Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 18
PETITIONER:
SUDARSAN TRADING CO.
Vs.
RESPONDENT:
GOVT. OF KERALA & ANR.
DATE OF JUDGMENT14/02/1989
BENCH:
MUKHARJI, SABYASACHI (J)
BENCH:
MUKHARJI, SABYASACHI (J)
RANGNATHAN, S.
CITATION:
1989 AIR 890 1989 SCR (1) 665
1989 SCC (2) 38 JT 1989 (1) 339
1989 SCALE (1)395
CITATOR INFO :
D 1989 SC1263 (8,10)
F 1990 SC 626 (5)
F 1990 SC1340 (8,9,11)
RF 1992 SC2192 (9,10)
ACT:
Arbitration Act, 1940: s. 30---Non-speaking
award--Validity of-Not open to court to probe the mental
process of the arbitrator-Reasonableness of the
reasons--Arbitrator the sole judge of quality and quantity
of evidence-Interpretation of contract by arbitrator--Court
cannot substitute its own decision--Setting aside of
award--Grounds for.
HEADNOTE:
The appellant-contractor undertook construction of
certain timebound projects. The work, however, could not be
completed within the scheduled time due to various reasons.
The contract was consequently cancelled at appellant’s risk.
The disputes arising therefrom between the parties were
referred to the arbitrator named in the agreement. He made
three awards allowing claim Nos. 1(e), 2, 5, 7(a), 7(b),
7(c), 13, 14, and 15 preferred by the appellant aggregating
to Rs.31.15 lakhs under the several heads mentioned therein.
Upon these awards, an application was made before the
court for passing decrees in terms thereof. Objections were
also filed.
The trial court took the view that it could not adjudi-
cate upon the justification for the conclusions arrived at
by the arbitrator unless such awards were the result of
corruption, fraud or there were errors apparent on the face
of the award, that it was not necessary for the arbitrator
to give reasons for his award, that there was no jurisdic-
tion to investigate into the merits of the case and to
examine the documentary and oral evidence for the purpose of
finding out whether or not the arbitrator had committed an
error of law or fact, that the arbitrator had not incorpo-
rated in the award any materials for his conclusion nor did
he incorporate the terms of the contract between the par-
ties. Under such circumstances the award could not be set
aside, especially when there was no error apparent on the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 18
face of it and there was nothing to show that the arbitrator
had misconducted the proceedings or that the award had been
improperly procured.
In appeal before the High Court it was contended for the
respon-
666
dents that there were errors apparent on the face of the
award, that the arbitrator had misconducted himself and
travelled beyond the terms of the contract, and that the
claims allowed were beyond and contrary to the agreement
between the parties, whereas for the appellants it was
contended that the award was a non-speaking award and,
therefore, it was not open to the court to go into the
correctness or reasonableness of the award.
The High Court set out the claims, noted the rival
contentious and referred to the various clauses and the
conditions of the contract, though the contract itself was
made no part of the award, and concluded that there were
errors apparent on the face of the award that the arbitrator
had misconducted himself and travelled beyond his power.
In the appeals by special leave, it was contended that
the High Court had exceeded its jurisdiction in acting in
the manner it did on the aforesaid aspects.
Allowing the appeals by special leave,
HELD: 1.1 The High Court fell into an error in deciding
the question on interpretation of the contract. It had no
jurisdiction to examine the different items awarded clause
by clause by the arbitrator and to hold that under the
contract these were not sustainable in the facts found by
the arbitrator. [688D,E]
1.2 Once there is no dispute as to the contract, what is
the interpretation of that contract, is a matter for the
arbitrator and on which the court cannot substitute its own
decision. So also, the court cannot substitute the decision
of the arbitrator, as to what was meant by the contract,
once a dispute under the contract is conceded to the arbi-
trator. [687B,D]
1.3 In the instant case the court had examined the
different claims not to find out whether these claims were
within the disputes referable to the arbitrator, but to find
out whether in arriving at the decision, the arbitrator had
acted correctly or incorrectly. This the court had no juris-
diction to do, namely, substitution of its own evaluation of
the conclusion of law or fact to come to the conclusion that
the arbitrator had acted contrary to the bargain between the
parties. Whether a particular amount was liable to be paid
or damages liable to be sustained, was a decision within the
competency of the arbitrator. By purporting to construe the
contract the court could not take upon itself
667
the burden of saying that this was contrary to the contract
and, as such, beyond jurisdiction. [686D-F]
1.4 Furthermore, if on a view taken of a contract, the
decision of the arbitrator on certain amounts awarded, is a
possible view though perhaps not the only correct view, the
award cannot be examined by the court in the manner done by
the High Court in the instant case. [688D]
F.R. Absalom, Ltd. v. Great Western (London) Garden
Village Society, Ltd., [1933] AC 592; Heyman & Anr. v.
Darwins, Ltd. [1942] AC 356 and Attorney General for Manito-
ba v. Kelly & Ors., [1922] 1 AC 268 distinguished.
State of Kerala v. Poulose, [1987] 1 KLT 781 and State
of Kerala v. Raveendranathan, [1987] 1 KLT 604 partly over-
ruled.
2.1 Where there are errors apparent on the face of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 18
award it can only be set aside if in the award there is any
proposition of law which is apparent on the face of the
award, namely, in the award itself or any document incorpo-
rated in the award. But where a specific question is re-
ferred, the award is not liable to be set aside on the
ground of an error on the face of the award even if the
answer to the question involves an erroneous decision on a
point of law. [684D-E]
Champsey Bhara & Co. v. Jivraj Balloo Spinning & Weaving
Co. Ltd. (L 1922 1A 324; M/s Alopi Parshad & Sons, Ltd. v.
The Union of India, [1951] S.C.R. 793; Jivarajbhai Ujamshi
Sheth & Ors. v. Chintamanrao Balaji & Ors., [1964] 5 SCR 480
and Upper Ganges Valley Electricity Supply Co. Ltd. v. U.P.
Electricity Board., [1973] 3 SCR 107 referred to.
2.2 An award can also be set aside if the arbitrator had
misconducted himself or the proceedings. One of the miscon-
ducts could be the decision by the arbitrator on a matter
which is not included in the agreement or reference. But in
such a case one has to determine the distinction between an
error within the jurisdiction and an error in excess of the
jurisdiction. [686C]
Anisminic Ltd. v. Foreign Compensation Commission,
[1969] 2 AC 147; Regina v. Noseda, Field, Knight & Fitzpat-
rick, [1958] 1 WLR 793 and Halsoury’s Laws of England, 4th
Edn. Vol. para 622 referred
tO.
668
2.3 An award may be remitted or set aside on the ground
that the arbitrator in making it had exceeded his jurisdic-
tion and evidence of matters not appearing on the face of it
will be admitted in order to establish whether the jurisdic-
tion had been exceeded or not, be because the nature of the
dispute is something which has to be determined outside the
award--whatever might be said about it in the award or by
the arbitrator. [685H; 686A-B]
Christopher Brown Ltd. v. Genossenschaft Oesterreigh-
ischer etc., [1954] 1 QB 8; Dalmia Dairy Industries Ltd. v.
National Bank of Pakistan, [1978] 2 Lloyd’s Rep, 223 and
Russell on The Law of Arbitration, 20th Edn. 427 referred
to.
2.4 An arbitrator acting beyond his jurisdiction, howev-
er, is a different ground from the error apparent of the
face of the award. In the former case the court can look
into the arbitration agreement but in the latter it cannot
unless the agreement was incorporated or recited in the
award. In the instant case the contract in question was not
incorporated or referred to in the award. [686B-C]
2.5 However, there is a distinction between disputes as
to the jurisdiction of the arbitrator and the disputes as to
in what way that jurisdiction should be exercised- There may
be a conflict as to the power of the arbitrator to grant a
particular remedy. The nature of the dispute has to be
determined. [686F-G]
Commercial Arbitration by Sir M.J. Mustill & Steward G.
Soyd page 84, referred to.
3.1 The court look into the reasoning only in a speak-
ing award. It is not open to the court to probe the mental
process of the arbitrator and speculate, where no reasons
are given by the arbitrator, as to what impelled the arbi-
trator to arrive at his conclusion. [683G-H]
3.2 Furthermore, in any event, reasonableness of the
reasons given by the arbitrator, cannot be challenged.
Appraisement of evidence by the arbitrator is never a matter
which the court questions and considers. If the parties have
selected their own forum, the deciding forum must be conced-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 18
ed the power of appraisement of the evidence. The arbitrator
is the sole judge of the quality as well as the quantity of
evidence and it will not be for the court to take upon
itself the task of being a judge on the evidence before the
arbitrator. [684B-C]
669
3.3 In the instant case, the award was not a speaking
award. The arbitrator had merely set out the claims and
given the history of the claims and then awarded certain
amount. He had not spoken his mind indicating why he had
done what he had done; he had narrated only how he came to
make the award. In the absence of any reasons for making the
award, it was not open to the court to interfere with the
award. [684A-B]
Hindustan Steel Works .Construction Ltd. v. C. Rajasek-
har Rao, [1987] 4 SCC 93 and Municipal Corporation of Delhi
v. M/s Jagan Nath Ashok Kumar & Anr., [1987] 4 SCC 497
referred to.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 840842 of
1989.
From the Judgment and Order dated 5.5.1988 of the Kerala
High Court in M.F.A. Nos. 72/83,346/83 and 380 of 1983.
K.K. Venugopal, Shiv Pujan Singh and Miss Niranjana for
the Appellant.
G. Vishwanath Iyer and K.R. Nambiar for the Respondents.
The Judgment of the Court was delivered by
SABYASACHI MUKHARJI, J. Leave granted.
These appeals arise from the judgment and order of the
High Court of Kerala, dated 5th May, 1988. The High Court by
the impugned judgment and order in M.F.A. Nos. 72,346 and
380 of 1983 allowed the appeals of the respondent--the Govt.
of Kerala, against the judgment and decree dated 25th Sep-
tember, 1982 passed by the principal Sub-Judge, Trivandrum
in S.P. (Arbitration) Cases Nos. 184, 185 and 186 of 1982 by
which the learned Sub-Judge had upheld the awards by the
arbitrator on the ground that it was not open to the court
to sit in appeal over the decision of the arbitrator and the
court could not adjudicate upon the justification for the
conclusions arrived at by the arbitrator unless such awards
were the result of corruption, fraud or when there were
errors apparent on the face of the award. The learned Sub-
Judge further held that there was no error apparent on the
face of the record and there was no allegation of corruption
or fraud. The High Court reversed the said decision.
670
The questions-involved in these appeals are: how should
the court examine an award to find out whether it was a
speaking award or not; and if it be a non-speaking award,
how and to what extent the court could go to determine
whether there was any error apparent on the face of the
award to be liable for interference by the court. The other
question that arises in this case is, to what extent can the
court examine the contract in question though not incorpo-
rated or referred to in the award.
It may be noted that on 23rd December, 1976 the agree-
ment No. 25/SESPC/1976-77 was entered into between the
appellant and the respondent herein for construction of
masonary dam across Siruvani river. Certain disputes arose
between the appellant and the respondent. These disputes
were referred to the arbitrator named in the agreement. The
arbitrator passed the awards dated 12th, 16th and 23rd
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 18
April, 1982, which were filed before the Sub-Judge and the
appellant prayed for passing of decree in terms of the
awards. The respondents filed petitions seeking to set aside
the awards. The learned Judge refused to set aside the
awards and passed decrees in terms of the awards. The Trial
Court held that there was no merit in the contention regard-
ing limitation; and that the claims under the award were not
barred by limitation. It was further held by the learned
Trial Judge that the arbitrator had not incorporated in the
award any material for his conclusion nor had he incorporat-
ed the terms of contract between the parties. Under such
circumstances the award could not be set aside, especially
when there was no error apparent on the face and that there
was nothing to show that the arbitrator had mis-conducted
the proceedings or that the award had been improperly pro-
cured. So the objection to the passing of the award was
turned down.
Aggrieved thereby, the respondent filed appeals before
the High Court. The High Court by the impugned judgment
dated 5.5. 1988 set aside the awards and the decree of the
Trial Court on the ground that there were errors of law
apparent on the face of the awards. It is contended that the
High Court in the circumstances of this case and in view of
the settled principles of law, exceeded its jurisdiction by
acting in the manner it purported to do. It is, therefore,
necessary to refer to the award to determine how has the
arbitrator proceeded and what actually the arbitrator has
decided. The arbitrator has noted in the first award that
the dispute related to the work of ’Siruvani drinking Water
Supply project--Construction of an Intak Tower and allied
structures’; and observed that an estimate amounting to Rs.
17.45 lakhs was sanctioned for the work and it was entrusted
on contract to the
671
claimant--appellant herein, on tenders. The value of the
work arranged on contract was Rs. 14.45 lakhs as per the
departmental estimate which the appellant undertook, as
understood by the arbitrator, to carry out works at a total
amount of Rs. 19.15 lakhs as per their tender. The contract
was embodied in agreement No. 18/SC/SPS/1977-78 dated
17.3.78 between the claimants on the one side and the re-
spondent No. 2 on behalf of the State of Kerala cited as
respondent No. 1 on the other, in these proceedings. The
work had been taken up as part of the scheme for augmenting
the drinking water supply to Coimbatore city from the yield
of the Siruvani river and due to acute scarcity of water in
the city, work was taken up on an urgent footing and it was
understood by both the parties that time was of utmost
importance in the execution of work. The site for the work
was handed over to the claimants on 17th December, 1977 and
the work had to be completed by 15.6.1978. Accordingly to
the arbitrator, however, it was clear that the work could
not be completed within the stipulated period due to various
reasons for which each party blamed the other. It was noted
in the award that according to the respondents, after carry-
ing out the work to the tune of Rs.3.46 lakhs (approx.)
against the accepted probably estimate of contract of Rs.
19.15 lakhs, the appellant refused to proceed with the.
balance work in spite of specific notices to them and so the
respondents were constrained to terminate the contract at
the risk and cost of the appellant. Several efforts were
made to re-arrange the balance works and finally as per the
situation obtaining then these works were to be expected to
be completed at an excess cost of Rs.0.97 lakhs over the
amount that would have been payable to the appellant as per
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 18
the terms of the original contract. The arbitrator, thereaf-
ter, noted that the appellant had raised in respect of the
dispute which is the subject-matter in the first award,
specific claims for an amount of Rs. 5.97 lakhs in addition
to release of their retention sum of Rs. 32,139 and the
security deposit of Rs.38,400 payment of final bill for the
work done including the above claims, interest on amounts
awarded and cost of the arbitration proceedings.
It seems from the award of the arbitrator that the
contention of the respondents had been that as per the terms
of the contract, they were entitled to realise the excess
cost on re-arrangement of the balance works estimated at
Rs.0.87 lakhs from the claimant and so they proposed to
appropriate the retention sum of Rs.32,139 lying in their
hands, the Security Deposit of Rs.38,400 and the sums due to
the claimant by way of final bill on other works as well. It
was noted by the arbitrator that there was a prayer by the
appellant for inspection of the site and the same was in-
spected on 9.12.80. It was contended on behalf
672
of the claimant that the site of work was situated on the
Western Ghats far away from human habitation in dense forest
infected with wild animals at an elevation of about 600 M
and subject to heavy precipitation of upto 400 cms. annually
and that access to the site was only from Coimbatore side in
Tamil Nadu. Several obstacles for access to the site were
highlighted before the arbitrator. Another important point
on which considerable stress was laid was the compensation
for losses occasioned to them on account of the unsatisfac-
tory law and order situation coupled with labour unrest,
stoppages and threats and even physical violence on the
agents of the appellant. It was further highlighted that the
termination of the contract at their risk despite the frus-
tration and impossibility of performance was clearly illegal
and unjustified. In the premises compensation was demanded
for loss of equipments. The arbitrator noted that the main
point of defence of the respondent was that the time for the
completion of the work forming part of the time-bound pro-
gramme was six months from the date of handing over the
site. As the site was handed over on 16.12.77, the date of
completion should have been 15.6.1978. Of the difficulties
arising out of the location of the site of the work, it was
emphasised by the respondent that the conditions under which
the contract had to be performed were within the knowledge
of the parties, and there could not be any ground for claim-
ing any addition than those contemplated in the contract. It
was definitely further stated that the additional haulage
was due to the alternate route via Thachampara which was
opened on 15.2.1977 and that any claim on this account
subsequent to the above date was unjustified. Furthermore,
that materials like sand, cement and steel were all issued
in time and there could hardly be any justification regard-
ing delays on these account. Regarding interruptions in
power supply the respondents’ case was that such interrup-
tions were not unexpected at a site to which the power lines
passed through virgin reserve area, and at any rate the
claimants were not assured by the respondents of uninter-
rupted power and there was hardly any items of machinery
belonging to the appellant which had remained idle for want
of power.
It was further stated that the various extra items of
works including the work on the quarries had been adequately
paid for by them and no further payments were due to the
appellant; that there was no serious deterioration of the
law and order situation; and that the losses were due to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 18
conduct of the claimant and the materials left over by the
claimant at the end of the second working seasons that had
been taken over by them, duly accounted for and the credit
thereof given in the final bill. It was further reiterated
by the respondent that the work
673
was not completed within the period agreed and, therefore,
the respondent issued notice to resume the work and on the
failure of the claimant to re-start the work, there was no
other alternative except to terminate the contract as the
work itself was part of a time-bound programme; and they had
to make alternate arrangements and that would have cost
Rs.0.87 lakhs additionally which was sought to be recovered
from the appellant appropriating the retention money and
security deposit. It was, therefore, claimed that the claims
of the appellant should be rejected.
Considering all these contentions and noting the several
respective claims, the arbitrator awarded as follows:
"Claims Nos. (1), (2) (a & b) and (3) These
claims are declined.
Claim No. 4 The Respondents shall pay the
Claimants a sum of Rupees Ninety Six Thousand
only (Rs.96,000) in satisfaction of this claim
including the various Sub Claims under the
same.
Claims No. 5(a), (b) & (c)--The Respondents
shall pay an amount of Rs. five thousand only
(Rs.5,000) to the Claimants in satisfaction of
this claim.
Claims Nos. (6), (7), (8) and (9)--These four
Claims are declined.
Claim No. (10)--The retention moneys recovered
from the Claimants in regard to this work
shall be refunded to them by the Respondents.
Claim No. 11--The f.oo. for the work shall be
paid to Claimant for the sums awarded under
Claims (4) and (5) Supra resulting in a net
payment of Rupees one Lakh and One thousand
only (Rs. 1,01,000).
Claim No. 12--The Respondents shall refund the
security deposit held by the Claimants for
this work subject to the rules regarding tax
clearance.
Claim No. 13--The Claim for interest is de-
clined.
Claim No. 14--The parties shall suffer their
respective costs in these proceedings."
674
Regarding the counter-claims it was held that the order
of the 2nd respondent terminating the contract in favour of
the appellant was valid and as such, the respondents were
free to arrange for the balance work in the manner they
thought fit. The counter claim for costs of the respondents
was also held by the arbitrator to be covered by other
claims. The award was passed on 12th April, 1982.
There was another award dated 16th April, 1982 which was
with regard to the dispute that arose for controlling the
work of "Siruvani Drinking Water Supply Project--Construct-
ing a Masonry dam across Siruvani River Block Nos. I, II and
III from Ch. 13 to 60 up to level + 883.00 metres and Block
No. III from ch. 60 to 82 upto level + 870 metres". In
respect of the aforesaid, an estimate amounting to Rs.71.5
lakhs had been sanctioned for the work and it was entrusted
on contract to the appellant. It appears that the value of
the work arranged on contract was Rs.67,72,760 as per de-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 18
partmental estimate which the appellant undertook to carry
out at a total amount of Rs.76,55,300 as per their tender.
The contract was embodied in the aforesaid agreement of 23rd
December, 1976. The arbitrator recited the original claim
and noted that the work could not be completed during the
scheduled time and the respective contentions of the parties
were, more or less, identical with the one made in the
previous case.
There was inspection of documents and the parties were
heard in person, it was noted. After noting the respective
contentions the arbitrator awarded as follows:
"Claim No. (1)(A)--The Claim for additional
payment on account of aslar work is declined.
Claim No. (1)(B)--The Respondents shall pay
the Claimants an additional amount of Rupees
One Lakh only (Rs. 1,00,000) in satisfaction
of this claim over and above the amounts al-
ready paid by them in the various part bills.
Claim No, (1)(c)--This claim for compensation
on account of loss in hire charges and short-
age of rubble is declined.
Claim No. 2--The Respondents shall pay the
Claimants a sum of Rupees three lakhs and
thirty six thousand only (Rs.3,36,000) in
satisfaction of this claim.
Claim Nos. 3 & 4--These two claims are de-
clined.
675
Claim No. 5--The Respondents shall pay the
Claimants an increase of forty (40) per cent
in the agreed rates for agreed items and rates
derived from the agreement for the extra items
for all work paid for after CC2 and part, such
increase being worked out on the cost of the
work excluding the value of the materials
supplied by the Respondents.
Claim No. 6--The Claimant shall be entitled to
a payment of Rupees twenty five thousand only
(Rs.25,000) in satisfaction of this claim and
the Respondent shall pay it accordingly.
Claim No. 7(a)(b) & (c)--The Claimants shall
be entitled to a consolidated payment of
Rupees fifty thousand only (Rs.50,000) from
the Respondents in satisfaction of these
claims and the same shall be paid accordingly
in addition to the payments already made. The
Claimants on receipt of such payment shall
have no lien whatsoever on the sheds, goods of
whatever description and materials lying at
the site of the work and said to belong to
them. Claims 8, 9, 10, 11 & 12--These five
claims are declined.
Claim No. 13--The retention amounts from the
bills of the Claimants lying in the hands of
the Respondents shall be released to them.
Claim No. 14--An amount of Rupees two lakhs
only (Rs.2,00,000 shall be paid to the claim-
ants in settlement of the final claims on the
work in addition to the specific items re-
ferred to in the other claims as per this
award.
Claim No. 15--The Security offered by the
Claimants for this work shall be released to
them subject to the rules regarding tax clear-
ance.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 18
Claim No. 16--The claim for interest is de-
clined.
Claim No. 17--The parties shall suffer their
respective costs in these proceedings."
Regarding the counter claims, it was reiterated by the
arbitrator that the respondents were entitled to arrange for
the balance work in any manner they deemed fit on the termi-
nation of the contract by
676
them. But the appellant should not be responsible for any
loss that might be sustained for this re-arrangement. The
counter claim for costs of the respondents was also dealt
with.
There was a third award dated 23.4.1982 which was in
respect of the sum due to Blocks Nos.7, 8 & 11. In respect
thereof an estimate of Rs.69.7 lakhs had been sanctioned for
the work and it was entrusted to the appellant. The value of
the work arranged on that contract was Rs.63.68 lakhs as per
the departmental estimate which the claimants undertook to
carry but at a total amount of Rs.71.96 lakhs as per their
tender. After reiterating that time was of the essence of
the contract, the difficulties that arose in carrying out
the contract and the respective contentions, which were
identical with those in respect of the first two contracts
were discussed. In respect of interruptions in power supply
the case of the respondent was that such interruptions were
not unexpected at a site through which the power lines
passed through virgin reserve forest and that the claimants
had not been assured by the respondents of uninterrupted
power and in any case there was hardly any item of machinery
belonging to the claimant which could have remained idle for
want of power. In respect of the medical facilities it was
submitted by the respondents that according to the terms of
the contract it was the primary, duty of the appellant to
provide for medical assistance to their work force. After
setting out the rival contentions the arbitrator awarded as
follows:
"Claim No. (1)(A)--The claim for additional
payment on account of aslar work is declined.
Claim No. (1)(B): The respondents shall pay
the claimants an additional amount of rupees
seventy five thousand only (Rs.75,000) in
satisfaction of this claim over and above the
amounts already paid by them in the various
part bills.
Claim No. (1)(C): The claim for compensation
on account of loss of hire charges and short-
age of rubble is declined.
Claim No. 2: The respondents shall pay the
claimants a sum of Rupees three lakhs and
seventy five thousand only (Rs.3,75,000) in
satisfaction of this claim.
Claim Nos. 3 & 4: These two claims are de-
clined.
Claim No. 5: The respondents shall pay the
claimants an
677
increase of Forty (40) per cent in the agreed
rates for agreed items and rate derived from
the agreement for extra items for all work
paid for after CC 2 and part, such increase
being worked out on the cost of the work
excluding the value of materials supplied by
the respondents.
Claim No. 6: the claimants shall be entitled
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 18
to a payment of rupees twenty five thousand
only (Rs.25,000) in satisfaction of this claim
and the respondents shall pay it accordingly.
Claim No. 7(a)(b) & (c): The claimants shall
be entitled to a consolidated payment of
rupees fifty thousand only (Rs.50,000) from
the respondents in satisfaction of these
claims and the same shall be paid accordingly
in addition to the payments already made. The
claimants on receipt of such payment shall
have no lien whatsoever on the sheds, goods of
whatever description and materials lying at
site of the work and said to belong to them.
Claims Nos. 8, 9, 10, 11 & 12: These five
claims are declined.
Claim No. 13: The retention amounts from the
bills of the claimant lying in the hands of
the respondents shall be released to them.
Claim No. 14: An amount of rupees fifty thou-
sand only (Rs.50,000) shall be paid to the
claimants in settlement of the final claims on
the work in addition to the specified items as
per this award.
Claim No. 15: The security offered by the
claimants for the work shall be released to
them subject to the rules regarding tax clear-
ance.
Claim No. 16: The claim for interest is de-
clined.
Claim No. 17: The parties shall suffer their
respective costs in these proceedings."
About the counter claims it was also stated that the
claimants would not be responsible to carry out the balance
work which the
678
respondents might arrange in any manner they thought fit on
termination of the contract, but it should not be at the
risk of the claimants.
Upon these awards, an application was made before the
Court of the Principle Sub-Judge, Trivandrum, for passing
decrees’ in terms of the award. Objections were also filed.
The learned Judge by his judgment and order dated 25th
September, 1982 dealt with the objections. He rejected the
contention that the claims were barred. He further held that
it was not necessary for the arbitrator to give reasons for
his award; and that there was no provision under the law
which required that the arbitrator should furnish reasons
for the award. It was submitted before him that the arbitra-
tor ought to have given separate findings for the issues
under claim No. 4 as the issues raised were entirely inde-
pendent of each other. It was submitted that under sub-claim
(a) in claim No. 4 the appellant had claimed loss on account
of the pressure tactics adopted by the labourers. Under
sub-claim (b) the appellant had claimed compensation for the
extra works done. In the statement of defence filed by the
respondents it was more or less conceded that the claim for
extra works would lie, and stated that the actuals should be
accounted and paid along with the final bill. The learned
judge noted that the arbitrator could only give a lump sum
award with respect to various claims and that he need not
quantify the sum awarded under each claim separately. It was
contended before the learned Sub-Judge that in respect of
claim No. 5, there was no evidence to support the claim.
Under that claim the appellant had detailed the value of
tools, plants and materials etc. that were left by him at
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 18
the site. In the defence statement itself the respondent
admitted that some materials belonging to the appellant were
taken possession of by them and the value thereof would be
paid in the final bill. Therefore, according to the learned
judge, it was not correct to say that there was no evidence
at all for allowing claim No. 5. Further,it was held that
there was no jurisdiction to investigate into the merits of
the case and to examine the documentary and oral evidence
for the purpose of finding out whether or not the arbitrator
had committed an error of law or fact. The learned judge
reiterated that the arbitrator had not incorporated in the
award any materials for his conclusion nor did he incorpo-
rate the terms of the contract between the parties. Under
such circumstances the award could not be set aside espe-
cially when there was no error apparent on the face of it;
and there was nothing to show that the arbitrator had mis-
conducted the proceedings or that the award had been improp-
erly procured. So the objection was repelled. In the prem-
ises the judgment in terms of the award was passed. In
respect of the three awards, three different judgments were
679
delivered incorporating more or less the same reasons.
Being aggrieved thereby the respondent preferred appeals
before the High Court. The Division Bench of the High Court
by the judgment under appeal in F.M.A. Nos. 72, 346 and 380
of 1983 disposed of the appeals.
Being aggrieved thereby, the appellant is before this
Court. In the judgment under appeal, the Division Bench of
the High Court has set out the claims and noted the rival
contentions and referred to the various clauses and the
conditions of the contract, though the contract itself was
made no part of the award. The Division Bench referred to
the decision of the learned Sub-Judge. Before the Division
Bench, the main contention which succeeded was that there
were errors apparent on the face of award, and further that
the arbitrator had misconducted himself and travelled beyond
the terms of the contract. On behalf of the appellant,
however, it was contended that the award was a nonspeaking
award and, hence, it was not open for the court to go into
the correctness of the reasons of the award. The High Court
referred to the several decisions of this Court and other
relevant decisions of the Kerala High Court. In order,
however, to appreciate the contentions, it is necessary to
refer in detail to the judgment under appeal. The High Court
referred to the various clauses of the contract which were
produced before the High Court. The submissions were made on
behalf of the respondents .that the claims allowed were
beyond and contrary to the agreement between the parties.
The High Court noted that the arbitrator had allowed claims
Nos. 1(b), 2, 5, 7(a), 7(b), 7(c), 13, 14 2 15 and had
passed an award for payment of an amount of Rs.31.15 lakhs
to the claimant towards his claim under the several heads
mentioned therein. The High Court noted the judgment of the
learned Sub-Judge. It was held by the learned Sub-Judge that
the court could set aside an award only when it was the
result of corruption, fraud or there were errors apparent on
the face of the award. According to the learned Sub-Judge
there was no error apparent on the face’ of the award and
there was no allegation of fraud. Thereafter, the different
points on which the learned Sub-Judge rested his decision,
were noted by the High Court. It was contended before the
High Court on behalf of the respondents that there were
errors apparent on the face of the award, and that the
arbitrator had misconducted himself and travelled beyond the
terms of the contract.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 18
The first contention urged on behalf of the respondents,
however, was that the award was a non-speaking award and,
there-
680
fore, it was not open to the court to go into the correct-
ness or reasonableness of the award. The High Court held
that when the arbitrator was constituted the sole and final
judge of all questions both of law and of facts, normally
his decision should stand final and it was only when there
was any error apparent on the face of the award either
because a question of law arose on the face of the award or
upon some paper accompanying or forming part of the award,
it could be interfered with. Thereafter, the High Court in
para 8 of its judgment observed that in the light of several
decisions it could say that there were any errors apparent
on the face of the award, and that the arbitrator had mis-
conducted himself and had travelled beyond his power. The
High Court referred to the decision of the Division Bench of
the Kerala High Court in State of Kerala v. Poulose, [1987]
1 KLT 781. The High Court, thereafter, observed that it was
not open to the arbitrator or the umpire to arrogate tO
himself jurisdiction and answer a question not referred to
him. In this connection, reference was made by the High
Court to several decisions, namely, Attorney General for
Manitoba v. Kelly and Ors., [1922] 1 AC 268; Upper Ganges
Valley Electricity Supply Co. Ltd. v. U.P. Electricity
Board, [1973] 3 SCR 107; M/s Alopy Parshad & Sons, Ltd. v.
The Union of India, [1951] 2 SCR 793 and Jivarajbhai Ujamshi
Sheth & Ors. v. Chintamanrao Balaji & Ors., [1964] 5 SCR480.
Regarding claim No. 1(b) it was the contention of the
respondent that the award was over and above the amounts
already paid under various part bills. It was argued before
the High Court that the Department had measured and paid for
all quantities of earth work and ruble work and the same had
been entered in the measurement book and accepted by the
contractor. Hence, the award of additional amount was unwar-
ranted. It was also argued that as per clause 10 of Form No.
83 (Notice inviting tender) which formed part of the agree-
ment, every tenderer was expected to inspect the site of the
proposed work and quarries, and satisfy himself about the
quality and availability of materials. It was also notified
in the same clause that the Govt. would not, after accept-
ance of the contract rate, pay any extra charges for lead or
any other reason in case the contractor was found later on
to have mis-judged the materials available. It was also
notified that the Department would not be liable for any
claim raised later on the plea of non-access to the site.
Ext. R2 was a copy of extract of Clause 10 of Form No. 83.
It was argued that the award of Rs.75,000 under claim 1(b)
was beyond the powers of the arbitrator. The High Court held
that the award on this aspect was beyond the provisions of
the agreement, and therefore there were errors apparent on
the face of the award.
681
Similarly, in respect of the claim for Rs.3,75,000 under
claim No. 2, it was contended on behalf of the respondents
that this was beyond the powers of the arbitrator and, as
such, there were errors apparent on the face of the award.
It was argued by him that clause No. 2 of the general speci-
fication and special conditions of the contract clearly
notified to the tenderers the site of the dam. It was also
contended by the Govt. Pleader that the period during which
the contractor had conveyed sand through Madukkarai, the
claimant had been actually paid additional conveyance
charges. Hence, after construing clause 10 of Form No. 83,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 18
namely, notice inviting tender, the High Court held that it
was necessary for the contractor to have inspected the site
before tender. Therefore, in awarding, the amount as the
arbitrator did on this head, there was error apparent on its
face and such award was liable to be set aside. The High
Court did so accordingly.
With regard to claim No. 5, it was contended that the
claim was beyond the powers of the arbitrator and reference
was made to clause 6(6)111 of the General Specification and
Special Conditions which stated that the Department was not
responsible for supply of uninterrupted electric supply, so
any damage on that basis was also unwarranted. The finding
on this issue found in the award was set aside.
Similarly, in connection with claim No. 6, there was a
claim for Rs.24,000 towards expenses for providing a perma-
nent doctor. It was held to be contrary to Clause 7 of (IV)
of the contract dealing with camp facilities--medical aid
etc. which, according to the high Court, indicated that the
contractor himself was responsible for providing medical
facilities to the contract labourers and that the respond-
ents were not bound to pay any additional medical expenses.
The claim on this construction and view of the contract, was
held to be not sustainable.
The arbitrator had awarded Rs.50,000 by way of damages
for sheds and other materials left by the contractor at the
site under claim No. 7. It was held by the High Court that
it was the duty of the contractor to remove the sheds and
materials brought by him and, therefore, the award allowing
such claim was definitely against the provision of the
contract. On this head it was held that the award by the
arbitrator was contrary to the provision of the agreement
and as such bad.
Regarding claim No. 14 for an additional amount of Rs.50,000
it
682
was held that it was unsustainable and due to the misconduct
of the arbitrator that it was awarded. It was further ob-
served that it was beyond the power of the arbitrator as it
was against the provisions of the contract.
While dealing with that part of the award which exoner-
ated the contractor from the risk after holding that the
termination of the contract by the respondent was valid, it
was held that the same was opposed to the provisions of the
agreement. The direction to release the amount and release
of security deposit without taking into account the liabili-
ty to account for the loss on re-arrangement of work amount-
ed to errors apparent on its face. In the aforesaid light,
the High Court held that the award under claims Nos. 1(b),
2, 5, 6 & 7 and also the award of an additional sum of
Rs.50,000 under claim No. 14 over and above the claim al-
lowed was against the terms of the contract and, therefore,
liable to be set aside.
Similarly, in M.F.A. No. 346/82, the High Court went
into the details of the claims and on the construction of
the contract, came to the conclusion that the termination of
the contract was legal and that the exoneration of the
contractor from the risk and losses was opposed to that
finding. In the aforesaid light, the High Court set aside
several claims as mentioned in the judgment on the award. On
similar or, more or less, identical grounds several items of
MFA No. 380/83, were set aside.
One of the claims under claim No. 4 was the award of
Rs.96,000. The High Court found that it was under clause
20(5) of the General Specification and Special Conditions of
the contract, which stated that the Department would not be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 18
liable to pay any damages or compensation for hold up caused
by intervention of the court, labour strike or any other
extraneous forces and therefore and award under claim No. 4
on the ground of labour unrest and extra work, suffered from
being erroneous and was liable to be set aside. The clause
of the contract covered only situations of labour strike and
not labour unrest.
It was submitted before us that the High Court had
exceeded its jurisdiction in acting in the manner it did on
these aforesaid aspects. The first question, therefore, that
arises for consideration in this case is, whether the award
in question was a speaking award or not. In our opinion, the
award was not a speaking award. An award can also be set
aside if the arbitrator had misconducted himself or the
proceedings or had proceeded beyond his jurisdiction. These
are separate and district
683
grounds for challenging an award. Where there are errors
apparent on the face of the award it can only be set aside
if in the award there is any proposition of law which is
apparent on the face of the award, namely, in the award
itself or any document incorporated in the award. The Judi-
cial Committee in Champsey Bhara & Co. v. Jivraj Balloo
Spinning & Weaving Co, Ltd., L 1922 IA 324 has discussed
this problem. It was held that an award of arbitration can
be set aside on the ground of error of law apparent on the
face of the award only when in the award or in a document
incorporated with it, as for instance a note appended by the
arbitrator stating the reasons for his decision, there is
found some legal proposition which is the basis of the award
and which is erroneous. In that case the appellants had sold
cotton to the respondents by a contract which contained a
submission to arbitration of disputes as to quality, and a
further clause submitting to arbitration all other disputes
arising out of the contract. Cotton was delivered, but the
respondents objected to its quality, and upon arbitration an
allowance was awarded; the respondents thereupon rejected
the cotton. The appellants claimed damages for the rejec-
tion, and upon that dispute being referred to arbitration
under the further clause, were awarded damages. The award
recited that the contract, the date and subject of which
were stated, was subject to the rules of the Bombay Cotton
Trade Association, which were not further referred to; and
that the respondents had rejected on the grounds contained
in a letter of a certain date. That letter stated merely
that as the arbitrators had made an allowance of a certain
amount the respondents rejected the cotton. The High Court
set aside the award, holding that it was bad on its face, in
that under one of the rules of the Association the respond-
ents were entitled to reject without liability. It was held
by the Judicial Committee that the award could not be set
aside; the terms of the contract were not so incorporated
with the award as to entitle the Court to refer to them as
showing, either that the award was wrong in law, or that
under them the contract, and therefore the jurisdiction of
the arbitrators, were terminated. This decision and the
ratio on this proposition of law has always been accepted by
the courts of this country and is well-settled.
The next question on this aspect which requires consid-
eration is that only in a speaking award the court can look
into the reasoning of the award. It is not open to the court
to probe the mental process of the arbitrator and speculate,
where no reasons are given by the arbitrator, as to what
impelled the arbitrator to arrive at his conclusion. See the
observations of this Court in Hindustan Steel Works Con-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 18
struction Ltd. v. C. Rajasekhar Rao, [1987] 4 SCC 93. In the
in-
684
stant case the arbitrator has merely set out the claims and
given the history of the claims and then awarded certain
amount. He has not spoken his mind indicating why he was
done what he has done; he has narrated only now he came to
make the award. In absence of any reasons for making the
award, it is not open to the court to interfere with the
award. Furthermore, in any event, reasonableness of the
reasons given by the arbitrator, cannot be challenged.
Appraisement of evidence by the arbitrator is never a matter
which the court questions and considers. If the parties have
selected their own forum, the deciding forum must be conced-
ed the power of appraisement of the evidence. The arbitrator
is the sole judge of the quality as well as the quantity of
evidence and it will not be for the court to take upon
itself the task of being a judge on the evidence before the
arbitrator. See the observations of this Court in Municipal
Corpn. of Delhi v. M/s Jagan Nath Ashok Kumar & Anr., [1987]
4 SCC 497.
The same principle has been stated in M/s. Alopi Parshad
& Sons, Ltd. v. The Union of India, (supra). There this
Court held that the award was liable to be set aside because
of an error apparent on the face of the award. An arbitra-
tion award might be set aside on the ground of an error on
the face of it when the reasons given for the decision,
either in the award or in any document incorporated with it,
are based upon a legal proposition which is erroneous. But
where a specific question is referred, the award is not
liable to be set aside on the ground of an error on the face
of the award even if the answer to the question involves an
erroneous decision on a point of law. But an award which
ignores express terms of the contract, is bad. Similarly, in
Jivarajbhai Ujamshi Sheth & Ors. v. Chintamanrao Balaji &
Ors. (supra), this Court reiterated that an award by an
arbitrator is conclusive as a judgment between the parties
and the court is entitled to set aside an award if the
arbitrator has misconducted himself in the proceeding or
when the award has been made after the issue of an order by
the Court superseding the arbitration or after arbitration
proceedings have become invalid under section 35 of the
Arbitration Act or where an award has been improperly pro-
cured or is otherwise invalid under section 30 of the Act.
An award may be set aside on the ground of error on the face
of the award, but an award is not invalid merely because by
a process of inference and argument it may be demonstrated
that the arbitrator has committed some mistake in arriving
at his conclusion. The Court, however, went into the ques-
tion whether the arbitrator had included depreciation and
appreciation of certain assets in the value of the goodwill
which he was incompetent to include by virtue of the limits
placed upon his authority by the deed of
685
reference. The Court found that was not a case in which the
arbitrator had committed an error of fact or law in reaching
his conclusions on the disputed questions submitted for
adjudication. It was a case of assumption of jurisdiction
not possessed by him and that rendered the award to the
extent to which it was beyond the arbitrators’ jurisdiction,
invalid. This was reiterated by Justice Hidayatullah that if
the parties set limits to action by the arbitrator, then the
arbitrator had to follow the limits set for him and the
court can find that he exceeded his jurisdiction on proof of
such excess. In that case the arbitrator in working out net
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 18
profits for 4 years took into account depreciation of immov-
able property. For this reason he must be held to have
exceeded his jurisdiction and it is not a question of his
having merely interpreted the partnership agreement for
himself as to which the Civil Court could have had no say,
unless there was an error of law on the face of the award.
Therefore, it appears to us that there are two different and
distinct grounds involved in many of the cases. One is the
error apparent on the face of the award, and the other is
that the arbitrator exceeded his jurisdiction. In the latter
case, the courts can look into the arbitration agreement but
in the former, it can not, unless the agreement was incorpo-
rated or recited in the award. In Upper Ganges Valley Elec-
tricity Supply Co. Ltd. v. U.P. Electricity Board (supra),
the respondent had taken over the appellant’s undertakings,
but as the parties were at variance on the true market value
to be paid to the appellant, the matter was referred to
arbitration. As the arbitrators were unable to agree on the
question whether the appellant was entitled to compensation
for the ’service lines’ which were laid with the help of
contributions made by consumers, they referred the question
to the umpire. The umpire framed an issue and gave a finding
that the appellant was not entitled to claim from the re-
spondent the value of the position of the service lines
which were laid at the cost of the consumers, for the sole
reason that they were laid at the cost of the consumers. The
appellant filed an application under section 30 of the
Arbitration Act, 1940 challenging the validity of the award
on the question. The lower court and the High Court held
against the appellant. Allowing the appeal, it was held by
this Court that the appellant’s application for setting
aside the award could succeed only if there was any error of
law on the face of the award. There, it was found, that the
umpire had made a speaking award and there was no question
of the construction of any document incorporated in or
appended to the award. If it was transparent from the award
that a legal proposition which forms its basis is erroneous,
the award is liable to be set aside.
An award may be remitted or set aside on the ground that the
686
arbitrator in making it, had exceeded his jurisdiction and
evidence of matters not appearing on the face of it, will be
admitted in order to establish whether the jurisdiction had
been exceeded or not, because the nature of the dispute is
something which has to be determined outside award--whatever
might be said about it in the award or by the arbitrator.
See in this connection, the observations of Russell on The
Law of Arbitration, 20th Edn. 427. Also see the observations
of Christopher Brown Ltd. v. Genossenschaft Oesterreichisch-
er etc., [1954] 1 QB 8 at p. 10 and Dalmia Dairy Industries
Ltd v. National Bank of Pakistan, [1978] 2 Lloyd’s Rep 223.
It has to be reiterated that an arbitrator acting beyond his
jurisdiction--is a different ground from the error apparent
on the face of the award. In Halsbury’s Laws of England (4th
Edn. Vol. 2 para 622) one of the misconducts enumerated, is
the decision by the arbitrator on a matter which is not
included in the agreement or reference. But in such a case
one has to determine the distinction between an error within
the jurisdiction and an error in excess of the jurisdiction.
See the observations in Anisminic Ltd. v. Foreign Compensa-
tion Commission, [1969] 2 AC 147 and Regina v. Noseda,
Field, Knight & Fitzpatrick, [1958] 1 WLR 793. But, in the
instant case the court had examined the different claims not
to find out whether these claims were within the disputes
referable to the arbitrator, but to find out whether in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 18
arriving at the decision, the arbitrator had acted correctly
or incorrectly. This, in our opinion, the court had no
jurisdiction to do, namely, substitution of its own evalua-
tion of the conclusion of law or fact to come to the conclu-
sion that the arbitrator had acted contrary to the bargain
between the parties. Whether a particular amount was liable
to be paid or damages liable to be sustained, was a decision
within the competency of the arbitrator in this case. By
purporting to construe the contract the court could not take
upon itself the burden of saying that this was contrary to
the contract and, as such, beyond jurisdiction. It has to be
determined that there is a distinction between disputes as
to the jurisdiction of the arbitrator and the disputes as to
in what way that jurisdiction should be exercised. There may
be a conflict as to the power of the arbitrator to grant a
particular remedy. See Commercial Arbitration by Sir N.J.
Mustil and Stewart C. Boyd page 84.
The High Court in the judgment under appeal referred to
the decision of the Division Bench of the Kerala High Court
in State of Kerala v. Poulose, (supra). Our attention was
also drawn to the said decision by the counsel for the
respondents that if an arbitrator or the umpire travels
beyond his jurisdiction and arrogates jurisdiction that does
not vest in him, that would be a ground to impeach the
award. If
687
an arbitrator, even in a non-speaking award decides contrary
to the basic features of the contract, that would vitiate
the award, it was held. It may be mentioned that in so far
as the decision given that it was possible for the court to
construe the terms of the contract to come to a conclusion
whether an award made by the arbitrator was possible to be
made or not, in our opinion, this is not a correct proposi-
tion in law and the several decisions relied by the learned
Judge in support of that proposition do not support this
proposition. Once there is no dispute as to the contract,
what is the interpretation of that contract, is a matter for
the arbitrator and on which court cannot substitute its own
decision.
Reference was also made to the decision in State of
Kerala v. Raveendranathan, [1987] 1 KLT 604. Insofar as the
court held therein that an arbitrator deciding a dispute
under the contract, is bound by the contract, the court is
right. The court cannot, however, substitute the decision of
the arbitrator as to what was meant by the contract, once
that dispute is conceded to the arbitrator. In so far and to
the extent the aforesaid decision of the Kerala High Court
decided to the contrary, the same is not the correct law.
The Kerala High Court in certain decisions relied on
certain authorities of England. In a decision of the House
of Lords in F.R. Absalom, Ltd. v. Great Western (London)
Garden Village Society, Ltd., [1933] AC 592 it was held that
the arbitrator had erred in his construction of clause 30 of
the contract. But as the judgment of Lord Warrington at page
600 of the report, made it quite clear that the arbitrator
had recited the terms of clause 32 of the contract in the
award, and thereafter on the construction of that clause,
the court decided that the arbitrator had misconstrued the
effect thereof. That was a case where dispute was not within
the contract. In Heyman & Anr. v. Darwins, Ltd., [1942] AC
356 the controversy was entirely different. Similarly, in
Attorney General for Manitoba v. Kelly & Ors., (supra), upon
which the High Court in the judgment under appeal referred
was again in a different context. There, in an action in
Manitoba against building contractors to recover sums im-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 18
properly paid to them under a contract, and for damages, a
judgment by consent was entered whereby it was provided,
inter alia, that the plaintiff should recover, among other
sums, "all loss to the plaintiff by reason of defective
workmanship and materials", and that these should be set off
against the sums recovered by the plaintiff the fair value
of the work done and materials provided at fair contractor’s
prices. The judgment, however, provided further that the
sums to be debited and
688
credited were to be determined by two appraisers, and that
any matter upon which they differed was to be referred to a
named umpire whose decision thereon was to be final; and
that the Manitoba Arbitration Act should not apply. The
defendants moved to set aside or vary an award. It was held
that under the words "all loss" there was jurisdiction to
award to the plaintiff not only sums actually expended, but
also a sum estimated as being necessary to make good the
defects, and that extrinsic evidence was not admissible to
show that the sum allowed to the defendants as set-off had
been reduced in respect of defective work for which they had
also been debited. Further, it was held that the award being
within the jurisdiction conferred by the submission, and
there being no error apparent on its face, it could not be
questioned either on the facts or on the law.
In the instant case, the High Court seems to have fallen
into an error of deciding the question on interpretation of
the contract. In the aforesaid view of the matter we are of
the opinion that the High Court was in error. It may be
stated that if on a view taken of a contract, the decision
of the arbitrator on certain amounts awarded, is a possible
view though perhaps not the only correct view, the award
cannot be examined by the court in the manner done by the
High Court in the instant case.
In light of the above, the High Court, in our opinion,
had no jurisdiction to examine the different items awarded
clause by clause by the arbitrator and to hold that under
the contract these were not sustainable in the facts found
by the arbitrator.
These appeals are, therefore, allowed. The judgment and
order of the High Court are set aside and the orders of the
learned Sub Judge are restored. In the facts and the circum-
stances of the case, however, the parties will bear their
own costs.
P.S.S. Appeals al-
lowed.
689