Full Judgment Text
$~32
* IN THE HIGH COURT OF DELHI AT NEW DELHI
rd
% Date of Judgment: 23 March, 2021
+ O.M.P. (COMM) 127/2021 and IA NOS. 4107/2021 &
4106/2021
NATIONAL HIGHWAYS AUTHORITY
OF INDIA ..... Petitioner
Through: Mr Saurabh Banerjee, Standing
Counsel for NHAI.
Versus
M/S. C.P. RAMA RAO [PROPRIETOR] ..... Respondent
Through: Mr. Ram Babu, and Mr Angad
Mehta, Advocates.
CORAM:
HON'BLE MR. JUSTICE VIBHU BAKHRU
VIBHU BAKHRU, J. (ORAL)
1. The petitioner (hereinafter ‘NHAI) has filed the present petition
under Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter the ‘A&C Act’), inter alia, impugning the Arbitral Award
dated 12.12.2020 (hereinafter the ‘impugned award’) passed by the
Arbitral Tribunal comprising of a Sole Arbitrator.
2. The impugned award was rendered in respect of disputes that
had arisen between the parties in relation to an agreement dated
30.07.2016 (hereinafter the ‘Contract Agreement’) entered into
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 1 of 18
between the parties for “ Collection of user fee of Vemapadu Fee Plaza
at Km. 795.498 for Ankaapalli to Tuni Section from Km. 358.00 to
Km. 272.00 (New Chainage from Km. 830.525 to Km. 741.255) of
NH-5 in the State of Andhra Pradesh ” (hereinafter the ‘project’).
3. On 17.06.2016, NHAI invited tenders by issuing a Request for
Proposal (RFP) in respect of work relating to collection of User Fee at
Vempadu Toll Plaza located at Km. 795.498 on the stretch extending
from Km. 830.525 to Km. 741.255 on National Highway No.5 (now
renamed as National Highway No.16) in the State of Andhra Pradesh.
4. On 21.07.2016, the respondent submitted the financial bid for
the aforesaid work. He was declared the highest bidder and NHAI
issued a Letter of Acceptance. Thereafter, on 30.07.2016, the parties
entered into a Contract Agreement, whereby the respondent was
granted the concession for collecting User Fee at Vempadu Toll Plaza
for a period of one year with effect from 08:00:00 hours on
01.08.2016 to 07:59:59 hours on 01.08.2017. In terms of the Contract
Agreement, the respondent was required to pay ₹2,24,40,274/- per
week to NHAI. The said payment was exclusive of any TCS or any
taxes or service charges as applicable.
5. In terms of Clause 19 of the Contract Agreement, the
respondent was liable to pay penalty at the rate of 0.2% per day for
initial one month delay and at the rate of 0.5% per day for further
delay beyond one month in remittance of the agreed amount. In terms
of Clause 17(b)(i) of the Contract Agreement, the respondent also
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 2 of 18
furnished the following performance security: (i) cross DD, Pay order
in the sum of ₹ 9,75,09,000/- and (ii) bank guarantee being BG No.
24/2016 dated 30.07.2016 in the sum of ₹9,75,09,000/- issued by
Indian Bank.
6. The Government of India rolled out the Goods of Services Tax
(GST) with effect from 01.07.2017. The said levy subsumed all
indirect taxes.
7. The respondent claimed that in view of the uncertainty
surrounding the implementation of GST, there was a rapid decline in
the movement of traffic and it adversely affected the collection of
tolls. The respondent brought this to the notice of NHAI by its letter
dated 05.07.2017.
8. The respondent informed NHAI that he had incurred a loss of
₹52,62,228/- on account of reduction in collection of tolls for the
period 28.06.2017 to 05.07.2017. According to the respondent, the
said communication was received by the Project Director (PD) and
was submitted to the Regional Office (RO) for assessment. Thereafter,
the respondent sent another letter dated 08.07.2017, tabulating the loss
incurred by him for the period from 28.06.2017 to 07.07.2017 at ₹
62,89,975/-. This was also followed by another letter dated 12.07.2017
whereby the respondent quantified the loss for the period from
28.06.2017 to 11.07.2017 at ₹ 85,21,924/-. The respondent also sent
letters claiming loss on account of demonetization and of high value
currency notes and unprecedented floods.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 3 of 18
9. Finally, on 08.08.2017, the respondent sent a letter quantifying
its loss for the period 28.06.2017 to 04.08.2017 at ₹ 2,39,28,340/-. The
respondent claimed as a shortfall in remittances at ₹1,31,73,252/-.
10. On 07.04.2018, the concerned PD sent a letter to the RO,
providing a detailed analysis of its determination of loss suffered by
the respondent for the period from 01.07.2017 to 04.08.2017 at
₹1,03,88,126/- on account of implementation of GST.
11. The respondent claimed that the roll out of GST and other
events fall within the scope of ‘force majeure events’ under the
Contract Agreement and accordingly, the respondent sought payment
of compensation and/or waiver of part of the remittance from NHAI.
The said communications were also accompanied by analysis and data
which, according to the respondent, established the loss incurred by
him.
12. The respondent claimed that the introduction of GST to
subsume all existing indirect taxes constituted a change in law. The
respondent further asserted that the same had a material effect on his
obligations under the Contract Agreement and therefore, constituted a
force majeure event in terms of sub-clause (v) of Clause 25(b) of the
Contract Agreement.
13. The loss suffered by the respondent was verified by two
separate and independent PDs and both PDs calculated and tabulated
the difference between the agreed and actual remittance and
accordingly, recommended the release of the amounts under the Force
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 4 of 18
Majeure clause of the Contract Agreement. PD (Shri J. Ch.
Venkataratnam) determined the loss occasioned to the respondent for
the period from 01.07.2017 to 04.08.2017 as ₹ 1,03,88,126/- while PD
(A. Srinavas Rao) independently determined the loss at the same
amount.
14. NHAI in its letter dated 20.01.2019 to the PD, rejected the
respondent’s claim on the ground that “ the variation in the traffic
comparing to July 2016 to July 2017 is only 1.362% which is very
nominal and hence does not qualify for Force Majeure… ”. Thereafter,
a learned Sole Arbitrator was appointed by this Court on 26.09.2019.
The parties referred the disputes to the Arbitral Tribunal and the
arbitral proceedings culminated in the impugned award.
15. The Respondent filed it Statement of Claims and claimed the
following: (i) to declare the period from 01.07.2017 to 04.08.2017 as a
Force Majeure event under Clause 25 of the Toll Agreement; (ii)
waiver of payment of ₹ 1,03,88,126/-; (iii) release of Performance
Security Bank Guarantee No. 24/2016 dated 30.07.2016 as executed
from time to time; (iv) Expenses of ₹ 41,64,750/- for locking of
Performance Security Bank Guarantee No. 24/2016 dated 30.07.2016
with effect from 01.08.2017 till the date of filing of the Statement of
Claim (that is, 24.09.2019) as well as the actual cost of renewal of
Performance Security Bank Guarantee No. 24/2016 dated 30.07.2016
till the actual date of release; (v) refund of both Performance Bank
Guarantees of ₹ 9,75,09,000/- [₹ 5,00,000 + ₹4,75,09,000] deposited
with NHAI along with interest at 18% per annum with effect from
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 5 of 18
30.08.2017; (vi) Interest of ₹ 1,85,35,3444/- towards interest paid by
the respondent towards overdraft of ₹ 7,25,00,000/-; and (vii) cost(s)
of the arbitration proceedings.
16. The Arbitral Tribunal considered the rival contentions. It held
that the introduction of GST was a new legislation approved by both
houses of the Parliament of India and NHAI itself had, in a circular
dated 16.03.2018, accepted the introduction of GST as a ‘change in
law’. It further held that in terms of Clause 25(b) of the Contract
Agreement, only that ‘change in law’ which has a ‘material adverse
effect’ on the obligations of the parties can be treated as a force
majeure event and an estimated loss of ₹1,03,88,126/-, as assessed by
the PD, cannot be considered as immaterial.
17. The Arbitral Tribunal further held that the respondent was
entitled to return of the two performance securities after termination of
the Contract Agreement and NHAI was obligated to release the same
within a period of thirty days from the date of termination of the
contract. Accordingly, the Contract closed on 04.08.2017 and thus, the
respondent was entitled to the same by 04.09.2017. Accordingly, the
Arbitral Tribunal also awarded a sum of ₹41,64,750/- on account of
expenses incurred on keeping the Bank Guarantees alive and the same
was also not disputed by NHAI.
18. The Arbitral Tribunal also awarded interest at 8% per annum
with effect from 04.09.2017 till the date of the award and if the same
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 6 of 18
was not paid within three mounts, then future interest at 8% per
annum from the date of the Arbitral Award till the date of payment.
19. A tabular statement summarising the award as set out in the
impugned award is reproduced below:
| SI.<br>No. | Claim No. | Claim Amount | Amount Awarded (In Rs.) |
|---|---|---|---|
| 1 | Claim No. 1 | Declaration | The period from<br>01.07.2017 to 04.08.2017<br>is declared as Force<br>Majeure period. |
| 2 | Claim No. 2 | ₹ 1,09,45,140/- | Payment of ₹ 1,03,88,126/-<br>waived off from the<br>remittances due. |
| 3 | Claim No. 3 | ₹ 9,75, 09,000/- | BG for ₹ 9,75,09,000/- to<br>be released in favour of<br>Claimant |
| 4 | Claim No. 4 | ₹ 41,64,750/- | ₹ 41,64,750/- |
| 5 | Claim No. 5 | ₹ 9,75,09,000/-<br>Plus interest @<br>18% pa | ₹ 8,33,77,524/- plus simple<br>interest @ 8% p.a w.e.f<br>04.09.2017 till date of<br>Award. If amount not paid<br>within 3 months of award<br>future interest @ 8% p.a<br>from date of award till date<br>of payment |
| 6 | Claim No. 6 | ₹ 1,85,35,344/- | Nil |
| 7 | Claim No. 7 | Interest as Due | Claim withdrawn |
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 7 of 18
| 8 | Claim No. 8 | Arbitration<br>Cost | ₹ 15,00,000/- |
|---|
Submissions
20. Mr Saurabh Banerjee learned counsel appearing for NHAI has
assailed the impugned award, essentially, on four fronts. First, he
submitted that the Arbitral Tribunal had grossly erred in ignoring
Clause (h) of the Contract Agreement whereby the respondent was
obliged to remit a sum of ₹2,24,40,274/- per week. The said amount
was calculated on the basis of the bid of ₹1,17,00,99,999/- submitted
by the respondent. He pointed out that Clause (h) also expressly
provided that “ the amount quoted above shall be exclusive of TCS.
Any tax and service charges as applicable shall be borne by the bidder
over and above the quoted amount ”. He submitted that since the
respondent was required to bear all taxes, it was not open for the
respondent to avoid any payment on account of change in the indirect
taxes regime.
21. Second, he submitted that the introduction of GST could not be
considered as a ‘change in law’ as contemplated under Clause 25(b)(v)
of the Contract Agreement. He submitted that GST was only a
simplified method of levy and collection of indirect taxes and had
replaced the multitude of indirect taxes. The same could thus not be
considered as any change in law that affect the Contract Agreement or
any of the obligations of the parties therein. Third, he submitted that
Sub-clause (v) of Clause 25(b) of the Contract Agreement referred to a
material adverse effect and the said expression was required to be
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 8 of 18
interpreted in light of its meaning in Sub-clause (ii) of Clause 25(b) of
the Contract Agreement. He submitted that Sub-clause (ii) of Clause
25(b) had explained the import of the expression “material adverse
impact”, to mean a complete blockade of road and since that was not
the case, the respondent could not claim the introduction of GST as a
force majeure event. He relied on the decision of this Court in
National Highway Authority of India v. TGV Projects and
Investments Private Limited: O.M.P. (COMM.) 445/2017, decided on
24.05.2018 , whereby this Court had accepted that floods or earthquake
would not constitute a force majeure event unless the same had
resulted in a complete blockade of road and accordingly, had set aside
the arbitral award impugned in that case. He submitted that the said
decision was also upheld by the decision of the Division Bench of this
Court in TGV Projects & Investments Pvt. Ltd. ‘v. National
Highways Authority of India: FAO(OS)(COMM) 244/2018, decided
on 11.12.2018 . Fourth, he submitted that the Arbitral Tribunal had
erred in referring the internal communication issued by the General
Manager, NHAI to all other Regional Offices. He submitted that the
letter dated 16.03.2018 was a mere internal communication and the
respondent cannot claim any sustenance on its basis.
Reasons
22. At the outset, it would be relevant to refer to Clause 25 of the
Contract Agreement, which is the heart of the controversy in the
present case. Sub-clause (b) of Clause 25 of the Contract Agreement
is set out below:
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 9 of 18
“ 25. (b) FORCE MAJEURE EVENT:
Except as stated in Clause (a) above, Force Majeure
event means an event or circumstances or a combination
of events and circumstances referred to in this clause
which are beyond the reasonable control of the Party or
Parties to this Contract and which party could not have
prevented or reasonably overcome with the exercise of
its reasonable skill and care in relation to performance of
its obligations pursuant to this Contract and which are of
the nature, without limitation of those described below:
(i) Publicly declared strike by registered and
recognised association of Transporters exceeding
7 days. The date of going on strike and
withdrawal or start of movement of traffic will
be inclusive for the purpose of calculation of 7
days under this clause.
(ii) Floods/Earthquake having materially adverse
impact i.e. complete blockade of road.
(iii) Act of war, invasion, armed conflict or act of
foreign enemy, unexpected call up of armed
forces, blockade, embargo, revolution, riot
sabotage, terrorism or act of such threat, or any
other political or social event having material
adverse impact on the performance of obligations
of the parties thereof.
(iv) Expropriation, acquisition, confiscation or
nationalisation of the User Fee collection
(v) Any change in law which has a material adverse
effect on the obligation of the parties hereto.
(vi) Any decision or order of a court or tribunal,
which has a material adverse effect on the
performance of obligations of the parties to this
Contract.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 10 of 18
(vii) Suspension of traffic on the said section of
National Highway/said bridge or any party
thereof, exceeding 15 (fifteen) days at a stretch.
(viii) Any event or circumstances of a nature
analogous to the foregoing.
Either party to this Contract shall be entitled to suspend
or excuse performance of his obligations, including
remittance of instalments by the Contractor to the
Authority for the period of continuance of the Force
Majeure event, under this Contract to the extent that
such performance is impeded by an event of Force
Majeure prevailing continuously for more than 7 (seven)
days at a time (or continuously for more than 3 (three)
days at a time in case of no user fee collection at all at
the toll plaza) for reasons not attributable to the
Contractor.”
23. The principal controversy before the Arbitral Tribunal related to
the respondent’s claim that the introduction of GST had led to an
uncertainty and a sharp reduction in traffic resulting in a lower
collection of ‘User Fee’. The respondent claimed that the introduction
of GST to replace other indirect taxes constituted a ‘change in law’ as
contemplated under Sub-clause (v) of Clause 25(b) of the Contract
Agreement. The same had a material adverse effect, as was evident
from the sharp reduction in the toll collection and therefore, the
respondent was entitled to claim remission in his payment obligation.
24. Although NHAI had stoutly contested the claim that the
introduction of GST constituted a change in law, however, the Arbitral
Tribunal did not accept the same. The Arbitral Tribunal referred to
Article 13(3) of the Constitution of India which defines the expression
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 11 of 18
“Law” to include any ordinance, order, by law, rule regulation,
notification, custom or usages having in the territory of India the force
of law. Considering the wide definition of the term “Law”, the
Arbitral Tribunal held that the notification issued by the Government
of India on 28.06.2017 providing for imposition of GST for the first
time in India, constituted a change in law.
25. The Arbitral Tribunal held that even though GST encompasses
the existing taxes and dues, it was not possible to immediately
ascertain the impact in a general manner and there was uncertainty and
doubts in the minds of suppliers/manufactures of goods resulting in
deferring of transportation of products. The Tribunal noted that this
was also accepted by NHAI as was evident from the circular dated
16.03.2018. The contents of the said circular are relevant and are set
out below:
“NHAI/13013/CO/17-18/CB/GST/114535 Date:
16.03.2018
To
All ROs.
Subject: Relief to User fee Collection Contractors on
Public Funded Projects at the toll plazas on NHs on
account of implementation of GST.
Sir,
Various representation have been received from
various Toll Contractors at Public Funded plazas
regarding loss in traffic and its impact on toll revenue
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 12 of 18
collection, if any, due to implementation of Goods and
Services Tax (GST) by Government of India w.e.f.
01.07.2017. AICUP and some other fee collection
agencies have requested to consider their representation
under Force Majeure Clause 25 (b) (v) of the Contract
Agreement:
“Any change in law which has a material adverse
effect on the obligation of the parties hereto.”
2. In this regard, although promulgation of GST
w.e.f. 01.07.2017 appears to be a change in law,
however, its material effect could not be proved as the
claims submitted by AICUF regarding reduction in
traffic of commercial vehicles after implementation of
GST are of generic nature without any project specific
inputs. Further, their claims regarding reduction in
tollable traffic due to implementation of GST had only
limited/short term effect on toll revenue.
3. Accordingly, the Competent Authority has
decided that such cases may be dealt by concerned RO
on case to case basis as per applicable contract
provisions after due verifications of facts regarding
reduction in traffic due to implementation of GST w.e.f.
01.07.2017 with delegated powers of ROs.
Yours faithfully
General Manager (CO)”
26. The Arbitral Tribunal held that the said letter also clearly
indicated that NHAI had accepted that the introduction of GST had
resulted in a ‘change in law’.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 13 of 18
27. This Court concurs with the said view. Plainly, it cannot be
disputed that enactment of the statute imposing GST brought into
force a new tax regime and the contention that the same did not
amount to any change in law is wholly unmerited.
28. Having stated the above, the principal controversy to be
addressed was whether the said change in law had a material adverse
effect on the obligation of the parties.
29. The Arbitral Tribunal accepted that with the implementation of
GST, traffic movement reduced sharply and thereby affected toll
collection and consequently, remittance to NHAI.
30. Undeniably, the said event had been duly notified to NHAI.
The Arbitral Tribunal also noted that NHAI had not disputed the said
claim at the material time. It was also noticed that two independent
PDs had evaluated the said claim and had also made their
recommendations. The Tribunal further held that the question –
whether the introduction of GST had any material adverse effect –
could be determined by assessing the impact of the said change on the
respondent’s ability to discharge his obligations under the Agreement.
The PDs had assessed the loss during the period from 01.07.2017 to
04.08.2017 at ₹1,03,88,126/-. The Arbitral Tribunal held that the said
amount could not be considered as immaterial and therefore,
concluded that a force majeure event, as contemplated under Sub-
clause (v) of Clause 25(b) of the Contract Agreement, had occurred.
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 14 of 18
31. It is well settled that the view of the Arbitral Tribunal is a
plausible view. It is also necessary to bear in mind that the question as
to the interpretation of the contract falls squarely within the
jurisdiction of the Arbitral Tribunal and its decision cannot be
interfered with, unless it is found to be patently illegal on the basis of
the record or otherwise falls foul of the fundamental policy of Indian
law. I need not elaborate on this well settled proposition of law and
reference to the observations made by the Supreme Court in State of
U.P. vs. Allied Constructions, (2003) 7 SCC 396 , extracted below,
would suffice:
“4. Any award made by an arbitrator can be set aside
only if one or the other term specified in Sections 30 and
33 of the Arbitration Act, 1940 is attracted. It is not a
case where it can be said that the arbitrator has
misconducted the proceedings. It was within his
jurisdiction to interpret clause 47 of the agreement
having regard to the fact-situation obtaining therein. It is
submitted that an award made by an arbitrator may be
wrong either on law or on fact and error of law on the
face of it could not nullify an award. The award is a
speaking one. The arbitrator has assigned sufficient and
cogent reasons in support thereof. Interpretation of a
contract, it is trite, is a matter for the arbitrator to
determine (see Sudarsan Trading Co. v. Govt. of Kerala
[(1989) 2 SCC 38 : AIR 1989 SC 890] ). Section 30 of
the Arbitration Act, 1940 providing for setting aside an
award is restrictive in its operation. Unless one or the
other condition contained in Section 30 is satisfied, an
award cannot be set aside. The arbitrator is a Judge
chosen by the parties and his decision is final. The court
is precluded from reappraising the evidence. Even in a
case where the award contains reasons, the interference
therewith would still be not available within the
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 15 of 18
jurisdiction of the court unless, of course, the reasons
are totally perverse or the judgment is based on a wrong
proposition of law. An error apparent on the face of the
records would not imply closer scrutiny of the merits of
documents and materials on record. Once it is found that
the view of the arbitrator is a plausible one, the court
will refrain itself from interfering (see U.P. SEB v.
Searsole Chemicals Ltd. [(2001) 3 SCC 397] and Ispat
Engg. & Foundry Works v. Steel Authority of India Ltd.
[(2001) 6 SCC 347]).”
32. In Mcdermott International v. Burn Standard Co. Ltd., (2006)
11 SCC 181, the Supreme Court held as under:
“ 112 . It is trite that the terms of the contract can be
express or implied. The conduct of the parties would
also be a relevant factor in the matter of construction of
a contract. The construction of the contract agreement is
within the jurisdiction of the arbitrators having regard to
the wide nature, scope and ambit of the arbitration
agreement and they cannot be said to have misdirected
themselves in passing the award by taking into
consideration the conduct of the parties. It is also trite
that correspondences exchanged by the parties are
required to be taken into consideration for the purpose
of construction of a contract. Interpretation of a contract
is a matter for the arbitrator to determine, even if it gives
rise to determination of a question of law. [See Pure
Helium India (P) Ltd. v. Oil and Natural Gas
Commission [(2003) 8 SCC 593 : 2003 Supp (4) SCR
561] and D.D. Sharma v. Union of India [(2004) 5 SCC
325] .]
113 . Once, thus, it is held that the arbitrator had the
jurisdiction, no further question shall be raised and the
court will not exercise its jurisdiction unless it is found
that there exists any bar on the face of the award.”
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 16 of 18
[Also see: Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran,
(2012) 5 SCC 306 .]
33. The learned counsel for the respondent had also referred to the
decision of a Coordinate Bench of this Court in National Highways
Authority of India v. Sahakar Global Limited: O.M.P. (COMM)
486/2020, decided on 29.09.2020 , whereby the learned arbitrator had
rejected the challenge to a similar Arbitral Award. This Court had
referred to NHAI’s letter dated 16.03.2018 and held that there was no
reason to deprive the respondent therein of the declaration accepting
the implementation of GST as ‘a change in law’. The Court had also
considered whether the reduction in traffic as a result of
implementation of GST falls within Clause 25(b)(v) of the Contract
Agreement.
34. This Court is not required to examine the merits of the aforesaid
view. Suffice it to state that it is a plausible view and therefore,
warrants no interference under Section 34 of the A&C Act.
35. The contention that a material adverse effect as contemplated
under Sub-clause (v) of Clause 25(b) of the Contract Agreement must
be read as a complete blockade of the road as contemplated under
Clause 25(b)(ii) of the Contract Agreement, is also unmerited. The
scope of the two Sub-clauses – Sub-clause (ii) and Sub-clause (v) of
Clause 25(b) – are different. Sub-clause (ii) relates to a force majeure
event caused by flood/earthquake and a material adverse impact of a
flood/earthquake would be one that results in a complete blockade of
road. No such qualification is provided under Sub-clause (v) in
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 17 of 18
respect of a material adverse effect resulting from any change in law.
Therefore, it would not be apposite to restrict the import of Sub-clause
(v) to only such changes in law which would result in a complete
blockade of the road.
36. As noticed above, the question of interpretation falls within the
jurisdiction of an Arbitral Tribunal and can be interfered with only on
limited grounds as set out in Section 34(2)/(2A) of the A&C Act.
37. The contention that the Arbitral Tribunal had erred in
proceeding on the basis that the letter dated 16.03.2018 issued by
NHAI was a Circular, is without any merit. The said letter had been
issued to all ROs (Regional Offices) and therefore, was intended for
wider circulation. There is no error in referring to the said letter as a
circular. It was, clearly, meant to provide general instructions to the
ROs. This Court had also considered the import of the said letter in
National Highways Authority of India v. Sahakar Global Limited
( supra ) and had declined to interfere with the award impugned therein.
38. In view of the above, this Court finds no ground to interfere
with the impugned award. The petition is, accordingly, dismissed. All
pending applications are also disposed of.
VIBHU BAKHRU, J
MARCH 23, 2021
RK
Signature Not Verified
Digitally Signed
By:DUSHYANT
RAWAL
O.M.P. (COMM). 127/2021 Page 18 of 18