Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
| of SLP(C | ) Nos.149 |
|---|---|
| tion Comp | any |
| … A | |
| M/s Kaikara Construction Company<br>VERSUS<br>State of Kerala and Ors.<br>J U D G M E N T<br>Sudhansu Jyoti Mukhopadhaya, J.<br>Leave granted.<br>2. These appeals are directed against<br>passed by the High Court of Ker<br>Arbitration Request No.39 of 2009. By |
and Conciliation Act, 1996 for appointment of arbitrator has
JUDGMENT
been rejected by the High Court.
The factual matrix of the case is as follows:
3.
On 27.1.2005, the appellant submitted tender, which was
accepted by the respondents on 21.7.2005. The possession of
the work site was handed over to the appellant on 2.9.2005.
The period for completion of the contract expired on 1.9.2007.
The case of the appellant is that the Company had completed a
major part of the work. This was disputed by the respondents.
According to them, only 41% of the work was completed as on
Page 1
2
22.12.2007, based on the original contract price. Based on the
revised contract price, the progress achieved was only 30% as
on 22.12.2007; the work carried out from 22.12.2007 to
1.3.2009 was only 12% as against 70% target.
| e appella | nt, a su |
|---|
respondents. As a condition for releasing the amount, the
appellant was compelled to execute a supplemental agreement.
The appellant sought extension of the period for completion
of the work which was granted up to 1.3.2009. On 7.3.2009,
the appellant requested for appointment of a ‘Dispute Review
Expert’ as stipulated in the General Conditions of Contract.
On 9.5.2009, the appellant again made a request for
appointment of ‘Dispute Review Expert’ and also for extension
of the "intended completion period". Another letter dated
10.6.2009 was written by the appellant to the Chairman of the
Council of Indian Roads Congress with similar prayer to
JUDGMENT
appoint a ‘Dispute Review Expert’ as stipulated in Clause
36.1 of ITB forming part of the agreement without any delay,
with due intimation to the appellant in writing.
On 7.08.2009, the Indian Roads Congress addressed a
letter to the Chief Engineer, PWD National Highways,
Thiruvananthapuram to inform about the appointment of Dispute
Review Expert. On 6.10.2009, the Indian Roads Congress wrote
another letter to the Chief Engineer, Ministry of Road
Transport & Highways, New Delhi requesting him to inform
Page 2
3
about the appointment of Dispute Review Expert. However, no
reply was given to the appellant.
4. In this background, the appellant moved before the High
Court under Section 11 (6) of the Arbitration and
| 96 for a | ppointme |
|---|
dated 19.07.2010 dismissed the request holding that no
arbitration agreement exists.
Review Petition filed by the appellant was also rejected
5.
by order dated 2.02.2011.
6. The appellant relied upon Clauses 24 and 25 of the
Standard Bidding Document which forms part of the contract
and read as follows:
" 24. Disputes
24.1 If the Contractor believes that a
decision taken by the Engineer was either outside
the authority given to the Engineer by the Contract
or that the decision was wrongly taken the decision
shall be referred to the Dispute Review Expert
within 14 days of the notification of the
Engineer's decision.
JUDGMENT
25. Procedure for Disputes .
25.1. The Dispute Review Expert (Board)
shall give a decision in writing within 28 days
of receipt of notification of a dispute.
25.2 The Dispute Review Expert (Board) shall
be paid daily at the rate specified in the Contract
Data together with reimbursable expenses of the
types specified in the Contract Data and the cost
shall be divided equally between the Employer and
the Contractor, whatever decision is reached by the
Dispute Review Expert. Either party may give notice
to the other to refer a decision of the Dispute
Review Expert to an Arbitrator within 28 days of
the Dispute Review Expert's written decision. If
neither party refers the dispute to arbitration
within the next 28 days, the Dispute Review
Page 3
4
Expert's decision will be final and
binding.
25.3 The arbitration shall be conducted in
accordance with the arbitration procedure stated in
the Special Conditions of Contract."
| ure has b<br>3 of the | een stip<br>Standard |
|---|
8. It appears that appellant by letter dated 11.8.2009
requested the Superintending Engineer, National Highway,
Central Circle, Kochi, to agree to the appointment of a sole
arbitrator mentioned in the letter. But no reply was given.
9. The respondents in their counter affidavit opposed the
prayer and contended that if arbitration is the mode of
settlement of disputes, the names of Dispute Review Experts
are to be specifically mentioned in the contract data, which
was not done in the present case. In the contract entered
into between the parties on 25.08.2005, there was a specific
clause which reads as follows:
JUDGMENT
"The parties to this contract agree and undertake
the condition that arbitration shall not be a means
of settlement of dispute or claims or anything on
account of this contract."
10. It was contended on behalf of the respondents that in
absence of nomination of Dispute Review Expert, there is no
valid arbitration agreement.
11. Learned counsel for the appellant relied upon decision
of this Court in M.K. Abraham and Company v. State of Kerala
Page 4
5
and another, (2009) 7 SCC 636. In the said case, the Court
noticed that a letter dated 28.9.1994 was issued by the
Ministry of Surface Transport, Government of India informing
all the State Public Works Departments and all Chief
| e States | dealing |
|---|
be followed for appointment of arbitrators was to be
incorporated in the bidding conditions for the National
Highway works and that the arbitration clause should be
compulsorily made part of the bidding conditions in the
respective states. In said case, this Court noticed the
aforesaid letter dated 28.08.1994 and Clauses 24 and 24(a) of
the notice inviting tenders for works as printed in the
standard form of agreement executed between the parties and
observed as follows:
In the present case, as noticed above, the
“24.
contract consists of a typewritten contract agree-
ment between the appellant and the second respon-
dent [which does not contain any terms and condi-
tions, but which merely states that the contract is
for execution of the described work as per the ac-
companying articles of agreement, plan, specifica-
tion and conditions of contract approved by the
Project Director (SE), National Highway (ADB), Cir-
cle Adappally, Cochin] with several printed forms
with cyclostyled additions as annexures and hand-
written corrections. The printed form of articles
of agreement has an attachment slip.
JUDGMENT
25. The contract in the present case does not
contain any handwritten terms in regard to arbitra-
tion. The contract has printed clauses barring ar-
bitration [Clauses 24 and 24( a ) of the notice
inviting tenders for works and a preamble clause
and Clause 3 in the articles of agreement]. A cy-
clostyled slip signed by both parties containing
the words “arbitration clause as per the Ministry
Page 5
6
of Surface Transport’s Letter No. RW/NH-34041/3/94-
DO-III dated 28-9-1994 will be applicable” is at-
tached to the printed articles of agreement.
By applying the well-settled principles re-
26.
lating to construction of contract the following
position will emerge:
| s of the<br>he terms | article<br>of noti |
|---|
( ii ) the term contained in the cyclostyled at-
tachment to the printed form of articles of agree-
ment will prevail over the terms of the printed ar-
ticles of agreement.
Consequently, the contents of the attachment slip
to the printed form of articles of agreement pro-
viding for arbitration will prevail over the bar on
arbitration contained in the notice inviting ten-
ders for works and the articles of agreement. As a
result, it has to be held that there is a provision
for arbitration in regard to the disputes between
the respective appellant and the respondents.”
However, the High Court distinguished the case relied
upon by the appellant.
In the letter of acceptance dated 21.07.2005, the
12.
Superintendant Engineer intimated the appellant the
JUDGMENT
acceptance of the offer given by the appellant at paragraph 9
therein, it was specifically mentioned that all terms and
conditions of notice inviting tenders and tender documents
shall be binding on the said contract and the contractor. In
the bidding document supplied to the appellant by respondent
no.3 arbitration clauses were incorporated at clause 25 and
25.3 as noticed above. At Clause 36 the provisions of Dispute
Review Expert was mentioned as follows:
“ 36. Dispute Review Expert
Page 6
7
| as not a<br>eview E<br>e appoint | greed on<br>xpert,<br>ed by th |
|---|
In the agreement clause (3) it was mentioned that the
13.
parties to the contract agreed and undertake the conditions
that arbitration shall not be means of settlement of disputes
or claims or anything on account of the said contract.
14. The case was heard and judgment was reserved.
Subsequently, parties have filed joint application showing
the name of the arbitrator mutually agreed to by the parties
as under:
“Hon. Justice Mr. K. John Mathew
Former Judge of the Hon. High Court of Kerala,
Veekshanam Road, Kochi, 682018
Kerala State
JUDGMENT
Sd/-
Advocate for the Petitioner
Babu Thomas K
For Rabin Maujumdar
Sd/-
Adv. M T George
Advocate for the respondents”
In view of stand taken by the parties and as they
15.
mutually agreed for arbitration by retired Hon’ble Judge of
the Kerala High Court, without going into the question of
Page 7
8
th
merit, we set aside the impugned order dated 19 July, 2010
and refer the matter to Hon’ble Mr. Justice K. John Mathew
(retired). The parties will negotiate and settle the terms
and conditions of arbitration. It is expected that the
| ng will b | e conclu |
|---|
observations. No costs.
…………………………………………………………………….J.
(SUDHANSU JYOTI MUKHOPADHAYA)
…………………………………………………………………….J.
(DIPAK MISRA)
NEW DELHI,
JULY 01, 2014.
JUDGMENT
Page 8
ITEM NO.1A COURT NO.6 SECTION XIA
(For Judgment)
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Civil Appeal No(s). …......../2014
(@ SLP (C) Nos. 14947-14948/2011)
M/S. KAIKARA CONSTRUCTION CO. Appellant(s)
VERSUS
STATE OF KERALA AND ORS. Respondent(s)
Date : 01/07/2014 These appeals were called on for pronouncement
of Judgment today.
JUDGMENT
For Appellant(s) Mr. Rabin Majumder ,Adv.
For Respondent(s) Mr. M. T. George ,Adv.
Hon'ble Mr. Justice Sudhansu Jyoti Mukhopadhaya pronounced
the reportable judgment of the Bench comprising His Lordship and
Hon'ble Mr. Justice Dipak Misra.
Page 9
The appeals are allowed in terms of the signed reportable
judgment.
(MEENAKSHI KOHLI) (USHA SHARMA)
COURT MASTER COURT MASTER
[Signed reportable judgment is placed on the file]
JUDGMENT
Page 10