Full Judgment Text
1
Non-Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs.7222-7223 OF 2012
[Arising out of SLP (Civil) No. 15029-15030 of 2007]
Executive Engineer LVP Division, Wardha .... Appellant
Versus
Maroti Bapurao Auchat & Others .... Respondent(s)
J U D G M E N T
K.S. Radhakrishnan, J.
1. Leave granted.
JUDGMENT
2. The first respondent herein filed Regular Civil Suit No.109 of
1995 praying for the grant of permanent injunction against the
appellant – Executive Engineer, Lower Vanna Project Division No.1,
Wardha and also for a direction to restore the land to him. It was
alleged that the defendants had undertaken the construction of the
canal of Lower Vanna Project through the middle portion of the
Page 1
2
plaintiff’s field, consequently a mandatory injunction was sought for
to restore the land prior to the commencement of constructing the
canal. The plaintiff alleged that the same was done to favour a
| at his la | nd could |
|---|
decreed and the defendants took up the matter in appeal which was
dismissed and the matter was carried to the High Court. The High
Court also dismissed the appeal on merits. The High Court in his
order stated as follows:
“I have carefully perused the documents
produced by the appellant before the first appellate
court. The submission made on behalf of the
respondent No.1 that these documents do not
disclose that the Government proposed to construct
the canal through the middle portion of the field of
respondent No.1 is acceptable and correct. Both
the Courts have considered the original plan/map
which was received from the custody of the
appellants before the trial court to hold that the
appellants had not proceeded with the construction
work of the canal as per the original map. The
Courts have further considered the other
voluminous evidence on record to hold that the
plaintiff was entitled to the grant of permanent and
mandatory injunction as sought for.
JUDGMENT
As already mentioned hereinabove, the
documents placed by the appellants before the first
appellate court merely relate to the acquisition of
Page 2
3
0.7R of land belonging to the plaintiff/respondent
No.1 but, none of the documents show the location
through which the canal was to be constructed as
per the original map.”
arose for consideration, in our view rightly. The matter came up for
hearing before this Court. This Court passed an order on
9.10.2009 which reads as follows:
“Petitioner’s counsel seeks four weeks’ time to
produce:
(1)the plan showing the original sanctioned alignment;
(2)the plan showing the actual alignment;
(3)the plan superimposing the actual alignment over the
sanctioned alignment to highlight the difference;
JUDGMENT
(4)the photographs of the land;
(5)the extent of bifurcated land on either side of canal in
survey No.174;
(6)the protective measures proposed by petitioner to
ensure that the unacquired portion of the land can
be made cultivable by avoiding seepage.
It is open to the petitioner to directly make an
offer of Rs.5 lakhs as compensation in lieu of
dismantling and fresh construction of canal without
prejudice.”
Page 3
4
4. When the matter came up for final hearing, learned counsel
appearing for the appellant brought before us a communication
| he office | of the E |
|---|
as follows:
“With reference to above cited subject under
caption, it is to inform you that if the Umra
Distributory of Lower Vanna Project is made close
for irrigation @ Survey No. 174 of Shri Maroti
Awachat as per order of the High Court then the
1019.34 Hq. of land and 635 No. of farmers will be
deprived from benefits of irrigation. Also length of
distributory ahead from Survey No. 174 will not be
useful for irrigation purpose.”
5. We notice if the alignment is now changed and Umra
JUDGMENT
Distributory of Lower Vanna Project stands closed for irrigation, it
would affect 1019.34 Hr of land and 635 numbers of farmers would
be deprived of the benefits of irrigation. But all the same, the
respondents have to be adequately compensated. The amount of
Rs.7.5 lakhs, in our view, would be an adequate compensation for
the illegality committed by the appellant. Consequently, we direct
Page 4
5
the appellant to pay Rs.7.5 lakhs to the respondents within the
period of two months from today which will settle all the disputes
pending between the parties. The appeals are disposed of as above.
| e is modi | fied acco |
|---|
disposed of with the above directions with no order as to costs.
……………………………….J.
(K.S. Radhakrishnan)
..………………………………J.
(Dipak Misra)
New Delhi,
October 4, 2012
JUDGMENT
Page 5