Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
PETITIONER:
AHMEDABAD MUNICIPAL CORPN. ETC.ETC.
Vs.
RESPONDENT:
SHARDABEN & ORS. ETC. ETC.
DATE OF JUDGMENT: 19/01/1996
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
NANAVATI G.T. (J)
CITATION:
JT 1996 (2) 453 1996 SCALE (2)311
ACT:
HEADNOTE:
JUDGMENT:
O R D E R
Leave granted.
We have heard learned counsel for both sides. The
notification under Section 4(1) of the Land Acquisition
Act (Act 1 of 1894) (for short, ’the Act’) was
published on September 23, 1980 acquiring a large
extent of land in different survey numbers for laying
Ring Road around Ahmedabad City. The Land Acquisition
Officer passed three awards relating to two villages,
Wadaj and Memnagar on three different dates, namely,
September 29, 1984, December 31, 1985 and September 23,
1986 fixing compensation ranging between Rs.50-80/- per
square meter Dissatisfied therewith, the claimant
sought references under Section 18. The City Civil
Court at Ahmedabad by three awards determined the
compensation. In the first award, the civil court
enhanced the compensation to Rs.100/- per square meter
and in the next two awards, it confirmed the award of
the Land Acquisition Officer. In other words, he made
nil award. On appeal under Section 54 of the Act, the
Division Bench of the High Court in the impugned
judgment dated August 4/5, 1993 uniformly enhanced the
compensation to Rs. 190/- per square meter. Thus, these
appeals by special leave.
Mr. B.K. Mehta, learned counsel for the
appellant, vehemently contended that the High Court was
wrong in its view. When no specific evidence relatable
to particular survey number of comparable sale had been
adduced by the parties, the High Court was wrong in
adopting the average and determining the compensation
on the basis of the average. Though we find force in
the contention of learned counsel for the appellants,
one important distinguishing feature which we have to
notice in these appeals is that the acquisition relates
to small strips of lands comprised in different survey
numbers cutting into several lands for the purpose of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
laying a running Ring Road. In other words, the
acquired land does not consist of a compact block for
determination of compensation in which event the
criticism of Shri Mehta would bear relevance and would
need closar scrutiny and examination. The burden is
always on the claimants to prove by adducing reliable
evidence that the compensation offered by the Land
Acquisition Officer is inadequate and the lands are
capable of fetching higher market value. It is the duty
of the Court to closely scrutinize the evidence, apply
the test of prudent and willing purchaser, i.e.,
whether he would be willing to purchase in open and
normal market conditions of the acquired lands and then
determine just and adequate compensation.
In these appeals we find that the claimants have
adduced evidence regarding sales of some lands in the
locality. Though the evidence as regards comparability
of those lands with the lands under acquisition was
general and not specific, it could still be relied
upon. So also, though the sale instances were of lands
situated near some of the lands acquired only, they
could still be relied upon as acquisition in these
cases is of contiguous plots. In the very nature of
acquisition, it would be difficult to find evidence of
sale of land identical with each piece of land
acquired. Under these circumstances, the High Court
has looked into the evidence generally and broadly and
then determined the compensation. Though this Court
has repeatedly not approved of the principle of
determination of compensation on the basis of average,
the conclusion reached by the High Court in the
peculiar facts and circumstances of these cases cannot
be said to be
unreasonable. Under these circumstances, we do not
think that these appeals call for any interference for
further enhancement of the compensation to reduce the
market value.
The appellant-Corporation is directed to pay the
balance amount and interest within four months from
today. Contempt Petition Nos.13-17 of 1995 and I.A.
Nos.45-70 are dismissed.
These appeals and cross-appeals are accordingly
dismissed. No costs.