Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
CASE NO.:
Appeal (civil) 7032 of 2001
PETITIONER:
RAJASTHAN STATE ROAD TRANSPORT CORPN.
RESPONDENT:
INDAG RUBBER LTD.
DATE OF JUDGMENT: 05/09/2006
BENCH:
H.K. SEMA & A.K. MATHUR
JUDGMENT:
JUDGMENT
A.K. MATHUR, J.
This appeal is directed against the order dated 22.12.2000 passed by
learned Single Judge of the High Court of Judicature for Rajasthan, Jaipur
Bench, Jaipur in S.B. Civil Misc. Appeal No.618 of 2000 whereby learned
Single Judge set aside the order passed by the District Judge, Jaipur City
in CMA (Arb.) No.256 of 1997 confirming the award dated 4.4.1997 passed by
the Arbitrator and issuing a decree in terms of the award in favour of the
Rajasthan State Road Transport Corporation (hereinafter to be referred to
as the Corporation).
The facts giving rise to this appeal are that an agreement was executed
between Indag Rubber Limited ( hereinafter to be referred to as the
Company) and the Corporation on 24.7.1991 for purchase of cold processing
retreading plant and retreading material. According to Clause 3 of the
agreement, in the cold processing plant of the company no other retreading
material except of Indag would be used during subsistence of the contract
provided the company supplies retreading material regularly and
uninterruptedly as per the need of the Corporation. Clause 4 contemplated
that the corporation would purchase retreading material from the company at
the prevailing rates against the rate contract of the Association of State
Road Transport Undertaking. Clause 5 deals with warranty for retreaded
tyres, according to which the company was required to guarantee performance
of 46000 KMs average life or 95% of new tyres in each division in similar
condition whichever is less and the performance would be assessed initially
after 12 months on the commissioning of plant and production of tyres and
subsequently on quarterly basis, and on failure of guaranteed kilometers,
the company is bound to compensate on pro rata basis. Clause 10 pertains to
arbitration. As per the arbitration clause any dispute between the parties
regarding interpretation of the terms and conditions or their fulfillment,
both the parties shall refer the dispute to the Chairman of the Corporation
who after hearing both the parties shall give the decision which shall be
final and binding on the parties.
The grievance of the Corporation was that retreaded tyres used on its
buses, such tyres could not achieve the guaranteed kilometers as per
warranty clause 5, whereupon the company was informed of such deficiency in
its retreaded tyres. The Corporation informed the company through their
various letters dated 27.2.1993, 30.3.1993, 12.5.1993, 29.6.1993,
15.7.1993, 20.1.1994 and 16.7.1994 that retreaded tyres used on its buses
in their eight regions were not giving the guaranteed kilometerage
resulting in loss to the corporation to the tune of Rs.1,19,53,430.92 paise
with 18% interest. Therefore, the Corporation called upon the company to
make payment of the aforesaid loss calculated on the basis of pro rata on
each retreaded tyre. The Corporation also claimed a sum of Rs.25 lacs
towards damages. Therefore, the total amount claimed by the Corporation
worked out to Rs.1,44,53,430.92 paise. The Company denied its liability and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
submitted that the Corporation has wrongly construed the agreement because
the essential feature of warranty clause 5 was that comparative assessment
of new tyre life with retreaded tyre was to be made in each division in
similar conditions. It was also submitted that as per clause 3 complete
retreading material which also included repair material was to be purchased
from the Company only because of the reason that after a tyre is worn out
it is first repaired so as to give it basic strength before it is retreaded
thereby repairing of tyre was essential part of the process of retreading.
Surprisingly enough the Corporation did not purchase any repair material
from the company resulting in breach of clause 3 of the agreement.
According to the company, since improper repair material was used by the
Corporation, therefore, 25% to 30% of the tyres allegedly removed
prematurely had caused damages on account of bursting, cutting of the
tyres, which could not have been used or considered for assessment of a
retreaded tyre’s life. It is alleged that the Company by its letters dated
14.11.1991, 16.11.1991, 17.1.1992 and 7.5.1992 had informed the Corporation
that while assessing performance of retreaded tyres, the tyres removed from
wheels prematurely due to bursts should be treated separately like one side
wear or spotty wear, run flat etc. should not be taken into account. For
the performance of remaining tyres only comparison should be made with the
new tyres. The Company also advised that the repair material should be
purchased from the company and it was also mentioned that the tyres should
be compared in similar condition and since the new tyres were fitted on the
rear axle, therefore the performance was bound to be lower and thus
assessment of performance of the retreaded tyres was not in similar
conditions. It was also pointed out that performance should be compared
with new tyres of the same design as on rear axles in each division before
comparison with performance of Indag retreaded tyres. It was also pointed
out by communication dated 14.5.1990 that the performance of retreaded
tyres when used on the front wheels should be compared with new tyres’
performance on the front wheels fitted to the vehicles operated on similar
routes likewise the tyres used on rear axle. It was also submitted that
since the Corporation used retreaded tyres in conditions not similar to one
in which new tyres were used, therefore, their performance was bound to
vary. The Company emphasized that the method of assessment adopted by the
Corporation was not proper. The Company cited the case of Maharashtra State
Road Transport Corporation and submitted that new tyres were fitted on the
same axle of the bus as of retreaded tyres and then the performance was to
the extent of 97 to 99 % with that of the new tyre. It was submitted that
because of not employing the same method of assessment the result has
varied. The Company cited the example of Ajmer Division and pointed out
that performance of retreaded and new tyres is satisfactory. It was also
pointed out that the performance was likely to vary Divisionwise because
Jaipur- Delhi national highway route could give a better result than the
Jaipur Lalsot route as it is not having similar condition as that of
Jaipur Delhi National Highway. The company also joined the issues with
regard to calculation of loss. On the basis of these pleadings, a sole
arbitrator was appointed i.e. the Principal Secretary, Home and Justice,
Government of Rajasthan. The arbitrator framed the following three issues
for determination.
" (1) Whether the retreaded tyres which failed for other reasons
like burst etc. should be taken into account while assessing
performance of the retreaded tyres ?
(2) Whether the claimant was required to use repair material
supplied by Indag only ? and
(3) Whether the retreaded tyres and new tyres were used in similar
conditions for the purpose of assessing their comparative
performance?"
The arbitrator after hearing the parties and taking into consideration the
documents on record decided all the issues in favour of the Corporation by
its award dated 4.4.1997 and concluded that the Corporation suffered a loss
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
to the tune of Rs.1,19,53,430.92 paise. However, the arbitrator declined to
grant additional sum of Rs.25 lacs claimed as damages by the Corporation.
After that award dated 4.4.1997 was produced in the Court of the District
Judge on 24.5.1997, the District Judge issued notice to both the parties
and after considering the matter and hearing the parties made the award as
a rule of the court by its order dated 22.11.1999. Aggrieved against the
said order, the Company filed an appeal before the High Court of Rajasthan
and the matter came up before the learned Single Judge for disposal.
Learned Single Judge after examining the matter held that the essential
feature of the warranty clause for comparative assessment of new tyres with
the retreaded tyres was necessary to be made in each division in similar
condition. Learned Single Judge further held that method of assessment was
not in conformity with reference to warranty clause 5 that comparative
assessment of performance of retreaded tyres with new ones, was improper.
It was also observed that as per figures shown by the Corporation they had
used 14,395 retreaded tyres from June, 1991 to May, 1992 out of which total
tyres received after completing retreaded life were 7,797. Learned Single
Judge also held that as per the inspection report dated 19.11.1991 total
148 tyres were inspected. Similarly, on 20.11.1991 30 tyres were inspected.
It was also observed that apart from joint inspection report, three other
inspections were held for 452 tyres on 4.10.1991, 135 tyres on 29.10.1991
and 522 tyres on 12.11.1991 and as per these joint inspection reports, the
Corporation claimed that the tyres had not performed according to their
warranty as stipulated in Clause 5 of the agreement. Learned Single Judge
further held that the inspection reports as well as other documentary
evidence led by both the parties did not show comparative assessment of
retreaded and new tyres with a view to find out as to the guaranteed
kilometerage as stipulated in clause 5 of the agreement. Learned Single
Judge concluded that in his considered opinion, the significant aspect
bearing material to the dispute under the arbitration as to the award of
compensation on pro rata basis has totally been ignored not only by the
arbitrator but also by the District Judge under the impugned award and
decree. Learned Single Judge further observed that the arbitrator did not
apply his mind to the joint inspection reports or calculation sheet on the
basis of which the Corporation has claimed compensation considering only
performance of retreaded tyres without making comparative assessment of
performance of both retreaded and new tyres. On the basis of the above
finding, learned Single Judge set aside the judgment and decree passed by
the District Judge, Jaipur City confirming the award dated 4.4.1997 passed
by the arbitrator and remanded back the matter to the Corporation for fresh
adjudication of the dispute by appointing an arbitrator other than the one
who has passed the award earlier. Aggrieved against this impugned order
passed by learned Single Judge, High Court of Rajasthan at Jaipur, the
present Special Leave Petition was filed by the Corporation.
We have heard learned counsel for the parties and perused the records.
Learned counsel for the appellant strenuously urged before us that the
learned Single Judge has upset the finding of fact recorded by the
arbitrator and has examined the matter like an appellate authority which is
not open to the learned Single Judge. Learned counsel for the appellant
submitted that the arbitrator after recording necessary evidence and after
examining the whole material on record, came to the finding that the claim
of the Corporation deserves to be accepted partially. But the learned
Single Judge sitting as a court of appeal has upset the finding of fact
recorded by the arbitrator. Learned counsel for the appellant in support of
his submission invited our attention to a decision of this Court in the
case of B.V. Radha Krishna v. Sponge Iron India Ltd., reported in [1997] 4
SCC 693 and submitted that it is not open to the learned Single Judge to
sit as a court of appeal while disposing of the award of the arbitrator
which was made the rule of the court. In the above decision, it was
observed as under:
"Bearing in mind the principles laid down by this Court in the
abovesaid cases, if we look into disposal of the matter by the High
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
Court, it would be evident that the High Court has substituted its
own view in place of the Arbitrator’s view as if it was dealing
with an appeal. That is exactly what is forbidden by the decisions
of this Court. Therefore, we have no hesitation to set aside the
judgment of the High Court on this issue."
In this connection, learned counsel for the appellant invited our attention
to a decision of this Court in the case of State of Rajasthan v. Puri
Construction Co.Ltd. & Anr., reported in [1994] 6 SCC 485 wherein it was
observed as under:
"However, in the anxiety to render justice to the party to arbitration, the
court should not reappraise the evidence intrinsically with a close
scrutiny for finding out that the conclusion drawn from some facts, by the
arbitrator is, according to the understanding of the court, erroneous. Such
exercise of power which can be exercised by an appellate court with power
to reverse the finding of fact, is alien to the scope and ambit of
challenge of an award under the Arbitration Act. If a question of law is
referred to arbitrator and the arbitrator comes to a conclusion, it is not
open to challenge the award on the ground that an alternative view of law
is possible. Even if it is assumed that on the materials on record, a
different view could have been taken and the arbitrators have failed to
consider the documents and materials on record in their proper perspective,
the award is not liable to be struck down in view of judicial decisions
referred to hereinbefore. Error apparent on the face of the record does not
mean that on the closer scrutiny of the import of documents and materials
on record, the finding made by the arbitrator by itself does not constitute
misconduct warranting interference with the award."
As against this, learned counsel for the respondent-Company submitted that
in fact there was no material on which the finding was recorded by the
Arbitrator. In support thereof, learned counsel invited our attention to a
decision of this Court in the case of K.P. Poulose v. State of Kerala &
Anr., reported in [1975] 2 SCC 236 wherein it was held that the award can
be set aside on the ground of misconduct if relevant documents are not
considered by the Arbitrator. Therefore, we asked learned counsel for the
appellant- Corporation to substantiate the finding recorded by the
arbitrator that it is based on the material on record. In pursuance to the
direction given by this Court, learned counsel for the Corporation filed
an affidavit on 12.7.2006 and submitted that the document wherein the
details on divisionwise average kilometer of new tyres and retreaded tyres
along with average short-fall in guaranteed kilometers for the various
periods was on record of arbitrator and same was produced before us. The
details were given of all the Divisions i.e. Bharatpur, Jaipur, Sikar,
Kota, Ajmer, Bikaner, Jodhpur and Udaipur. In all these eight divisions
for the various period i.e. from June 1991 to February, 1994 the details
have been given to substantiate the allegations that what was the average
mileage of the new tyre and what was the average mileage given by the
retreaded tyres and on that basis, the short-fall was given and
accordingly, the amount of loss was worked out. These details which were
placed before us formed part of the record before the arbitrator. The
arbitrator in his detailed award has recorded his finding on the basis of
the average performance of new vehicle tyres witht that of the retreaded
tyres of the Company and on that basis he has worked out the assessment in
paragraph 17 of the award. Paragraph 17 of the award reads as follows :
"The RSRTC has compared the performance of retreaded tyres with the
performance of new tyres in each division. In each division, as mentioned
earlier, the road conditions, the vehicles used, the weather conditions,
the general driving skills of the drivers and the level of maintenance and
upkeep of vehicles were similar for the new tyres as well as retreaded
tyres. The retreaded tyres should have given a kilometerage of 46,000 or 95
% of the life of new tyres. Therefore, the assessment of the performance
done by the RSRTC is strictly in conformity with the provisions of clause 5
of the agreement. Notwithstanding the acceptance by the respondent of an
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
error of judgment in guaranteeing 46,000 kms for a retreaded tyre, from the
Statements enclosed by the claimant with its letters mentioned in para 5 of
this order, it is clear that the retreaded tyres performance fell short of
the guaranteed level. I, therefore, find claim of the RSRTC to be fully
justified."
This is the finding of fact given by the arbitrator. As against this,
learned Single Judge as mentioned above, has held that there was no
assessment in each division in similar conditions. Therefore, the learned
Single Judge set aside the award but it is not factually correct. As
mentioned above, there was a comparative assessment given by the
Corporation and that was part of the record before the arbitrator and on
that basis the finding of fact was recorded by the arbitrator. Learned
counsel for the respondents strenuously urged before us that the
performance of new tyres and of retreaded tyres on roads like Jaipur-Delhi
would be better as against the road of Jaipur-Lalsot. Therefore, there was
no assessment of performance of the new tyres vis-a-vis the retreaded tyres
supplied by the Company in similar conditions. In fact, an average has to
be taken of each division. It is not necessary that in each of the
divisions of the Corporation, the road conditions will be similar. Once the
company has entered into an agreement knowing fully well the conditions
obtaining in the State of Rajasthan that all the routes in the State are
not the roads of Class ‘A’ category but there are roads of Class ‘A’, Class
‘B’ and Class ‘C’ categories also. Therefore, the average performance has
been recorded taking into consideration this aspect. It is unlikely that
all over the State of Rajasthan the road condition like Jaipur-Delhi will
be available for all other divisions. Therefore, in all the divisions the
average performance has been taken into consideration. The assessment has
been based on average of similar conditions of the roads i.e. the good
quality as well as the poor quality. Therefore, average performance of the
new tyres with the retreaded tyres has to be taken on the basis of roads
available in Rajasthan. The average running of the new tyres on these road
conditions with that of the retreaded tyres was to be compared to find out
whether the performance of retreaded tyres was up to 95% average or not.
After assessing the comparative assessment and going through the materials
on record the arbitrator has recorded his finding. It was for the company
if they wanted more information or wanted to allege that the road
conditions are not similar or that the performance of the tyres which were
fitted in the rear axle or on the front axle would not be the same, all
these details if it wanted, it could have obtained from the Corporation but
they did not do so and only at this stage the company wants to bring this
factual controversy that retreaded tyres were not used in similar
conditions. This argument at this belated stage cannot be accepted as all
the materials have been considered by the arbitrator and after taking into
consideration the average of each tyre in each region of the corporation
has worked out that the performance of the retreaded tyres was not to the
extent of 95%. This was a finding of fact recorded by the arbitrator and
the same was made rule of the court by the District Judge. But the learned
Single Judge erroneously took upon himself to sit as a court of appeal and
disturbed this finding of fact. In our opinion, the view taken by the
learned Single Judge of the High Court cannot be sustained.
Learned counsel for the respondent-company next submitted that the
arbitrator has awarded interest at the rate of 12% per annum from the date
of the award i.e. 4.4.1997. Learned counsel for the respondent submitted
that it was excessive as long spell of time has expired since the date of
the award. Therefore, granting of interest at the rate of 12% per annum
will be burdensome for the company. Therefore, learned counsel for the
respondent prayed that some relief in interest be given. After bestowing
our best of consideration, we are of opinion that awarding of interest at
the rate of 12% per annum from the date of award i.e. 4.4.1997 till the
realization of the amount will be too excessive. Therefore, looking to the
peculiar facts and circumstances of this case, we reduce the rate of
interest from 12% to 6% per annum. We allow this appeal and set aside the
judgment and order dated 22.12.2000 passed by learned Single Judge of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
High Court of Rajasthan at Jaipur in SBCMA No.618 of 2000 and affirm the
decree passed by the District Judge, Jaipur City making the award rule of
the Court. The appellant shall be entitled to interest at the rate of 6%
per annum from the date of the award till realization of the amount in
question. No order as to costs.