permitted to have their grievances voiced before the State
authorities under Section 48 rather than under Section 5-A
of the Act at such a late stage. Consequently, despite our
finding in favour of the appellants on Point No. 1, we do
not think that this is a fit case to set aside the
acquisition proceedings on the plea of the appellants about
non-compliance with Section 5-A at this late stage. it is
also obvious that if on this point the notifications are
quashed for non-compliance of Section 5-A, that would open a
pandora’s box and those occupants who are uptill now sitting
on the fence may also get a hint to file further proceedings
on the ground of discriminatory treatment by the State
authorities. All these complications are required to be
avoided and hence while considering the question of exercise
of our discretionary jurisdiction under Article 136 of the
Constitution of India, we do not think that this is a fit
case for interference in the present proceedings with the
impugned notifications. Point No. 3, therefore, is answered
in the affirmative against the appellants and in favour of
the respondents.
Point No. 4
Now remains the moot question as to what proper orders
can be passed in the present proceedings in the light of our
findings on the aforesaid points. We have already noted that
the real and the only contention of the appellants for
effectively challenging the acquisition proceedings is that
because their lands are having abadi they are covered by the
existing state policy for into acquiring such lands under
the Act. Whether these lands are having abadi or not is a
vexed question of fact which we have kept open for
consideration of appropriate authorities instead of
relegating the appellants to the remedy under Section 5-A of
the Act. We deem it fit to relegate the appellants to the
remedy by way of suitable representation before the
appropriate state authorities under Section 48 of the Act.
It reads as under:
" 48. Completion of acquisition not
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 27
compulsory, but compensation to be
awarded when not completed. - (1)
Except in the case provided for in
Section 36, the Government shall be
at liberty to withdraw from the
acquisition of any land of which
possession has not been taken.
(2) Whenever the Government
withdraws from any such
acquisition, the collector shall
determine the amount of
compensation due for the damage
suffered by the owner in
consequence of the notice or of any
proceedings thereunder, and shall
pay such amount to the person
interested, together with all costs
reasonably incurred by him in the
prosecution of the proceedings
under this Act relating to the said
land.
(3) The provisions of Part III of
this Act shall apply, so far as may
be , to the determination of the
compensation payable under this
section."
As laid down by sub-section (1) of section 48 the
Government is at liberty to withdraw from the acquisition of
any land of which possession has not been taken. Learned
senior counsel of the contesting respondents submitted that
possession of these lands has already been taken. Our
attention was invited to a possession receipt annexed to the
counter affidavit filed on behalf of Respondent No. 4,
Secretary, New Okhla Industrial Development Authority. It is
stated in the counter that NOIDA has been put in possession
of the acquired lands from 30th March 1992 and the lands
under acquisition now form a part of Sectors 43 and 44 of
NOIDA. Secretary of New Okhla Industrial Development
Authority, Shri Rama Shankar has also earlier filed counter
affidavit to that effect. In para 6 thereof it is averred as
under:
" 6. I further say an submit that
the Hon’ble High Court of
Judicature at Allahabad on
31.3.1992 passed an interim order
to the effect that there would be
status quo and/or that the
petitioners would not be
dispossessed from the land in
dispute unless he has already been
dispossessed. i say and submit that
a day prior to the date on which
the interim order was passed, the
Petitioner had already lost
possession and the 4th Respondent
was put in actual physical
possession of the land which is the
subject matter of this petition."
Our attention was also invited to possession
certificate at Page 202 which mentions that for the elands
detailed in the Certificate, possession should be given to
the Tehsildar/Administrative officer, NOIDA on 30th March
1992. Number of lands are listed totalling to 492.91 acres
wherein appellants’ khasra numbers are also mentioned. It is
difficult to appreciate as to how the possession Certificate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 27
for all these numbers of lands would necessarily include
actual taking over of number of lands on which there were
constructions on the spot at the relevant time. It is also
pertinent to note that the possession Certificate is dated
30th March 1992 and the High Court of Allahabad granted
status quo order on the next day, i.e., 31st March 1992. It,
therefore, appears to us that so far as the appellants’
lands are concerned, only an effort was made to take paper
possession on 30th March, 1992 and actual possession does
not seem to have been taken. No possession receipt signed by
any of the appellants could be produced to substantiate that
contention. Not only that, as noted earlier, the evidence on
record showed that even pending the writ petition, the Site
Inspection Report of 11th March 1996 showed that some of the
lands in question were actually occupied by residents and
the lands were constructed upon and factory was being run.
Consequently, it is not possible to agree with the
submission of learned senior counsel for the respondents
that the possession of the acquired lands belonging to the
appellants was actually taken on the spot on 30th March,
1992. It is not in dispute that status quo order granted by
the High Court continued all throughout till the dismissal
of the writ petition. It was them contended that, before
this Court could grant any interim relief, possession
appeared to have been taken of these lands at least on 18th
November 1995. Our attention was invited to the authority
letter written by one Shri Chandra Pal Singh, Additional
District Magistrate, Land Acquisition, NOIDA, Ghaziabad that
possession should be given on 18th November 1995. it is
obviously after the decision of the High Court dated 24th
August, 1995. However, it must be noted that this Court by
order dated 29th September, 1995 had already granted ad
interim stay limited to the extent that any existing
construction should not be demolished without leave of the
court and that order has continued all throughout till the
hearing of the present appeals. It is, therefore, difficult
to appreciate as to how despite the order of this Court,
possession of the present appellants’ lands could have been
taken on 18th November, 195. However, Shri Mehta, learned
senior counsel for NOIDA submitted that this Court order was
only not to demolish the construction and has nothing to do
with taking possession It is difficult to appreciate this
submission. If the constructions on the disputed lands under
acquisition were not to be distributed, how it could be
contended that still the possession of the constructions was
with Noida and that they would not demolish the construction
having taken their possession. Even that apart, the
authority letter dated 18th November, 1995 itself shows the
details lands possession of which was given to NOIDA and the
land of Survey No. 488 is not one of them. For all these
reasons, therefore, it must be held that possession of the
lands under acquisition belonging to the present appellants
has remained with the appellants till date. Once that
conclusion is reached, Section 48 sub-section (1) can be
legitimately invoked by the appellants for consideration of
the State authorities. It is, of course, true that the said
provision gives liberty to the State to withdraw form
acquisition of any land but if the appellants are in the
position to convince the State authorities that their lands
were having abadi on the date on which section 4
notification was issued on 5th January, 1991 and it was that
abadi which had continued without any additional
construction thereon till the date of Section 6 notification
and thereafter and such abadi was squarely covered by the
Sate policy of not acquiring lands having abadi, then it
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 27
will be open to the State authorities to pass appropriate
orders for withdrawing such lands from acquisition and give
appropriate relief to the applicants concerned. We,
therefore, grant liberty to the appellants, if so advised,
to file written representations before appropriate
authorities of the State of Uttar Pradesh invoking State
Government’s powers under Section 48 Sub-section (1) of the
Act. It is made clear that we express no opinion on the
question whether the appellants’ lands had such abadi on the
date of section 4 notification which would attract the State
policy of not acquiring such lands and whether such policy
had continued thereafter at the stage of Section 6
notification of 7th January, 1992 and whether such policy is
still current and operative at the time when the appellants’
representations come up for consideration of appropriate
authorities of the state Government. it will be for the Stat
authorities to take their informed decision in this
connection. We may not be under stood to have stated any
thing on this aspect, nor are we suggesting that the Stat
must release these lands from acquisition if the State
authorities ar not satisfied about the merits of the
representations. The State authorities will have to be
satisfied on the following aspects in this connection:
(i) Whether there was any abadi on the acquired lands at
the time of Section 4(1) notification;
(ii) whether such abadi was a legally permissible abadi;
(iii) Whether such abadi has continued to exist till the
date of representation;
(iv) Whether such abadi was covered by any Government policy
in force at the time of issuance of Section 4(1)
notification and/or section 6 notification for not
acquiring lands having such abadi;
(v) whether such Government policy has continued to be in
force till the date of representation.
In short, the entire matter is left at large for the
consideration of the State authorities in the appellants’
representation. We also make it clear that if the appellants
file their written representation the aforesaid effect or
before 31.8.1998 then the appropriate authorities of the
State Government shall consider their representations
regarding the feasibility of releasing such lands from
acquisition under Section 48(1) of the Act on the ground
that there were ’abadis’ on these lands at the relevant time
and are governed by any existing state policy for releasing
such lands from acquisition on that score as indicated
hereinabove and for that purpose they may give hearing to
the appellants, either personally or through their counsel,
and permit them to lead whatever evidence they want to lead
in this connection. The State authorities shall consider
these written representations within a period of two months
from the date such representations are received, i.e. latest
by 31.10.1998 and will take appropriate decisions on these
representations and will inform the representationists
concerned in writing about the decision of the State
Government in this Connection.
Subject to the aforesaid liberty given to the
appellants, these appeals will, therefore, stand dismissed.
We may, however, state that the status quo regrading
possession on spot in connection with the appellants’ lands
shall be maintained by all concerned till 30.11.1998 within
that time the consideration of the appellants’
representation under Section 48(1) of the Act is completed
by the State authorities and result thereof is communicated
to the representationists. We also make it clear that if the
appellants do not file such representations on or before
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 27 of 27
31.8.1998 the State authorities will not be required to
consider any such representation filed thereafter and the
status quo order regarding possession as granted by us will
stand recalled after 31.8.1998 qua the concerned appellants
who do not file such representations within the time granted
by us for the purpose.
Before parting with the present proceedings we may
mention one request made by learned senior counsel Shri K.
K. Venugopal appearing for respondent No. 5 whose
intervention application was granted in S. L. P. (C) No.
20905 of 1995. Learned senior counsel stated that many
serious objections are required to be considered against the
acquisition of the eland of the intervener and it was his
contention that lands were acquired for being allotted to
persons closely related to the Chairman and other powers
that be, but as these contentions raise disputed question of
fact and as Respondent No. 5 had not filed any writ petition
in the High Court he may be given liberty to file writ
petition under Article 226 of the Constitution of India
before the High Court. The said request is reasonable. In
the present appeals arising out of judgment of the High
Court in writ petitions filed by the appellants, Respondent
No. 5’s independent grievance cannot be examined. It would,
therefore, be appropriate to relegate Respondent No. 5
intervener to the remedy of filing a substantive writ
petition under Article 226 of the Constitution of India
before the High Court. The respondent-authorities had no
objection to such course being adopted. Consequently,
Respondent No. 5 - intervener’s contentions are not being
examined by us in these proceedings. It is trite to observe
that as and when Respondent No. 5 files a substantive writ
petition under Article 226 of the Constitution of India
before the High Court it will be for the High Court to
decide the merits of the said writ petition including the
question whether the writ petition at such a stage is
required to be entertained or not. In short, we express no
opinion on the merits of such writ petition that may be
filed by the intervener - Respondent No. 5 in the High
Court. The Said petition will have to be decided on its
merits including the question of its maintainability by the
High Court after hearing the parties concerned.
In the result, these appeals fail and are dismissed,
subject to eh aforesaid liberty reserved to the appellants
for filing written representations under Section 48 sub-
section (1) of the Act. There will be no order as to costs
in the facts an circumstances of the cases.
IN THE MATTER OF: