Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.11095 OF 2018
GMR WARORA ENERGY LIMITED ...APPELLANT (S)
VERSUS
CENTRAL ELECTRICITY REGULATORY
COMMISSION (CERC) & ORS. ...RESPONDENT (S)
WITH
CIVIL APPEAL NOS.11910-11911 OF 2018
CIVIL APPEAL NOS.12055-12056 OF 2018
CIVIL APPEAL NO.3123 OF 2019
CIVIL APPEAL NO.5372 OF 2019
CIVIL APPEAL NO. 6641 OF 2019
CIVIL APPEAL NOS. 2935-2936 OF 2020
CIVIL APPEAL NOS. 4628-4629 OF 2021
CIVIL APPEAL NOS. 5583-5584 OF 2021
CIVIL APPEAL NO. 39 OF 2021
CIVIL APPEAL NO. 5005 OF 2022
Signature Not Verified
Digitally signed by
Narendra Prasad
Date: 2023.04.20
11:59:43 IST
Reason:
CIVIL APPEAL NO. 4089 OF 2022
1
Index
I. INTRODUCTION…………………………………………….. Paras 1 to 5
II. BRIEF FACTS AND SUBMISSIONS…………………….. Paras 6 to 91
III. ADDITIONAL ISSUES……………………………………… Para 92
IV. CONSIDERATION…………………………………………… Paras 93 to 130
V. CONCLUSION………………………………………………… Paras 131 to 168
VI. EPILOGUE…………………………………………………….. Paras 169 to 184
List of abbreviations:
| 1. APTEL - Appellate Tribunal for Electricity | |
|---|---|
| 2. CEA - Central Electricity Authority | |
| 3. CERC - Central Electricity Regulatory Commission | |
| 4. CIL - Coal India Limited | |
| 5. COD - Commercial Operation Date | |
| 6. CSA - Coal Supply Agreement | |
| 7. DISCOMS - Distribution Companies | |
| 8. ECL - Eastern Coalfield Limited | |
| 9. EFC - Evacuation Facility Charges | |
| 10. FSA - Fuel Supply Agreement | |
| 11. GCV - Gross Calorific Value | |
| 12. LoA - Letter of Assurance | |
| 13. LPS - Late Payment Surcharge | |
| 14. MAT - Minimum Alternate Tax | |
| 15. MCL - Mahanadi Coalfield Limited | |
| 16. MERC - Maharashtra Electricity Regulatory Commission | |
| 17. MoC - Ministry of Coal | |
| 18. MoP - Ministry of Power | |
| 19. MSEDCL - Maharashtra State Electricity Distribution Company Limited | |
| 20. NCDP - New Coal Distribution Policy | |
| 21. PPAs - Power Purchase Agreements | |
| 22. RFP - Request for Proposal | |
| 23. SBAR - State Bank Advance Rate | |
| 24. SECL - South Eastern Coal Limited | |
| 25. SHAKTI - Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India | |
| 26. SHR - Station Heat Rate | |
| 27. TANGEDCO- Tamil Nadu Generation and Distribution Corporation | |
| 28. UHV - Useful Heat Value | |
2
J U D G M E N T
B.R. GAVAI, J.
I. INTRODUCTION
1.
When we heard this batch of Electricity appeals, it was
agreed between all the parties that this Court should first decide
Civil Appeal No. 684 of 2021 ( Maharashtra State Electricity
Distribution Company Limited v. Adani Power Maharashtra
1
Limited & Ors. ) [“ MSEDCL v. APML & Ors. ” for short] and Civil
Appeal No. 6927 of 2021 ( Maharashtra State Electricity
Distribution Company Limited v. GMR Warora Energy Ltd. &
ors. ), inasmuch as three of the issues involved in all the appeals
in the batch were common. It was submitted that those two
appeals could be decided by deciding the three common issues.
However, insofar as the other appeals are concerned, it was
submitted that, in addition to the three common issues, certain
1
2023 SCC OnLine 233
3
| additional issues were also involved and it was agreed that after | |
|---|---|
| those two appeals are decided, the other appeals should be heard | |
| for considering these additional issues. | |
| 2. The said three common issues are thus: | |
| (i) Whether ‘Change in Law’ relief on account of New Coal | |
| Distribution Policy, 2013 (“NCDP 2013” for short) | |
| should be on ‘actuals’ viz. as against 100% of | |
| normative coal requirement assured in terms of New | |
| Coal Distribution Policy, 2007 (“NCDP 2007” for short) | |
| OR restricted to trigger levels in NCDP 2013 viz. 65%, | |
| 65%, 67% and 75% of ACQ? | |
| (ii) Whether for computing ‘Change in Law’ relief, the | |
| operating parameters should be considered on | |
| ‘actuals’ OR as per technical information submitted in | |
| bid? | |
| (iii) Whether ‘Change in Law’ relief compensation is to be | |
| granted from 1st April 2013 (start of Financial Year) or | |
| 31st July 2013 (date of NCDP 2013)? |
4
3. After extensively hearing all the learned counsel for the
rd
parties, vide the judgment and order dated 3 March 2023 in the
case of MSEDCL v. APML & Ors. (supra), this Court decided
those two appeals after considering the aforesaid three issues.
4. The first issue was answered by this Court, holding that the
‘Change in Law’ relief for domestic coal shortfall should be on
‘actuals’, i.e. as against 100% of normative coal requirement
assured in terms of the NCDP, 2007. Insofar as the second issue
is concerned, it was held that the Station Heat Rate (“SHR” for
short) and Auxiliary consumption should be considered as per
the Regulations or actuals, whichever is lower. The third issue
was answered holding that the Start date for the ‘Change in Law’
st
event for the NCDP, 2013 is 1 April 2013.
5. After we decided those appeals, we have heard the present
appeals in which some of the issues which were decided by us
vide the said judgment in the case of MSEDCL v. APML & Ors.
(supra) also arose for consideration along with other issues.
However, most of the issues in all these appeals are overlapping
5
and, therefore, we propose to decide these appeals by this
common judgment.
II. BRIEF FACTS AND SUBMISSIONS
Civil Appeal No. 11095 of 2018 and Civil Appeal Nos. 11910-
11911 of 2018
6. These cross appeals challenge the common judgment and
th
order dated 14 August 2018 passed by the learned Appellate
Tribunal for Electricity, New Delhi (hereinafter referred to as
“APTEL”) in Appeal No. 111 of 2017 & I.A. No.450 of 2018 and in
Appeal No.290 of 2017 & I.A. No.519 of 2017.
7. Civil Appeal No.11095 of 2018 is filed by GMR Warora
Energy Ltd. (hereinafter referred to as “GWEL”/”Generator”) to
the extent it was denied compensatory benefits on certain
components on the ground of ‘Change in Law’.
8. Civil Appeal Nos. 11910-11911 of 2018 have been filed by
DNH Power Distribution Co. Ltd. (DPDCL) (hereinafter referred to
as “DNH-DISCOM”), being aggrieved by the order of the learned
6
APTEL accepting the claim of GWEL on certain issues and
holding the same to be ‘Change in Law’.
9. The facts, in brief, giving rise to these appeals are as under:
10. GWEL had set up a Thermal Power Station at Warora,
District Chandrapur in the State of Maharashtra with an
installed capacity of 600 MW (2 x 300 MW). The Commercial
th
Operation Date (“COD” for short) of Unit 1 was 19 March 2013
st
and that of Unit 2 was 1 September 2013.
11. GWEL had entered into long term Power Purchase
Agreements (“PPAs” for short) with DNH-DISCOM for supply of
200 MW power to Maharastra State Electricity Distribution
th
Company Limited (“MSEDCL” for short) on 17 March 2010
st
[“MSEDCL PPA”) and for supply of 200 MW power on 21 March
2013 (“DNH PPA”), after it emerged as the successful bidder for
supply of power to MSEDCL/ DNH-DISCOM. The Scheduled
th
delivery date under the MSEDCL PPA was 17 March 2014,
st
whereas under the DNH PPA, it was 1 April 2013. GWEL is also
supplying 150 MW power from its power plant to Tamil Nadu
7
| Generation and Distribution Corporation (“TANGEDCO” for | ||||
|---|---|---|---|---|
| short) by way of back-to-back arrangement with trading company | ||||
| GMR Energy Trading Limited, for which purpose, a PPA was | ||||
| signed on 27th November 2013 (“TANGEDCO PPA”). | ||||
| 12. In terms of the PPAs, the cut-off date, which is 7 days prior | ||||
| to the bid deadline, is to be considered for the purpose of claims | ||||
| under ‘Change in Law’. Following are the cut-off dates under the | ||||
| said PPAs. | ||||
| DNH PPA | MSEDCL PPA | TANGEDCO PPA | ||
| Cut-off date | 1.6.2012 | 31.7.2009 | 27.2.2013 | |
| 13. Certain ‘Change in Law’ events occurred with regard to | ||||
| MSEDCL PPA and DNH PPA after the cut-off date. The same were | ||||
| notified by GWEL to MSEDCL/ DNH-DISCOM. | ||||
| 14. GWEL filed Petition No. 8/MP/2014 before the Central | ||||
| Electricity Regulatory Commission (hereinafter referred to as | ||||
| “CERC”) seeking relief for ‘Change in Law’. |
8
st
15. Vide Order dated 1 February 2017, certain claims were
allowed and certain claims were disallowed by the CERC.
16. The claims which were allowed by the CERC are thus:
“i. Increase in CVD from 8% to 10%
and 10% to 12%;
ii. Increase in Excise Duty;
iii. Increase in Service Tax;
| 17. The claims which were disallowed by the CERC are thus: |
9
ii. Design changes in Coal Handling
Plant (CHP);
iii. Increase in the rate of Minimum
Alternate Tax (MAT);
iv. Increase in Busy Season Surcharge
and Development surcharge on
transportation of coal by Indian
Railways (IR);
v. Increase in sizing charges and
surface transportation charges by
Coal India Ltd. (CIL);
vi. Increase in operating cost on
account of specification of coal
quality to be used for the TPS;
vii. Change from UHV to GCV based
pricing of coal;
viii. Incremental increase in Interest on
| 18. Being aggrieved by the judgment and order passed by the | |
| CERC, cross-appeals were filed by both GWEL and DNH- | |
| DISCOM. | |
| 19. Vide the impugned judgment, the learned APTEL, while | |
| concurring with the view of CERC on the claims allowed by it, |
10
| further allowed the claims on the ground of ‘Change in Law’ on | |
|---|---|
| the following components: | |
| (i) Busy Season Surcharge and Development Surcharge; | |
| (ii) Ministry of Environment and Forest (“MoEF”) | |
| Notification on coal quality; and | |
| (iii) Change in NCDP and Carrying Cost. | |
| 20. However, the rest of the claims were disallowed by the | |
| learned APTEL, concurring with the view taken by the CERC. | |
| Insofar as the appeal filed by DNH-DISCOM is concerned, the | |
| same was dismissed by the learned APTEL. Hence, these cross- | |
| appeals. | |
| 21. We have heard Mr. Vishrov Mukherjee, learned counsel | |
| appearing on behalf of the GWEL and Mr. Samir Malik, learned | |
| counsel appearing on behalf of MSEDCL and Mr. M.G. | |
| Ramachandran, learned Senior Counsel appearing on behalf of | |
| the DNH-DISCOM. |
11
| 22. Mr. Vishrov Mukherjee submits that the learned APTEL has | |
|---|---|
| erred in disallowing the claim on the following items: | |
| (i) Withdrawal of Deemed Export Benefit by way of Circular | |
| dated 28th December 2011 and Notification dated 28th | |
| December 2011 issued by the Directorate General of | |
| Foreign Trade (“DGFT”) and amendment to the Foreign | |
| Trade Policy dated 21st March 2012; | |
| (ii) Imposition of Crushing/Sizing charges and Surface | |
| Transportation Charges by Notification dated 15th | |
| October 2009; | |
| (iii) Change in system of classification of coal by Coal India | |
| Limited (“CIL” for short) from Useful Heat Value (“UHV” | |
| for short) to Gross Calorific Value (“GCV” for short) | |
| system of pricing by way of Notification dated 30th | |
| December 2011; | |
| (iv) Increase in levy of Minimum Alternate Tax (“MAT” for | |
| short) pursuant to amendment of Section 115JB of the | |
| Income Tax Act, 2012; |
12
| (v) Design changes in Coal Handling Plant in terms of letter | |
|---|---|
| issued by the Central Electricity Authority (“CEA” for | |
| short) dated 19th April 2011; | |
| (vi) Increase in working capital. | |
| 23. It is submitted that all these changes have taken place on | |
| account of the Notifications/Orders/Circulars issued by the | |
| instrumentalities of the State and as such, the learned APTEL | |
| ought to have allowed the claim for compensation on account of | |
| ‘Change in Law’ on the aforesaid items also. | |
| 24. It is submitted that the compensation on account of the | |
| ‘Change in Law’ is based on the principle of restitution so as to | |
| put back the party to the same economic position it was in, had | |
| the ‘Change in Law’ event not taken place. However, this has | |
| not been considered in the correct perspective by the learned | |
| APTEL. | |
| 25. Learned counsel appearing on behalf of the DNH-DISCOM | |
| and MSEDCL, on the contrary, submit that the learned APTEL | |
| has erred in considering the Busy Season Surcharge and |
13
Development Surcharge, MoEF Notification on coal quality,
Change in NCDP and Carrying Cost as ‘Change in Law’ events.
He submits that when the Generator had submitted its bid, it
was aware that there was a likelihood of variations on certain
payments to be made and the same were factored in while
submitting the bid. It is, therefore, submitted that the learned
APTEL erred in granting ‘Change in Law’ benefits on the said
issues.
Civil Appeal Nos. 4628-4629 of 2021
26. These appeals have been filed by Uttar Haryana Bijli Vitran
Nigam Limited and Dakshin Haryana Bijli Vitran Nigam Limited
(hereinafter referred to as “Haryana Discoms”) challenging the
th
common judgment and order dated 7 June 2021 passed by the
learned APTEL in Appeal No.158 of 2017 & I.A. No.575 of 2018
and Appeal No. 316 of 2017. Appeal No.158 of 2017 & I.A.
No.575 of 2018 were filed by Adani Power (Mundra) Limited
(hereinafter referred to as “AP(M)L”), being aggrieved by the order
th
passed by the CERC dated 6 February 2017, whereby the CERC
14
had denied certain claims for compensation on certain
components on account of ‘Change in Law’, whereas Appeal
No.316 of 2017 was filed by Haryana Discoms challenging grant
of claim of compensation on certain components on the ground
of ‘Change in Law’.
27. The Chart of claims which were allowed and disallowed by
the CERC is as under:
“107. Based on the above analysis and
decisions, the summary of our decision
under the Change in Law during the
operating period of the project is as
under:
| Components | Change in<br>Law Event |
|---|---|
| Change in Rate of Royalty | Allowed |
| Levy of Central Excise Duty subject<br>to directions in para 32 of the order | Allowed |
| Levy of Clean Energy Cess | Allowed |
| Levy of Customs Duty on energy<br>removed from SEZ to DTA | Allowed |
| Increase in Busy Season Surcharge<br>on transportation of coal | Not Allowed |
15
| Increase in Development Surcharge<br>on transportation of coal | Not Allowed |
| Levy of Service Tax on<br>transportation of coal | Allowed |
| Levy of Green Energy Cess in<br>Gujarat | Liberty granted<br>to approach after<br>Hon`ble<br>Supreme Court’s<br>Decision |
| Increase in Sizing Charges of coal | Not Allowed |
| Increase in Surface Transportation | Not Allowed |
| Change in pricing of coal from UHV<br>to GCV basis | Not Allowed |
| Change in class from 140 to 150 for<br>Railway freight for coal for trainload<br>movement | Not Allowed |
| Levy of Minimum Alternate Tax on<br>plants situated in SEZ | Not Allowed |
| Linking railway tariff revision with<br>movement in cost of fuel | Not Allowed |
| Imposition of Swachh Bharat Cess | Allowed |
| Payment to National Mineral<br>Exploration Trust | Allowed |
16
| Payment to District Mineral<br>Foundation | Allowed |
| Installation of FGD as per<br>Environmental clearance dated<br>20.5.2010<br>Auxiliary consumption due to FGD<br>installation affecting capacity<br>charges<br>Additional operating expenditure on<br>FGD | Not decided<br>and liberty<br>granted |
| Carrying cost | Not Allowed |
.”
28. Being aggrieved by the order of the CERC, cross-appeals
were filed by AP(M)L so also by Haryana Discoms before the
learned APTEL. The Haryana Discoms challenged that part of
the order of the CERC which allowed claim on components on
the ground of ‘Change in Law’, whereas AP(M)L challenged that
part of the order of the CERC which disallowed its claim on
various components.
17
| 29. Though AP(M)L had sought ‘Change in Law’ compensation | |
|---|---|
| on various components, the same was allowed by the learned | |
| APTEL by the impugned order only on the ground of: | |
| (i) ‘Busy Season Surcharge and Developmental Surcharge | |
| on transportation of coal’, and | |
| (ii) ‘Carrying Cost’. | |
| 30. The claim of AP(M)L pertaining to increase in Surface | |
| Transportation Charges so also Sizing Charges of coal were | |
| denied by the learned APTEL, concurring with the view taken by | |
| the CERC. | |
| 31. Being aggrieved by the orders passed by the CERC and the | |
| learned APTEL allowing ‘Change in Law’ on certain components, | |
| the Haryana Discoms have approached this Court. | |
| 32. We have heard Ms. Poorva Saigal, learned counsel | |
| appearing on behalf of the Haryana Discoms and Dr. A.M. | |
| Singhvi, learned Senior Counsel appearing on behalf of AP(M)L. |
18
33. Ms. Poorva Saigal submits that the learned APTEL grossly
erred in reversing the well-reasoned findings of the CERC on the
issue of Busy Season Surcharge and Developmental Surcharge
on transportation of coal. She, therefore, submits that the
finding of the learned APTEL with regard to the same needs to be
set aside.
34. Dr. A.M. Singhvi, on the contrary, submits that the Busy
Season Surcharge as well as the Developmental Surcharge are
revised as per the Notifications/Circulars issued by the Ministry
of Railways and as such, they would come within the definition
of ‘Change in Law’.
Civil Appeal Nos. 12055-12056 of 2018
35. These appeals, filed by Jaipur Vidyut Vitran Nigam Ltd.,
Ajmer Vidyut Vitaran Nigam Ltd. and Jodhpur Vidhyut Vitaran
Nigam Ltd. (hereafter referred to as “Rajasthan Discoms”),
th
challenge the common judgment and order dated 14 August
2018, passed by the learned APTEL in Appeal No. 119 of 2016 &
19
| I.A. Nos. 668 and 674 of 2016 and in Appeal No.277 of 2016 & | |
|---|---|
| I.A. No.572 of 2016. | |
| 36. Appeal No. 119 of 2016 & I.A. Nos. 668 & 674 of 2016 were | |
| filed by M/s Adani Power Rajasthan Ltd. (“APRL” for short), being | |
| aggrieved by the judgment and order dated 15th March 2016, | |
| passed by the Rajasthan Electricity Regulatory Commission | |
| (hereinafter referred to as “State Commission”) thereby | |
| disallowing some of its claims on account of ‘Change in Law’, | |
| whereas Appeal No. 277 of 2016 and I.A. No.572 of 2016 were | |
| filed by the Rajasthan Discoms, being aggrieved by the order of | |
| the State Commission of the same date vide which some of the | |
| ‘Change in Law’ claims were allowed by the CERC. | |
| 37. The ‘Change in Law’ claims which were allowed by the State | |
| Commission are as under: | |
| i. Change in Rate of Royalty Payable on Domestic Coal; | |
| ii. Levy of Service Tax on Transportation of Goods by Indian | |
| Railways (IR); and | |
| iii. Increase in Fee for ‘Consent to Operate’. |
20
| 38. The ‘Change in Law’ claims which were not allowed by the | |||
|---|---|---|---|
| State Commission are thus: | |||
| 1. | Change in Pricing Mechanism of Coal from<br>Useful Heat Value (UHV) Basis to Gross<br>Calorific Value Basis (GCV) | ||
| 2. | Increase in Sizing Charges for coal charged by<br>Coal India Ltd. (CIL) | ||
| 3. | Increase in Surface Transportation Charges | ||
| 4. | Increase in Busy Season Surcharge on<br>Transportation of Coal by Indian Railways | ||
| 5. | Increase in Development Surcharge levied on<br>Transportation of Coal by Railways | ||
| 6. | Levy of Fuel Adjustment Component | ||
| 7. | Levy of Port Congestion Surcharge | ||
| 8. | Levy of Forest Tax | ||
| 9. | Change in Classification of Coal for Train<br>Load Movement |
the appeal of the Rajasthan Discoms and partly allowed the
appeal of APRL allowing its claims on the ground of ‘Busy Season
21
Surcharge’, ‘Development Surcharge’, ‘Port Congestion
Surcharge, ‘Forest Tax’ and ‘Carrying Cost’. Being aggrieved
thereby, the Rajasthan Discoms have approached this Court.
40. We have heard Mr. V. Giri, learned Senior Counsel
appearing on behalf of the Rajasthan Discoms and Dr. A.M.
Singhvi, learned Senior Counsel appearing on behalf of the APRL.
41. Mr. V. Giri submits that clause 10 in the PPA is referable
only to taxes under Article 268 of the Constitution of India. He
submits that the learned APTEL has, therefore, erred in allowing
‘Change in Law’ benefits on the issues related to Busy Season
Surcharge, Development Surcharge, Port Congestion Charges,
Forest Tax and Carrying Cost which are not taxes referable to
Article 268 of the Constitution.
42. Dr. Singhvi made arguments on similar lines as have been
made in the other appeals.
Civil Appeal Nos. 2935-2936 of 2020
43. These appeals have been filed by the Rajasthan Discoms
and Rajasthan Urja Vikas Nigam Ltd. challenging the common
22
| judgment and order dated 29th January 2020, passed by the | ||
|---|---|---|
| learned APTEL in Appeal no.284 of 2017 and Appeal No. 09 of | ||
| 2018. | ||
| 44. Appeal No. 284 of 2017 was filed by APRL challenging the | ||
| order dated 8th June 2017 passed by the State Commission, | ||
| being aggrieved by the disallowance of its claim on some | ||
| components on the ground of ‘Change in Law’ and carrying cost, | ||
| whereas Appeal No.9 of 2018 was filed by Rajasthan Discoms | ||
| being aggrieved by the claims which were allowed by the State | ||
| Commission. | ||
| 45. The list of the components which were allowed and which | ||
| were not allowed on the ground of ‘Change in Law’ is thus: | ||
| “Sr.<br>No. | Change in Law's items | Decision of the<br>Commission |
| A | Levies on Royalty<br>(i) National Mineral Exploration<br>Trust effective from 14.08.2015<br>(ii) District Mineral Foundation<br>effective from 12.01.2015 | Allowed |
| B | Levy of Swachh Bharat Cess (SBC)<br>along with Service Tax for rail | Allowed |
23
| transportation effective from<br>15.11.2015 | ||
|---|---|---|
| C | Levy of Swachh Bharat Cess @0.5%<br>along with Service Tax - Operation<br>Period effective from 15.11.2015 | Not Allowed |
| D | Levy of Krishi Kalyan Cess (KKC)<br>along with Service Tax and Swachh<br>Bharat Cess for rail transportation<br>from lst June 2016 | Allowed |
| E | Levy of Krishi Kalyan Cess @0.5%<br>along with Service Tax and Swachh<br>Bharat Cess - Operation Period<br>from 1st June 2016. | Not Allowed |
| F | Amendment to Environmental<br>(Protection) Rules 1986 | Not Allowed |
| G | Levy of Coal Terminal Surcharge<br>(CTS) effective from 22.08.2016 | Not Allowed |
| H | Utilization of Fly Ash generated<br>from coal and lignite based thermal<br>power projects | Not Allowed |
| I | CG Paryavaran Upkar | Not Allowed |
| J | CG Vikas Upkar | Not Allowed |
| K | Service Tax on transportation of<br>goods by a vessel from a place<br>outside India up to the custom<br>station of clearance in India | Not Allowed |
24
| L | Carrying Cost | Not Allowed” |
| 46. As stated above, being aggrieved by that part of the order | |
| which disallowed its claim, APRL preferred the aforesaid Appeal | |
| before the learned APTEL, whereas the Rajasthan Discoms, being | |
| aggrieved by that part of the order which allowed claims on | |
| certain components, also filed an Appeal before the learned | |
| APTEL. | |
| 47. The learned APTEL, while dismissing the appeal of the | |
| Rajasthan Discoms, partly allowed the appeal of the APRL by | |
| allowing compensation on certain other components on the | |
| ground of ‘Change in Law’. | |
| 48. The components on which ‘Change in Law’ benefits were | |
| granted by the learned APTEL are thus: | |
| (i) Coal Terminal Surcharge; | |
| (ii) Chhattisgarh Paryavaran Upkar; | |
| (iii) Chhattisgarh Vikas Upkar; |
25
| (iv) Change in Swacch Bharat Cess at the rare of 0.5% on | |
|---|---|
| Service Tax for Operation Period; | |
| (v) Change in Krishi Kalyan Cess at the rate 5% on Service | |
| Tax for Operation Period; | |
| 49. In addition to grant of relief on the ground of ‘Change in | |
| Law’, the learned APTEL also granted ‘Carrying Cost’. | |
| 50. Arguments similar to the ones advanced in Civil Appeal No. | |
| 12055-12056 of 2018 were advanced by Mr. V. Giri, learned | |
| Senior Counsel appearing on behalf of the Rajasthan Discoms, | |
| as well as by the learned counsel for the respondents. | |
| Civil Appeal No. 3123 of 2019 and Civil Appeal No.5372 of | |
| 2019 | |
| 51. These are cross appeals. Civil Appeal No.3123 of 2019 has | |
| been filed by Bihar State Power (Holding) Company Ltd. | |
| (hereinafter referred to as “Bihar Discoms”) and Civil Appeal | |
| No.5372 of 2019 has been filed by GMR Kamalanga Energy | |
| Limited and GMR Energy Limited (hereinafter referred to as | |
| “GKEL”), challenging the judgment and order dated 21st |
26
| December 2018 passed by the learned APTEL in Appeal No.193 | |
|---|---|
| of 2017 & I.A. No. 449 of 2018. | |
| 52. Appeal No.193 of 2017 & I.A. No.449 of 2018 were filed by | |
| GKEL challenging the order of the CERC dated 7th April 2017, | |
| aggrieved by the denial of its claims on certain components on | |
| the ground of ‘Change in Law’. The Bihar Discoms have | |
| challenged that part of the order of the learned APTEL which | |
| allowed claims of GKEL on the ground of ‘Change in Law’. | |
| 53. By the impugned order, the learned APTEL granted claims | |
| on the ground of: | |
| (i) Change in NCDP (cancellation of Captive Block vis-à-vis | |
| tapering linkage), | |
| (ii) busy season surcharge and developmental surcharge, | |
| (iii) carrying cost; and | |
| (iv) add on premium price. | |
| 54. We have heard Mr. Vishrov Mukerjee, learned counsel | |
| appearing on behalf of the GKEL/Generator and Ms. Anushree |
27
| Bardhan, learned Counsel appearing on behalf of the Bihar | |
|---|---|
| Discoms. | |
| 55. Mr. Vishrov Mukerjee submits that the learned APTEL as | |
| well as the CERC have grossly erred in rejecting the claim for | |
| compensation on the ground of: | |
| (i) change in source of coal from Mahanadi Coalfields Ltd. | |
| (“MCL” for short) to Eastern Coalfields Ltd. (“ECL” for | |
| short) vide Notification dated 26th February 2014 issued | |
| by the CIL; | |
| (ii) change in mode of transportation from rail to road vide | |
| Notification dated 29th September 2014 issued by MCL; | |
| (iii) increase in levy of Minimum Alternate Tax (“MAT” for | |
| short); and | |
| (iv) interest on working capital. | |
| 56. Learned counsel submitted that change in source of coal | |
| from MCL to ECL was on account of the notification issued by | |
| the CIL, which is an instrumentality of the State. Similarly, he |
28
submitted that the change in mode of transportation from rail to
road was on account of the notification issued by the MCL.
Learned counsel submits that, since, on account of these
notifications, the cost of transportation of coal increased,
applying the restitutionary principle, the CERC as well as the
learned APTEL ought to have granted claims on the basis of
‘Change in Law’. He further submits that increase in levy of MAT
has also been increased by the Union of India and, as such, the
same would also amount to ‘Change in Law’. It is further
submitted that interest on working capital was also increased on
account of the orders of the instrumentalities of the State and,
as such, compensation also ought to have been granted for the
same.
57. Learned counsel for the Bihar Discoms submits that the
CERC as well as the learned APTEL have grossly erred in allowing
claims on certain components on the ground of ‘Change in Law’.
29
| Civil Appeal No. 6641 of 2019 | |
|---|---|
| 58. This appeal filed by GKEL arises out of the judgment and | |
| order dated 27th May 2019, passed by the learned APTEL in | |
| Appeal No.195 of 2016, thereby partly allowing the appeal. | |
| 59. GKEL filed Petition No.79/MP/2013 before the CERC | |
| claiming compensation on various component on the ground of | |
| ‘Change in Law’ events. | |
| 60. The CERC, vide order dated 3rd February 2016, disallowed | |
| compensation for the following components: | |
| (a) Change from UHV to GCV based pricing of coal | |
| pursuant to notification issued by the Government | |
| of India; | |
| (b) Increase/revision in the railway freight charges | |
| pursuant to notifications issued by Ministry of | |
| Railways and Ministry of Finance; | |
| (c) Increase in the rate of Minimum Alternate Tax | |
| (“MAT”) rates; |
30
| (d) Increase in Value Added Tax in the State of Odisha; | ||
|---|---|---|
| (e) Increase in water charges pursuant to notifications | ||
| issued by the Government of Odisha; | ||
| (f) Incremental increase in interest on working capital | ||
| on account of increase in costs during the operating | ||
| period. | ||
| 61. Being aggrieved thereby, Appeal No.195 of 2016. was | ||
| preferred by GKEL. As stated above, the learned APTEL partly | ||
| allowed the appeal and held that GKEL was entitled to | ||
| compensation on following grounds. | ||
| (i) Increase/revision in the railway freight charges in terms | ||
| of notifications issued by the Ministry of Railways and | ||
| Ministry of Finance on account of imposition of | ||
| development surcharge, busy season surcharge and | ||
| service tax; | ||
| (ii) VAT rate enhancement from 4% to 5% from 30.03.2012 | ||
| onwards; |
31
| (iii) Carrying cost/interest on compensation on the above | |
|---|---|
| items after ascertainment of the same by computation, | |
| which shall be assessed from the date of respective | |
| notification/circular/order from the concerned | |
| Ministry/Department/Governmental instrumentality till | |
| payment is made. | |
| 62. Appellant-GKEL, being unsatisfied with the same, has | |
| approached this Court praying for a direction that it is also | |
| entitled to compensation on various other components, viz., | |
| (i) Increase in Water Charges; | |
| (ii) Shift from UHV to GCV methodology of pricing of coal; | |
| (iii) Increase in rate of MAT; and | |
| (iv) Interest on working capital. | |
| 63. Arguments similar to the ones advanced in Civil Appeal No. | |
| 3123 of 2019 and Civil Appeal No.5372 of 2019 were advanced | |
| by the learned counsel for the parties. | |
32
| Civil Appeal Nos. 5583-5584 of 2021 | |
|---|---|
| 64. These appeals, filed by Bihar Discoms, arise out of the | |
| judgment and order dated 6th August 2021, passed by the | |
| learned APTEL in Appeal No. 423 of 2019 and in Appeal No.173 | |
| of 2021. | |
| 65. In the said case, the learned APTEL, vide order dated 21st | |
| December 2018, had allowed the following claims as ‘Change in | |
| Law’ and remanded the matter back to the CERC to determine | |
| compensation due to GKEL: | |
| (a) Shortfall in linkage coal and deviation in NCDP; | |
| (b) Cancellation of captive coal block; | |
| (c) Imposition of Busy Season Surcharge and Development | |
| Surcharge; | |
| (d) Levy of Add-On Premium over and above the notified | |
| price of coal; and | |
| (e) Carrying Cost. |
33
th
66. Upon remand, the CERC passed order dated 16 September
2019, thereby granting compensation on certain components on
the ground of ‘Change in Law’ including carrying cost.
67. Contending that the order passed by the CERC did not give
effect to the ‘Change in Law’ components as directed by the
learned APTEL, an appeal being Appeal No. 423 of 2019 came to
be preferred by GKEL before the learned APTEL.
68. Bihar Discoms had also filed an appeal being Appeal No.173
of 2021, before the learned APTEL, being aggrieved by the
benefits which were granted by the CERC.
69. By the impugned order, the learned APTEL held that the
GKEL was entitled to recover expenditure involved in
procurement of alternate coal due to shortfall in domestic coal
supply corresponding to scheduled generation pertaining to the
obligations under the Bihar PPA. The learned APTEL held that
this was required to be done in order to restore the appellant-
GKEL to the same economic position as before as if no ‘Change
in Law’ event had occurred.
34
70. We have heard Ms. Anushree Bardhan, learned counsel
appearing on behalf of the appellant-Bihar Discoms and Mr.
Maninder Singh, learned Senior Counsel appearing on behalf of
GKEL.
71. Ms. Anushree Bardhan submits that the learned APTEL
ought to have granted benefit of ‘Change in Law’ restricting it to
shortfall for only 894.5 MW, which was the amount specified in
the PPA, and not for the entire 1050 MW, which is the installed
capacity. She further submits that the learned APTEL had also
erred in granting add on premium on account of extension of
tapering linkage by three years.
72. Shri Maninder Singh, learned Senior Counsel submits that
insofar as the first issue with regard to shortfall of coal supply is
concerned, the same is squarely covered by the judgments of this
Court in the cases of Energy Watchdog v. Central Electricity
2
Regulatory Commission and others , Jaipur Vidyut Vitaran
2
(2017) 14 SCC 80
35
Nigam Ltd. and others v. Adani Power Rajasthan Limited
3
and another (hereinafter referred to as “ Adani Rajasthan
case ”) and MSEDCL v. APML & Ors. (supra).
73. He further submits that the delay in operationalization of
the captive mines was not on account of any reason attributable
to GKEL . He submits that, since the allotment of coal blocks was
cancelled on account of the judgment of this Court in the case of
4
Manohar Lal Sharma v. The Principal Secretary & Ors. ,
GKEL was also entitled for the benefit for the said period.
74. Insofar as Busy Season Surcharge is concerned, he submits
that there is a concurrent finding of fact. He submits that, in any
case, the said charges are issued by the Railway Board by issuing
Notifications/Circulars. He submits that since the Railway is an
instrumentality of the State, both the CERC and the learned
APTEL have concurrently held that the Generator would be
entitled to compensation on the ground of ‘Change in Law’.
3
2020 SCC Online SC 697
4
(2014) 9 SCC 516 and 2014 (9) SCC 614
36
Civil Appeal No. 39 of 2021
75. This appeal filed by the DNH-DISCOM arises out of the
th
judgment and order dated 13 October 2020, passed by the
learned APTEL in Appeal No.283 of 2019 & I.A. Nos. 2188 & 1229
of 2019, thereby dismissing the said appeal arising out of the
th
judgment and order passed by the CERC dated 16 May 2019.
76. The DNH-DISCOM had initiated a competitive bidding
process through issuance of a Request for Proposal (“RFP” for
short) in March 2012 for procurement of power on Long Term
Basis under Case-1 bidding procedure. As per the RFP, the cut-
st
off date was 1 June 2012.
77. The respondent-GWEL emerged as the successful bidder for
supplying Aggregated Contracted Capacity of 200 MW at a
levelized tariff of Rs.4.618 per Unit.
78. Accordingly, Letter of Intent (LoI) was issued by DNH-
th
DISCOM on 14 August 2012. An application/petition being
Petition No.87/2012 came to be filed before the Joint Electricity
Regulatory Commission (hereinafter referred to as “Joint
37
Commission”) for approval of the PPA and adoption of tariff.
GWEL was also joined as a co-petitioner in the said Petition. The
th
Joint Commission, vide order dated 19 February 2013,
approved the PPA. Accordingly, the PPA came to be executed on
st
21 March 2013.
79. GWEL filed Petition No. 8/MP/2014 before the CERC
seeking compensation on certain components on the ground of
‘Change in Law’. The same was decided by the CERC vide order
st
dated 1 February 2017. Aggrieved thereby, both the appellant-
DNH-DISCOM and the respondent-GWEL filed appeals before the
learned APTEL. In appeal, the learned APTEL remanded the
th
matter to the CERC vide order dated 14 August 2018 for
considering certain issues. Being aggrieved by the order dated
th
14 August 2018, the appellant-DNH-DISCOM filed an appeal,
being Civil Appeal No.11910 of 2018, before this Court. The said
appeal is also being decided in the present batch of appeals, by
this common judgment.
38
th
80. On remand, the CERC passed an order dated 16 May 2019
and allowed the claim of GWEL/Generator on the ground of
‘Change in Law’ occurring on account of the enforcement of the
‘Scheme for Harnessing and Allocating Koyala (Coal)
Transparently in India’ (“SHAKTI Policy” for short). Being
aggrieved thereby, DNH-DISCOM had filed an appeal before the
learned APTEL. As stated herein above, the same was dismissed
by the learned APTEL vide the impugned judgment.
81. We have heard Mr. C.A. Sundaram, learned Senior Counsel
appearing on behalf of the DNH-DISCOM and Mr. Niranjan
Reddy, learned Senior Counsel appearing on behalf of the
respondent-GWEL.
82. Mr. C.A. Sundaram submits that, from the presentation
which was given by the GWEL, it was apparent that it was given
on the basis that coal supply would be restricted only to 65%. He
submits that, as such, the grant of benefit on account of ‘Change
in Law’ on the ground that there was 100% assurance by CIL is
39
not permissible. He, therefore, submits that the judgment and
order of the learned APTEL deserves to be set aside to that extent.
83. Mr. Niranjan Reddy, on the contrary, submits that the bid
th
of GWEL was submitted on 8 June 2012, on which date NCDP
2007 was in force. He submits that, subsequently, the NCDP
st
2007 was modified on 31 July 2013 and thereafter SHAKTI
nd
Policy has come into effect on 22 May 2017 and, as such,
judgment and order of the learned APTEL warrants no
interference.
Civil Appeal No. 5005 of 2022 and Civil Appeal No. 4089 of
2022
84. These appeals challenge the common judgment and order
nd
dated 22 March 2022 passed by the learned APTEL in Appeal
No. 118 of 2021 and 40 of 2022, filed by Rattan India Power
Limited (hereinafter referred to as “Rattan India”) and Adani
Power Maharashtra Limited (for short, “APML”) respectively,
st rd
thereby challenging the orders dated 1 January 2019 and 3
August 2018, passed by Maharashtra Electricity Regulatory
40
Commission (hereinafter referred to as ‘MERC’) in Case No. 227
of 2018 and Case No. 124 of 2018 respectively.
85. The facts in brief giving rise to the present appeals are as
under:
nd
Rattan India has entered into PPAs dated 22 April 2010
th
and 5 June 2010 with MSEDCL for supply of 1200 MW
aggregate power at levelized tariff of Rs.3.260 KWH for a period
of 25 years. It filed a petition before MERC, being Case No. 227
of 2018, claiming compensation on the ground of ‘Change in Law’
th
occurring on account of the circular dated 19 December 2017
issued by CIL, vide which it levied the Evacuation Facility
Charges (for short, “EFC”). The same was rejected by MERC, vide
st
order dated 1 January 2019. A similar petition being Case No.
124 of 2018 was also filed by APML, raising a similar claim before
MERC, which was also rejected by MERC, vide its earlier order
rd
dated 3 August 2018.
86. Being aggrieved thereby, Rattan India had filed an Appeal
No. 118 of 2021 and APML had preferred an Appeal No. 40 of
41
2022. By the impugned order, the learned APTEL had held EFC
th
imposed by CIL vide Circular dated 19 December 2017 to be a
‘Change in Law’ event and, accordingly, held the Generators to
be entitled to compensation on the said ground. Being aggrieved
thereby, the MSEDCL has preferred these appeals.
87. We have heard Shri Balbir Singh, learned Additional
Solicitor General (for short, “ASG”) and Shri G. Saikumar,
learned counsel appearing on behalf of the appellant and Shri
Sajan Poovayya, learned Senior Counsel for the respondents in
Civil Appeal No. 5005 of 2022 and Shri Vishrov Mukherjee,
learned counsel appearing on behalf of the respondents in Civil
Appeal No. 4089 of 2022.
88. Shri Balbir Singh, relying on Clause 9.1 of the Coal Supply
th
Agreement (for short, “CSA”) dated 28 December 2012 entered
into between Southeastern Coalfields Limited and APML,
submitted that CSA defines as to what shall be the base price of
coal. He submitted that Clause 9.2 of the said CSA specifically
provides for other charges which are permissible. Relying on
42
Clause 9.4 of the CSA, he submitted that in all cases, the entire
freight charges, irrespective of the mode of transportation of coal
supplied, shall be borne by the purchaser. The learned ASG
submitted that the EFC does not partake the character of a
statutory levy. However, he submitted that, in any case, it does
not have the force of law. He, therefore, submitted that APTEL
th
has grossly erred in holding the circular of CIL dated 19
December 2017 to qualify as ‘Change in Law’.
89. Shri Singh further submitted that the direction to pay the
carrying cost at the rate provided for Late Payment Surcharge (for
short, “LPS”) is also not permissible in law. He submitted that
this Court, in Adani Rajasthan case (supra), has directed the
carrying cost to be paid at the rate of 9% and as such, in the
present case, it ought to have been directed to be paid at the
same rate.
90. Shri Singh also relies on the judgment of this Court in the
case of Ashoka Smokeless Coal India (P) Limited and Others
43
5
v. Union of India and Others in support of the proposition
that CIL is free to fix the price of coal and that the Union of India
has no control over it.
91. Shri Poovayya, on the contrary, submitted that the levy is
mandatory in nature. Unless the said levies are paid, the coal
would not be supplied. He further submitted that since the CIL
is an instrumentality of the Government, the order issued by it
would amount to a law within the definition of “Law” as defined
in the PPA. He further submitted that insofar as the carrying
cost is concerned, there is a specific provision in the PPA in
Article 11.8.3, which is binding on the parties. He submitted that
on account of non-payment of the dues of the generating
companies by DISCOMS, the generating companies are required
to borrow the funds at the market rate and as such, applying the
restitutionary principle, it is entitled to carrying cost as provided
under the agreement.
5
(2007) 2 SCC 640
44
| III. ADDITIONAL ISSUES | |
|---|---|
| 92. After hearing the learned counsel for the parties at length, | |
| we find that, apart from the three issues that were already | |
| decided by this Court in the case of MSEDCL v. APML & Ors. | |
| (supra), the issues as to whether the following components could | |
| be considered as ‘Change in Law’ events fall for consideration | |
| herein: | |
| (i) Busy Season Surcharge & Development Surcharge and | |
| Port Congestion Surcharge; | |
| (ii) MoEF Notification on coal quality; | |
| (iii) Shortfall in linkage coal due to Change in NCDP; | |
| (iv) Forest Tax; | |
| (v) Add on Premium price. | |
| (vi) Evacuation Facility Charges (EFC). | |
| Apart from that, another question that requires | |
| consideration is, as to whether various taxes/charges imposed |
45
by various State Governments would also fall under ‘Change in
Law’ events or not.
The other question that requires considerations is, as to
whether at what rate the Generators would be entitled to
‘carrying cost’.
IV. CONSIDERATION
93. For appreciating the rival submissions, we will have to
construe the term “Law”, which has been defined in the PPAs,
which reads thus:
““Law” means, in relation to this Agreement,
all laws including Electricity Laws in force in
India and any statute, ordinance, regulation,
Notification or code, rule, or any
interpretation of any of them by an Indian
Governmental Instrumentality and having
force of law and shall further include all
applicable rules, regulations, orders,
Notifications by an Indian Governmental
Instrumentality pursuant to or under any of
them and shall include all rules, regulations,
decisions and orders of the CERC and the
MERC.”
94. Perusal of the definition of the term “Law” itself would
clearly show that the term “Law” would mean all laws including
46
| Electricity Laws in force in India and any statute, ordinance, | ||
|---|---|---|
| regulation, Notification or code, rule, or any interpretation of any | ||
| of them by an Indian Governmental Instrumentality and having | ||
| force of law. It would further reveal that the term “Law” shall also | ||
| include all applicable rules, regulations, orders, Notifications by | ||
| an Indian Governmental Instrumentality and shall also include | ||
| all rules, regulations, decisions and orders of the CERC and the | ||
| MERC. | ||
| 95. In any case, the issue as to what would amount to “Law” is | ||
| no more res integra. This Court, in the case of Energy Watchdog | ||
| (supra), has observed thus: | ||
| “57. Both the letter dated 31-7-2013 and the | ||
| revised Tariff Policy are statutory documents | ||
| being issued under Section 3 of the Act and | ||
| have the force of law. This being so, it is clear | ||
| that so far as the procurement of Indian coal | ||
| is concerned, to the extent that the supply | ||
| from Coal India and other Indian sources is | ||
| cut down, the PPA read with these | ||
| documents provides in Clause 13.2 that | ||
| while determining the consequences of | ||
| change in law, parties shall have due regard | ||
| to the principle that the purpose of | ||
| compensating the party affected by such |
47
| change in law is to restore, through monthly | |
|---|---|
| tariff payments, the affected party to the | |
| economic position as if such change in law | |
| has not occurred. Further, for the operation | |
| period of the PPA, compensation for any | |
| increase/decrease in cost to the seller shall | |
| be determined and be effective from such | |
| date as decided by the Central Electricity | |
| Regulation Commission. This being the case, | |
| we are of the view that though change in | |
| Indonesian law would not qualify as a change | |
| in law under the guidelines read with the | |
| PPA, change in Indian law certainly would.” |
Watchdog (supra) has been approved by a Bench of three
learned Judges of this Court in Adani Rajasthan case (supra)
and also followed by this Court when the two linked matters out
of this batch of appeals were decided by this Court in the case of
MSEDCL v. APML & Ors. (supra). It cannot be denied that CIL
is an instrumentality of the Government of India and its orders,
insofar as price of fuel are concerned, are binding on all its
subsidiaries.
97. It will further be relevant to refer to Clause 9.0 of the CSA,
which reads thus:
48
| “9.0 PRICE OF COAL:<br>The “As Delivered Price of Coal” for the Coal<br>supplies pursuant to this Agreement shall be<br>the sum of Base Price, Other Charges and<br>Statutory Charges, as applicable at the time<br>of delivery of Coal.” | “9.0 PRICE OF COAL: | ||
|---|---|---|---|
| The “As Delivered Price of Coal” for the Coal | |||
| supplies pursuant to this Agreement shall be | |||
| the sum of Base Price, Other Charges and | |||
| Statutory Charges, as applicable at the time | |||
| of delivery of Coal.” | |||
| It is thus clear that price of coal includes the sum of base price, | |||
| other charges and statutory charges as applicable at the time of | |||
| delivery of coal. | |||
| 98. As discussed herein above, the term ‘Law’ would also | |||
| include all applicable rules, regulations, orders, Notifications | |||
| issued by an Indian Governmental Instrumentality. | |||
| 99. It would thus be clear that all such additional charges | |||
| which are payable on account of orders, directions, Notifications, | |||
| Regulations, etc., issued by the instrumentalities of the State, | |||
| after the cut-off date, will have to be considered to be ‘Change in | |||
| Law’ events. The Generators would be entitled to compensation | |||
| on the restitutionary principle on such changes occurring after | |||
| the cut-off date. |
49
100. Having held thus, we will now consider some of the
components which are common in most of these appeals.
Busy Season Surcharge, Development Surcharge And Port
Congestion Surcharge
101. Insofar as increase in Busy Season Surcharge, Development
Surcharge on transportation of coal, and Port Congestion
Surcharge by the Indian Railways are concerned, the learned
APTEL had found that the Indian Railways is an instrumentality
of the State. It has been found that the Busy Season Surcharge,
Development Surcharge and Port Congestion Surcharge were
increased from time to time vide Circulars/Notifications issued
by the Ministry of Railways, through the Railway Board.
102. A Constitution Bench of this Court, in the case of Railway
Board, Government of India v. M/s Observer Publications (P)
6
Ltd. , has held the Railway Board to be a State within the
meaning of Article 12 of the Constitution of India.
6
(1972) 2 SCC 266
50
103. As such, no error could be found in the finding of the
learned APTEL that the revision of charges to be paid on Busy
Season Surcharge, Development Surcharge and Port Congestion
Charges from time to time by the ‘Railway Board’ would come
within the ambit of ‘Change in Law’.
MoEF Notification on Coal Quality
104. Insofar as MoEF notification on coal quality is concerned,
nd
the MoEF, vide Notification dated 2 January 2014, i.e.
st
subsequent to the particular cut-off date, i.e. 1 June 2012, has
mandated power projects to use beneficiated coal with ash
content lower than 34%. The draft notification of MoEF dated
th nd
11 July 2012 culminated into the final Notification dated 2
January 2014. By no stretch of imagination, can it be said that
MoEF is not an instrumentality of the State.
105. By the said Notification, MoEF has mandated power
projects to use beneficiated coal with ash content lower than
34%. Admittedly, prior to the cut-off date, the same was not a
th
requirement. It is thus clear that the said Notifications dated 11
51
nd
July 2012 and 2 January 2014 would amount to “Change in
Law’. As such, no fault can be found with the finding of the
learned APTEL that the same would amount to ‘Change in Law’.
Shortfall in Linkage Coal due to Change in NCDP
106. Insofar as shortfall in linkage coal due to changes in the
NCDP issued by the Ministry of Coal (“MoC” for short) is
concerned, the issue is no more res integra . This Court in the
case of Energy Watchdog (supra) so also in Adani Rajasthan
case (supra) and recently in MSEDCL v. APML & Ors. (Supra)
has held that the change in NCDP would amount to ‘Change in
Law’.
Forest Tax
107. Insofar as Forest Tax is concerned, perusal of the material
placed on record would reveal that, as on the cut-off date, there
was no Forest Tax applicable on coal mined and transported from
South Eastern Coalfields Limited (“SECL” for short) mines
located in Forest area. For the first time, vide Notification of the
Chhattisgarh State Government, Department of Forest, under
52
the provisions of Chhattisgarh Transit (Forest Produce Rule)
2001, a fee at the rate of Rs.7 per ton was levied. Undisputedly,
the said Notification is issued by the Forest Department of the
Government of Chhattisgarh, which is an instrumentality of the
State. As such, no error can be found with the finding of the
learned APTEL in that regard.
Add on Premium Price
108. Insofar as ‘Add on premium price’ is concerned,
undisputedly, ‘add on premium’ was required to be paid on
account of cancellation of captive coal blocks and inordinate
delay on account of Go-No-Go policy. As such, it cannot be said
that the reasoning adopted by the learned APTEL is perverse and
arbitrary.
Evacuation Facility Charges (EFC)
109. Undisputedly, EFC was imposed by CIL vide its Circular
th
dated 19 December 2017.
110. As already discussed herein above, CIL is an
instrumentality of the State. It is thus clear that, on the cut-off
53
date, there was no requirement of EFC, which has been brought
th
into effect only on 19 December 2017. As such, the circular of
th
CIL dated 19 December 2017 would also amount to ‘Change in
Law’.
111. As discussed herein above, it is also not in dispute that EFC
has been paid by the generators while paying the base price,
other charges and statutory charges at the time of delivery of
coal. As such, no interference would be warranted with the said
finding.
112. That leaves us with the issue with regard to carrying cost.
Carrying Cost
113. This is the issue on which there is a serious contest between
the DISCOMS and the Generators.
114. On one hand, it is the submission of the DISCOMS that
since there is no description of the same in the PPAs, the rate for
granting carrying cost should be a reasonable rate. On the
contrary, it is the submission of the Generators that there is a
specific provision in the PPAs, which provides that the carrying
54
| cost has to be paid at the rate as per the rate specified for late | ||
|---|---|---|
| payment surcharge. It is submitted that this is provided in the | ||
| PPA so as to give effect to the restitutionary principle. | ||
| 115. For considering the rival submissions, it will be apposite to | ||
| refer to the following Articles, which are almost common in most | ||
| of the PPAs. | ||
| “11. Billing and payment.— | ||
| *** | ||
| 11.3. Payment of monthly bills.— | ||
| *** | ||
| 11.3.4. In the event of delay in payment of a | ||
| monthly bill by any procurer beyond its due | ||
| date, a late payment surcharge shall be | ||
| payable by the procurer to the seller at the | ||
| rate of two (2) per cent in excess of the | ||
| applicable SBAR per annum, on the amount | ||
| of outstanding payment, calculated on a day | ||
| to day basis (and compounded with monthly | ||
| rest), for each day of the delay. | ||
| *** | ||
| 11.8. Payment of supplementary bill.— | ||
| 11.8.1. Either party may raise a bill on the | ||
| other party (“supplementary bill”) for | ||
| payment on account of: | ||
| (i) Adjustments required by the Regional | ||
| Energy Account (if applicable); | ||
| (ii) Tariff payment for change in parameters, | ||
| pursuant to provisions in Schedule 5; or |
55
| (iii) Change in law as provided in Article 13 | ||
|---|---|---|
| and such Bill shall be paid by the other | ||
| party. | ||
| *** | ||
| 11.8.3. In the event of delay in payment of a | ||
| supplementary bill by either party beyond | ||
| one month from the date of billing, a late | ||
| payment surcharge shall be payable at same | ||
| terms applicable to the monthly bill in Article | ||
| 11.3.4.” | ||
| 116. A perusal of Article 11.3.4 of the PPA would reveal that in | ||
| the event of delay in payment of a monthly bill by any procurer | ||
| beyond its due date, a late payment surcharge shall be payable | ||
| by the procurer to the seller at the rate of 2% in excess of the | ||
| applicable State Bank Advance Rate (“SBAR” for short) per | ||
| annum, on the amount of outstanding payment, calculated on a | ||
| day to day basis (and compounded with monthly rest), for each | ||
| day of the delay. Article 11.8 of the PPA deals with Payment of | ||
| Supplementary Bill. It enables either party to raise a | ||
| supplementary bill on the other party for payment on account of | ||
| certain events. Clause (iii) of Article 11.8.1 of the PPA deals with | ||
| ‘Change in Law’ as provided in Article 13. It requires the bill to |
56
be paid by the other party. Article 11.8.3 of the PPA also provides
that in the event of delay in payment of a supplementary bill by
either party beyond one month from the date of billing, a late
payment surcharge shall be payable at same terms applicable to
the monthly bill in Article 11.3.4.
117. This Court in the case of Uttar Haryana Bijli Vitran
Nigam Limited (UNHVNL) and another v. Adani Power
7
Limited and others , after considering the provisions of Article
11, which deals with ‘Billing’ and Article 13, which deals with
‘Change in Law’, has observed thus:
“ 9. It will be seen that Article 13.4.1
makes it clear that adjustment in
monthly tariff payment on account of
change in law shall be effected from the
date of the change in law [ see sub-clause
( i ) of clause 4.1], in case the change in law
happens to be by way of adoption,
promulgation, amendment , re-enactment
or repeal of the law or change in law. As
opposed to this, if the change in law is on
account of a change in interpretation of
law by a judgment of a Court or Tribunal
7
(2019) 5 SCC 325
57
or governmental instrumentality, the
case would fall under sub-clause ( ii ) of
clause 4.1, in which case, the monthly
tariff payment shall be effected from the
date of the said order/judgment of the
competent authority/Tribunal or the
governmental instrumentality. What is
important to notice is that Article 13.4.1
is subject to Article 13.2 of the PPAs.
10. Article 13.2 is an in-built
restitutionary principle which
compensates the party affected by such
change in law and which must restore,
through monthly tariff payments, the
affected party to the same economic
position as if such change in law has not
occurred. This would mean that by this
clause a fiction is created, and the party
has to be put in the same economic
position as if such change in law has not
occurred i.e. the party must be given the
benefit of restitution as understood in
civil law. Article 13.2, however, goes on to
divide such restitution into two separate
periods. The first period is the
“construction period” in which
increase/decrease of capital cost of the
project in the tariff is to be governed by a
certain formula. However, the seller has
to provide to the procurer documentary
proof of such increase/decrease in capital
58
cost for establishing the impact of such
change in law and in the case of dispute
as to the same, a dispute resolution
mechanism as per Article 17 of the PPA is
to be resorted to. It is also made clear that
compensation is only payable to either
party only with effect from the date on
which the total increase/decrease
exceeds the amount stated therein.
11. So far as the “operation period” is
concerned, compensation for any
increase/decrease in revenues or costs to
the seller is to be determined and effected
from such date as is decided by the
appropriate Commission. Here again, this
compensation is only payable for
increase/decrease in revenue or cost to
the seller if it is in excess of an amount
equivalent to 1% of the Letter of Credit in
aggregate for a contract year. What is
clear, therefore, from a reading of Article
13.2, is that restitutionary principles
apply in case a certain threshold limit is
crossed in both sub-clauses ( a ) and ( b ).
There is no dispute that the present case
is covered by sub-clause ( b ) and that the
aforesaid threshold has been crossed.
The mechanism for claiming a change in
law is then set out by Article 13.3 of the
PPA.”
59
118. It could thus be seen that this Court has held that insofar
as the “operation period” is concerned, compensation for any
increase/decrease in revenues or costs to the seller is to be
determined and effected from such date as is decided by the
appropriate Commission. It has further been held that the
compensation is only payable for increase/decrease in revenue
or cost to the seller if it is in excess of an amount equivalent to
1% of the Letter of Credit in aggregate for a contract year. It has
been held that restitutionary principles apply in case a certain
threshold limit is crossed. It has been held that an in-built
restitutionary principle compensates the party affected by such
‘Change in Law’ and the affected party must be restored through
monthly tariff payment to the same economic position as if such
‘Change in Law’ had not occurred.
119. From the perusal of paragraph 9, it would also be clear that
in case the ‘Change in Law’ happens to be by way of adoption,
promulgation, amendment, re-enactment or repeal of the law or
60
‘Change in Law’, it has to be effected from the date on which such
change occurs.
120. In this respect, it will also be apposite to refer to the
following observations of this Court in the case of Maharashtra
State Electricity Distribution Company Limited v.
Maharashtra Electricity Regulatory Commission and
8
Others :
PTEL
“ 173. The A correctly found that:
( Maharashtra Pradesh Electricity Regulatory
Commission case [ Maharashtra State
Electricity Distribution Co.
Ltd. v. Maharashtra Pradesh Electricity
Regulatory Commission , 2021 SCC OnLine
APTEL 13] , SCC OnLine APTEL para 13)
“ 13 . … On the contrary, there is
a conscious exclusion regarding
any suo motu change in the rate to
be applied while calculating LPS , it
being incorrect to argue on the
assumption that the contract
permits automatic change in
system.”
(emphasis supplied)
8
(2022) 4 SCC 657
61
174. This Court is unable to accept Mr
Singh's submission that the conclusion
PTEL
of A that LPS is not tariff is erroneous.
The meaning of the expression tariff has to
be considered, and has rightly been
PTEL
considered by A in the context of the
relevant provision of the power purchase
agreements. The dictionary meaning of tariff
may be charge. However, in Article 13 of the
Stage 1 and Article 10 of the Stage 2 power
purchase agreements, tariff means monthly
tariff and tariff adjustment consequential to
change in law, is of monthly tariff in respect
of supply of electricity.
175. As argued by the respondent power
generating companies appearing through Mr
Rohatgi, Mr Singhvi, Mr Mukherjee and Ms
Anand respectively, LPS is only payable
when payment against monthly bills is
delayed and not otherwise.
176. The object of LPS is to enforce and/or
encourage timely payment of charges by the
procurer i.e. the appellant. In other words,
LPS dissuades the procurer from delaying
payment of charges. The rate of LPS has no
bearing or impact on tariff. Changes in the
basis of the rates of LPS do not affect the rate
at which power was agreed to be sold and
purchased under the power purchase
agreements. The principle of restitution
62
under the change in law provisions of the
power purchase agreements are attracted in
respect of tariff.
177. LPS cannot be equated with carrying
cost or actual cost incurred for the supply of
power. The appellant has a contractual
obligation to make timely payment of the
invoices raised by the power generating
companies, subject, of course, to scrutiny
and verification of the same. Mr Mukul
Rohatgi has a point that if the funding cost
was so much lesser than the rate of LPS, as
contended by the appellant, the appellant
could have raised funds at a lower rate of
interest, made timely payment of the invoices
raised by the power generating companies,
and avoided LPS.
178. The proposition that courts cannot
rewrite a contract mutually executed
between the parties, is well settled. The
Court cannot, through its interpretative
process, rewrite or create a new contract
between the parties. The Court has to simply
apply the terms and conditions of the
agreement as agreed between the parties, as
observed by this Court in Shree Ambica
Medical Stores v. Surat People's Coop.
Bank [ Shree Ambica Medical Stores v. Surat
People's Coop. Bank Ltd. , (2020) 13 SCC 564,
para 20] , cited by Ms Divya Anand. This
63
| appeal is an attempt to renegotiate the terms | ||
|---|---|---|
| of the PPA, as argued by Ms Divya Anand as | ||
| also other counsel. It is well settled that | ||
| courts cannot substitute their own view of | ||
| the presumed understanding of commercial | ||
| terms by the parties, if the terms are | ||
| explicitly expressed. The explicit terms of a | ||
| contract are always the final word with | ||
| regard to the intention of the parties, as held | ||
| by this Court in Nabha Power Ltd. v. Punjab | ||
| SPCL [Nabha Power Ltd. v. Punjab SPCL, | ||
| (2018) 11 SCC 508, paras 45 and 72 : (2018) | ||
| 5 SCC (Civ) 1], cited by Ms Anand.” | ||
| 121. This Court has clearly held that the DISCOMS have a | ||
| contractual obligation to make timely payment of the invoices | ||
| raised by the power generating companies, subject to scrutiny | ||
| and verification of the same. This Court has rejected the | ||
| contention that the funding cost was much lesser than the rate | ||
| of LPS. This Court has reiterated the proposition that the courts | ||
| cannot rewrite a contract which is executed between the parties. | ||
| This Court has emphasized that it cannot substitute its own view | ||
| of the presumed understanding of commercial terms by the | ||
| parties, if the terms are explicitly expressed. It has been held that |
64
the explicit terms of a contract are always the final word with
regard to the intention of the parties.
122. As already discussed hereinabove, Article 11.8 of the PPA
entitles either party to raise a supplementary bill on the other
party on account of ‘Change in Law’ as provided in Article 13 and
such bills are required to be paid by the either party. Article
11.8.3 of the PPA specifically provides that in the event of delay
in payment of a supplementary bill by either party beyond one
month from the date of billing, a late payment surcharge shall be
payable at the same terms applicable to the monthly bill in Article
11.3.4. Article 11.3.4 of the PPA specifically provides a late
payment surcharge to be paid by the procurer to the seller at the
rate of 2% in excess of the applicable SBAR per annum on the
amount of outstanding payment calculated on day to day basis
(and compounded with monthly rest), for each day of the delay.
123. Recently, this Court, in the case of Uttar Haryana Bijli
Vitran Nigam Limited and Another v. Adani Power (Mundra)
65
| Limited and Another9, had an occasion to consider the similar | ||
|---|---|---|
| issue. The Court observed thus: | ||
| “20. It is clear that the restitutionary | ||
| principles encapsulated in Article 13.2 would | ||
| take effect for computing the impact of | ||
| change in law. We see no reason to interfere | ||
| with the impugned judgment [Adani Power | ||
| (Mundra) Ltd. v. CERC, 2021 SCC OnLine | ||
| APTEL 67] , wherein it has been held by the | ||
| Appellate Tribunal that Respondent 1 Adani | ||
| Power had started claiming change in law | ||
| event compensation in respect of installation | ||
| of FGD unit along with carrying cost, right | ||
| from the year 2012 and that it has | ||
| approached several fora to get this claim | ||
| settled. Respondent 1 Adani Power finally | ||
| succeeded in getting compensation towards | ||
| FGD unit only on 28-3-2018, but the | ||
| carrying cost claim was denied. The relief | ||
| relating to carrying cost was granted to | ||
| Respondent 1 Adani Power by the Appellate | ||
| Tribunal vide order dated 13-4-2018 [Adani | ||
| Power Ltd. v. CERC, 2018 SCC OnLine | ||
| APTEL 5] which was duly tested by this | ||
| Court and upheld on 25-2-2019 [Uttar | ||
| Haryana Bijli Vitran Nigam Ltd. v. Adani | ||
| Power Ltd., (2019) 5 SCC 325 : (2019) 2 SCC | ||
| (Civ) 657] . Once carrying cost has been | ||
| granted in favour of Respondent 1 Adani | ||
| Power, it cannot be urged by the appellants | ||
| that interest on carrying cost should be | ||
| calculated on simple interest basis instead of |
9
(2023) 2 SCC 624
66
compound interest basis. Grant of
compound interest on carrying cost and that
too from the date of the occurrence of the
change in law event is based on sound logic.
The idea behind granting interest on carrying
cost is not far to see, it is aimed at restituting
a party that is adversely affected by a change
in law event and restore it to its original
economic position as if such a change in law
event had not taken place.
xxx xxx xxx
23. We are not persuaded by the submission
made on behalf of the appellants that since
no fault is attributable to them for the delay
caused in determination of the amount, they
cannot be saddled with the liability to pay
interest on carrying cost; nor is there any
substance in the argument sought to be
advanced that there is no provision in the
PPAs for payment of compound interest from
the date when the change in law event had
occurred.
24. The entire concept of restitutionary
principles engrained in Article 13 of the PPAs
has to be read in the correct perspective. The
said principle that governs compensating a
party for the time value for money, is the very
same principle that would be invoked and
applied for grant of interest on carrying cost
on account of a change in law event.
Therefore, reliance on Article 11.3.4 read
with Article 11.8.3 on the part of the
67
| appellants cannot take their case further. | ||
|---|---|---|
| Nor does the decision in Priya Vart | ||
| case [Priya Vart v. Union of India, (1995) 5 | ||
| SCC 437] have any application to the facts of | ||
| the present case as the said case relates to | ||
| payment of compensation under the Land | ||
| Acquisition Act and the interest that would | ||
| be payable in case of delayed payment of | ||
| compensation.” | ||
| 124. It is thus clear that this Court has reiterated that once | ||
| carrying cost has been granted, it cannot be urged that interest | ||
| on carrying cost should be calculated on simple interest basis | ||
| instead of compound interest basis. It has been held that grant | ||
| of compound interest on carrying cost and that too from the date | ||
| of the occurrence of the ‘Change in Law’ event is based on sound | ||
| logic. It has been held that it is aimed at restituting a party that | ||
| is adversely affected by a ‘Change in Law’ event and restore it to | ||
| its original economic position as if such a ‘Change in Law’ event | ||
| had not taken place. | ||
| 125. The argument that there is no provision in the PPAs for | ||
| payment of compound interest from the date when the ‘Change |
68
in Law’ event had occurred, has been specifically rejected by this
Court.
126. In view of this consistent position of law and application of
restitutionary principles and privity of contractual obligations
between the parties as contained in the PPAs, we do not find that
the view taken by the learned APTEL with regard to carrying cost
warrants interference.
Concurrent Finding of Fact
127. Apart from the aforesaid issues, there is one another
common thread in all these appeals. Many of these appeals arise
out of concurrent findings recorded by the Central/State
Electricity Regulatory Commissions and the learned APTEL.
128. This Court, in the case of MSEDCL v. APML & Ors. (supra),
after considering the statutory provisions in the Electricity Act,
2003, held that the CERC, SERCs and the learned APTEL are
bodies consisting of experts in the field.
129. This Court, in the said case, observed thus:
69
“ 120. It could thus be seen that two expert
bodies i.e. the CERC and the learned APTEL
have concurrently held, after examining the
material on record, that the factors of SHR
and GCV should be considered as per the
Regulations or actuals, whichever is lower.
The CERC as well as the State Regulatory
bodies, after extensive consultation with the
stakeholders, had specified the SHR norms
in respective Tariff Regulations. In addition,
insofar as GCV is concerned, the CEA has
opined that the margin of 85-100 kcal/kg
for a non-pit head station may be considered
as a loss of GCV measured at wagon top till
the point of firing of coal in boiler.
121. In this respect, we may refer to the
following observations of this Court in the
case of Reliance Infrastructure
Limited v. State of Maharashtra [ (2019) 3
SCC 352].
“ 38. MERC is an expert body which is
entrusted with the duty and function to
frame regulations, including the terms
and conditions for the determination of
tariff. The Court, while exercising its
power of judicial review, can step in where
a case of manifest unreasonableness or
arbitrariness is made out. Similarly,
where the delegate of the legislature has
70
failed to follow statutory procedures or to
take into account factors which it is
mandated by the statute to consider or
has founded its determination of tariffs
on extraneous considerations, the Court
in the exercise of its power of judicial
review will ensure that the statute is not
breached. However, it is no part of the
function of the Court to substitute its own
determination for a determination which
was made by an expert body after due
consideration of material circumstances.
39. In Assn. of Industrial Electricity
Users v. State of A.P. [ Assn. of Industrial
Electricity Users v. State of A.P. , (2002) 3
SCC 711] a three-Judge Bench of this
Court dealt with the fixation of tariffs and
held thus : (SCC p. 717, para 11)
“ 11 . We also agree with the High
Court [ S. Bharat Kumar v. State of
A.P. , 2000 SCC OnLine AP 565 : (2000)
6 ALD 217] that the judicial review in a
matter with regard to fixation of tariff
has not to be as that of an appellate
authority in exercise of its jurisdiction
under Article 226 of the Constitution.
All that the High Court has to be
satisfied with is that the Commission
has followed the proper procedure and
71
unless it can be demonstrated that its
decision is on the face of it arbitrary or
illegal or contrary to the Act, the court
will not interfere. Fixing a tariff and
providing for cross-subsidy is
essentially a matter of policy and
normally a court would refrain from
interfering with a policy decision
unless the power exercised is arbitrary
or ex facie bad in law.”
xxx xxx xxx
123.
Recently, the Constitution Bench of
this Court in the case of Vivek Narayan
Sharma v. Union of India [2023 SCC OnLine
SC 1] has held that the Courts should be
slow in interfering with the decisions taken
by the experts in the field and unless it is
found that the expert bodies have failed to
take into consideration the mandatory
statutory provisions or the decisions taken
are based on extraneous considerations or
they are ex facie arbitrary and illegal, it will
not be appropriate for this Court to
substitute its views with that of the expert
bodies.”
130. As is indicated in the aforesaid judgments, this Court
should be slow in interfering with the concurrent findings of fact
72
unless they are found to be perverse, arbitrary and either in
ignorance of or contrary to the statutory provisions.
V. CONCLUSION
131. In the light of our aforesaid findings, we will now consider
each of the appeals independently.
Civil Appeal No. 11095 of 2018 and Civil Appeal Nos. 11910-
11911 of 2018
132. In these batch of appeals, insofar as the appeal of DNH-
DISCOM is concerned, they are aggrieved by the order of the
learned APTEL allowing Busy Season Surcharge and
Development Surcharge, MoEF Notification on coal quality and
Change in NCDP. They are also aggrieved by the finding of the
learned APTEL with regard to carrying cost.
133. Insofar as the compensation on the ground of Change in
NCDP is concerned, as already discussed, the same is squarely
covered by the judgment of this Court in the case of MSEDCL v.
APML & Ors. (supra)
73
134. Insofar as the Busy Season Surcharge and Development
Surcharge are concerned, they are issued under the
Circulars/Notifications of Indian Railways. The notification on
coal quality is issued by MoEF. All these are the
instrumentalities of the State, and these would, therefore,
amount to ‘Change in Law’.
135. Insofar as rest of the claims, which are concurrently allowed
and disallowed by both the CERC and the learned APTEL, are
concerned, in view of the judgments of this Court on this issue,
as stated above, we do not find any reason to interfere with the
same, not noticing any perversity, arbitrariness and/or any
contravention of the statutory provisions. The appeals of both
the Generator and the DNH-DISCOM are, therefore, liable to be
dismissed.
Civil Appeal Nos.4628-4629 of 2021
136. The learned APTEL allowed the claim of the Generator only
on the ground of Busy Season Surcharge and Development
Surcharge on transportation of coal, and the Carrying Cost.
74
137. In view of our finding on the issues as above, no error can
be found with the finding of the learned APTEL in that regard.
We find no merit in the appeals. The appeals are, accordingly,
liable to be dismissed.
Civil Appeal Nos. 12055-12056 of 2018
138. The issue of Busy Season Surcharge, Development
Surcharge and Port Congestion Surcharge have already been
considered by us herein above. All these are charges under the
Notifications issued by the Indian Railways, through the Railway
Board. As such, no error can be found with the finding of the
learned APTEL that they would amount to ‘Change in Law’
events.
139. Insofar as levy of ‘Forest Tax’ is concerned, the same is
levied by the State Government under the statutory provisions.
140. The issue with regard to ‘Carrying Cost’ has also been
discussed by us herein above.
75
141. In that view of the matter, we do not find any reason to
interfere with the order of the learned APTEL. The appeals are,
accordingly, liable to be dismissed.
Civil Appeal Nos. 2935-2936 of 2020
142. In addition to the ‘Change in Law’ benefits granted by the
State Commission, ‘Coal Terminal Surcharge’, ‘Chhattisgarh
Paryavaran Upkar’ and ‘Chhattisgarh Vikas Upkar’ were also
considered to be ‘Change in Law’ events by the learned APTEL.
143. The ‘Coal Terminal Surcharge’ was levied by the Indian
Railways subsequent to the cut-off date. Similarly, the
Government of Chhattisgarh, under Section 8 of the
Chhattisgarh Adhosanrachna Vikas Evam Paryavaran Upkar
th
Adhiniyam, 2005, vide Notification dated 16 June 2015, which
is admittedly after the cut-off date, introduced ‘Chhattisgarh
Paryavaran Upkar’ and ‘Chhattisgarh Vikas Upkar’. Even the
Change in Swacch Bharat Cess at the rate of 0.5% on Service Tax
for Operation Period and Change in Krishi Kalyan Cess at the
rate of 5% on Service Tax for Operation Period, which had been
76
| granted concurrently by the State Commission and the learned | |
|---|---|
| APTEL, were notified by the Union of India after the cut-off date. | |
| 144. It could thus be seen that all these additional taxes or | |
| cesses were introduced by the instrumentalities of the | |
| Government of India or by the Government of Chhattisgarh. The | |
| same are issued under the provisions of the concerned statutes, | |
| rules, notifications, orders, etc. It is thus clear that they would | |
| amount to ‘Law’ within the meaning of the term ‘Law’ as defined | |
| in the PPAs. As such, no error can be found with the order of the | |
| learned APTEL. | |
| 145. We, therefore, find no merit in the appeals. The appeals are, | |
| accordingly, liable to be dismissed. | |
| Civil Appeal No. 3123 of 2019 and Civil Appeal No.5372 of | |
| 2019 | |
| 146. In the present matter, in addition to the claims granted by | |
| the CERC, the learned APTEL also granted the following claims: | |
| (i) Change in NCDP (cancellation of Captive Block vis-à-vis | |
| tapering linkage), |
77
| (ii) Busy Season Surcharge and Developmental Surcharge, | |
|---|---|
| (iii) Carrying Cost; and | |
| (iv) Add on Premium Price. | |
| 147. Insofar as the issue with regard to change in NCDP is | |
| concerned, this Court in the case of Energy Watchdog (supra) | |
| so also in Adani Rajasthan case (supra) and recently in MSEDCL | |
| v. APML & Ors. (Supra) has held that the change in NCDP would | |
| amount to ‘Change in Law’. As such, the finding in that regard | |
| warrants no interference. | |
| 148. Insofar as Busy Season Surcharge and Development | |
| Surcharge are concerned, we have already discussed hereinabove | |
| as to how it would amount to ‘Change in Law’. | |
| 149. Insofar as ‘Add on premium price’ is concerned, | |
| undisputedly, ‘add on premium’ was required to be paid on | |
| account of cancellation of captive coal blocks and inordinate | |
| delay on account of Go-No-Go policy. As such, it cannot be said | |
| that the reasoning adopted by the learned APTEL is perverse and | |
| arbitrary. |
78
150. Insofar as the issue with regard to ‘carrying cost’ is
concerned, we have already discussed the issue at length in the
foregoing paragraphs. As such, no interference is warranted on
that finding also.
151. Insofar as other claims which were concurrently allowed
and disallowed by the CERC and the learned APTEL are
concerned, in view of the concurrent findings, we are not inclined
to interfere with the same.
152. The appeals of both DISCOMS as well as Generating
Companies are, therefore, liable to be dismissed.
Civil Appeal No. 6641 of 2019
153. This appeal is filed by GKEL, being aggrieved by the
concurrent denial of benefits on certain components.
154. As already discussed herein above by us, in view of the
concurrent findings recorded by the CERC as well as the learned
APTEL for disallowing the claims, we are not inclined to interfere
with the same. The appeal is, accordingly, liable to be dismissed.
79
| Civil Appeal Nos. 5583-5584 of 2021 | |
|---|---|
| 155. In the present case, the benefit is granted on following | |
| grounds: | |
| (i) Shortfall in domestic coal on account of Change in NCDP; | |
| (ii) Add on premium on account of existing tapering linkage | |
| by three years; | |
| (iii) Busy Season Surcharge | |
| 156. The first issue sands covered by the judgments of this Court | |
| in the cases of Energy Watchdog (supra), Adani Rajasthan | |
| case (supra) and MSEDCL v. APML & Ors. (supra) and as such, | |
| no interference is warranted. | |
| 157. Insofar as Busy Season Surcharge is concerned, apart from | |
| there being concurrent findings of facts, we have already given | |
| reasons herein above as to how the same would amount to | |
| ‘Change in Law’. | |
| 158. We do not find any merit in the appeals. The same are, | |
| accordingly, liable to be dismissed. |
80
| Civil Appeal No. 39 of 2021 | |
|---|---|
| 159. The CERC has granted benefit on the following grounds. | |
| i. Shortfall in linkage coal on account of NCDP 2013 and | |
| SHAKTI Policy; | |
| ii. Change in coal quality pursuant to amendment of the | |
| Environment (Protection) Rules, 1986; | |
| iii. Increase in Busy Season Surcharge and Development | |
| Surcharge on transportation of coal by Indian Railways; | |
| and | |
| iv. Carrying cost on allowed ‘Change in Law’ claims. | |
| 160. The view taken by the CERC has been affirmed by the | |
| learned APTEL. As such, the appeal arises out of the concurrent | |
| findings of fact. | |
| 161. Insofar as first issue with regard to benefit of ‘Change in | |
| Law’ event on account of NCDP 2013 is concerned, the same is | |
| squarely covered by the judgments of this Court in the cases of |
81
Energy Watchdog (supra), Adani Rajasthan case (supra) and
MSEDCL v. APML & Ors. (supra).
162. Insofar as the benefit of ‘Change in Law’ on account of
SHAKTI Policy is concerned, it is covered by the judgment and
order of the even date of this Court in the case of Civil Appeal No.
10
5684 of 2021 and in the case of Civil Appeal Nos. 677-678 of
11
2021 .
163. The other components, i.e. change in coal quality pursuant
to amendment of the Environment (Protection) Rules, 1986, and
increase in Busy Season Surcharge and Development Surcharge
on transportation of coal by Indian Railways, have already been
considered by us herein to amount to ‘Change in Law’ events. We
have also considered the issue regarding ‘Carrying Cost’. As
such, no interference is warranted in the concurrent findings by
the learned APTEL, especially in view of the judgments of this
Court. The appeal is, accordingly, liable to be dismissed.
10
Uttar Haryana Bijli Vitran Nigam Limited and another v. Adana Power (Mundra) Limited and another
11
Maharashtra State Electricity Distribution Company Limited v. Adani Power Maharashtra Limited and
another
82
Civil Appeal No. 5005 of 2022 and Civil Appeal No. 4089 of
2022
164.
The appeals are filed being aggrieved by the order of the
learned APTEL granting compensation on account of ‘EFC’ and
‘carrying cost’.
165. Undisputedly, the EFC was imposed by CIL vide its Circular
th
dated 19 December 2017.
166. As discussed herein above, it is not in dispute that EFC has
been paid by the Generators while paying the base price, other
charges and statutory charges at the time of delivery of coal. As
such, no interference is warranted with the said finding.
167. Insofar as ‘carrying cost’ is concerned, we have elaborately
discussed the said issue herein above. As such, no interference,
therefore, is warranted on the said issue also.
168. We do not find any merit in the appeals. The same are,
accordingly, liable to be dismissed.
83
VI. EPILOGUE
169. Before we part with the judgment, we must note that we
have come across several appeals in the present batch which
arise out of concurrent findings of fact arrived at by two statutory
bodies having expertise in the field. We have also found that in
some of the matters, the appeals have been filed only for the sake
of filing the same. We also find that several rounds of litigation
have taken place in some of the proceedings.
170. Recently, this Court, in the case of MSEDCL v. APML &
Ors. (supra), has noted that one of the reasons for enacting the
Electricity Act, 2003 was that the performance of the Electricity
Boards had deteriorated on account of various factors. The
Statement of Objects and Reasons of the Electricity Act, 2003
would reveal that one of the main features for enactment of the
Electricity Act was delicensing of generation and freely permitting
captive generation. In the said judgment, we have recorded the
statement of the learned Attorney General made in the case of
Energy Watchdog (supra) that the electricity sector, having been
84
privatized, had largely fulfilled the object sought to be achieved
by the Electricity Act. He had stated that delicensed electricity
generation resulted in production of far greater electricity than
was earlier produced. The learned Attorney General had further
urged the Court not to disturb the delicate balance sought to be
achieved by the Electricity Act, i.e. that the producers or
generators of electricity, in order that they set up power plants,
be entitled to a reasonable margin of profit and a reasonable
return on their capital, so that they are induced to set up more
and more power plants. At the same time, the interests of the
end consumers also need to be protected.
171. However, we find that, in spite of this position, litigations
after litigations are pursued. Though the concurrent orders of
statutory expert bodies cannot be said to be perverse, arbitrary
or in violation of the statutory provisions, the same are
challenged.
172. It will be relevant to note the following observations of the
th
CERC in its judgment and order dated 16 May 2019, passed in
85
| Petition No. 8/MP/2014, which falls for consideration in Civil | ||
|---|---|---|
| Appeal No. 39 of 2021 before this Court: | ||
| “(d) Approaching the Commission every | ||
| year for allowance of compensation for such | ||
| Change in Law is a time-consuming | ||
| process. Accordingly, the mechanism | ||
| prescribed above may be adopted for | ||
| payment of compensation due to Change in | ||
| Law events allowed as per PPA for the | ||
| subsequent period as well.” | ||
| 173. It will also be relevant to refer to some of the observations | ||
| of the learned APTEL in its order dated 21st December 2021, | ||
| which falls for consideration in Civil Appeal No.2908 of 2022 | ||
| before this Court, which read thus: |
its Report (dated 07.03.2018) on Energy
titled ‘ Stressed/ Non-Performing Assets
in Electricity Sector ’ has recognized the
financial stress faced by generating
companies on account of delay in
recovery of Change in Law
compensations and has recommended
thus:
“ The Committee, therefore, recommend
that appropriate steps should be taken
to ensure that there should be
consistency and uniformity with
86
regard to orders emanating from the
status of change in law. Provisions
should also be made for certain
percentage of payments of
regulatory dues to be paid by
Discoms in case the orders of
regulators are being taken to
APTEL/ higher judiciary for their
consideration and decision”
116. The Report lays stress on the obligation of
the distribution companies to pay the
approved Change in Law compensation
even while Regulatory Commission’s
orders are challenged. The Policy
directive dated 27.08.2018 issued in
terms of Section 107 of the Electricity
Act, 2003 by the Ministry of Power
(MoP) to the CERC emphasized on the
need to ensure expeditious recovery
of Change in Law compensation. The
desirability of this was recognized by
this tribunal in its judgment dated
14.09.2019 in Jaipur Vidyut Vitran
Nigam Limited vs. RERC & Ors, 2019
SCC Online APTEL 98. It is against
such backdrop that Electricity
(Timely Recovery of Costs due to
Change in Law) Rules, 2021, notified
by MoP on 22.10.2021, providing for
timely recovery of compensation on
account of occurrence of Change in
Law events have been framed. The
MoP, vide notification dated 09.11.2021,
put in public domain the policy directive
87
on “ Automatic pass through of the fuel
and power procurement cost in tariff for
ensuring the viability of the power ”
recognizing that in order to ensure that
the power sector does not face any
constraints in maintaining assured
power supply to meet the demand, all the
stakeholders in the value chain of power
sector must ensure that there is timely
recovery of cost. This involves the cost
pass through by the generating
companies to the distribution
companies.
117. In sharp contrast, it is seen from the
factual narrative of the events leading to
the appeal at hand that the appellants
(Haryana Utilities) have been adopting
dilatory tactics which not only defeats
the public policy but also has the
undesirable fall-out of adding to the
burden of the end-consumers they
profess to serve on account of increasing
Carrying Cost.
118. Concededly, in compliance with the Taxes
and Duties Order dated 06.02.2017, the
appellants paid to the generator the
taxes and duties for certain period but,
thereafter, unilaterally withheld such
claims, raising issues (found merit-less)
regarding IPT of coal for first time in
January 2018. It is after the impugned
order was passed that the appellants are
stated to have started complying, to an
88
extent, by making payments. It is the
case of the first respondent that the
appellants have withheld past payments
including towards taxes and duties its
entitlement to recover corresponding
Late Payment Surchage (“LPS”) being
over and above the same to be computed
after discharge of the former liability. We
agree that such withholding is in
violation of Articles 11.3.2 and
11.6.9 of the PPAs (quoted earlier)
which cast a specific mandate on the
procurer (Haryana Utilities) to honor
the invoices raised, irrespective of
dispute, and impose a specific bar
against unilateral deductions/setting
off.
119. We find the dilatory conduct of the
Haryana Utilities, to delay the
implementation of the binding orders
concerning compensation on account of
coal shortfall and corresponding taxes
and duties, detrimental to the interest of
end consumers since it burdens the
consumers with incremental LPS for
delay in making payments to the
generator. This cannot be countenanced,
given the earlier dispensation on the
subject by the statutory regulator and
appellate forum(s), since it smacks of
approach that is designed to frustrate
the legislative command, and extant
State policy, as indeed constitutes abject
indiscipline infringing the rule of law.
89
Borrowing THE WORDS OF Hon’ble
Supreme Court in SEBI vs. Sahara India
Real Estate Corpn. Ltd., (2014) 5 SCC
429 “
non-compliance with the orders
passed … shakes the very foundation of
our judicial system and undermines the
rule of law” which this tribunal is also
duty-bound to “honour and protect”, so
essential “to maintain faith and
confidence of the people of this country in
the judiciary ”.”
[emphasis supplied]
174. It could thus be seen that even the Standing Committee of
Parliament, in its report, has recommended that there should be
consistency and uniformity with regard to orders emanating from
the status of ‘Change in Law’. It has also recommended that the
provisions should also be made for certain percentage of
payments of regulatory dues to be paid by DISCOMS in case the
orders of regulators are being taken to learned APTEL/higher
judiciary for their consideration and decision. The learned
th
APTEL has also referred to the Policy Directive dated 27 August
2018 issued in terms of Section 107 of the Electricity Act, 2003
by the MoP to the CERC, where it emphasized the need to ensure
90
expeditious recovery of ‘Change in Law’ compensation. The
learned APTEL has also referred to the Electricity (Timely
Recovery of Costs due to Change in Law) Rules, 2021, notified by
nd
MoP on 22 October 2021, which provide for timely recovery of
compensation on account of occurrence of ‘Change in Law’
events. The learned APTEL found that the Haryana Utilities have
been adopting dilatory tactics, which not only defeat the public
policy but also have the undesirable fallout of adding to the
burden of the end-consumers they profess to serve on account of
increasing ‘Carrying Cost’. The learned APTEL further found that
withholding of past payments, including towards taxes and
duties by the DISCOMS, is in violation of the provisions of the
PPAs, which casts a specific mandate on the procurer to honour
the invoices raised, irrespective of dispute, and impose a specific
bar against unilateral deductions/setting off.
175. It is further to be noted that this Court, in the case of Uttar
Haryana Bijli Vitran Nigam Limited (UNHVNL) and another
91
12
v. Adani Power Limited and others , has specifically observed
that the ‘Change in Law’ events will have to accrue from the date
on which Rules, Orders, Notifications are issued by the
instrumentalities of the State. Even in spite of this finding, the
DISCOMS are pursuing litigations after litigations.
176. We find that, when the PPA itself provides a mechanism for
payment of compensation on the ground of ‘Change in Law’,
unwarranted litigation, which wastes the time of the Court as
well as adds to the ultimate cost of electricity consumed by the
end consumer, ought to be avoided. Ultimately, the huge cost of
litigation on the part of DISCOMS as well as the Generators adds
to the cost of electricity that is supplied to the end consumers.
177. We further find that non-quantification of the dues by the
Electricity Regulatory Commissions and the untimely payment of
the dues by the DISCOMS is also detrimental to the interests of
the end consumers. If timely payment is not made by DISCOMS,
12
(2019) 5 SCC 325
92
under the clauses in the PPA, they are required to pay late
payment surcharges, which are much higher. Even in case of
‘Change in Law’ claims, the same procedure is required to be
followed.
178. Ultimately, these late payment surcharges are added to the
cost of electricity supplied to the end consumers. It is, thus, the
end consumers who suffer by paying higher charges on account
of the DISCOMS not making timely payment to the Generators.
179. It is further to be noted that the appeal to this Court under
Section 125 of the Electricity Act, 2003 is only permissible on any
of the grounds as specified in Section 100 of the Code of Civil
Procedure, 1908. As such, the appeal to this Court would be
permissible only on substantial questions of law. However, as
already observed herein, even in cases where well-reasoned
concurrent orders are passed by the Electricity Regulatory
Commissions and the learned APTEL, the same are challenged
by the DISCOMS as well as the Generators. On account of
pendency of litigation, which in some of the cases in this batch
93
has been more than 5 years, non-payment of dues would entail
paying of heavy carrying cost to the Generators by the DISCOMS,
which, in turn, will be passed over to the end consumer. As a
result, it will be the end consumer who would be at sufferance.
We are of the opinion that such unnecessary and unwarranted
litigation needs to be curbed.
180. To a pointed query, the learned counsel for the DISCOMS
fairly conceded the position that the prices at which the
electricity is purchased from the ‘Independent Power Producers’
is substantially lesser than the power purchased from the ‘State
Generating Companies’.
181. We, therefore, appeal to the Union of India through Ministry
of Power (“MoP” for short) to evolve a mechanism so as to ensure
timely payment by the DISCOMS to the Generating Companies,
which would avoid huge carrying cost to be passed over to the
end consumers.
94
182. The Union of India, through MoP, may also evolve a
mechanism to avoid unnecessary and unwarranted litigation, the
cost of which is also passed on to the ultimate consumer.
183. Before we part with the judgment, we place on record our
appreciation for the valuable assistance rendered by Mr. Balbir
Singh, learned Additional Solicitor General, Dr. A. M. Singhvi,
Mr. V. Giri, Mr. M.G. Ramachandran, Mr. C.A. Sundaram, Mr.
Maninder Singh, Mr. Sajan Poovayya and Mr. Niranjan Reddy,
learned Senior Counsel, and Mr. Vishrov Mukerjee, Ms. Poorva
Saigal, Ms. Anushree Bardhan, and Ms. Poonam Sengupta,
learned counsel.
184. In view of the above, all the appeals are dismissed. No costs.
…….........................J.
[B.R. GAVAI]
…….........................J.
[VIKRAM NATH]
NEW DELHI;
APRIL 20, 2023
95