Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 21
CASE NO.:
Appeal (civil) 3703 of 2003
PETITIONER:
M/s. Girnar Traders
RESPONDENT:
State of Maharashtra & Ors
DATE OF JUDGMENT: 27/08/2007
BENCH:
B.N. Agrawal & P.K. Balasubramanyan & P.P. NAOLEKAR
JUDGMENT:
J U D G M E N T
WITH
CIVIL APPEAL NO. 3922 of 2007
[arising out of S.L.P.(C) No. 11446 of 2005]
M/s. S.P. Building Corporation & Anr. \005\005 Appellants
Versus
State of Maharashtra & Ors. \005\005Respondents
P.P. Naolekar, J.
1. We have had the benefit of perusing the judgment
prepared by learned brother P.K. Balasubramanyan, J. in Civil
Appeal No.3703 of 2003 titled M/s. Girnar Traders v. State of
Maharashtra and Others, wherein learned brother has taken
into consideration various decisions of this Court,
including decisions delivered by 3-Judge Benches, and
various aspects considered therein, and thought it proper to
refer the question regarding interpretation and applicability of
Section 11A introduced into the Land Acquisition Act, 1894
(for short \023the LA Act\024) by Amendment Act 68 of 1984 to the
Maharashtra Regional and Town Planning Act, 1966 (for short
\023the MRTP Act\024) for consideration by a larger Bench. A 3-
Judge Bench of this Court in Nagpur Improvement Trust
v. Vasantrao and Others, (2002) 7 SCC 657 and U.P. Avas
Evam Vikas Parishad v. Jainul Islam and Another,
(1998) 2 SCC 467, on interpretation of the provisions of the
Acts under challenge, has held that the LA Act was
incorporated in those statutes, that is, they were cases of
legislation by incorporation and, therefore, the amendment
brought about subsequently in the LA Act would not apply to
the statutes in question. However, beneficial amendment of
payment of compensation under the amended provisions of
the LA Act was made applicable and the owner of the land was
held to be entitled to the beneficial payment of compensation.
It appears, it was so held to save the Acts from the vice of
arbitrary and hostile discrimination. There does not appear to
be any justifiable reason for not applying this principle so far
as it relates to the acquisition of land. If the land is not
acquired within the stipulated time, then the whole
proceedings in acquisition comes to an end, and thereby the
owner of the land would be entitled to retain his land which
appears to be the superior right than the owner\022s right
to get the compensation for acquisition of his land. A 2-
Judge Bench of this Court in State of Maharashtra and
Another v. Sant Joginder Singh Kishan Singh and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 21
Others, 1995 Supp. (2) SCC 475 has held that Section 11A of
the LA Act is a procedural provision and does not stand on the
same footing as Section 23 of the LA Act. We find it difficult to
subscribe to the view taken. Procedure is a mode in which the
successive steps in litigation are taken. Section 11A not only
provides a period in which the land acquisition proceedings
are to be completed but also provides for consequences,
namely, that if no award is made within the time stipulated,
the entire proceedings for the acquisition of the land shall
lapse. Lapsing of the acquisition of the land results in owner
of the land retaining ownership right in the property and
according to us it is a substantive right accrued to the owner
of the land, and that in view thereof we feel Section 11A of the
LA Act is part of the law which creates and defines right, not
adjective law which defines method of enforcing rights. It is a
law that creates, defines and regulates the right and powers of
the party. For this and the other reasons assigned by our
learned brother, we are in agreement with him that the
question involved requires consideration by a larger Bench
and, accordingly, we agree with the reasons recorded by my
learned brother for referring the question to a larger Bench.
However, on consideration of the erudite judgment prepared
by our esteemed & learned brother Balasubramanyan, J.,
regretfully we are unable to persuade ourselves to agree to the
decision arrived at by him on interpretation of Section 127 of
the MRTP Act and also reference of the case to a larger Bench.
Section 127 of the MRTP Act is a special provision and would
be attracted in the peculiar facts and circumstances
mentioned in the Section itself. The Section provides a
procedure for the land owner to get his land de-reserved if
steps are not taken by the State Government within the
stipulated period and the relief which the owner of the land is
entitled to is also provided therein. The steps to be taken for
acquisition of land as provided under Section 127 of the MRTP
Act have to be taken into consideration keeping in mind the
time lag between the period the land is brought under
reservation and inaction on the part of the State to acquire it.
Section 127 of the MRTP Act is a unique provision providing
remedial measure to the owner of the land whose land is
under the planning scheme for a long period of time, which
would be interpreted in the facts and circumstances of each
individual case. It does not have any universal application
and, therefore, the applicability thereof would depend on the
facts of each case. S.L.P.(C) No.11446 of 2005 titled M/s. S.P.
Building Corporation and Anr. v. State of Maharashtra and
Others, is required to be decided by this Bench only and,
therefore, we propose to decide it as follows:
2. Leave granted.
3. The brief facts necessary for deciding the questions
raised in this appeal are that appellant No.1 is a partnership
firm registered under the Indian Partnership Act, 1932 and
is the owner of an immovable property, i.e. a piece of land,
bearing City Survey No.18/738, admeasuring about 5387.35
sq.yds. situated at Carmichael Road, Malabar Hill Division,
Mumbai-400026.
4. On 7.7.1958, Bombay Municipal Corporation had
issued a declaration under Section 4(1) of the Bombay Town
Planning Act, 1954 (hereinafter referred to as \023the Act of
1954\024), expressing its intention to prepare a development plan
for the area under its jurisdiction and published a
development plan in accordance with the provisions of the said
Act on 9.1.1964. The plan was submitted by the Corporation
to the Government of Maharashtra for sanction on 8.7.1964
and on 6.1.1967 the Government of Maharashtra accorded
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 21
sanction to the development plan which pertained to \021D\022 Ward
of the Corporation area and the plan came into force on
7.2.1967. The land of the appellant was notified for
development as \021Open Space and Children\022s Park\022. On
11.1.1967, the Maharashtra Regional and Town Planning Act,
1966 (hereinafter referred to as \023the MRTP Act\024) repealed the
Act of 1954 saving the proceedings already initiated under the
Act of 1954.
5. Proceedings were taken up for acquisition of the land.
Since no award was made as per Section 11A of the Land
Acquisition (Amendment) Act, 1984 which came into force on
24.9.1984, the acquisition proceedings were declared by the
Land Acquisition Officer to have lapsed. Later on a revised
development plan sanctioned by the State Government on
6.7.1991 came into effect on 16.9.1991. On 3.2.1998 the
appellants served notice through their advocates under
Section 127 of the MRTP Act asking for re-notifying the
property or to release the said property from reservation and
accord sanction/approval to develop the property by the
owner. In reply, the Municipal Corporation, Greater Mumbai
informed the appellants that purchase notice issued by their
advocates was invalid as ten years had not expired since the
sanction of the revised development plan, came into force on
16.9.1991. On 18.10.2000, the appellants again served
purchase notice under Section 127 of the MRTP Act. Again
the Municipal Corporation of Greater Mumbai informed the
appellants that the notice was invalid as the period of ten
years had not lapsed from the date of the revised plan.
6. On 15.3.2002, the appellants addressed yet another
notice to the Municipal Corporation, Greater Mumbai under
Section 127 of the MRTP Act stating therein that ten years\022
period had lapsed on 16.9.2001 and since no proceedings for
acquisition of the land as contemplated under Section 127(1)
of the MRTP Act or under the Land Acquisition Act , 1894
(hereinafter referred to as \023the LA Act\024) having been
commenced nor has any award been made or compensation
paid, the property should be de-reserved. The purchase notice
was served on the Municipal Commissioner, Greater Mumbai
on 19.3.2002.
7. The counsel for respondent-Municipal Corporation
has submitted certain documents before us at the time of
hearing. In pursuance of the purchase notice served on the
Municipal Corporation, Greater Mumbai, a meeting of the
Improvement Committee was called. On 9.9.2002 (document
no.1), the Improvement Committee passed Resolution No.183
recommending the Municipal Corporation to initiate the
acquisition proceedings under the provisions of Section 126(2)
and (4) of the MRTP Act read with Section 6 of the LA Act, as
amended upto date, or in the alternative to recommend
acquisition as provided under Section 126(1) of the MRTP Act.
The rates for acquisition under the LA Act and that under the
provisions of Section 126(1) of the MRTP Act were also
provided for. On 13.9.2002 (document no.2) without there
being any resolution sanctioning acquisition or taking steps
for acquisition, an application was sent by the Chief Engineer
(Development Plan) to the State Government for initiating
acquisition proceedings under Section 126 of the MRTP Act as
amended upto date read with Section 6 of the LA Act.
Thereafter, on 16.9.2002 (document no.3) the Corporation
passed Resolution No.956 whereby sanction was given to
initiate the acquisition proceedings of the land and the
Municipal Commissioner was authorised to make an
application to the State Government under the provisions of
Section 126(2) & (4) of the MRTP Act read with Section 6 of the
LA Act, as amended upto date; and / or, initiate proceedings
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 21
under Section 90(1) & (3) of the Bombay Municipal
Corporation Act, 1888 as amended upto date, for the land
being purchased by the Commissioner on behalf of the
Corporation. After the Resolution was passed, on 17.9.2002
(document no.4) a letter was written by the Chief Engineer
(Development Plan) to the Secretary, Urban Development
Department, Government of Maharashtra informing that the
Corporation have accorded sanction to initiate acquisition
proceedings and for the said purpose authorized the Municipal
Commissioner to make an application to the State Government
as per the provisions of Section 126(1) of the MRTP Act as
amended upto date to issue orders for acquisition of the
property under the MRTP Act read with Section 6 of the LA
Act. The letter dated 17.9.2002 is reproduced herein:-
\023To,
The Secretary,
Urban Development Dept.,
Govt. of Maharashtra,
Mantralaya,
Mumbai-400032
Sub: Acquisition of land bearing C.S.No.18738 of
Malabar Hill division reserved for Children Park.
Ref: i) TPB-4302/572/UD-11 dtd.27.3.02
ii) CHE/ACQ/C/962 dtd. 13.9.2002
Sir,
With reference to above, it is to be mentioned
here that Corporation by their Resolution No. 956 of
16.9.2002 (copy enclosed) have accorded sanction to
initiate the acquisition proceedings for the above
mentioned land reserved for Children\022s Park adm.
approximately 4504.52 sq.mt. and also authorized
the Municipal Commissioner to make application to
State Govt. as per provision of 126(1) of the
M.R.&T.P. Act 1966 as amended upto date to issue
order for the acquisition of property under reference
as provided under the provisions of sec. 126(2) (3)
and (4) of the M.R.&T.P. Act 1966 as amended upto
date read with section 6 of L.A. Act 1894. The
application to State Govt. along with the required
information in the usual proforma in triplicate & three
copies of plans have already been submitted vide
this office letter issued u/no. CHE/ACQ/C/962 dtd.
13.9.2002 (copy enclosed). This is for information
and further necessary action.
Yours faithfully,
Sd/-
CHIEF ENGINEER
(DEVELOPMENT PLAN)\024
Later on the State Government on 20.11.2002 issued a
notification exercising the power conferred by sub-section (4)
read with sub-section (2) of Section 126 of the MRTP Act read
with Section 6 of the LA Act.
8. Having aggrieved by the action of the respondents,
the appellants filed a writ petition in the High Court of
Judicature at Bombay which was registered as Writ Petition
No.353 of 2005 (M/s. S.P. Building Corporation & Anr. vs.
State of Maharashtra and Ors.) challenging the proceedings
initiated by the respondents. It was contended by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 21
appellants that under Section 127 of the MRTP Act, no steps
having been taken within the period prescribed, the reservation
is deemed to have lapsed; and secondly, the acquisition
proceedings initiated under the MRTP Act, are deemed to have
lapsed in view of Section 11A of the LA Act, the award having
not been admittedly made within two years from the date of
publication of the declaration. The Division Bench of the
Bombay High Court dismissed the petition on both counts. It
was held by the Bombay High Court that the resolution of the
Improvement Committee passed on 9.9.2002 and the letter
written by the Chief Engineer dated 13.9.2002 would constitute
a ‘step\022 taken by the Municipal Corporation as provided under
Section 127 of the MRTP Act. The Division Bench relying on a
judgment of this Court in the case of State of Maharashtra
and Another v. Sant Joginder Singh Kishan Singh and
Others, 1995 Supp. (2) SCC 475, has held that Section 11A of
the LA Act as amended is not applicable to the proceedings for
acquisition initiated under the MRTP Act and dismissed the writ
petition.
9. The appellants filed this appeal by way of S.L.P. (C)
No. 11446 of 2005 challenging the order of the Division Bench
of the Bombay High Court. This Court by an order dated
11.7.2005, issued notice and tagged the case along with C.A.
No. 3703 of 2003 wherein a 2-Judge Bench of this Court had
doubted the correctness of the decision rendered by this Court
in Sant Joginder Singh Case (supra) on which the Bombay
High Court has relied, in regard to the applicability of the
newly inserted provision of Section 11A of the LA Act, to the
acquisition under Chapter VII of the MRTP Act. Thus, the
matter has been heard along with C.A. No.3703 of 2003
wherein the only question raised is in regard to the
applicability of the new provision of Section 11A of the LA Act
to the acquisition made under the MRTP Act; whereas, apart
from the said question, in this case we are also required to
decide the scope and ambit of Section 127 read with Section
126 of the MRTP Act for the purposes of de-reservation of the
land reserved under a development plan.
10. The question that requires consideration and
answer in the present case is : Whether the reservation has
lapsed due to the failure of the planning authority to take
steps within the period of six months from the date of service
of the notice of purchase as stipulated by Section 127 of the
MRTP Act; and also the question as regards applicability of
new Section 11A of the LA Act to the acquisition of land under
the MRTP Act.
11. Under Section 2(19) of the MRTP Act, the planning
authority means a local authority and includes other
authorities provided in clauses (a) and (b). The local authority
is defined in Section 2(15) which for the purposes of this case
would be the Municipal Corporation of Greater Mumbai
constituted under the Bombay Municipal Corporation Act.
12. Chapter VII of the MRTP Act deals with land
acquisition. Sections 125 to 129 fall in Chapter VII. Section
125 provides that any land required, reserved or designated in
a regional plan, development plan or town planning scheme
for a public purpose or purposes including plans for any area
of comprehensive development or for any new town shall be
deemed to be land needed for a public purpose within the
meaning of the LA Act. Section 126 provides three modes of
acquisition of the land included in the town planning scheme
for the public purpose. Section 127 provides for lapsing of
reservation if the land reserved, allotted or designated is not
acquired by agreement within 10 years from the date on which
a final regional plan or final development plan comes into force
or if proceedings for acquisition of land under the MRTP Act or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 21
under the LA Act are not commenced within such period, then
the owner or any person interested in the land may serve a
notice. If within six months from the date of service of such
notice, the land is not acquired or no steps as aforesaid are
commenced for its acquisition, the reservation, allotment or
designation shall be deemed to have lapsed and the land shall
be deemed to be released from such reservation. Section
128(1) confers the power on the State Government to acquire
the land needed for a public purpose different from any public
purpose under the scheme, or purpose of the planning
authority or development authority or appropriate authority;
the State Government may, notwithstanding anything
contained in the MRTP Act, acquire the land under the
provisions of the LA Act. Section 129(1) empowers the
Collector after the publication of the declaration under Section
126(2) to enter on and take possession of the land under
acquisition after giving a notice of 15 days.
13. Section 127 falling in Chapter VII requires
interpretation in the present case. However, the same cannot
be understood without reference to Section 126 which has an
important bearing while interpreting the words used in Section
127, namely, \023the land is not acquired or no steps as aforesaid
are commenced for its acquisition\024. Therefore, the relevant
provisions to be considered are Sections 126 and 127 of the
MRTP Act. Section 126 of the MRTP Act reads as follows:
\023126. Acquisition of land required for public
purposes specified in plans.- (1) When after the
publication of a draft Regional Plan, a Development
or any other plan or Town Planning Scheme, any
land is required or reserved for any of the public
purposes specified in any plan or scheme under this
Act at any time the Planning Authority,
Development Authority, or as the case may be, any
Appropriate Authority may, except as otherwise
provided in section 113A, acquire the land, \026
(a) by agreement by paying an amount agreed
to, or
(b) in lieu of any such amount, by granting the
land-owner or the lessee, subject, however, to
the lessee paying the lessor or depositing with
the Planning Authority, Development Authority
or Appropriate Authority, as the case may be,
for payment to the lessor, an amount
equivalent to the value of the lessor’s interest
to be determined by any of the said
Authorities concerned on the basis of the
principles laid down in the Land Acquisition
Act, 1894, Floor Space Index (FSI) or
Transferable Development Rights (TDR)
against the area of land surrendered free of
cost and free from all encumbrances, and also
further additional Floor Space Index or
Transferable Development Rights against the
development or construction of the amenity
on the surrendered land at his cost, as the
Final Development Control Regulations
prepared in this behalf provide, or
(c) by making an application to the State
Government for acquiring such land under the
Land Acquisition Act, 1894,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 21
and the land (together with the amenity, if any, so
developed or constructed) so acquired by agreement
or by grant of Floor Space Index or additional Floor
Space Index or Transferable Development Rights
under this section or under the Land Acquisition
Act, 1894, as the case may be, shall vest absolutely
free from all encumbrances in the Planning
Authority, Development Authority, or as the case
may be, any Appropriate Authority.
(2) On receipt of such application, if the State
Government is satisfied that the land specified in
the application is needed for the public purpose
therein specified, or if the State Government (except
in cases falling under section 49 and except as
provided in section 113A) itself is of opinion that
any land included in any such plan is needed for
any public purpose, it may make a declaration to
that effect in the Official Gazette, in the manner
provided in section 6 of the Land Acquisition Act,
1894, in respect of the said land. The declaration so
published shall, notwithstanding anything
contained in the said Act, be deemed to be a
declaration duly made under the said section:
Provided that, subject to the provisions of sub-
section (4), no such declaration shall be made after
the expiry of one year from the date of publication of
the draft Regional Plan, Development Plan or any
other Plan, or Scheme, as the case may be.
(3) On publication of a declaration under the said
section 6, the Collector shall proceed to take order
for the acquisition of the land under the said Act;
and the provisions of that Act shall apply to the
acquisition of the said land, with the modification
that the market value of the land shall be, --
(i) where the land is to be acquired for the
purposes of a new town, the market value
prevailing on the date of publication of the
notification constituting or declaring the
Development Authority for such town;
(ii) where the land is acquired for the purposes
of a Special Planning Authority, the market
value prevailing on the date of publication of
the notification of the area as an undeveloped
area; and
(iii) in any other case the market value on the
date of publication of the interim development
plan, the draft development plan or the plan
for the area or areas for comprehensive
development, whichever is earlier, or as the
case may be, the date or publication of the
draft town planning scheme :
Provided that, nothing in this sub-section shall
affect the date for the purpose of determining the
market value of land in respect of which
proceedings for acquisition commenced before the
commencement of the Maharashtra Regional and
Town Planning (Second Amendment) Act, 1972:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 21
Provided further that, for the purpose of clause (ii)
of this sub-section, the market value in respect of
land included in any undeveloped area notified
under sub-section (1) of section 40 prior to the
commencement of the Maharashtra Regional and
Town Planning (Second Amendment) Act, 1972,
shall be the market value prevailing on the date of
such commencement.
(4) Notwithstanding anything contained in the
proviso to sub-section (2) and sub-section (3), if a
declaration is not made within the period referred to
in sub-section (2) (or having been made, the
aforesaid period expired on the commencement of
the Maharashtra Regional and Town Planning
(Amendment) Act, 1993), the State Government may
make a fresh declaration for acquiring the land
under the Land Acquisition Act, 1894, in the
manner provided by sub-sections (2) and (3) of this
section, subject to the modification that the market
value of the land shall be the market value at the
date of declaration in the Official Gazette made for
acquiring the land afresh.\024
Under sub-section (1) of Section 126, after publication of the
draft regional plan, a development or any other plan or town
planning scheme, any land required or reserved for any of the
public purposes specified in any plan or scheme under the
MRTP Act, may be acquired (a) by agreement between the
parties by paying an amount agreed to; or (b) by granting the
land owner or the lessee, Floor Space Index (FSI) or
Transferable Development Rights (TDR) against the area of
land surrendered free of cost and free from all encumbrances
and also further additional Floor Space Index or Transferable
Development Rights against the development or construction
of the amenity on the surrendered land at his cost, as the
Final Development Control Regulations prepared in this behalf
provide; or (c) by making an application to the State
Government for acquiring such land under the LA Act. Sub-
section (2) provides that on receipt of such application or on
its own motion, the State Government would satisfy itself that
the land specified in the application, is needed for a public
purpose and, if it is so found, would make a declaration by
issuing a notification in the Official Gazette in the manner
provided in Section 6 of the LA Act. Proviso is added to sub-
section (2) whereunder a declaration under Section 6 of the LA
Act in the Official Gazette has to be made within one year from
the date of publication of the draft regional plan, development
plan or any other plan or scheme, as the case may be. Sub-
section (3) postulates that on publication of a declaration in
the Official Gazette under Section 6 of the LA Act, the Collector
shall proceed to take orders for the acquisition of the land
under the LA Act and the provisions of that Act shall apply to
the acquisition of the said land with certain modifications as
provided in clauses (i), (ii) and (iii) of sub-section (3) for
determination of the market value on the basis of different
dates. Sub-section (3) makes it abundantly clear that after
publication of the declaration in the Official Gazette under
Section 6 of the LA Act, the entire procedure which shall be
followed will be as provided under the LA Act, that is to say,
from Section 8 onwards upto Section 28 of the LA Act which
deal with acquisition of land under the LA Act.
14. Sub-section (2) of Section 126 provides for one
year\022s limitation for publication of the declaration from the
date of publication of the draft plan or scheme. Sub-section
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 21
(4), however, empowers the State Government to make a fresh
declaration under Section 6 of the LA Act even if the
prescribed period of one year has expired. This declaration is
to be issued by the State Government for acquisition of the
land without there being any application moved by the
planning/local authority under clause (c) of Section 126(1).
Sub-section (4) of Section 126 authorizes the State
Government to make a declaration for acquisition of the land
under Section 6 of the LA Act without any steps taken by the
planning authority, i.e., Bombay Municipal Corporation.
Under sub-section (4) of Section 126, the State Government
can make a fresh declaration if the declaration under sub-
section (2) of Section 126 was not made within the time
stipulated for acquisition of the land, if it is satisfied that the
land is required for a public purpose, subject to the
modification that the market value of the land shall be the
market value at the date on which the declaration in the
Official Gazette is made for acquisition of the land afresh.
Sub-section (4) is the provision whereunder only the State
Government is authorized and empowered to issue fresh
declaration for acquiring the land under the LA Act.
15. Section 127 of the MRTP Act which requires
consideration in the present case is a provision which
provides, as is clear from its heading itself, for lapsing of
reservation of the lands included in the development plan.
The development authority for utilization of the land for the
purpose for which it is included in the plan has to take steps
and do things within the period stipulated in a particular span
of time, the land having been reserved curtailing the right of
the owner of its user. Section 127 reads as under:
\023127. Lapsing of reservations.- If any land
reserved, allotted or designated for any purpose
specified in any plan under this Act is not acquired
by agreement within ten years from the date on
which a final Regional Plan, or final Development
Plan comes into force or if proceedings for the
acquisition of such land under this Act or under the
Land Acquisition Act, 1894, are not commenced
within such period, the owner or any person
interested in the land may serve notice on the
Planning Authority, Development Authority or as
the case may be, Appropriate Authority to that
effect; and if within six months from the date of the
service of such notice, the land is not acquired or no
steps as aforesaid are commenced for its
acquisition, the reservation, allotment or
designation shall be deemed to have lapsed, and
thereupon the land shall be deemed to be released
from such reservation, allotment or designation and
shall become available to the owner for the purpose
of development as otherwise permissible in the case
of adjacent land under the relevant plan.\024
Section 127 prescribes two time periods. First, a period of 10
years within which the acquisition of the land reserved,
allotted or designated has to be completed by agreement from
the date on which a regional plan or development plan comes
into force, or the proceedings for acquisition of such land
under the MRTP Act or under the LA Act are commenced.
Secondly, if the first part of Section 127 is not complied with
or no steps are taken, then the second part of Section 127 will
come into operation, under which a period of six months is
provided from the date on which the notice has been served by
the owner within which the land has to be acquired or the
steps as aforesaid are to be commenced for its acquisition.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 21
The six-month period shall commence from the date the owner
or any person interested in the land serves a notice on the
planning authority, development authority or appropriate
authority expressing his intent claiming de-reservation of the
land. If neither of the things is done, the reservation shall
lapse. If there is no notice by the owner or any person
interested, there is no question of lapsing reservation,
allotment or designation of the land under the development
plan. Second part of Section 127 stipulates that the
reservation of the land under a development scheme shall
lapse if the land is not acquired or no steps are taken for
acquisition of the land within the period of six months from
the date of service of the purchase notice. The word ‘aforesaid\022
in the collocation of the words \023no steps as aforesaid are
commenced for its acquisition\024 obviously refers to the steps
contemplated by Section 126 of the MRTP Act.
16. If no proceedings as provided under Section 127 are
taken and as a result thereof the reservation of the land
lapses, the land shall be released from reservation, allotment
or designation and shall be available to the owner for the
purpose of development. The availability of the land to the
owner for the development would only be for the purpose
which is permissible in the case of adjacent land under the
relevant plan. Thus, even after the release, the owner cannot
utilize the land in whatever manner he deems fit and proper,
but its utilisation has to be in conformity with the relevant
plan for which the adjacent lands are permitted to be utilized.
17. It is an admitted position that on 16.9.1991 the
revised development plan was sanctioned and 10 years have
expired on 15.9.2001 without there being any acquisition or
steps being taken for acquisition of the land in question. On
15.3.2002, the purchase notice under Section 127 was given
by the appellants which was received by the authorities on
19.3.2002. Under the second part of Section 127, the land
was either required to be acquired or steps in that regard have
to be commenced by 18.9.2002. For the first time after the
service of purchase notice, on 9.9.2002 a proposal was made
by the Improvement Committee recommending the Municipal
Corporation for sanction to initiate the acquisition
proceedings. On 13.9.2002 without there being any resolution
by the Municipal Corporation, the Chief Engineer
(Development Plan) sent an application to the State
Government for initiating the acquisition proceedings. For the
first time on 16.9.2002, a resolution was passed by the
Municipal Corporation whereby sanction was given to initiate
the acquisition proceedings of land and the Municipal
Commissioner was authorised to make an application to the
State Government and on 17.9.2002 a letter was sent by the
Chief Engineer (Development Plan) to the Secretary, Urban
Development Department, Government of Maharashtra for
initiating acquisition proceedings. Admittedly, in the present
case, the land was neither acquired nor were the steps taken
within 10 years from the date on which the final regional plan
or final development plan came into force.
18. Shri Shekhar Naphade, Senior Advocate appearing
for the State and Shri Bhim Rao Naik, Senior Advocate
appearing for the Municipal Corporation contended that the
steps were taken on 17.9.2002 when in pursuance of the
resolution passed by the Municipal Corporation of Greater
Mumbai, the Chief Engineer (Development Plan) sent a letter
to the State of Maharashtra enclosing therewith a copy of
Resolution No. 956 dated 16.9.2002, requesting that the steps
be taken for acquisition of the land and this step taken by the
respondents would constitute ‘steps\022 for the acquisition of the
land under clause (c) of Section 126(1) of the MRTP Act, the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 21
same having been taken on 17.9.2002 when the period of six
months had not expired, the same to be expired on 18.9.2002
and, therefore, the provision of de-reservation under Section
127 would not apply.
19. It is contended by Shri Soli J. Sorabjee and Shri
U.U. Lalit, learned senior counsel appearing for the appellants,
that the intent and purpose of Section 127 of the MRTP Act is
the acquisition of land within six months or the steps are
taken for acquisition of the land within six months, which
could only be when a declaration under Section 6 of the LA Act
is published in the Official Gazette. It is submitted by the
learned senior counsel that the words \023if within six months
from the date of the service of such notice, the land is not
acquired or no steps as aforesaid are commenced for its
acquisition\024 are not susceptible of a literal construction and
the words have to be given a meaning which safeguards a
citizen against arbitrary and irrational executive action which,
in fact, may not result in acquisition of the land for a long
period to come. It cannot be doubted that the period of 10
years is a long period where the land of the owner is kept in
reservation. Section 127 gives an opportunity to the owner for
de-reservation of the land if no steps are taken for acquisition
by the authorities within a period of six months in spite of
service of notice for de-reservation after the period of 10 years
has expired.
20. While interpreting the purpose of Section 127, this
Court in the matter of Municipal Corporation of Greater
Bombay v. Dr. Hakimwadi Tenants\022 Association and
Others, 1988 (Supp.) SCC 55, has said :
\02311. \005 It cannot be doubted that a period of 10
years is long enough. The Development or the
Planning Authority must take recourse to
acquisition with some amount of promptitude in
order that the compensation paid to the
expropriated owner bears a just relation to the real
value of the land as otherwise, the compensation
paid for the acquisition would be wholly illusory.
Such fetter on statutory powers is in the interest of
the general public and the conditions subject to
which they can be exercised must be strictly
followed.\024
The Court also said:
\023While the contention of learned counsel appearing
for the appellant that the words ‘six months from
the date of service of such notice\022 in Section 127 of
the Act were not susceptible of a literal
construction, must be accepted, it must be borne in
mind that the period of six months provided by
Section 127 upon the expiry of which the
reservation of the land under a Development Plan
lapses, is a valuable safeguard to the citizen against
arbitrary and irrational executive action. Section
127 of the Act is a fetter upon the power of eminent
domain.\024
21. Giving a plain meaning to the words used in the
statute would not be resorted to when there is a sense of
possible injustice. In such a case, the simple application of
the words in their primary and unqualified sense is not always
sufficient and will sometimes fail to carry out the manifest
intention of law-giver as collected from the statute itself and
the nature of subject-matter and the mischiefs to be remedied.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 21
If the plain words lead apparently to do some injustice or
absurdity and at variance with, or not required by, the scope
and object of the legislation, it would be necessary to examine
further and to test, by certain settled rules of interpretation,
what was the real and true intention of the legislature and
thereafter apply the words if they are capable of being so
applied so as to give effect to that intention. Where the plain
literal interpretation of statutory provision were to manifestly
result in injustice never intended by the legislature, the court
is entitled to modify the language used by the legislature so as
to achieve the intention of the legislature and to produce a
rational construction.
22. Where the legislature has used words in an Act
which if generally construed, must lead to palpable injustice
and consequences revolting to the mind of any reasonable
man, the court will always endeavour to place on such words a
reasonable limitation, on the ground that the legislature could
not have intended such consequence to ensue, unless the
express language in the Act or binding authority prevents
such limitation being interpolated into the Act. In construing
an Act, a construction ought not be put that would work
injustice, or even hardship or inconvenience, unless it is clear
that such was the intention of the legislature. It is also settled
that where the language of the legislature admits of two
constructions and if construction in one way would lead to
obvious injustice, the courts act upon the view that such a
result could not have been intended, unless the intention had
been manifested in express words. Out of the two
interpretations, that language of the statute should be
preferred to that interpretation which would frustrate it. It is
a cardinal rule governing the interpretation of the statutes that
when the language of the legislature admits of two
constructions, the court should not adopt the construction
which would lead to an absurdity or obvious injustice. It is
equally well settled that within two constructions that
alternative is to be chosen which would be consistent with the
smooth working of the system which the statute purported to
be regulating and that alternative is to be rejected which will
introduce uncertainty, friction or confusion with the working
of the system. [See Collector of Customs v. Digvijaysinhji
Spinning & Weaving Mills Ltd. (1962) 1 SCR 896, at page
899 and His Holiness Kesvananda Bharati v. State of
Kerala, AIR 1973 SC 1461].
23. The court must always lean to the interpretation
which is a reasonable one, and discard the literal
interpretation which does not fit in with the scheme of the Act
under consideration.
24. In series of judgments of this Court, these
exceptional situations have been provided for. In
Narashimaha Murthy v. Susheelabai, (1996) 3 SCC 644
(at page 647), it was held that:
\023\005The purpose of law is to prevent brooding
sense of injustice. It is not the words of the law but
the spirit and eternal sense of it that makes the law
meaningful\005.\024
In the case of American Home Products Corporation v.
Mac Laboratories Pvt. Ltd. and Another, AIR 1986 SC
137 (at page 166, para 66), it was held that:
\023 .. It is a well-known principle of
interpretation of statutes that a construction should
not be put upon a statutory provision which would
lead to manifest absurdity or futility, palpable
injustice, or absurd inconvenience or anomaly. \005\024
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 21
Further, in the case of State of Punjab v. Sat Ram Das,
AIR 1959 Punj. 497, the Punjab High Court held that:
\023To avoid absurdity or incongruity,
grammatical and ordinary sense of the words can,
in certain circumstances, be avoided.\024
25. Many a times, it becomes necessary to look into the
true intention of the legislature in order to give a proper effect
to the statutory provisions and in order to achieve the actual
intended goal behind the legislation. In the case of Tirath
Singh v. Bachittar Singh and others, AIR 1955 SC 830 (at
page 833, para 7), it was held by the Court that:
\023\005Where the language of a statute, in its
ordinary meaning and grammatical construction,
leads to a manifest contradiction of the apparent
purpose of the enactment, or to some inconvenience
or absurdity, hardship or injustice, presumably not
intended, a construction may be put upon it which
modifies the meaning of the words and even the
structure of the sentence\024.
The same has been upheld by the Supreme Court in
Commissioner of Income Tax, Bangalore v. J.H. Gotla,
AIR 1985 SC 1698 and in Andhra Cotton Mills Ltd. v.
Lakshmi Ganesh Cotton Mill, (1996) 1 ALT 537 (AP).
Similarly, in the case of State of Rajasthan v. Leela Jain
and Others, AIR 1965 SC 1296 (at page 1299, para 11), it was
held that:
\023\005Unless the words are unmeaning or absurd, it
would not be in accord with any sound principle of
construction to refuse to give effect to the provisions
of a statute on the very elusive ground that to give
them their ordinary meaning leads to consequences
which are not in accord with the notions of
propriety or justice\005\024
26. Learned senior counsel appearing on both sides
have strongly relied on the decision of this Court in Municipal
Corporation of Greater Bombay v. Dr. Hakimwadi
Tenants\022 Association and Others, 1988 (Supp.) SCC 55. It
is contended by the learned senior counsel for the appellants
that the decision squarely covers the proposition of law
wherein it has been held that the development or the planning
authority must take recourse to acquisition with some amount
of promptitude in order that the compensation paid to the
expropriated owner bears a just relation to the real value of
the land; and that the period of six months provided by
Section 127 upon the expiry of which the reservation of the
land under a development plan lapses, is a valuable safeguard
to the citizens against the arbitrary and irrational executive
action. Section 127 of the Act is a fetter upon the power of
eminent domain. On the other hand, the learned senior
counsel for the State submits that if we read para 11 of the
above judgment, it is clearly held that the steps for
commencement of the acquisition obviously refer to the steps
contemplated by Section 126(1) which means the step taken of
making an application under clause (c) of Section 126(1) of the
MRTP Act and has contended that this Court had already
observed that after the service of notice from the owner or any
person interested in the land as provided under Section 127 of
the MRTP Act, the steps taken within six months of such
service, included any step taken by the appropriate authority
for the acquisition of land as contemplated under the
provisions of Section 126 (1) of the MRTP Act. It has been
further contended that such observation of this Court is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 21
binding as precedent.
27. At this juncture, it will be appropriate for us to refer
some of the judicial pronouncements to illustrate what
constitutes the binding precedent. This Court in Additional
District Magistrate, Jabalpur v. Shivakant Shukla,
(1976) 2 SCC 521 has observed:
\023394. \005The Earl of Halsbury, L.C. said in Quinn v.
Leathem, 1901 AC 495, 506 that the generality of
the expressions which may be found in a judgment
are not intended to be expositions of the whole law
but are governed and qualified by the particular
facts of the case in which such expressions are to
be found. This Court in the State of Orissa v.
Sudhansu Sekhar Misra, (1968) 2 SCR 154, 163,
uttered the caution that it is not a profitable task to
extract a sentence here and there from a judgment
and to build upon it because the essence of the
decision is its ratio and not every observation found
therein\005\024
474. \005when we are considering the observations of
a high judicial authority like this Court, the greatest
possible care must be taken to relate the
observations of a judge to the precise issues before
him and to confine such observations, even though
expressed in broad terms, in the general compass of
the question before him, unless he makes it clear
that he intended his remarks to have a wider ambit.
It is not possible for judges always to express their
judgments so as to exclude entirely the risk that in
some subsequent case their language may be
misapplied and any attempt at such perfection of
expression can only lead to the opposite result of
uncertainty and even obscurity as regards the case
in hand...\024
In Union of India and Others v. Dhanwanti Devi and
Others, (1996) 6 SCC 44, a three-Judge Bench of this Court
has observed as follows:
\0239. \005It is not everything said by a Judge while
giving judgment that constitutes a precedent. The
only thing in a judges\022 decision binding a party is
the principle upon which the case is decided and for
this reason it is important to analyse a decision and
isolate from it the ratio decidendi. According to the
well-settled theory of precedents, every decision
contains three basic postulates - (i) findings of
material facts, direct and inferential. An inferential
finding of facts is the inference which the Judge
draws from the direct, or perceptible facts; (ii)
statements of the principles of law applicable to the
legal problems disclosed by the facts; and (iii)
judgment based on the combined effect of the
above. A decision is only an authority for what it
actually decides. What is of the essence in a
decision is its ratio and not every observation found
therein nor what logically follows from the various
observations made in the judgment. Every judgment
must be read as applicable to the particular facts
proved, or assumed to be proved, since the
generality of the expressions which may be found
there is not intended to be exposition of the whole
law, but governed and qualified by the particular
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 21
facts of the case in which such expressions are to
be found. It would, therefore, be not profitable to
extract a sentence here and there from the
judgment and to build upon it because the essence
of the decision is its ratio and not every observation
found therein. The enunciation of the reason or
principle on which a question before a court has
been decided is alone binding as a precedent. The
concrete decision alone is binding between the
parties to it, but it is the abstract ratio decidendi,
ascertained on a consideration of the judgment in
relation to the subject matter of the decision, which
alone has the force of law and which, when it is
clear what it was, is binding. It is only the principle
laid down in the judgment that is binding law under
Article 141 of the Constitution. A deliberate judicial
decision arrived at after hearing an argument on a
question which arises in the case or is put in issue
may constitute a precedent, no matter for what
reason, and the precedent by long recognition may
mature into rule of stare decisis. It is the rule
deductible from the application of law to the facts
and circumstances of the case which constitutes its
ratio decidendi.
10. Therefore, in order to understand and
appreciate the binding force of a decision it is
always necessary to see what were the facts in the
case in which the decision was given and what was
the point which had to be decided. No judgment can
be read as if it is a statute. A word or a clause or a
sentence in the judgment cannot be regarded as a
full exposition of law. Law cannot afford to be static
and therefore, Judges are to employ an intelligent
technique in the use of precedents\005\024
Similarly, in Director of Settlements, A.P. and Others v.
M.R. Apparao and Another, (2002) 4 SCC 638, a Bench
comprising of three Judges, has observed:
\0237. \005But what is binding is the ratio of the decision
and not any finding of facts. It is the principle found
out upon a reading of a judgment as a whole, in the
light of the questions before the Court that forms
the ratio and not any particular word or
sentence\005A judgment of the Court has to be read in
the context of questions which arose for
consideration in the case in which the judgment
was delivered. An \023obiter dictum\024 as distinguished
from a ratio decidendi is an observation by the
Court on a legal question suggested in a case before
it but not arising in such manner as to require a
decision...\024
This Court in Shin-Etsu Chemical Co. Ltd v. Aksh Optifibre
Ltd. and Another, (2005) 7 SCC 234 has observed:
\02369. \005if the court thinks that an issue does not
arise, then any observation made with regard to
such an issue would be purely obiter dictum. It is a
well-settled proposition that the ratio decidendi of a
case is the principle of law that decided the dispute
in the facts of the case and, therefore, a decision
cannot be relied upon in support of a proposition
that it did not decide. [See also: Mittal Engg.
Works (P) Ltd. v. CCE, (1997) 1 SCC 203 at p. 207
(para. 8); Jagdish Lal v. State of Haryana, (1997)
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 21
6 SCC 538 at p. 560 (para. 17); Divisional
Controller, KSRTC v. Mahadeva Shetty, (2003) 7
SCC 197 at p. 206 (para. 23).]\005\024
28. We will now analyse that whether the observations
of the Court in Municipal Corporation of Greater Bombay
Case (supra) as extracted from paragraph 11 of that Judgment
(supra) constituted binding or authoritative precedent with
respect to the question of law arising in the present case. In
Municipal Corporation of Greater Bombay Case (supra), the
planning authority had published a draft Development Plan in
which land of a trust property was reserved for a recreation
ground. The Development Plan was finalised and sanctioned
by the State Government on 6.1.1967. The final development
scheme came into effect from 7.2.1967. Since no action had
been taken for acquisition of the land until 1.1.1977, the
owners thereof, i.e., the trustees, served a purchase notice
dated 1.7.1977 on Corporation either to acquire the same or
release it from acquisition, and the same was received on
4.7.1977. On 28.7.1977 the Corporation\022s Executive Engineer
wrote a letter to the trustees asking information regarding the
ownership of the land and the particulars of the tenants
thereof. It was also stated that the relevant date under
Section 127 of the MRTP Act would be the date upon which
such information was received. The trustees, by their lawyer\022s
letter dated 3.8.1977, conveyed that the date of six months
stipulated by Section 127 had to be computed from the date of
the receipt from them of the information required and that
Corporation could not make an inquiry at that stage without
taking a decision on the material question. The Executive
Engineer once again wrote to trustees stating that the period
of six months allowed by Section 127 would commence on
4.8.1977, i.e., the date when the requisite information was
furnished. The Corporation passed a resolution dated
10.1.1978 for the acquisition of the land and made an
application to the State Government which on being satisfied
that the land was required for a public purpose issued the
requisite notification dated 7.4.1978 under Section 6 of the LA
Act for acquisition of the land. A petition was filed before the
High Court to quash the aforementioned notification, which
was allowed by the Single Judge and subsequently maintained
by the Division Bench. The contention of the appellant
Corporation before this Court was that the period of six
months after the notice by the owner or any person interested
in the land as specified under section 127, would start from
date when such person had provided the requisite information
to the Corporation.
29. In light of the above-mentioned factual matrix, the
question of law involved in the Municipal Corporation of
Greater Bombay Case (supra) was as follows:
\0232. The short point involved in this appeal by
special leave from a judgment of a Division Bench of
the Bombay High Court dated June 18, 1986, is
whether the period of six months specified in
Section 127 of the Act is to be reckoned from the
date of service of the purchase notice dated July 1,
1977 by the owner on the Planning Authority i.e.
the Municipal Corporation of Greater Bombay here,
or the date on which the requisite information of
particulars is furnished by the owner.\024
The Court has answered the above question as follows:
\0237. According to the plain reading of Section 127 of
the Act, it is manifest that the question whether the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 21
reservation has lapsed due to the failure of the
Planning Authority to take any steps within a period
of six months of the date of service of the notice of
purchase as stipulated by Section 127, is a mixed
question of fact and law. It would therefore be
difficult, if not well nigh impossible, to lay down a
rule of universal application. It cannot be posited
that the period of six months would necessarily
begin to run from the date of service of a purchase
notice under Section 127 of the Act. The condition
pre-requisite for the running of time under Section
127 is the service of a valid purchase notice. It is
needless to stress that the Corporation must prima
facie be satisfied that the notice served was by the
owner of the affected land or any person interested
in the land. But, at the same time, Section 127 of
the Act does not contemplate an investigation into
title by the officers of the Planning Authority, nor
can the officers prevent the running of time if there
is a valid notice\005\024
30. Thus, after perusing the judgment in Municipal
Corporation of Greater Bombay Case (supra), we have
found that the question for consideration before the Court in
the Municipal Corporation of Greater Bombay Case (supra)
has reference to first step required to be taken by the owner
after lapse of 10 years\022 period without any step taken by the
authority for acquisition of land, whereby the owners of the
land served the notice for dereservation of the land. The Court
was not called upon to decide the case on the substantial step,
namely, the step taken by the authority within six months of
service of notice by the owners for dereservation of their land
which is second step required to be taken by the authority
after service of notice. The observations of this Court regarding
the linking of word \021aforesaid\022 from the wordings \021no steps as
aforesaid are commenced for its acquisition\022 of Section 127 with
the steps taken by the competent authority for acquisition of
land as provided under Section 126(1) of the MRTP Act, had
no direct or substantial nexus either with the factual matrix or
any of the legal issues raised before it. It is apparent that no
legal issues, either with respect to interpretation of words \021no
steps as aforesaid are commenced for its acquisition\022 as
stipulated under the provisions of Section 127 or any link of
these words with steps to be taken on service of notice, were
contended before the Court. Thus, observations of the Court
did not relate to any of the legal questions arising in the case
and, accordingly, cannot be considered as the part of ratio
decidendi. Hence, in light of the aforementioned judicial
pronouncements, which have well settled the proposition that
only the ratio decidendi can act as the binding or authoritative
precedent, it is clear that the reliance placed on mere general
observations or casual expressions of the Court, is not of
much avail to the respondents.
31. When we conjointly read Sections 126 and 127 of
the MRTP Act, it is apparent that the legislative intent is to
expeditiously acquire the land reserved under the Town
Planning Scheme and, therefore, various periods have been
prescribed for acquisition of the owner\022s property. The intent
and purpose of the provisions of Sections 126 and 127 has
been well explained in Municipal Corporation of Greater
Bombay Case (supra). If the acquisition is left for a time
immemorial in the hands of the concerned authority by simply
making an application to the State Government for acquiring
such land under the LA Act, 1894, then the authority will
simply move such an application and if no such notification is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 21
issued by the State Government for one year of the publication
of the draft regional plan under Section 126(2) read with
Section 6 of the LA Act, wait for the notification to be issued by
the State Government by exercising suo motu power under
sub-section (4) of Section 126; and till then no declaration
could be made under Section 127 as regards lapsing of
reservation and contemplated declaration of land being
released and available for the land owner for his utilization as
permitted under Section 127. Section 127 permitted inaction
on the part of the acquisition authorities for a period of 10
years for de-reservation of the land. Not only that, it gives a
further time for either to acquire the land or to take steps for
acquisition of the land within a period of six months from the
date of service of notice by the land owner for de-reservation.
The steps towards commencement of the acquisition in such a
situation would necessarily be the steps for acquisition and
not a step which may not result into acquisition and merely
for the purpose of seeking time so that Section 127 does not
come into operation. Providing the period of six months after
the service of notice clearly indicates the intention of the
legislature of an urgency where nothing has been done in
regard to the land reserved under the plan for a period of 10
years and the owner is deprived of the utilization of his land as
per the user permissible under the plan. When mandate is
given in a Section requiring compliance within a particular
period, the strict compliance is required thereof as
introduction of this Section is with legislative intent to balance
the power of the State of \023eminent domain\024. The State
possessed the power to take or control the property of the
owner for the benefit of public cause, but when the State so
acted, it was obliged to compensate the injured upon making
just compensation. Compensation provided to the owner is
the release of the land for keeping the land under reservation
for 10 years without taking any steps for acquisition of the
same. The underlying principle envisaged in Section 127 of
the MRTP Act is either to utilize the land for the purpose it is
reserved in the plan in a given time or let the owner utilize the
land for the purpose it is permissible under the Town Planning
Scheme. The step taken under the Section within the time
stipulated should be towards acquisition of land. It is a step
of acquisition of land and not step for acquisition of land. It is
trite that failure of authorities to take steps which result in
actual commencement of acquisition of land cannot be
permitted to defeat the purpose and object of the scheme of
acquisition under the MRTPAct by merely moving an
application requesting the Government to acquire the land,
which Government may or may not accept. Any step which
may or may not culminate in the step for acquisition cannot
be said to be a step towards acquisition.
32. It may also be noted that the legislature while
enacting Section 127 has deliberately used the word ‘steps\022 (in
plural and not in singular) which are required to be taken for
acquisition of the land. On construction of Section 126 which
provides for acquisition of the land under the MRTP Act, it is
apparent that the steps for acquisition of the land would be
issuance of the declaration under Section 6 of the LA Act.
Clause (c) of Section 126(1) merely provides for a mode by
which the State Government can be requested for the
acquisition of the land under Section 6 of the LA Act. The
making of an application to the State Government for
acquisition of the land would not be a step for acquisition of
the land under reservation. Sub-section (2) of Section 126
leaves it open to the State Government either to permit the
acquisition or not to permit, considering the public purpose for
which the acquisition is sought for by the authorities. Thus,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 21
the steps towards acquisition would really commence when
the State Government permits the acquisition and as a result
thereof publishes the declaration under Section 6 of the LA
Act.
33. The MRTP Act does not contain any reference to
Section 4 or Section 5A of the LA Act. The MRTP Act contains
the provisions relating to preparation of regional plan, the
development plan, plans for comprehensive developments,
town planning schemes and in such plans and in the
schemes, the land is reserved for public purpose. The
reservation of land for a particular purpose under the MRTP
Act is done through a complex exercise which begins with land
use map, survey, population studies and several other
complex factors. This process replaces the provisions of
Section 4 of the LA Act and the inquiry contemplated under
Section 5A of the LA Act. These provisions are purposely
excluded for the purposes of acquisition under the MRTP Act.
The acquisition commences with the publication of
declaration under Section 6 of the LA Act. The publication of
the declaration under sub-sections (2) and (4) of Section 126
read with Section 6 of the LA Act is a sine qua non for the
commencement of any proceedings for acquisition under the
MRTP Act. It is Section 6 declaration which would commence
the acquisition proceedings under the MRTP Act and would
culminate into passing of an award as provided in sub-section
(3) of Section 126 of the MRTP Act. Thus, unless and until
Section 6 declaration is issued, it cannot be said that the steps
for acquisition are commenced.
34. There is another aspect of the matter. If we read
Section 126 of the MRTP Act and the words used therein are
given the verbatim meaning, then the steps commenced for
acquisition of the land would not include making of an
application under Section 126(1)(c) or the declaration which is
to be made by the State Government under sub-section (2) of
Section 126 of the MRTP Act.
35. On a conjoint reading of sub-sections (1), (2) and (4)
of Section 126, we notice that Section 126 provides for
different steps which are to be taken by the authorities for
acquisition of the land in different eventualities and within a
particular time span. Steps taken for acquisition of the land
by the authorities under clause (c) of Section 126(1) have to be
culminated into Section 6 declaration under the LA Act for
acquisition of the land in the Official Gazette, within a period
of one year under the proviso to sub-section (2) of Section
126. If no such declaration is made within the time
prescribed, no declaration under Section 6 of the LA Act could
be issued under the proviso to sub-section (2) and no further
steps for acquisition of the land could be taken in pursuance
of the application moved to the State Government by the
planning authority or other authority. Proviso to sub-section
(2) of Section 126 prohibits publication of the declaration after
the expiry of one year from the date of publication of draft
regional plan, development plan or any other plan or scheme.
Thus, from the date of publication of the draft regional plan,
within one year an application has to be moved under clause
(c) of Section 126(1) which should culminate into a declaration
under Section 6 of the LA Act. As per the proviso to sub-
section (2) of Section 126, the maximum period permitted
between the publication of a draft regional plan and
declaration by the Government in the Official Gazette under
Section 126(2) is one year. In other words, during one year of
the publication of the draft regional plan, two steps need to be
completed, namely, (i) application by the appropriate authority
to the State Government under Section 126(1)(c); and (ii)
declaration by the State Government on receipt of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 21
application mentioned in clause (c) of Section 126(1) on
satisfaction of the conditions specified under Section 126(2).
The only exception to this provision has been given under
Section 126(4). In the present case, the amended regional
plan was published in the year 1991. Thereafter, the steps by
making an application under clause (c) of sub-section (1) of
Section 126 for issuance of the declaration of acquisition and
the declaration itself has to be made within the period of one
year from the date of the publication of regional plan, that is,
within the period of one year from 1991. The application
under Section 126(1)(c) could be said to be a step taken for
acquisition of the land if such application is moved within the
period of one year from the date of publication of regional
plan. The application moved after the expiry of one year could
not result in the publication of declaration in the manner
provided under Section 6 of the LA Act, under sub-section (2)
of Section 126 of the MRTP Act, there being a prohibition
under the proviso to issue such declaration after one year.
Therefore, by no stretch of imagination, the step taken by the
Municipal Corporation under Section 126(1)(c) of making an
application could be said to be a step for the commencement
of acquisition of the land. After the expiry of one year, it is left
to the Government concerned under sub-section (4) of Section
126 to issue declaration under Section 6 of the LA Act for the
purposes of acquisition for which no application is required
under Section 126(1)(c). Sub-section (4) of Section 126 of the
MRTP Act would come into operation if the State Government
is of the view that the land is required to be acquired for any
public purpose.
36. The High Court has committed an apparent error
when it held that the steps taken by the respondent-
Corporation on 9.9.2002 and 13.9.2002 would constitute
steps as required under Section 126(1)(c) of the MRTP Act.
What is required under Section 126(1)(c) is that the
application is to be moved to the State Government for
acquiring the land under the LA Act by the planning/local
authority. Passing of a resolution by the Improvement
Committee recommending that the steps be taken under
Section 126(1)(c) or making an application by the Chief
Engineer without there being any authority or resolution
passed by the Municipal Corporation, could not be taken to be
steps taken of moving an application before the State
Government for acquiring the land under the LA Act. The
High Court has committed an apparent error in relying on
these two documents for reaching the conclusion that the
steps for acquisition had been commenced by the Municipal
Corporation before the expiry of period of six months which
was to expire on 18.9.2002. Further, if we look at the letter
dated 17.9.2002 which, as per the counsel for the respondent-
Corporation, is a request made by the Municipal Corporation
to the State Government under clause (c) of Section 126(1), we
cannot agree with the submissions of the respondents. The
letter itself shows that the resolution was passed by the
Municipal Corporation on 16.9.2002 whereby it was informed
that the sanction had been accorded to initiate the acquisition
proceedings for the land in question. The letter also
mentioned that the authorization had been given to the
Municipal Commissioner to make an application to the State
Government as per the provisions of Section 126(1) of the
MRTP Act. Under Section 2(19) read with Section 2(15) with
Section 126(1) of the MRTP Act, the application to the State
Government under clause (c) of Section 126(1) has to be made
by the planning/local authority, i.e. the Municipal
Corporation of Greater Mumbai constituted under the Bombay
Municipal Corporation Act. The Municipal Corporation had
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 21
passed a resolution delegating authority to Municipal
Commissioner for making an application to the State
Government, but the application/letter either dated 13.9.2002
or 17.9.2002 were made to the State Government by the Chief
Engineer (Development Plan). The authority was given by the
Municipal Corporation to the Municipal Commissioner to
make an application to the State Government. No such
application or letter moved by the Municipal Commissioner
has been produced before us. On being asked by this Court,
as many as six documents have been produced before us by
the counsel for the Municipal Corporation who has stated
before us that these documents were also placed before the
Division Bench of the Bombay High Court. Therefore, we have
permitted production of these documents before us. On a
minute and careful scrutiny of the documents produced before
us, we do not find that the application under clause (c) of
Section 126(1) was moved by the officer authorized by the
Municipal Corporation, i.e. the Municipal Commissioner, to
the State Government for acquisition of the land, so that it
could be said that steps as contemplated were taken for the
commencement of acquisition proceedings.
37. In view of our decision on the interpretation and
applicability of Section 127 of the MRTP Act to the facts of the
present case, the appellants are entitled to the relief claimed,
and the other question argued on the applicability of the newly
inserted Section 11A of the LA Act to the acquisition of land
made under the MRTP Act need not require to be considered
by us in this case.
38. For the aforesaid reasons, the impugned judgment
and order dated 18.3.2005 passed by the Division Bench of
the Bombay High Court is set aside and this appeal is allowed.
As no steps have been taken by the Municipal Corporation for
acquisition of the land within the time period, there is deemed
de-reservation of the land in question and the appellants are
permitted to utilise the land as permissible under Section 127
of the MRTP Act.