FOOD CORPORATION OF INDIA vs. ABHIJIT PAUL

Case Type: Civil Appeal

Date of Judgment: 18-11-2022

Preview image for FOOD CORPORATION OF INDIA vs. ABHIJIT PAUL

Full Judgment Text

REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS. 8572­8573/2022 ARISING OUT OF SLP (C) NOS. 16009­16010 OF 2019 FOOD CORPORATION OF INDIA & ORS.           ....APPELLANT(S) VERSUS ABHIJIT PAUL        …RESPONDENT(S) WITH CIVIL APPEAL NOS.8574­8579/2022 ARISING OUT OF SLP (C) NOS. 16063­16068 OF 2019 WITH CIVIL APPEAL NOS.8580­8581/2022 ARISING OUT OF SLP (C) NOS. 4045­4046 OF 2021 J U D G M E N T PAMIDIGHANTAM SRI NARASIMHA, J.  Leave granted. 1. 1 2. Food Corporation of India , the Appellant herein, procures and distributes foodgrains across the length and breadth of the country Signature Not Verified as a part of its statutory duties. In the process, it enters into many Digitally signed by Rajni Mukhi Date: 2022.11.18 16:46:28 IST Reason: contracts   with   transport   contractors.   In   one   such   contract,   the 1 hereinafter referred to as ‘Corporation’. Page 1 of 24 subject matter of present appeals, the Corporation empowered itself (under clause XII (a)) to recover damages, losses,  charges , costs and other expenses suffered due to the contractors’ negligence from the sums payable to them. The short question arising for consideration is   whether   the   demurrages   imposed   on   the   Corporation   by   the Railways can be, in turn, recovered by the Corporation from the contractors   as  “charges” recoverable   under   clause  XII   (a)  of  the contract. In other words, does contractors’ liability for “charges”, if any, include demurrages?  3. The Single Judge and the Division Bench of the High Court of Tripura have held that demurrages cannot be recovered as a charge by the Corporation. After examining the contract in its entirety, including its nature and scope, we conclude that the parties did not intend to include liability on account of demurrages as part and parcel of the expression “charges”. The liability of the contractors in the present contracts is clearly distinguishable from other contracts entered into by the FCI in 2010 and 2018, having a different scope and   objective.  Because   of   our   conclusions,   we   have   upheld   the judgments of the High Court and dismissed the appeals filed by the Page 2 of 24 Corporation. Before considering the submissions, analysis and the conclusions, we will refer to the necessary facts and contractual provisions.  4. There are three appeals. In the first set of appeals arising out of   Special   Leave   Petition   Nos.   16009­16010   of   2019,   the Corporation notified a Tender inviting a bid from road transport contractors   for   transporting   foodgrains   from   railway   siding, Churaibari   in   Assam,   to   Food   Security   Depot   Chandrapur   in Tripura,   on   a   regular   basis   for   a   period   of   two   years.   The Respondent   –   Mr.   Abhijit   Paul,   was   selected   as   the   successful 2 tenderer . He deposited an amount of Rs. 44,95,000/­ towards the 3 security   deposit,   leading   to   the   execution   of   the   contract .   The Corporation awarded several such Work Orders to the Respondent and   also   to   other   contractors   for   transportation   of   foodgrains between its multiple Food Security Depots. 5. The contract was discharged by performance by July 2014. More than a year thereafter, by a letter dated 22.12.2015 followed by   a   Notice   dated   29.11.2016,   the   Corporation   called   upon   the 2 hereinafter referred to as ‘contractor’. 3 Contract No. Cont.9/NEFR/TC/CBZ­CDR/2011 dated 25.04.2012, hereinafter referred to as ‘Work Order’ or the ‘contract’. Page 3 of 24 contractor to reimburse the amount of demurrages imposed on it by the Railways. As this demand was bereft of any reason and rightly objected to, it was followed by another letter dated 27.06.2017 by the Corporation. In this letter, the Corporation explained that it had incurred   heavy   losses   on   account   of   demurrages   due   to   the contractor’s inability to readily provide trucks at railway sidings, inhibiting the Corporation from unloading foodgrains from railway wagons   within   the   “free   time”   specified   by   the   Railways.   The Corporation sought to recover the demurrages from the contractor by withholding the security deposit tendered under the Work Order. 6. The contractor objected to this unilateral action, contending that there was no power to recover demurrages under the Work Order. Being unsuccessful in pursuing the Corporation to withdraw the letters, demand and the unilateral action, the contractor filed a 4 writ petition   before the High Court of Tripura for quashing the illegal and arbitrary action.   7. This writ petition was allowed by the Single Judge of High Court. It clarified that the Corporation was only entitled to recover 4 WP No. 1351 of 2016. Page 4 of 24 losses   that   were   incurred   due   to   the   contractor’s   dereliction   of duties under the contract, as permissible under Section 73 of the Indian Contract Act 1872, which provides for recovery of damages for the breach of a contract. This would not permit the recovery of losses   that   were   causally   distant   from   the   contractor’s   actions. Further, it held that the Corporation had unilaterally determined and imposed demurrages on the contractor, and directed it to settle its claims through a civil suit of recovery.  The Corporation filed a 5 writ appeal  and the Division Bench of the High Court by its order dated 07.09.2018 dismissed the same on the ground of delay. A 6 Review Petition  filed by the Corporation was also dismissed by the Division   Bench   of   the   High   Court   on   22.01.2019.   The   present appeals are against the orders in the writ appeal as well as in the review. The   second   set   of   civil   appeals   are   also   filed   by   the 8. Corporation.   It  arises   out  of  Special  Leave   Petition  Nos.  16063­ 16068 of 2019 and it impugns the decision of the Division Bench of the   High   Court   of   Tripura   dated   15.05.2019.   Therein,   the   High 5 Writ Appeal No. 56 of 2018. 6 Review Petition No. 02 of 2019. Page 5 of 24 Court similarly dismissed the writ appeals on the ground that the Corporation had no power to recover demurrages from contractors under the clauses of the contract therein.   9. The   third   set  of   civil   appeals,   arising   out   of   Special  Leave Petition Nos. 4045­4046 of 2021, are filed by the contractors. They have challenged the orders of the Division Bench of the High Court 7 of Tripura dismissing their writ appeals  and upholding the decision of the Single Judge of the High Court dated 25.11.2019, directing the contractors to avail alternative remedies.  10. Submission of Parties : Shri Neeraj Kishan Kaul, learned Senior Counsel   appearing   on   behalf   of   the   Appellant   started   his submissions   preempting   a   preliminary   objection   about   the dismissal of a Special Leave Petition against an adverse order of the 8 High Court on the same issue , and relatedly, about   not appealing another adverse decision of the High Court of Tripura on identical 9 10 issues .   Relying   on   State   of   Maharashtra   v.   Digambar ,   he submitted   that   the   dismissal   of   a   Special   Leave   Petition   at   the 7 Writ Appeals Nos. 186 of 2020 dated 04.01.2021 and 187 of 2020 dated 18.01.2021. 8  SLP No 3391 of 2018, dismissed  in limine  on 26.03.2018. 9 Writ Appeal Nos. 25­27 of 2016 (Tripura High Court) 10 (1995) 4 SCC 683. Page 6 of 24 admission stage did not operate as  res judicata.  He also explained that   the   Corporation   refrained   from   appealing   against   the aforementioned judgment of the High Court because the amount recoverable   therein   was   low.   Moreover,   in   those   cases,   the Corporation   had   already   issued   No   Dues   Certificates   to   the contractors.   11. Before proceeding any further, we make it clear here itself that we   do   not   propose   to   dismiss   the   Corporation’s   appeals   on preliminary   objections.   We   will   therefore   consider   Shri   Kaul’s submission on the merits of the case.  12. Referring to and relying on the contractual clauses, Shri Kaul submitted that the expression “charges” in clause XII (a) of the Work Order clearly includes demurrages, and the Corporation is empowered to recover the same. He relied on the decision of this 11 Court in  Raichand Amulakh Shah   and Anr.  v.  Union of India   and 12 Trustees of the Port of Madras  v.  Aminchand Pyarelal & Ors   to say that demurrages constitute a charge He also submitted that the .   11 (1964) 5 SCR 148. 12 (1976) 3 SCC 167. Page 7 of 24 13 Handbook used by Corporation  would demonstrate that “charges” certainly include “demurrage”.  13. Supplementing the above submissions, Shri Ajit Puduserry, AOR submitted that in the construction of contractual terms, the interpretation proposed by the author of the tender document must be relied on. He referred to   Agmatel India Pvt Ltd   v.   Resoursys 14 Telecom & Ors   for this purpose. He further submitted that the action of the Corporation is unexceptionable as it merely followed the directions of the High Court in an earlier round of litigation where the court directed it to issue notice before taking a decision on the contractors’ liability. It is his contention that notices were accordingly   issued   before   recoveries   were   made.   Appearing   on behalf of the Corporation in the third appeal, Shri Abhay Kumar, AOR, supported the arguments of the Appellant Corporation on the same grounds. 14. Shri  Sanjay   Parikh,   learned   Senior   Counsel   appearing   on behalf of the Respondents submitted that the Corporation acted arbitrarily. It failed to follow due process of law to determine the 13 Movement Operations in Food Corporation of India (FCI Handbook 2020). 14 (2022) 5 SCC 362. Page 8 of 24 liability   of   the   contractors,   despite   specific   instructions   in   a previous   round   of   litigation.   He   also  submitted   that  contractors were not responsible for loading and unloading of foodgrains from railway wagons. Hence, the event which leads to the incurrence of demurrages,   i.e.,   delayed   unloading   of   foodgrains   from   railway wagons, was not within the scope of contractor’s responsibilities. He took us through the contracts that were executed in 2010 and 2018 by   the   Corporation,   which   delegated   the   task   of   loading   and unloading the foodgrains to contractors, and therefore the relevant expression   “demurrages”   was   present   in   the   liability   clauses   in those contracts.  15. Supplementing   the   above   submissions,   Shri   Shoeb   Alam, Advocate, submitted that the Corporation was not entitled to be a judge in their own cause and to unilaterally determine the liability with   respect   to   demurrages.   He   placed   reliance   on   State   of 15 Karnataka   v.   Shree   Rameshwara   Rice   Mills ,   BSNL   and   Anr.   v. 16 17 Motorola India (P) Ltd  and  J.G. Engineers (P) Ltd  v.  Union of India .  15 (1987) 2 SCC 160. 16 (2009) 2 SCC 337. 17 (2011) 5 SCC 758. Page 9 of 24 Analysis: 16. The core question arising for our consideration is whether the contractual clause enabling the Corporation to recover “charges” includes the recovery of demurrages. It is pertinent to extract the relevant clauses of the   road transport contract , i.e., Work Order. The   clauses   detailing   the   description   of   work,   liability   of   the contractors, and the power to recover losses, which are identical in the three appeals before us, read as under: (B) Brief description of work i)   Transportation   of   foodgrains   from Depots/Mandis/Rail   Heads   of   Churaibari   to   various destinations as per Appendix­I... ... X. Liability of Contractor for losses suffered by Corporation a) The Contractor shall be liable for all costs, damages, registration   fees,   charges   and   expenses   suffered   or incurred   by   the   Corporation   due   to   the   Contractor's negligence   and   unworkmanlike   performance   of   any services under this Contract, or breach of any terms of the Contract, or failure to carry out the work under the Contract, and for all damages or losses occasioned to the Corporation, or in particular to any property or plant belonging to the Corporation, due to any act whether negligent   or   otherwise,   of   the   Contractor   or   his employees. ... ... XII. Recovery of losses suffered by the Corporation (a)   The   Corporation   shall   be   at   liberty   to   reimburse themselves for any damages, losses, charges, costs or expenses suffered or incurred by them, or any amount payable by the Contractor as Liquidated Damages as provided in Clauses X above.   The total sum claimed shall be deducted from any sum then due, or which at Page 10 of 24 any time thereafter may become due, to the Contractors under this, or any other, Contract with the Corporation. In the event of the sum which may be due from the Contractor as aforesaid being insufficient, the balance of   the   total   sum   claimed   and   recoverable   from   the Contractors as  aforesaid shall be deducted from the Security   Deposit,   furnished   by   the   contractor   as specified in Clause IX... ”         (emphasis supplied) 17. The   Corporation   seeks   to   recover   demurrages   as   a   part   of “charges” provided under clause XII(a) as extracted hereinabove. The expression “charges”, stand alone, is not amenable to a precise meaning.   Its   dictionary   meaning   is   open   textured,   defining “charges” as “any consideration that one must pay for goods and services provided”. Therefore, the scope of the expression “charges” must be understood as intended by the parties to the contract. The process of interpretation, though the exclusive domain of the Court, inheres the duty to decipher the meaning attributed to contractual terms by the parties to the contract. It is with this purpose that we shall now proceed to understand the meaning of the expression “charges”.   18. There are certain basic principles evolved by courts of law for deciphering   the   true   and   correct   meaning   of   expressions   in   a Page 11 of 24 contract. In   Bihar State Electricity Board, Patna and Ors.   v.   M/s 18 Green   Rubber   Industries   and   Ors. ,   this   Court   observed   that, “Every contract is to be considered with reference to its object and the whole of its terms and accordingly the whole context must be considered in endeavouring to collect the intention of the parties, even though the immediate object of enquiry is the meaning of an isolated clause.19 19. In  Union of India  v.  Raman Iron Foundry ,  this Court held that contractual terms cannot be interpreted in isolation, following strict etymological rules or be guided by popular connotation of terms, at variance with the contractual context. It observed:  It is true that the words “any claim for the payment 8. of a sum of money” occurring in the opening part of Clause 18 are words of great amplitude, wide enough to cover even a claim  for damages, but  it  is a well settled   rule   of   interpretation   applicable   alike   to instruments as to statutes that the meaning of ordinary words is to be found not so much in strict etymological propriety of language nor even in popular use as in the subject or occasion on which they are used and the object which is intended to be attained. The context and collocation of a particular expression may show that it was  not  intended   to  be  used  in  the  sense  which   it ordinarily   bears.   Language   is   at   best   an   imperfect medium of expression and a variety of meanings may often lie in a word or expression. The exact colour and shape of the meaning of any word or expression should not   be   ascertained   by   reading   it   in   isolation,   but   it 18 (1990) 1 SCC 731, ¶23. 19 (1974) 2 SCC 231. Page 12 of 24 should be read structurally and in its context, for its meaning   may   vary   with   its   contractual   setting.   We must,   therefore,   read   the   words   ‘any   claim   for   the payment of a sum of money’ occurring in the opening part of Clause 18 not in isolation but in the context of the whole clause, for the intention of the parties is to be gathered not from one part of the clause or the other but from the clause taken as a whole. It is in the light of this principle of interpretation that we must determine whether the words ‘any claim for the payment of a sum of  money’  refer only to  a  claim  for a sum  due  and payable   which   is   admitted   or   in   case   of   dispute, established in a Court of law or by arbitration or they also include a claim for damages which is disputed by the contractor.”                      (emphasis supplied) 20. In  Provash Chandra Dalui and Anr.  v.  Biswanath Banerjee and 20   noting that the intention of the parties must be discerned Anr. , from the context of the contract, this Court observed: 10.   ‘Ex praecedentibus et consequentibus optima fit interpretatio.’ The best interpretation is made from the context. Every contract is to be construed with reference to   its   object   and   the   whole   of   its   terms.  The   whole context must be considered to ascertain the intention of the parties. It is an accepted principle of construction that   the   sense   and   meaning   of   the   parties   in   any particular   part   of   instrument   may   be   collected   ‘ex antecedentibus et consequentibus;’ every part of it may be brought into action in order to collect from the whole one uniform and consistent sense, if that is possible.  ... In   construing   a   contract   the   court   must   look   at   the words used in the contract unless they are such that one may suspect that they do not convey the intention correctly. If the words are clear, there is very little the court can do about it.  In the construction of a written instrument it is legitimate in order to ascertain the true meaning of the words used and if that be doubtful it is 20 1989 Supp (1) SCC 487. Page 13 of 24 legitimate   to   have   regard   to   the   circumstances surrounding  their  creation  and  the  subject  matter  to which   it   was   designed   and   intended   they   should apply.”          (emphasis supplied) 21 21. In  BESCOM  v.  E.S. Solar Power Pvt Ltd and Ors this Court held that in  case of two possible interpretations of a contractual term, the court must accord primacy to the one that is consistent with the underlying purpose of the contract. It noted: 17.   ... In seeking to construe a clause in a contract, there   is   no   scope   for   adopting   either   a   liberal   or   a narrow   approach,   whatever   that   may   mean.   The exercise which has to be undertaken is to determine what the words used mean. It can happen that in doing so   one   is   driven   to   the   conclusion   that   clause   is ambiguous, and that it has two possible meanings. In those circumstances, the court has to prefer one above the other in accordance with the settled principles.  If one  meaning is  more in accord  with what the  court considers to be the underlined purpose and intent of the contract, or part of it, than the other, then the court will choose the former or rather than the latter...”                                                        (emphasis supplied) 22. Keeping   in   mind   the   above   referred   principles   we   have   to examine the expression “charges” in the context of its related words in the contract, which are  costs, damages, registration fees, and expenses.   These   expressions   indicate   the   different   heads   under which   losses   are   recoverable   from   the   contractors   for   acts   of 21 (2021) 6 SCC 718. Page 14 of 24 negligence, unworkmanlike performance of any service, breach of terms   and   failure   to   carry   out   the   work   in   the   context   of   the working of the contract. These expressions are equally wide and do not   aid   us   in   understanding   the   meaning   of   the   expression “charges”.  Under these circumstances, we have to understand the meaning of the expression “charges” in the larger context of the contract.  23.  The preamble of the contract, i.e., the Work Order, reads that the   contractor   is   engaged   for   “ transportation   of   foodgrains   from depots, mandis, rail heads of Churaibari to various destinations as per appendix 1 ”. Further, clause XIII of the Work Order detailing the responsibilities   of   the   contractor,   to   the   extent   relevant   for   our purposes, reads as under:­ XIII. Responsibilities of the Contractor (a) The Contractor shall be responsible to supply adequate and sufficient number of trucks for transportation of food grains  and   carrying   out   any   other   services   under   the Contract in accordance with the instructions issued by the General Manager or an officer acting on his behalf. ... (f) The Contractor shall be responsible for the safety of the goods  from the time they are loaded on their truck from godowns/mandis/rail heads until they have been unloaded from   the   trucks   at   godowns  or   at   other   destinations   as specified   in   the   Contract   or  as   directed   by   the   General Manager/Area Manager or any other officer acting on his behalf...        (emphasis supplied) Page 15 of 24 24. We   have   scanned   the   entire   contract,   in   addition   to scrutinising the provisions extracted above, and seen that there is no contractual provision requiring the contractors to undertake the task   of   loading   and   unloading   of   foodgrains   from   the   railway wagons.   This is confirmed by the written submissions on behalf of the Corporation, where the imposition of demurrages is justified only for the reason that the contractor did not provide adequate number   of   trucks   near   the   railway   sidings,   to   enable   the Corporation   to   promptly   hand   over   the   foodgrains   to   them   to commence   transportation.   The   relevant   portion   is   extracted   as under:­ “ 10.   The   reason   why   demurrage   charges   get   levied during   the   performance   of   an   RTC   contract   is   on account   of   the   failure   of   the   contractor   to   supply required number of trucks even after prior intimation about the placing of the railway rakes due to which the Petitioner   is   unable   to   empty   the   wagons   as   the foodgrains are liable to get spoiled if they are unloaded onto the siding due to rain etc. Even after unloading unless   they   are   removed   from   the   railway   premises within the free time available wharfage is charged by the   Railways.   The   failure   to   prove   trucks   leads   to detention of wagons beyond the free time allowed by the Railways... ” 25. We may note that there is a dispute about the availability of trucks for the transportation of foodgrains by the contractor. While Page 16 of 24 the  Corporation  asserts   that   trucks   were   not  made  available in numbers as well as in time, the contractor denies the same stating that   their   trucks   were   kept   waiting   at   the   Corporation’s   Food Security Depots.   26.  Irrespective of the disputed fact, the real question is whether the contractors had any obligation towards loading and unloading of   foodgrains   from   the   railway   wagons.   It   is   evident   from   the contractual provisions and also the admissions of the Corporation in written submissions, that the task of loading or unloading of foodgrains from the railway wagons was not a part of the contract. Thus, based on interpretation of the expression “charges” in the contractual context, we are of the opinion that it did not include liability on account of demurrages. Consequently, the Corporation cannot impose and collect demurrages from the contractors.  27.   Interpretation of contracts concerns the discernment of the true   and   correct   intention   of   the   parties   to   it.   Words   and expressions used in the contract are principal tools to ascertain such intention. While interpreting the words, courts look at the expressions   falling   for   interpretation   in   the   context   of   other Page 17 of 24 provisions of the contract and also in the context of the contract as a whole. These are intrinsic tools for interpreting a contract. As a principle of interpretation, courts do not resort to materials external to the contract for construing the intention of the parties. There are, however,   certain   exceptions   to   the   rule   excluding   reference   or reliance   on   external   sources   to   interpret   a   contract.   One   such exception is in the case of a   latent ambiguity , which cannot be resolved without reference to extrinsic evidence. Latent ambiguity exists when words in a contract appear to be free from ambiguity; however, when they are sought to be applied to a particular context or question, they are amenable to multiple outcomes. This position 22 is well­explained in the following passage of  Halsbury’s :Latent ambiguity: When the instrument appears on its face to be free from ambiguity but, upon the endeavour being made to apply it to persons or things indicated, it appears that the words are equally applicable to two or more persons, or two or more things, either without any inaccuracy or with a common inaccuracy... ” 22  Halsbury’s Laws of England  (5th edn, 2012) vol 32, para 409. Page 18 of 24 Extrinsic evidence, in cases of latent ambiguity, is admissible both to ascertain where necessary, the meaning of the words used, and 23 to identify the objects to which they are to be applied.   28.  Applying the above­referred principles to the present case, we will juxtapose the present contracts with  similar but not identical contracts   entered   into   by   the   Corporation,   to   confirm   our interpretation that the word “charges” in the contract is exclusive of liability   for   demurrages.   Pursuantly,  we   will   examine   certain contracts entered into by the Corporation with other transporters. For   example,   we   will   refer   to   a   contract   entered   into   by   the Corporation in 2010, which is prior in time to the present contract. The relevant clauses read as under:­ “   B. Brief description of work I. Unloading/Loading of foodgrain bags from/into railway wagons, trucks etc. stacking...and transporting of   foodgrains   from   Railway   Station   to   Corporation’s Godown or vice­versa...” XII. Liability   of   Contractors   for   losses   etc. suffered by Corporation a) The   contractor   shall   be   liable   for   all   costs, damages,  demurrages, wharfage, forfeiture of wagon, registration fees, charges and expenses...due to...their failure   to   carry   out   the   work   with   a   view   to   avoid incurrence of demurrage etc ... 23  Halsbury’s Laws of England  (5th edn, 2012) vol 32, para 394. Page 19 of 24 b)   The   Corporation   shall   be   at   liberty   to   reimburse themselves of any damages, losses, charges, costs, or expenses   suffered   or   incurred   by   them   due   to contractors   negligence   and   un­workmanlike performance of service under the contract or breach of any terms thereof... ”          (emphasis supplied) 29. It is evident from the above that the contracts delegating the responsibility of loading and unloading of foodgrains from railway wagons,  as an integral part of the contract,  include a clear and distinctive   clause   for   the   imposition   of   liability,   inter   alia ,   on account   of   demurrages.   Evidently,   the   liability   clause   in   these contracts, termed the Handling and Transport Contracts, is starkly distinct from the present Road Transport Contracts. 30. We   have   every   reason   to   believe   that   the   Corporation, statutorily obligated to procure and distribute foodgrains across the nation, enters into contracts depending on the services it requires. These   contracts   naturally   vary   depending   on   the   needs   and purposes of the Corporation. With the aid of the provisions in the Handling   and   Transport   Contract   from   2010,   we   are   able   to understand   the   intention   of   the   parties   while   entering   into   the present Road Transport Contracts. As the present contracts do not Page 20 of 24 involve the task of loading and unloading of foodgrains from the railway wagons as a part of the contractors’ responsibility, there is no clause enabling the recovery of demurrages from them by the Corporation. Thus, our interpretation of the expression “charges”, as exclusive of liability for demurrages, stands confirmed. 31. We   will   proceed   to   examine   yet   another   Handling   and Transport   Contract   which   was   executed   seven   years   after   the present contract, i.e., in 2018. The relevant clauses of the contract are as under:­ “B. Brief description of work I. Unloading/Loading of foodgrain bags from /into railway wagons, trucks etc. stacking the foodgrains in bags, bagging, weighment, standardization, cleaning of foodgrains,   etc.,   and   transporting   of   foodgrains   from Railway Good Shed/siding to Corporation Godown or vice­versa or transporting them from any place to any other place in and around Railhead KUMARGHAT/FSD KUMARGHAT... ... X.  Liability   of   Contractors   for   losses   etc. suffered by Corporation a) The   contractor   shall   be   liable   for   all   costs, damages,  demurrages, wharfage, forfeiture of wagon, registration   fees,   charges   and   expenses   suffered   or incurred   by   the   Corporation   due   to   the   contractor’s negligence   and   un   workmanlike   performance   of   any services under this contract, or breach of any terms thereof or his failure to carry out the work with a view to   avoid   incurrence   of   demurrage   etc.   under   this contract or breach of any terms thereof or his failure to carry out the work with a view to avoid incurrence of demmurage;   etc.   and   for   all   damages   or   losses occasioned to the Corporation due to any act whether Page 21 of 24 negligent or otherwise of the contractor themselves or his employees. The decision of the General Manager regarding   such   failure   of   the   contractor   and   their liability for the losses, etc. suffered by the Corporation, and the quantification of such losses, shall be final and binding on the contractor ...” (emphasis supplied) 32. It is evident from the above that the Handling and Transport Contract from 2018, similarly involved loading and unloading of foodgrains from the railway wagons within the scope of contractors’ duties,   thereby   necessitating   the   inclusion   of   demurrages   as   a penalty   for   non­performance   of   contractual   duties.   Thus,   the present Road Transport Contract is distinct from the Handling and Transport Contract from 2018, as the responsibility of loading and unloading   of   foodgrains   from   railway   wagons   is   absent   in   the present contract. For this reason, the Corporation in the present contract has chosen not to include the power to recover demurrages and   as   such   the   expression   “charges”   cannot   be   interpreted   to include demurrages.  33. In light of the foregoing conclusions, we are not inclined to adopt a textual approach for the interpretation of the contractual term “charges”, and hence, the decisions of this Court in  Raichand Page 22 of 24 24 25 Amulakh Shah   and  Trustees of the Port of Madras  are of no aid, as they   simply   describe   demurrages   as   a  charge.   Demurrage is undoubtedly   a   charge,   however,   such   a   textual   understanding would not help us decipher the true and correct intention of the parties to the present contract.  34. For   these   reasons,   Civil   Appeals   arising   out   of   SLP   Nos. 16009­16010 of 2019 and SLP Nos. 16063­16068 of 2019, filed by the Corporation are dismissed. The decisions of the High Court of Tripura in Writ Appeal No. 56 of 2018 dated 07.09.2018 and Review Petition No. 02 of 2019 dated 22.01.2019 are upheld. The decision of the High Court of Tripura in Writ Appeal Nos. 53­58 of 2017 dated 15.05.2019 is also upheld. We may clarify that our decision has no bearing on any other remedy available to the Corporation, like the institution of a suit for recovery, if law enables them to do so. 35. In so far as Civil Appeals arising out of SLP Nos. 4045­4046 of 2021 filed by the contractors are concerned, they are allowed for the same reasons as indicated above. The judgments of High Court of 24 Supra note 11. 25 Supra note 12. Page 23 of 24 Tripura in Writ Appeal Nos. 186 of 2020 and 187 of 2020 dated 04.01.2021 and 18.01.2021 respectively are set­aside and the Civil Appeals stand allowed.  36.  The parties shall bear their own costs. ……………………………….J.                                                             [A.S. BOPANNA] ……………………………….J. [PAMIDIGHANTAM SRI NARASIMHA] NEW DELHI; NOVEMBER 18,2022                          Page 24 of 24