Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 28
PETITIONER:
JIYAJEERAO COTTON MILLS LIMITED AND ANOTHER
Vs.
RESPONDENT:
MADHYA PRADESH ELECTRICITY BOARD AND OTHERS
DATE OF JUDGMENT12/09/1988
BENCH:
SHARMA, L.M. (J)
BENCH:
SHARMA, L.M. (J)
SEN, A.P. (J)
CITATION:
1989 AIR 788 1988 SCR Supl. (2) 978
1989 SCC Supl. (2) 52 JT 1988 (4) 737
1988 SCALE (2)1039
ACT:
Indian Electricity Act, 1910--Section 22B--Company
entering into agreement with Electricity Board for supply of
electricity--Board supplying additional energy and billing
at penal rates--Action of Board--Whether valid and legal.
%
Madhya Pradesh Electricity (Supply and Consumption
Regulation) Order 1975/Madhya Pradesh Electricity
(Generation, Control and Consumption) Order 1975: Clause
3(i) Regulation Order--Consumers to reduce consumption--
Board entitled to disconnect supply for breach or charge
penal rates for excess energy consumed--Generation Order
provided for assessment of generating capacity of captive
power of consumer.
Words and Phrases: ‘Regulate’--Meaning of.
HEADNOTE:
In October 1971 the appellant company entered into an
agreement with the Madhya Pradesh Electricity Board,
respondent No. 1, for supply of electricity. The quantity of
electricity to be supplied varied from time to time.
To meet the situation arising out of insufficient
generation of electricity, the State of Madhya Pradesh
issued two orders. By the Madhya Pradesh Electricity (Supply
and Consumption Regulation) Order, 1975 the consumers were
asked to reduce their consumption failing which they would
have to pay charges at penal rates for excess consumption,
without prejudice to the Board’s power to disconnect the
supply. By the Generation Order, the consumers who had
alternative sources of captive power were required to
generate electricity to the maximum extent technically
feasible, from their own sources of electricity.
After the assessment of their generating capacity, the
appellant was directed to generate additional electricity of
2,500 K.W. Sub-Clause (iii) of Proviso to clause 3 of the
Generation Order provided that if in certain contingencies
there was reduction in the generation of electricity by the
PG NO 979
consumer, the Board would try to make good the deficit
against the appropriate charge for it. Under this provision
the appellant, on pleading emergency, was supplied
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 28
additional energy from time to time. For excess consumption
drawn without the Board’s prior approval, the appellant was
sent bills at penal rate.
The appellant company challenged the demand before the
High Court by filing a writ application under Article 226 of
the Constitution, which was dismissed by the High Court
except for granting some minor reliefs.
Before this Court, it was contended by the appellant:
(l) There is no sanction in Law for charging at the
Penal rate for the electricity consumed beyond what is
permissible under the Generation Order.
(2) That the assessment of their generating capacity was
not made by the authority empowered to do so. i.e. the
Divisional Engineer, and (3) that the assessment was based
on irrelevant and extraneous considerations
Dismissing the appeal, it was,
HELD: (1) A perusal of the documents on record,
including admissions on the part of the appellant company.
furnishes unimpeachable evidence, proving that the
assessment of the maximum feasible capacity of the
appellant’s capative power sets was duly made in accordance
with the Generation Order, and that the Divisional Engineer,
who had been authorised by the Generation Order to assess
the appellant’s generating capacity, reached the conclusion
after personally considering the matter thoroughly.
(2) In pursuance of the assessment of the generating
capacity the required direction was issued which was acted
upon by the parties for a number of years. The Company not
only took steps to generate the additional energy as was
required of it, it also took advantage of the provisions of
proviso (iii) to clause 3 of the Generation Order and
benefited by it from time to time. [988A-B]
(3) The appellant company was fully conscious of the
fact that it was consuming electricity beyond its
entitlement under the two Orders. For several years the
Company was particular to obtain the permission of the Board
PG NO 980
for drawing electricity in excess of what it was entitled to
by the agreement, as modified by the Regulation Order and
the Generation Order, but later, it not only stopped
seeking the advance sanction in this regard, it did not even
care to inform the Board of the excess drawal. [1001B-C;F-G]
(4) Section 22B of the Indian Electricity Act, 1910
permits the State Government to issue an appropriate order
for regulating the supply, distribution and consumption of
electricity. [1010B]
(5) The expression "regulate" occurs in other statutes
also, as for example, the Essential Commodities Act, 1955,
and it has been found difficult to give the word a precise
definition. It has different shades of meaning and must take
its colour from the context in which it is used having
regard to the purpose and object of the relevant provisions,
and as has been repeatedly observed, the Court while
interpreting the expression must necessarily keep in view
the object to be achieved and the mischief sought to be
remedied. [1010C-D]
(6) There does not appear to be any doubt that either
under S. 49(1) of the 1948 Act read with the agreement or
under s. 49(3) or under both the provisions the respondent
Board was fully authorised to levy and to make a demand at
a higher rate than the usual tariff.[1014E-F]
(7) The necessity for issuing the two orders arose out
of the scarcity of electricity available to the Board for
supplying to its customers. The situation did not leave any
option to the Board but to make limited supply of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 28
electricity to its consumers. and it must be held to have,
in the circumstances,. the right to stagger or curtail the
supply. The orders were issued in this background and to
make the direction mentioned therein effective it was
considered essential to impose sanctions which could take
any reasonable from; either disconnection in case of
gross violation or the lesser sanction of enhanced tariff.
Hence none of the two Orders was illegal or unreasonable.
Adoni Cotton Mills v. A.P. State Electricity Board,
[1976] 4 SCC 68; State of U.P. v Hindustan Aluminium
Corporation, [1979] 3 SCC 229 and New Central Jute Mills v
U.P. State Electricity Board, [1986] Supp. SCC581.
JUDGMENT:
CIVlL APPELLATE JURISDICTION: Civil Appeals Nos. 3510-
3511 of 19822.
PG NO 981
From the Judgment and Order dated 23.9.1982 and I8/
19.10.1982 of the Madhya Pradesh High Court in Misce. W.P.
NO. 888/81 and Review M.C.C.No. 352 of 1982.
D. Gupta, M.C. Bhandare, O.P. Khaitan, Anil Bhatnagar,
Krishan Kumar, Dhruv Agarwal and Mrs. Kiran Choudhary for
the Appellants.
S.N. Kacker, M.L. Jaiswal, Vivek Gambhir and S.K.
Gambhir for the Respondents.
The Judgment of the Court was delivered by
SHARMA, J. The dispute in these appeals is in regard to
the additional demand of electric charges made by the
respondent no. 1 on the appellant no. 1 for energy consumed.
By a writ application filed before the Madhya Pradesh High
Court the appellant challenged the demand of Rs.
1,86,97,880.97 for the period 12.11.1979 to 30.6.1981.
Except for granting a minor relief as indicate in paragraph
45 of its judgment, the High Court dismissed the writ
application. The writ petitioner-appellants have impugned
the judgment before this Court by special leave.
2. The appellant no. 1 Jiyajeerao Cotton Mills Ltd.
hereinafter referred to as the Company which runs a textile
mill in Gwalior, entered into an agreement dated 27.10.1971
with the respondent no. 1 Madhya Pradesh Electricity Board
in short the Board a licensee under the Indian Electricity
Act, 1910 hereinafter referred to as the 1918 Act for supply
of electricity in accordance with the terms and conditions
mentioned therein. The quantity of electricity to be
supplied varied from time to time under supplementary
agreements and the Board had to supply 2,500 K.W. on A.T.
basis with effect from 1.11.1973. Since 1975 the Board is
not able to generate sufficient electricity to meet the full
demand of the consumers and with a view to ease the
situation two orders were issued by the States of Madhya
Pradesh under s. 22B of the 1910 Act on 4.4.1975 called as
the Madhya Pradesh Electricity Supply and Consumption
Regulation Order, 1975 and the Madhya Pradesh Electricity
Generation, Control and Consumption Order. 1975. The learned
counsel for the parties have in their arguments referred to
these orders as Regulation Order and Generation Order
respectively. By the Regulation Order , the consumers were
asked to reduce their consumption in accordance with the
provisions therein. It was further provided that without
prejudice to the Board’s power to disconnect the supply in
PG NO 982
the event of any violation thereof, the consumer will have
to pay the charges at penal rates for the excess energy
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 28
consumed. The Generation Order said that if a consumer had
an alternative source of generating power from his own
generating set (described as captive power by the parties)
it may be required to generate electricity to the maximum
extent technically feasible and the supply by the Board
would be reduced to that extent. The Order in Clause 3
provided for assessment of the generating capacity of the
captive power of the consumer. The contract demand under the
agreement was directed to remain reduced accordingly. Sub
clause (iii) of Proviso to Clause 3 said, that if in certain
contingencies, there was reduction in the generation of
electricity by the consumer, the Board would try to make
good the deficit against an appropriate charge for it. An
arbitration clause with respect to any dispute was included
in the 6th paragraph of the Order as its last term.
3. Both the Orders came into force with effect from the
7th of April, 1975. The Divisional Engineer, Gwalior
informed the appellant Company by the letter dated 17.5.1975
(marked as Annexure ‘B’, page 121, Vol. II of the paper
book) that its additional generation capacity technically
feasible by its own generating sets had been assessed at
2,700 K.W. In view of the contract under which the Board was
to supply 2,500 K.W. with effect from 1.11.11973,, the
Company was directed to generate additional electricity to
that extent, thus reducing the demand on the Board to nil.
After several letters passed between the parties, which will
be dealt with at some length later, another letter dated
10.10.1975 (marked as Annexure ‘O’, page 136, Vol. II of the
paper book) was sent to the Company issuing a fresh
direction for generating additional electricity to the
extent of 2,500 K.W. with effect from 31.10.1975.
4. It appears that the Board did not bill the appellant
Company for any additional energy supplied at the penal rate
for the next several years. According to its case the
Company invoked the provisions of Proviso (iii) to Clause 3
of the Generation Order pleading emergency. arising from
time to time, covered by the Proviso, and was supplied
additional energy accordingly. The Company was under a duty
to place its difficulties before the Board and obtain
permission before drawing additional energy under this
provision of emergency supply. It appears that after
11.11.1979 additional power was drawn by the appellant
without the Board’s prior approval and a letter Annexure ‘T’
dated 5.8.1980 was ultimately sent to the Company explaining
the situation and telling it that the supply availed by it
with effect from 12.11.1979 would be billed at the penal
PG NO 983
rate. In the meantime two additional contracts were executed
by the parties; the first one on 11.7.1979 (Annexure ‘C’)
for supplying additional 800 K.W., and the second one dated
26.2.1980 (Annexure ‘D’ for additional 190 K.W. Thus the
total demand under the agreements added to 3,490 K.W. The
Board by its letter Annexure ‘U’ dated 13.10.1980 reiterated
its stand taken under Annexure ‘T’ intimating the appellant
the maximum amount of electricity it was entitled to
consume at the normal rate. The letter further added that no
additional power would be allowed as emergency supply to the
Company even during the period of overhauling of the
generating sets as was done earlier under Proviso (iii) to
Clause 3 of the Generation Order. The matter was debated for
some time and ultimately the additional demand for the
period 12.11.1979 to 30.9.1980 amounting to Rs.94,41,745.60
was served on the appellant Company by the letter Annexure
‘X’ dated 15.1.1981. The further bills were also sent on the
same basis.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 28
5. On 5.8.1981 the application under Article 226 of the
Constitution was filed before the Madhya Pradesh High Court
challenging Annexure ‘H’, ‘O’, ‘T’ and ‘U’. The main case
of the petitioner-appellant was rejected by the High Court,
but marginal reliefs with respect to the Board’s demands for
the period 12.11.1979 to 25.2.1980 and from 26.2.1980 to
31.7.1980 were allowed on the basis of errors in
calculation. The High Court also pointed out that under the
terms of the Generation Order the Board was under a duty to
consider and allow the additional emergency supply when
conditions arose making the Proviso (iii) to Clause 3
applicable and the Board could not refuse to do so as was
observed in some of its letters. Subject to these minor
modifications the writ application was dismissed by the
judgment dated 23.9.1982. The Company thereafter filed an
application for review, which was dismissed by a speaking
order of 19.10.1982. The present appeals have been filed by
special leave against these two judgments.
6. The appeals have been argued at considerable length
by Mr Dipankar Gupta on behalf of the appellant and Mr. S.N.
Kacker representing the respondents with great ingenuity and
resourcefulness. Mr. Gupta appearing in support of the
appeals, however did not press some of the points urged on
behalf of the appellant in the High Court and relied upon
some new grounds. We. therefore do not consider it necessary
to deal with all the points disposed of in the High Court
judgments except making reference to some of them while
dealing with the points urged before us.
PG NO 984
7. It will be necessary to examine the relevant portions
of the Regulation and Generation Orders (Annexures ‘E’ and
G’) before considering the arguments of the learned counsel.
They were both issued on 4.4.1975 by the State Government of
Madhya Pradesh under s. 22B of the 1910 Act, which reads as
follows:
"22. B(1) If the State Government is of opinion that it
is necessary or expedient so to do, for maintaining the
supply and securing the equitable distribution of energy, it
may by order provide for regulating the supply,
distribution, consumption or use thereof.
(2) Without prejudice to the generality of the powers
conferred by sub-section (1) an order made thereunder may
direct the licensee not to comply, except with the
permission of the State Government with--
(i) The provisions of any contract, agreement or
requisition whether made before or after the commencement
of the Indian Electricity (Amendment) Act, 1959,for or the
supply (other than the resumption of supply) or an increase
in the supply of energy to any person, or
(ii) any requisition for the resumption of supply of
energy to a consumer after a period of six months, from the
date of its discontinuance, or
(iii) any requisition for the resumption of supply of
energy made within six months of its continuance , where
the requisitioning consumer was not himself the consumer
of the supply the time of its discontinuance."
Clauses 3 and 4(i) of the Regulation Order
(Annexure‘E’) have been refer,red to by the learned counsel
for the parties repeatedly and they are quoted below:
"3.(1). No consumer receiving supply electrical energy
from the Board and consuming or using electrical energy
for any of the categories specified in column (2) of PART-
(of Schedule VII shall consume or use during any month or
day electrical energy in excess of that specified in
PG NO 985
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 28
respective entry in column (3) of the said Schedule;
(2) (a). If at any time during the month, on inspection
of the meter reader or any other person authorised by the
Divisional Engineer/Assistant Engineer of the Board having
jurisdiction, the consumer is found to have already reached
or exceeded the quantity of electricity indicated in column
(3) of Part-A of Schedule VII the Divisional
Engineer/Assistant Engineer of the Board, having
jurisdiction over the area where the consumer’s premises is
situated, may by an order in writing require the consumer
not to utilise electrical energy for the rest of the month
and such order shall be complied with by the consumer forth-
with. Appeal shall, however, lie with the Deputy Chief
Engineer of the Board having jurisdiction whose decisions
thereon shall be final.
(b) Any H.T. consumer who makes default in complying
with the directions contained in sub-clause (1) and item (a)
of this sub-clause shall be warned in the first instance in
writing by the Divisional Engineer/Assistant Engineer of the
Board having jurisdiction over the area where the consumer’s
premises is situated and if the default continues, the said
Divisional Engineer/Assistant Engineer shall after
reasonably satisfying himself disconnect power supply
altogether to such consumer and supply shall not be resumed
without orders of the Deputy Chief Engineer of the Board
having jurisdiction."
"4. Without prejudice to the Board’s powers to
disconnect supply in the event of violation of Clause 3
above the Board shall bill the electricity consumed or used
in excess of the monthly limit specified in column (3) of
the Schedule VII at the penal rates as mentioned below:
(i) All H.T. consumers as specified in Schedules I, II,
III and IV--Four times of normal tariff (both in respect of
demand charges and energy charges) includ- ing fuel cost
adjustment charges."
The expressions "average monthly consumption", average
demand" and "average daily consumption" have been defined
in Clause 2 of Annexure ‘E’ by taking January, February and
March 1975 as the base period. The VIIth Schedule mentioned
PG NO 986
in Clause 3 above has not been included in the paper books
with reference to which arguments have been addressed but a
copy thereof was filed during the hearing and accepted as a
correct copy by the both sides.
8. This Regulation Order was substituted by another
Order and later by still a third Order, amending the penal
rate and the Schedules to the Order. However, the learned
counsel for the parties stated that except for change in
the penal rate and the figures in the Schedules, the Order
has remained the same all through, and it is not necessary,
therefore, to refer to the other Orders.
9. So far as the Generation Order is concerned, it
requires such consumers, who have their private generating
sets, to generate electrIcity to the maximum extent
technically feasible in the following terms:
"3. Any consumer who is receiving electrical energy from
the Board and also has an alternative source of generation
of power by his own generation set may be required by the
respective Divisional Engineer of the Board having
jurisdiction to generate electricity from his set (or sets)
to the maximum extent technically feasible in the opinion of
the Divisional Engineer and the Board’s supply of electrical
energy to such consumer shall be reduced to the extent of
additional generation assessed as feasible by the Divisional
Engineer;
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 28
Provided that---
(i) Before assessing the additional generation feasible
and directing the consumer accordingly, the Divisional
Engineer shall consult the local Manager or Engineer in
charge of the set;
(ii) The Board shall, during the period such a direction
is in force, reduce the contract demand of the consumer to a
corresponding extent and
(iii) if due to an emergency outage, which in the
opinion of the Divisional Engineer of the Board having
jurisdiction is not due to any negligence or failure of
those responsible for maintaining and running the set. there
is reduction is additional generation, or if in the opinion
PG NO 987
of the Divisional Engineer, the set has to be taken out for
maintenance during the period of such emergency or
maintenance outage the Board shall try its best to make good
the reduction to the consumer, levying an appropriate charge
for it."
Its 6th Clause directed any dispute between the consumer
and the Officer acting under Clauses 3 and 4 to be referred
to the Electrical Adviser and Chief Electrical Inspector to
the State Government, for his decision.
10. While Regulation Order was meant for general
application to all consumers, the Generation Order was
confined only to such consumers who were having captive
power source. It is also manifest that such a consumer was
under a duty to generate additional electricity only when
the maximum technically feasible capacity of the generating
set or sets of the consumer was assessed under Proviso (i)
to Clause 3 and was followed by a direction to that effect.
The main argument of the learned counsel for the appellant
has been that none of the two assessments and directions
contained in Annexures ‘H’ and ‘O’ was sustainable in law on
the grounds that--
(a) in making the assessment of the technically feasible
maximum capacity, relevant factors were not considered. and
irrelevant and extraneous matters were taken into account;
(b) the requisite opinion was not arrived at and the
assessment was not made by the authority empowered to do so;
and
(c) the participation of the appellate authority in
process of’ assessment, completely vitiated it in law.
Mr. Gupta argued that instead of examining the point on
its merit. the High Court erroneously brushed it aside on
the plea of waiver and acquiescence. Relying on a number of
letters sent by the appellant to the respondent Board it was
urged that the appellant Company was protesting against the
impugned directions issued by the Board and it is not right
to shut it out on the technical ground of estoppel. Mr.
Kacker, on the other hand interpreted the High Court’s
judgment differently. According to him none of the points
raised by the Company was rejected without examining the
merits. He strongly relied on some of the letters referred
to in the argument of the Company itself as also a few other
letters in support of his submission that they furnished
PG NO 988
unimpeachable evidence including admissions on the part of
the appellant Company proving that the assessment of the
maximum feasible capacity of the appellant’s captive power
sets was duly made in accordance with the Generation Order
and in pursuance thereof the required direction was issued
which was acted upon by the parties for a number of years.
The Company not only took steps to generate the additional
energy as was required of it, it also took advantage of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 28
provisions of Proviso (iii) to Clause 3 of the Generation
Order and benefitted by it from time to time.
11. For appreciating the argument of the learned counsel
for the appellant it is necessary to examine some of the
Orders and letters issued in March and April 1975. As has
been mentioned earlier. the two Government Orders were
issued on 4.4. l975. It appears that the matter was being
discussed by the different authorities of the State
Government and the Electricity Board since before this date
and advisability to require the consumers having captive
power to generate as much energy as was technically feasible
was under consideration for some time. The question as to
their capacity in this regard, naturally assumed importance
and some steps for assessing the same were taken a few days
before the Orders actually came into effect. On 28.3.1975 a
letter sent from the Board to Sri H.K. Aggarwal the
Electrical Adviser and Chief Electrical Inspector to the
State Government (Annexure ‘R-1’) referred to a telephonic
talk in connection with the assessment of the generating
capacity of the captive power set. It was mentioned "that it
would be necessary to make a realistic assessment in respect
of each of the consumers" by keeping in mind the suggested
factors. The letter further said that with that object the
Board had constituted a Committee consisting of Sri Aggarwal
himself. the Superintending Engineer of the concerned
Circle of the Board and the Divisional Engineer
(Generation), Jabalpur of the Board as Members. The
appellant Company is mentioned as one of the 17 consumers in
this category. Along with his letter dated the 3rd of May
1975 Sri Aggarwal sent the report as desired. It has been
contended on behalf of the appellant that the Generation
Order authorised the Divisional Engineer of the Board to
assess the additional feasible capacity of the captive
power source and any other person or authority or Committee
could not usurp this jurisdiction. The impugned letter
Annexure ‘H’ issued by the Divisional Engineer has been
characterised as illegal on the ground that it was based
upon the assessment by the Committee headed by Sri H.K.
Aggarwal and not by the Divisional Engineer. the learned
counsel proceeded to say that immediately after receipt of
the intimation by the Board, the Company protested on
21.5.1975. The Board’s reply dated 2.6.1975 has been relied
PG NO 989
upon as showing that the direction was issued on the basis
of the assessment of the Committee and not of the Divisional
Engineer. It was also pointed out that Electrical Adviser
and Chief Electrical Inspector to the State Government (the
then incumbent being Sri H.K. Aggarwal) was the appellate
authority under Clause 6 of the Generation Order and could
not, therefore, take part in the original assessment
proceeding. The reply of the Board is that the Committee no
doubt inspected the generating sets and discussed the
matter with the consumers, and thus collected relevant data
for the purpose of assessment of the capacity, but the
Divisional Engineer while relying on the material collected,
did not mechanically accept the conclusion of the Committee.
He (the Divisional Engineer) applied his mind before issuing
the Order Annexure ‘H’. Mr. Kacker further said that the
matter did not rest there. After taking into account the
objection raised by the Company the Divisional Engineer took
up the matter afresh and applied his mind independently.
Ultimately he came to a similar conclusion as is evident by
the second direction as contained in Annexure ‘O’ dated
10.10.1975. The argument of Mr. Kacker appears to be well
founded.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 28
12. On receipt of the letter Annexure ‘H’ dated
17.5.1975 whereby the Divisional Engineer directed the
Company to generate 2,500 K.W. of electricity by its own
generating sets, the appellant Company protested by its
letter dated 21.5.1975 (at page 195 of the Paper Book Vol.
II). Mr. Gupta strenuously relied on this letter which
stated that the Company failed to understand as to how its
additional generating capacity had been assessed at 2,700
K.W. It will be necessary to discuss this letter in some
detail later in the judgment while dealing with another
point as Mr. Kacker also has relied on certain statements
made therein. At this stage, however, we should like to
point out that the appellant did not challenge the
assessment on the ground that it was not made by the
authority mentioned in the Generation Order; and in the
last paragraph the request made was for "review". The next
document referred to by the learned counsel for the
appellant is the letter dated 30.5.1975 (page 305 of the
Paper Book Vol. II), wherein the Company stated that:
"as desired by the Board, we have started generating
about 2,000 K.W. additional power at our generating station
tonnes daily for this additional generation."
PG NO 990
Finally a request was made in the letter to the
Superintending Engineer of the Board to recommend the
appellant’s case for allotment of additional wagons for
transport of coal. Instead of advancing the appellant’s
case, the letter shows that the assessment and the direction
mentioned in Annexure ‘H’ were accepted by the Company and
steps were taken to implement the same. Chronologically
proceeding, the letter dated 2.6.1975 (Annexure ‘I’ at page
122 of the Paper Book Vol. II) was relied on by Mr. Gupta
as proving the fact that the assessment of additional
generating capacity had been done by the Committee mentioned
in the letter dated 28.3.1975 (supra) and not by the
Divisional Engineer as required by the Generation Order. The
learned counsel far the parties next placed before us the
letters dated 3.6.1975 (document no. 3 at page 302 of the
Paper Book Vol. II) and dated 4.6.1975 (document no. 1, at
page 300 of the Paper Book Vol. II), another letter of the
same date (Annexure ‘J’ at page 123 of the Paper Book Vol.
II) and then dated 8.8.1975 (Annexure ‘K’ at page 132 of the
Paper Book Vol. II) and 1().10.1975 (Annexure ‘O’ at page
136 of the Paper Book Vol. ll).
13. The argument of Mr. Kacker has been that the
Divisional Engineer applied his mind independently to the
question of assessment of the capacity of the appellant’s
generating sets, and while so doing took in consideration
the factual data collected by the Committee mentioned in
the letter of 28.3.1975. It was pointed out that all the
three persons constituting the Committee were very highly
placed officers and there could not be any legitimate
objection if the Divisional Engineer referred to the data
collected by them in presence of the Company’s Officers
after personally verifying them. Even a judicial tribunal
or a regular court is allowed to rely upon evidence
collected by an enquiry officer or commissioner. The learned
counsel heavily relied on the letter dated 3.6.1975 from the
Divisional Engineer to the Superintending Engineer (document
no. 3). On behalf of the appellant it was said that the
Company had no knowledge of this letter in 1975. We do not
think that this is a correct stand. The letter mentions an
inspection of’ the Company’s power House by the Divisional
Engineer and the materials supplied by the Company to him.
The details with respect to the boilers of the Company and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 28
the other figures mentioned therein correctness whereof is
not challenged by the appellant, fully establish that the
inspection was made in presence of and the figures were
collected with the assistance of the officers of the
appellant Company and the conclusion regarding the
assessment was reached after taking into account the case of
the Company. It has been argued on behalf of the Board
before us that the method adopted by the Divisional Engineer
as disclosed by this letter (document No. 3) was different
PG NO 991
from that followed by the Committee, as a result of which
there was some difference in their final result. On the
basis of his independent assessment the Divisional Engineer
issued another instruction as contained in Annexure ’O’
dated 10.10.1975 (at page 136 of the Paper Book Vol. II),
mentioned earlier. This second direction which was effective
from 31.10.1975 naturally superseded the earlier one under
Annexure ‘H’. The Board’s impugned demand does not relate to
any period before 31.10.1975 and, therefore, it is
immaterial if the direction in Annexure ’H’ is completely
ignored on account of its supersession by Annexure ’O’ or on
any other ground and it be assumed that in absence of a
feasible assessment of the capacity, the Generation Order
was not applicable to the appellant Company before 31. 10.
1975.
14. Mr. Gupta relied on the letter dated 4.6.1975
(document No. 1), referred to above, for showing that the
Company emphatically protested against the assumption that
it could generate additional 2500 K.W. It was said that its
capability in this regard was limited to 1200 K.W. The
learned counsel referred to the other letters also for a
similar purpose. We think that in view of the revised order
of the Divisional Engineer passed on 10.10.1975, vide
Annexure ’O’, earlier correspondence is not material for the
purpose for which the appellant is trying to use them. The
learned counsel for the respondent has relied on some of
them for his argument on the other points and we will have
to deal with them again when we take up those points. So far
as the question as to whether an assessment of the feasible
capacity of the generating sets of the appellant Company was
made by the Divisional Engineer as required by the
Generation Order is concerned, we have no hesitation in
deciding the issue in favour of the respondent.
15. On behalf of the appellant it was urged that since
the Electrical Adviser-cum-Chief Electrical Inspector of the
State Government who has been mentioned as the appellate
authority under Clause 6 of the Generation Order was
associated with the assessment by acting as a member of the
Committee (vide Annexure ’R-1’ at page 256 of the Paper Book
Vol. II), the entire process in this regard should be held
to be completely vitiated. In view of our finding in the
preceding paragraph, the argument has to be rejected.
Besides, it is not correct to assume that an appeal against
the assessment was provided by Clause 6 of the Generation
Order which reads as follows:
"6. In case of any dispute between the consumer and the
Divisional Engineer acting under Clauses 3, and 4, it shall
PG NO 992
be referred to the Electrical Adviser and Chief Electrical
Inspector to the Government of Madhya Pradesh whose decision
shall be final."
The above is obviously an arbitration clause in case of a
dispute and since the maintainability of the appellant’s
writ application before the High Court was decided in its
favour, it cannot make a grievance on this score. Besides,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 28
if the appellant Company had a grievance against the
assessments which were made in 1975, it ought to have
challenged the same then and not to have waited for a number
of years before approaching the High Court.
16. Mr. Gupta challenged the assessment still on another
ground. He contended that while making the assessment, the
relevant factors were ignored, and irrelevant and extraneous
considerations were taken into account. The argument which
is based on certain scientific technical hypothesis
proceeded thus: The Company had 3 Generator Sets described
as M.V. Turbo Generator Set, B.B. Turbo Generator Set and
AEG Turbo Generator Set; and five Boilers. Another
Boiler was added in 1977. Every generator set has a rated
capacity which has been described by the learned counsel as
the level at which operation can continue satisfactorily for
indefinite period. This rated capacity is declared by the
manufacturer and can be accurately ascertained without
difficulty. The terms ’overload’ and ’overload capacity’
have been explained by the learned counsel as "one exceeding
the level at which operation can continue satisfactorily for
an indefinite period" and "excess capacity of a generator
over that of its rating", respectively. It was urgued that
overloading may lead to distortion or to overheating with
risk of damage, depending on the type of circuit or device,
and so in many cases only temporary overloads are
permissible. The overload capacity, it has been said, is
referrable generally for a specified time. The
criticism against the report of the Committee is that
the Committee took into account the overload capacity of the
sets and not the rated capacity. Mr. Gupta stressed on the
point that the AEG Turbo Generator Set was maintained as a
standby to be operated only when other sets were not
available for any reasons. He also said that the feasible
generation capacity of a set is also dependent on other
factors and conditions, namely, age and condition of the
set, availability of coal of requisite quality and
specification, adequate and continuous supply of water
etcetera. Referring to the report of the Divisional Engineer
dated 3.6.1975 (document No. 3 at page 302 of the Paper Book
Vol. Il) it was argued that the Divisional Engineer picked
out a moment of time when the plants reached the generation
PG NO 993
of 7500 K.W. and concluded therefrom that the appellant was
capable of generating 1800 extra K.W. from its captive
plant. It was further suggested that in any view of the
matter on the basis of the aforesaid opinion of the
Divisional Engineer the appellant Company ought to have been
asked to generate only 1800 K.W. more and not 2500 K.W.
Finally it was argued that the Board has to be confined to
the reasons in support of the assessment orders which are
mentioned therein and cannot be allowed to travel beyond the
same.
17. Mr. Kacker took great pains in going into the
reports and specially through the aforementioned report of
the Divisional Engineer dated 3.6.1975, with a view to meet
the criticism of the appellant and support the report as a
correct one on merits. He also relied on a number of letters
sent by the appellant showing that the assessment was
accepted as binding on it and claiming from time to time
benefits under Proviso (iii) to Clause 3 of the Generation
Order which was allowed for a number of years. The learned
counsel relied on this aspect as furnishing strong
circumstantial evidence in support of the correctness and
binding nature of the assessment impugned belatedly when the
appellant approached the High Court.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 28
18. It is significant to note that at no point of time
either in 1975 or later the appellant chose to get a
scientific assessment of its generating sets made by an
expert, nor even after filing the present writ petition in
the High Court did it file any opinion of a person having
scientific expert knowledge showing the impugned assessments
to be erroneous or undependable. It is also important to
appreciate that the appellant has not either earlier or now
made any complaint of mala fides or bias against any of the
members of the Committee or the Divisional Engineer or for
that matter against any officer of the respondent Board or
the State. On the other hand, the Officers of the Board
appear to have taken a very sympathetic attitude towards the
appellant for more than four years and allowed it the
benefit of additional energy under Proviso (iii) to Clause 3
of the Generation Order very generously. It was only when
the Board discovered in 1980 that the appellant had stopped
even informing the Board and obtaining its prior approval as
envisaged by the Generation Order before consuming extra
energy that the matter was closely examined by the Board’s
Officers. Mr. Kacker is also right in relying upon the
conduct of the parties for about four or five years after
the assessment was made as furnishing important circumstance
relevant to the issue. We may, therefore, examine a number
of letters in this regard some of which have already been
mentioned earlier.
PG NO 994
19. The very first letter of the appellant Company
after receiving the impugned direction in Annexure ’H’ dated
17.5.1975 was sent within 4 days on 21.5.1975 and is
included at page 195 of Vol. II of the paper book. It will
be seen that the protest against the assessment referred to
by the learned counsel for the appellant was not founded on
any of the grounds pressed know. The basis was "only due to
steam limitation", assuring that "once our boiler under
erection starts steaming, we can enhance our generation to
the full installed capacity." The prayer in the end of the
letter was to "review the whole matter". The Divisional
Engineer, as mentioned earlier, personally examined the
entire matter be novo. Although in its letter dated the 21st
May 1975 the Company had stated that it was not advisable to
generate more than 12 K.W. from its own sets, by the next
letter dated 30.5.1975 (page 305, Vol. II) the appellant
informed the Board that they were generating about 2000
additional K.W., but were in the need of additional coal,
for which the Board was requested to make a recommendation.
In Annexure ’J’ dated 4.6.1975 (page 123 Vol. II) the
protest against the assessment was once more reiterated on
account of some trouble with the boilers. The first
paragraph of this letter indicates that the question was
under discussion of the Divisional Engineer with the
Company’s representatives who was armed during the
conference "with all relevant records". In this background
the fresh independent assessment was made by the Divisional
Engineer as per the document No. 3 dated 3.6.1975 (page 302,
Vol. II). Before the fresh independent direction by the
Divisional Engineer as contained in the impugned Annexure
’O’ dated 10. l0.1975 was issued, a suggestion was made on
behalf of the Board to the appellant Company for its
satisfaction as to the correctness of the assessment by
"actually taking the load on the set, after running it in
parellel with the Board’s supply system". The learned
counsel for the parties before us explained the scientific
implications of the test by "parellel running", but we do
not consider it necessary to go in its technical details.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 28
The Board requested the Company’s consent for such a test,
to be communicated positively within a week. By its reply
dated 25.8.1975 Annexure ’L’ (page 133, Vol. II) the
Company rejected the suggestion on two grounds, namely, that
it was "not having protection system like power relay
etc."and" in case of tripping of Board’s supply we would be
doing the parellelling of the sets"; which was not safe. In
reply thereto the Board satisfactorily met the objections by
its next letter Annexure ’M’ dated 25.10.1975 (page 134,
Vol. II). It was pointed out that the parellel running test
will be undertaken only for a short period after which the
captive sets would be separated from the Board’s system; and
a disturbance free period could be chosen for the same.
Besides, the objections to the suggested test have to be
PG NO 995
rejected as frivolous in view of the stand of the Company
itself as indicated in the letter Annexure ’N’ (page 135,
Vol. II) dated 6.11.1975, stating that it had no objection
into the suggested trial, which the appellant claims to have
sent to the Board which fact is however denied. In the
meantime the second assessment order under Annexure ’O’ had
already been communicated. It was, therefore, open to the
appellant either to accept and act upon this fresh assess-of
the boilers in steam generation as the ground for not being
able to generate additional electricity as required by the
impugned directions. It was also mentioned that after a
sixth boiler became available, the difficulty would stand
resolved. In this background Mr. Kacker placed before us
several letters starting with the letter of the Company
dated 14.2.1977 (at pages 4 to 8 of additional paper book
PG NO 996
prepared and filed by the respondent Board, which was
referred to by the learned counsel as Vol. IV of the Paper
Book). The Company, by this letter requested the Board to
charge at the normal tariff for the additional electricity
consumed by the Company as emergency supply as per Proviso
(iii) to Clause 3 of the Generation Order. The statements
made in the letter appear to be extremely important for the
purpose of the Board’s case and it may be useful to consider
them in some detail.
21. In the first paragraph the Company stated that it
was again placing for the Board’s consideration, the reasons
why it could not generate the additional power according to
the direction issued. In the second paragraph the main
difficulty has been mentioned as steam limitation and reason
therefor has been stated in the third paragraph as the
inferior quality of coal. Later it was stated thus;
"These problems would not have arisen in case our Sixth
Boiler recently erected was commissioned and running without
any trouble."
It was said that although the sixth boiler was taken in
August, it did not work properly for some time. Proceeding
further the letter stated:
"It is only since the beginning of January the Sixth
Boiler has been in continuous service, as a result of which
we were in a position to repair our other Boilers also.
Since the last week of January, we are generating our
full requirement and not even availing the 6U0 K.W. allowed
by the Board.
In the penultimate paragraph of the letter, the case for
normal tariff on the additional electricity already supplied
by the Board was argued in the following manners:
"Considering all the above facts, we sincerely hope,
that as due to no fault of our own we had to take power from
M.P. E.B., more than allotted to us, it is requested that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 28
the charges made to us may be on the usual terms as
previously granted by the Board for which we will be ever
grateful. "
(emphasis added)
The letter is not only conspicuous by the absence of the
objections which were taken later in 1980 before filing of
PG NO 997
this writ case, but it positively indicates that the Company
accepted the assessment as correct, and as expected, it was
actually able to generate the required additional
electricity after the addition of the sixth boiler and was
pleading for normal tariff for the additional electricity
already consumed earlier. This position is re-inforced by
several further letters of the Company, but before we go to
them we would like to point out another very important fact
emerging out of this very letter. At page 7 of Vol. II of
the paper book the letter dealt with another aspect highly
relevant to the present dispute. Another Limited Company
known by the name of "Gwalior Rayons" is having a factory
near the appellant Company’s factory and the appellant was
supplying electric energy to the other factory illegally and
without the permission of the Board. On an objection by the
Board this matter was dealt with in the following words:
"It is not out of place to mention in this appeal that
we had given now and then some power in the past to the
Gwalior Rayons, in emergency for their Beam Dyeing Plant
whenever M.P.E.B. power failed. This was due to the fact as
the Beam dyeing plant is a pressure dyeing plant, with a
continuous process, there used to be heavy damage to very
costly Beams. Since this issue was raised by your Divisional
Engineer, we have completely stopped this type of supply to
them, though the same was given to them after reducing our
humidity or waste plant load.
It is again our request here that the same may be
allowed in emergency under whatever arragement the Board
may so decide to avoid costly damage to the cloth.
A fervent appeal in the interest of the other factory
belonging to a different Limited Company altogether was made
in the above terms. It has to be remembered that in view of
the provisions of s. 28(1) of the 1910 Act, the Company was
prohibited from supplying any energy to the other factory.
This aspect was stressed in term 2(b) of the agreement
between the appellant and the Board as per Annexure ’A (page
62 of Vol. II). It was not the appellant’s case then or
before us now that it had obtained the previous sanction of
the State Government for so doing. Under Cluase 4 of the
Generation Order which reads as follows, jurisdiction was
vested in the Divisional Engineer ot the Board to direct a
consumer having captive source of power to supply
electricity to the Board or to any other consumer only if
the consumer was having surplus generation:
PG NO 998
"4. If the consumer having own generating set(s) can have, a
result of additional generation reasonable in the opinion of
the Divisional Engineer of the Board having jurisdiction,
energy, surplus to his requirement, the Divisional Engineer
may direct him to supply the surplus to the Board or to
another consumer nearby who has been taking supply from the
Board and who is willing to take the supply from the
consumer having generating sets:
Provided that
(i) the contract demand of and the supply to the other
consumer from the Board shall be reduced correspondingly,
whether or not the other consumer avails of the supply from
the consumer having the set,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 28
(ii) the other consumer shall pay to the consumer having
generating set(s) for such supply as if it is supplied from
the Board,
(iii) if the payment receivable by the consumer having
the set under the last preceding clause is less than his
incremental cost of additional generation, the Board shall
make good the difference to the consumer having the set(s)
and
(iv) the consumer having the set(s) will not be required
to incur any additional expenditure for laying lines for
transmitting energy to the other consumer; such lines if
required being laid by and at the cost of the Board."
How could, in these circumstances, the appellant pass on to
a third party some of the electricity meant for it, there is
no explanation on the records. Mr. Gupta the learned counsel
for the appellant argued that since the other factory was in
the neighbourhood it was in the interest of the appellant
Company for the sake of security to see that other factory
was not plunged in darkness when the supply was inter-rupted
on account of tripping. Mr. Kacker rightly pointed out that
no such suggestion was ever made on behalf of the appellant
in any of its letters. On the other hand, the reason pleaded
in the letter quoted above was to save the other Company
from incurring loss due to costly damage to the cloth. In
his final reply Mr. Gupta said that the appellant was
passing on some electricity to the Gwalior Rayons only after
reducing its humidity or waste plant load as stated in the
letter. The explanation is too vague and it cannot be
PG NO 999
assumed that the appellant was making the contribution to
its sister concern by creating artificial shortage of supply
to its mills. The appellant’s conduct cannot be explained
except on the premise that it was able to generate adequate
additional electricity for its purpose and was taking for
granted the sympathetic attitude of the Officers of the
Board in liberally allowing it additional emergency supply
at normal tariff.
22. Another letter which calls for a detailed
consideration was sent by the apellant on 30.5.1979 and is
included at pages 16 to 20 of Vol. IV. A fresh request for
emergency supply under Proviso (iii) to Clause 3 of the
Generation Order was made in this letter on the ground that
the sixth boiler was out for annual overhaul. It was stated
in the opening sentence that this boiler was giving some
trouble earlier but later ’stabilised’. The Company was,
therefore, self-sufficient "without drawing any power from
the Board so far". The letter proceeded to state that the
sixth boiler would be going for annual overhaul and after
that the annual overhauling of the other boilers would be
carried out; and therefore, 1875 K.W. should be allowed to
be drawn for the period mentioned therein. Assurance about
the future was held in the following terms:
Now when our Sixth Boiler has been stabilised we would
normally not draw any power from the Board after 15.9.1977
when overhauling of all the boilers is complete except in
case of emergency due to outage of any of the
boilers.
It was further requested that during the period of breakdown
emergency power as detailed should be supplied and.
"we would request you that for the power availed by us
from the Board for above purpose, say up to a total of 7
days in a month. we may be charged at the same tariff .
Insisting again that it should be allowed to supply
electricity to Gwalior Rayons, described as its sister
concern. the letter read as follows:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 28
"Here we may also mention that we have been supplying
power to our sister concern M/s Gwalior Rayons. in
accordance with the provisions of sanction granted to us
under Section ’8 of the I.E. Act vide Govt. Order No.
PG NO 1000
1313/6U61/XIII/74 dated 8.4.1975. However. it had not been
possible for us to obtain prior Permission from S.E. Gwalior
before switching over power to Gwalior Rayons. It may be
mentioned here that power has to be supplied to M/s Gwalior
Rayons during the period the Board’s supply remained off.
and it is not practically possible to obtain prior
permission for supply in such cases. We would, there-fore,
request you that prior permission should be given once for
all for supplying power to the Gwalior Rayons during the
period supply from the Board to M/s Gwalior Rayons remained
off ’
This letter dated 30.5.1977 confirms the conclusions
derived from the earlier letter dated 14.2.1977 and
clarifies that the first letter was not sent by some mistake
on the part of the appellant Company. Request for emergency
supply was, however, made from time to time in 1978 and for
some time in 1979, which was allowed by the Board. The other
letters including those dated 30.5.1978, 29.6.1978, 7.7.1978
and D 9.9.1978 are all consistent with a correctly made
binding assessment of the feasible additional capacity from
the generating sets belonging to the Company.
23. Mr. Gupta contended that throughout the period 1975
to 1979 there was never a demand made by the Board for any
energy consumed by the appellant at the penal rate and it
was only in 1980 that the Board suddenly decided to press
for the additional demand on the basis of the Generation
Order. The learned counsel emphasised that before the
provisions of the Generation Order can be relied upon by the
Board it is essential for it to make an assessment of the
consumer’s capacity to generate electricity from its captive
power plant. The fact that no demand was made for many years
leads to the conclusion that such an assessment as required
by the provisions of the Generation Order to be made, had
not in fact been made, and alternatively assuming that
factually the capacity had been assessed, the same must be
ignored on account of the conduct of the parties for several
years. The stand of Mr. Kacker, as has been stated earlier,
is that the parties acted on the basis that an assessment
had been made in accordance with the Generation Order and on
that basis the appellant demanded the benefit under Proviso
(iii) to Clause (3) of the Order. The documents relied on by
him and discussed in the preceding paragraphs support the
respondents’ stand. They also explain as to why demand on
the penal rate wa. not made earlier. but it would be
helpful to consider a few more facts relevant to this
aspect.
PG NO 1001
24. The system of supply of power to the consumers is
such that they can go on drawing electricity beyond their
entitlement without any further positive step by the
officers of the Board. The Board is, however, in a position
to, by keeping a certain switch known as Air Break Switch
open, put a restriction on the consumer from drawing excess
energy. A letter dated 4.6.1975 (document no. l, at page
300 of Vol. II) sent by the appellant has been strongly
relied on by Mr. Kacker for showing that Air Break Switch
was permitted to remain closed with a view to assure
uninterrupted supply of the appellant at its request. The
result was that the appellant was in a position to draw
excess electricity without reference to the officers of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 28
Board. That letter indicates that the Board was
contemplating to keep the switch open and the Company by
this letter made a request not to do so. The appellant
Company was fully conscious of the fact that it was
consuming electricity beyond its entitlement under the two
Orders, by claiming the benefit of the provisions dealing
with emergency supply. and was also alive to the fact that
this had to be done only with the prior approval of the
Board. The relevant portion of the letter is in the
following terms:
"Further at no time it may kindly be noted that power
has been availed from MPEB without prior intimation by
phone either to Divisional Engineer or Supdt. Engineer. By
keeping the A.B. Switch open at your end, the delay in
supply to J.C. Mills will be considerable which will cause
very heavy losses to the J .C. Mills for no fault of their
own. This may kindly be reviewed and ...."
The learned counsel for the Board was right in saying
that on account of this request by the appellant the line
was kept open for it unhindered. This did not mean that the
Company was entitled to misuse the privilege, draw extra
energy without prior permission and thereafter refuse to pay
higher charges when demanded. It has been conclusively
established by a large number of letters on the records of
the case that for several years the Company was particular
in obtaining the permission of the Board for drawing
electricity in excess of what it was entitled to, by the
agreement as modified by the Regulation Order and Generation
Order, but later, it not only stopped seeking the advance
sanction in this regard, it did not even care to inform the
Board ot the excess drawal. The Branch of the respondent
Board at Gwalior sent the bills on the basis of the normal
tariff, as the question of grant of additional emergency
supply was being dealt with by the Head Office at Jabalpur.
The Gwalior Office was not at all dealing with the matter
PG NO 1002
relating to the excess emergency supply which aspect was
being exclusively dealt with at Jabalpur, and as soon as the
relevant facts came to the knowledge of the Head Office of
the Board it took up the matter with the appellant Company.
The entire conduct of the parties furnishes strong
circumstantial evidence in support of the Board’s case.
25. Another argument addressed by Mr. Gupta is based on
the letters Annex. ‘P’ series sent by the Board to the
appellant Company from time to time. They have been included
at pages 137 to 156 of Vol. Il of the paper book, and
according to Mr. Gupta they are inconsistent with the
Board’s case regarding the appellant’s entitlement to
receive the amount of energy from the Board. He has pointed
out that these letters do not suggest that the contract
demand had been reduced to nil in accordance with Annexures
‘H’ and ‘O’. By way of illustration he relied on the letter
dated 31.10.1975 (at page 138 of Vol. II) stating that
the Company’s maximum demand should not exceed 1875 KW".
We do not find any merit in the submission. The letters
marked as ‘P’ series did not deal with the entitlement of
the appellant Company as a result of both the Orders--
Regulation and Generation. The Regulation Order was ot
universal application to all the consumers while the
Generation Order applied to only such of them who had their
own generating sets. Under the Regulation Order the contract
demand was reduced by a certain percentage and provided for
payment of charges at penal rate in case of excess
consumption. The rate of cut and the penal rate for
additional consumption did not remain constant, and were
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 28
revised from time to time. It appears that as and when the
revision in the rates took place the consumers were informed
as to the effect of the Regulation Order as it stood after
modification. Mr. hacker was right in saying that since the
Regulation Order was applicable to all the consumers and
letters similar to those marked as Annexure P’ series were
being addressed to all of them, there could not be any
objection in the Board sending similar letters to the
appellant and others having their private generating sets
dealing with the effect of the Regulation Order alone,
without taking into account the Generation Order. A perusal
of these letters fully supports the respondents’ stand that
they were being issued with reference to the Regulation
Order alone. Further, a close examination of the Generation
Order would show that the maximum permissible limit
available under the Regulation Order had not ceased to be
relevant even after the application of the Generation Order.
The entitlement of the appellant due to emergency outage
under Proviso (iii) to Clause 3 ot the Generation Order was
limited to the original contract demand as reduced by the
Regulation Order. It was, therefore, important for the
PG NO 1003
appellant to keep in mind that at no point of time it could
be entitled to ask for beyond this limit as emergency supply
on any ground what-soever. As this limit fluctuated from
time to time on the change in the percentage of reduction in
the Regulation Order, the appellant was rightly reminded of
the latest position in this regard. The learned counsel for
the respondents was also right in saying that these letters
could not have misled the appellant in any manner. The
numerous letters discussed earlier clearly indicate that the
appellant correctly appreciated its position and repeatedly
made requests for emergency supply under the Generation
Order on the assumption that its entitlement had been
rendered to zero. The appellant’s letter dated 30.5.1977 (at
page 16 of Vol. IV) referred to earlier, fully demonstrates
that the plea raised by the appellant is devoid of any
merit. A portion of the said letter (not dealt with earlier)
is in the following terms:
"During the period of break down we would request you to
agree to the following arrangement:
i. Before availing Board’s power during the emergency
we will intimate the B.E., MPEB, Gwalior as well as
S.E.MPEB, Gwalior and send a copy of our letter to the
Director (Com), MPEB, Jabalpur.
ii(a) In case 6th boiler is out and other boilers arc
working satisfactorily we may be allowed to draw power upto
1200 KW.
(b) In case 6th boiler is on range and one of our M V
boilers is out we may be allowed to draw power upto l200 KW.
(c) In case 6th boiler is not and one of our M.V.
boilers is also out we may be allowed to draw power upto
1875 KW.
If present stand of the appellant be assumed to be correct,
there was no occasion for it to claim varying quantities of
power in changing circumstances as mentioned above.
26. It was also urged on behalf of the appellant that
the Board’s letter dated 13.10.1980, Annexure ‘U’, (at page
182. Vol. II) impugned by the appellant is also inconsistent
with the Board’s stand in the present case. By this letter
the appellant was informed that the contract demand of 3490
PG NO 1004
KW as per the agreements between the parties was going to be
reduced to 1250 KW under the provisions of the Generation
Order, and on further reduction under the Regulation Order
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 28
it would come down to 875 KW only. The appellant was
accordingly directed to draw power upto 875 KW with effect
from 1.8.1980. The Board further informed the appellant that
no additional power will be supplied during the period of
overhauling of the private generating sets. This part of
Annexure ’U’ has been set aside by the High Court on the
ground that under Proviso (iii) to Clause 3 ot the
Generation Order the Board was under a duty to permit the
appellant to draw additional electricity on satisfaction ot
the relevant conditions for emergency supply, which it could
not deny. The Board has not challenged this part of the High
Court’s decision, and the same is not relevant for purposes
of the present appeal. Reliance on behalf of the appellant
has been placed on the earlier part of the letter directing
it to limit its drawal to 875 KW. Mr. Gupta explained the
situation thus: The contract demand as per the original
agreement and the subsequent agreements by the date on which
the letter was issued admittedly was 3490 KW. If the Board’s
case that the appellant’s capacity to generate electricity
from its own sets was assessed at 2500 KW be accepted as
correct, then the appellant would have been held entitled to
draw KW only and not 1250 KW as mentioned in the letter. Mr.
Gupta invited us to consider this aspect along with the
Board s earlier letter Annexure ‘R’ dated 28.12.1979 (page
158 of Vol. II), informing the appellant that additional
power to the extent of l90 KW had been sanctioned. The
admitted position in regard to different agreements between
the parties is that initially the parties entered into a
contract with respect to 1500 KW only which was later raised
to 2500 KW. The Regulation and Generation Orders came into
existence at that stage. In July 1979, a supplementary
agreement was executed between the parties for supply of
additional 800 KW. and in December 1979 the Board further
sanctioned l90 KW. The relevant part of the letter relied on
by Mr. Gupta is quoted below:
"The Board has sanctioned l90 KW additional power (over
and above 3300 KW) at 33 KV subject to the following
conditions:
(1) The Contract Demand shall be reduced in terms of
Govt. Control Order No. 1254/2048/XIII/75 dated 4.4.75 after
the decision of the Committee headed by the Electrical
Adviser & Chief Electrical Inspector to Govt. of M.P.
regarding re-assessment of the capacity of the consumer’s
generating set is known."
PG NO 1005
The argument is that the Board could mention about a
Committee proceeding to assess the capacity of the
consumer’s captive plant only if there had not been earlier
any assessment. The reduction in the contract demand under
the Generation Order should have been made after the
assessment work was completed, but as a matter of fact, no
such assessment was made and ultimately the letter Annexure
‘U’ dated 13.10.1980 was issued arbitrarily without any
basis. In absence of an assessment of the capacity under the
Generation Order, no reduction was permissible.
27. Mr. Kacker’s reply is that since the appellant for
the period of more than 4 years was pleading for emergency
supply from time to time on one ground or the other, an
internal Committee of Superintending Engineers which had
visited the Company’s plant on 25.9.1980 suggested that the
appellant Company be granted additional power to the extent
of 260 KW on regular basis instead of examining the grounds
relied upon by the appellant every now and then. The latter
part of the letter informing the appellant that it would not
in the future be supplied additional power on the ground of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 28
emergency has been referred to in support of this argument.
Mr. Kacker further said that unfortunately the Board was
held liable for the emergency supply if the necessary
conditions were satisfied and thus the appellant has got
double advantage and this cannot be the basis for accepting
the appellant’s case. The learned counsel proceeded to say
that the letter Annexure ‘R’ was issued in connection with
the sanction of 190 KW additional power, subject to the
Government Orders, and the reduction thereunder was only a
matter of arithmetical calculation which should have been
done without reference to a Committee. The letter was not
sent in connection with any controversy about the assessment
of the generating capacity under the Generation Order, and
it cannot be interpreted in the manner as suggested on
behalf of the appellant. It was further pointed out that
admittedly there was no question of a committee headed by
the Electrical Adviser and Chief Electrical Inspector to the
Government of Madhya Pradesh to make a fresh assessment
under the Generation Order or to undertake the realistic
assessment of the additional capacity over again. The
assessment had to be made by the divisional Engineer of the
Board. It was lastly said that this argument addressed by
Mr. Gupta before this Court was not advanced before the High
Court nor was the point taken in the writ petition or any
affidavit there. On a consideration of the documents and the
re,levant circumstances we agree with Mr. Kacker. The use of
the word "re-assessment" in the letter quoted above instead
of "assessment" also supports the respondents’ case. The
term "re-assessment" implies that there had already been an
PG NO 1006
assessment earlier. Even interpreting the letter as
suggested by Mr. Gupta, the existence of the earlier
assessment by the Divisional Engineer cannot be ignored. If
the appellant was not satisfied with it, it should have
taken appropriate step for getting the same quashed in 1975
itself and should not have waited for four or five years
before approaching the High Court, and in the meantime
taking the benefit of the provisions regarding emergency
supply on its basis.
28. Now in this background let us come back to the
argument of Mr. Gupta as mentioned earlier in paragraph 16
above. In reply Mr. Kacker asserted that it is not correct
to assume that a machine can function on a regular basis
only according to the rated capacity as declared by the
manufacturer. By way of illustration he relied upon the
specifications relating to a machine issued by the Bharat
Heavy Electricals Ltd. indicating that the "Peaking
capacity’ of the machine with "No time limit" was higher
than the "rated output" mentioned. The learned counsel also
analysed the report of the Divisional Engineer along with
the data mentioned by the Committee which in his opinion
indicated that the maximum capacity of the appellant’s sets
technically feasible was much more than that actually
assessed and could not be less by any calculation even
before the 6th boiler was erected. After the sixth boiler
became available the capacity rose to at least 9700 KW but
the Board taking a generous view did not call upon the
appellant to generate further additional electricity than
that directed earlier.
29. We have heard the learned counsel at considerable
length on this aspect and we think that the question as to
what should be considered the correct feasible capacity of
the appellant’s sets is one involving complex technical
knowledge and the High Court (or for that matter this Court)
was well advised not to have attempted to determine it. We
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 28
must reiterate the circumstances which appear to be highly
relevant, namely, (i) that the Divisional Engineer who has
been rightly considered by the Generation Order to have
sufficient expert knowledge in this regard reached the
conclusion which is under challenge in the present case
after personally considering the matter thoroughly along
with the Officers of the Company as is apparent by many of
the letters; (ii) the figures collected by the members of
the Committee are not challenged as incorrect or inaccurate;
(iii) it is not suggested that any of the members of the
Committee or the Divisional Engineer or for that matter any
Officer of the respondent Board or of the Stale Government
had any prejudice or bias against the appellant Company;
PG NO 1007
(iv) the appellant did not get an independent assessment of
its generating sets made by any person having expert
knowledge; (v) the appellant avoided to get the correctness
of the assessment verified by the parellel running test as
suggested by the Board; and (vi) the conduct of both the
appellant and the respondent Board as emerging from the
documents placed by the parties on the records of the case
furnish valuable circumstantial evidence in support of the
respondents’ case. The argument of the appellant challenging
the assessment as illegal must, therefore, be rejected.
30. Mr. Gupta by way of an alternative plea pressed an
argument for granting a limited relief. He urged that even
assuming that the assessment of maximum feasible capacity
of the appellant’s sets was correctly made in 1975 so as to
be binding on the appellant, it is fully established even by
the letters of the Board that the position stood materially
altered by November 1979 which called for a re-assessment.
The Board s letters dated 27.11.1979 (page 157 Vol. II) and
28.12.1979 (page 158, Vol. 11), according to the learned
counsel. indicate that irrespective of whether the initial
assessment was good or not, the Board accepted the position
that steps for re-assessment had to be taken and after
taking into account the circumstances, decided to grant an
ad hoc benefit of 260 KW by its letter Annexure ‘U’ dated
13.10.1980 (page 182, Vol. Il), discussed earlier. Although
the appellant does not agree that the grievance of the
appellant was properly met by the grant of the additional
260 KW but since this was allowed by the Board itself, the
relief should have been granted with effect from November
˜979 and not from 1.8.1980 as mentioned in Annexure ‘U’. The
plea of the respondent that this additional power was
allowed on account of the recurring demand by the Company
for emergency supply under Proviso (iii) to Clause 3 of the
Generation Order has been challenged as incorrect. It is
urged that the letter Annexure ‘U’ granting additional 260
KW over and above 875 KW the appellant was held entitled to
draw, must be read in the background of Annexure Q dated
27.11.1979 (page 157, Vol. II) and Annexure ’R’ dated
28.12.1979 (page 158, Vol. II). These letters have been
discussed earlier while dealing with another argument. The
argument of the appellant is that the Board had recognised
the need of re-assessment of the capacity and had decided to
entrust the work to a committee and it must be presumed that
the team must have submitted some report. However, no such
report has been placed by the Board on the records of this
case and the suggestion is that it is a case of suppression
by the respondent and the Board cannot be heard to say that
the team did not go i˜ e question of re-assessment. Since
the matter was raised by the appellant in November 1979
PG NO 1008
which ultimately resulted in the partial relief up to 260 KW
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 28
about 11 months later, the benefit ought to have been
allowed with effect from November 1979 if not earlier. The
stand of the Board with respect to this additional 260 KW
has already been mentioned earlier. It is argued by the
Board that the Generation Order contemplates only a single
assessment leading to a single direction and the appellant
was not entitled to re-assessment. The word "re-assessment"
in Annexure ’R’ was, according to the respondents, mentioned
due to inadvertence or under a misconception of the exact
legal position. In any event the additional energy was
allowed as the result of the repeated demand by the
appellant for emergency grant. With a view to meet the
situation which was arising every now and then a generous
attitude was taken to allow additional 260 KW. It is
contended that no further claim can be legitimately founded
on this act of generosity. As a result of the High Court’s
decision the appellant’s claim for emergency supply was
being considered on merits. The appellant is thus having the
advantage of the double benefit with effect from 1.8.1980.
because the Board has neither appealed against that part of
the High Court judgment, nor has it withdrawn the special
benefit of 260KW, but a further claim cannot be allowed on
account of this sympathetic attitude. In view of our finding
that a proper and binding assessment of the capacity of the
appellant’s generating sets was made in 1975 by the
Divisional Engineer in pursuance of which the direction in
Annexure O was issued and in view of the further fact that
on that basis the appellant from time to time asked for and
was allowed emergency relief under proviso (iii) to Clause 3
of the Generation Order, the argument of Mr. Kacker appears
to be correct. The appellant has, in our view. failed to
establish any right ot additional relief from an earlier
date.
31. The next point taken on behalf of the appellant is
that there is no sanction in law for charging at the penal
rate for the electricity consumed beyond what is
permissible on application of the Generation Order. Section
22B of the 191() Act confers powers of framing subordinate
legislation on the State Government for the purposes and to
the extent mentioned therein and consequence of
contravention of any such Order is provided in s.42 (e)
mentioned below:
"42. Whoever
.......................................
(e) makes default in complying with any order issued
JIYAJEERAO COTTON MILLS v. ELECTRICITY BOARD [SHARMA. J ]
1009
to him under section 22B or sub-section (2) of section 34;
shall be punishable with fine which may extend to one
thousand rupees, and, in the case of a continuing offence or
default, with a daily fine which may extend to one hundred
rupees."
The argument is that s. 22B cannot be so construed as to
include a delegated power to impose penalty of the
delegate’s choice for the contravention of an order issued
under the Section. Since the legislature itself exercised
its legislative power in that field by including s. 42 in
the statute, the State had or has no authority to take any
further step for the enforcement of its Order, except by
resorting to s. 42. Dealing with s. 78-A of the 1948 Act
which says that in the discharge of its functions, the Board
shall be guided by such directions on questions of policy
as may be given to it by the State Government. Mr. Gupta
contended that it cannot be interpreted to effectively
clothe the State to direct the Board to do a thing which it
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 28
is itself nOt empowered to do. The Board, therefore. should
have either prosecuted the appellant under s. 42(e) or
disconnected the electric supply altogether, but it was not
entitled to demand penal charges. Mr. Kacker countered by
saying that s. 42 of the 1910 Act belongs to the group of
sections 39 to 50 dealing with Criminal Offences and
Procedure as is apparent by the heading just above s. 39,
and deals with the criminal liability only. The same set of
events may give rise at the same time to civil rights as
well as to a criminal offence and it is not correct to
suggest that merely because provisions arc specifically
included in the Act dealing With criminal liability, the
civil liability is deemed to have disappeared. By way of
illustration, a simple case of theft ot movable article may
be considered: the owner ot the property can set the
criminal law in motion and at the same time may claim the
property or compensation for it under the civil law. Mr.
Kacker appears to be right in his stand that merely because
the appellant became liable to the penalty as mentioned in
s. 42(e) it cannot on that ground defend an additional
demand on account of supply of the extra energy , if
otherwise maintainable under the law. Besides, s. 48 puts
the matter beyond controversy by expressly stating that the
penalty imposed by the aforesaid section shall be in
addition to, and not in derogation of, any liability in
respect of the payment of compensation which the offender
may have incurred.
32. While commencing his argument, Mr. Gupta had
indicated that one of the points on which the appellant
relied upon, related to the validity of Clause 3 of the
PG NO 1010
Generation Order mandatorily requiring a consumer to
generate maximum feasible electricity from its own
generating set. It was suggested that the provisions in the
said Clause being in excess of the power under s. 22B, were
ultra vires. After completing his argument on the other
points he said that he was not pressing this point. Mr.
Kacker, therefore, did not address us on this aspect. We may
not in these circumstances detain ourselves on this question
except mentioning the decisions in Adoni Cotton Mills v.
A.P. State Electricity Board, [1976] 4 SCC 68; State of U.P.
v. Hindustan Aluminium Corporation, [1979] 3 SCC 229; and
New Central Jute Mills v. U. P. State Electricity Board,
[1986] Supp. SCC 581, showing in unambiguous terms that the
power is there. S. 22B permits the State Government to issue
an appropriate order for regulating the supply, distribution
and consumption of electricity The expression "regulate ’
occurs in other statutes also, as for example, the Essential
Commodities Act, 1955, and it has been found difficult to
give the word a precise definition. It has different shades
of meaning and must take its colour from the context in
which it is used having regard to the purpose and object of
the relevant provisions, and as has been repeatedly
observed, the Court while interpreting the expression must
necessarily keep in view the object to be achieved and the
mischief sought to be remedied. The necessity for issuing
the two Orders arose out of the scarcity of electricity
available to the Board for supplying to its customers. The
situation did not leave any option to the Board but to make
limited supply of electricity to its consumers, and it must
be held to have, in the circumstances the right to stagger
or curtail the supply. The Orders were issued in this
background and to make the direction mentioned therein
effective it was considered essential to impose sanctions
which could take any reasonable form; either disconnection
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 28
in case of gross violation or the lesser sanction of
enhanced tariff. By the Order issued under s. 22B and quoted
in paragraph 7 of the judgment in Adoni Cotton Mills case
(supra) the State Government directed a reduction in supply
of electricity to the extent of 75% of the previous average
monthly demand and provided for payment of the charges for
excess consumption at double the tariff rates. The
Electricity Board thereafter proceeded to impose further
restrictions. Aggrieved by these measures the Adoni Cotton
Mills, an aggrieved consumer approached the Court, but its
challenge was repelled. On behalf of the appellant Mr. Gupta
attempted to distinguish the decision on the ground that the
fixing of a higher tariff for the excess consumption was
against public policy and that this aspect was not
considered by this Court in Adoni Cotton Mills case. We do
not find any merit in this argument. The demand of higher
charges/tariff
PG NO 1011
for electricity consumed beyond legally fixed limit is a
reasonable deterrent measure providing an appropriate
sanction--not as harsh as disconnection of supply of energy
altogether--and cannot be opposed on the ground of public
policy. We, therefore, hold that none of the two Orders is
illegal or unreasonable.
33. Mr. Gupta alternatively contended that the
provisions fixing the electric charges at 4 times the normal
tariff for the excess consumption are to be found only in
the Regulation Order and since there is no corresponding
provision in the Generation Order, there is no sanction for
demanding the penal rate for the electricity consumed
incontravention of the Generation Order. He proceeded to say
that there is no language in either of the two Orders to
link them with each other. The different measure taken under
the two Orders operate under different conditions and
circumstances, and they cannot, therefore, be lumped
together. In reply to the argument of Mr. Kacker that since
the Schedule to the Regulation Order refers to the ’contract
demand’ which expression denotes the original contract
demand as reduced by the provisions of both the Regulation
Order and the Generation Order, leading to the conclusion
that the provisions regarding the payment of penal charges
take into account both the Orders together, Mr. Gupta
contended that although it is true that by reason of the
Generation Order the contract demand is reduced but it
cannot be said that a new contract comes into existence for
the reduced amount to justify the argument of Mr. Kacker,
because the reduction is as a result of operation of law. In
other words, the reduced amount cannot be termed as
’contract’ demand as it is in supersession of the contract
demand. The contract demand, therefore, remains the same as
before although there is introduced a statutory bar from
drawing it in full measure. Applying this logic, it was
argued by the learned gcounsel that the Generation Order has
to be kept apart while working out the effect of the
Regulation Order. He also referred to the subsequent
Regulation Order of 1978 in which the relevant Schedule
prescribes 50 KW as the minimum entitlement which is
inconsistent with the Board’s case. It is urged that the
argument on behalf of the Board that the two Orders have to
be read together must, therefore, be rejected.
24. The reply of Mr. Kacker is three-fold: he point was
not taken in the writ application before the High Court nor
in the grounds before this Court and since it is not a pure
question of law it should not be allowed to be raised in the
argument; (ii) the two Orders were issued on the same date
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 28
with the common object to remedy the same problem as is
evident from their preambles and so they cannot be read in
PG NO 1012
isolation; and (iii) in any event the Electricity Board in
levying and making the impugned demand must be deemed to
have exercised its power under s.49 of the 1948 Act which it
is certainly entitled to.
Mr.Gupta said that it was not right to suggest that the
point was not raised in the High Court. He placed before us
the review petition filed in the High Court after the
disposal of the writ case and relied on the statement in
paragraph 3 of the judgment disposing of the review
petition. He stated that the written arguments of the
Company consisted of three parts under the heads ’list of
dates, notes of argument’ and a ’reply’. Mr. Gupta fairly
conceded that the point was not taken in the writ petition
before the High Court and he was not in a position to assert
that it was actually argued on behalf of the Company in the
first argument addressed before the High Court. but he
claimed that the Company did press the point during the
final reply. He could not deny that the point was not taken
when the present appeals were filed in this Court. The
judgment of the High Court does not deal with the point. In
the circumstances, the question arises as to whether the
question should be allowed to be urged now and if so how
should it be answered .
35 Mr. Gupta contended that merely because the two
Orders are issued under the same provision of law on a
particular date, they cannot be dovetailed. The similarity
in the preamble of the two Orders is described as not great
consequence as it merely borrows the language from s.22B.
Many Orders are issued under s. 3 of the Essentila
Commodities Act,the argument proceeds, and it cannot, there
fore, be suggested that the penalty imposed in one has to be
applied to the other without express language to that
effect in either of two Orders. We do not think in view of
the fact that the point was not taken on behalf of the
Company while instituting the writ application in the High
Court and filing the present appeals in this Court, it
should be allowed to be urged at the hearing. Let us assume
that the argument of Mr. Gupta is correct. Immediately the
next question would arise as to whether the Board is
otherwise authorised in law to levy and demand charges for
the excess electricity at the higher rate and if so whether
the Board can be said to have exercised its power in this
regard. Mr. Kacker contended that apart from the power of
the state Government to limit the supply of electricity to
the consumers by an order under s. 22B and direct payment
of penal charges for excess consumption, the Board is also
empowered to impose sanctions by charging enhanced tariff
and the authority to do so is derived both under s. 49(3)
PG NO 1013
of the 1948 Act and s. 49(1) read with the original
argeement. The relevant provisions are quoted below:
"49. Provision for the sale of electricity by the Board
to persons other than licensees.
(1) Subject to the provisions of this act and of
regulations, if any, made in this behalf, the Board may
supply electricity to any person not being a licensee upon
such terms and conditions as the Board thinks fit and may
for the purposes of such supply frame uniform tariffs.
(2) ....................................................
(3) Nothing in the foregoing provisions of this section
shall derogate from the power of the Board, if it considers
it necessary or expedient to fix different tariffs for the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 28
supply of electricity to any person not being a licensee,
having regard to the geographical position of any area, the
nature of the supply and purpose for which supply is
required and any other relevant factors.
(4) In fixing the tariff and terms and conditions for
the supply of electricity, the Board shall not show undue
preference to any person.
Reliance was placed on several decisions of this Court
of the High Courts. It was further contended that it is not
essential for the Board to frame regulations tot the
exercise of such power. The leaned counsel appears to be
right. In Adoni Cotton Mills ’ case (supra) the State
Government had made an order under s. 22B of the 1910 Act
limiting the supply to 75% of the previous consumption as
was done in the present case and directed the payment of
punitive rates for excess consumption. The Board made
supplementary orders for placing further onerous conditions
on certain groups of consumers. This was challenged before
the High Court inter alia on the ground that since the State
Government had already acted under s. 22B, the Board could
not further pass supplementary orders and that in any event
since the Board had not made regulations laying down the
principles under s. 79(j) of the 1948 Act, the orders were
bad. Both the points (along with several others) raised by
PG NO 1014
the appellant in that case were rejected by this Court.
Referring to s. 49(1) of the 1948 Act, the Court observed
that the power to enhance the tariff is included in the
Section and the expression that "the Board may supply
electricity .. upon such terms and conditions as the Board
thinks fit" in s. 49(1) iS related to the terms and
conditions of the agreement between the parties. Sub-section
( 1) confers power on the Board to supply electricity upon
such terms and conditions as it thinks fit and the terms and
conditions include the power of the Board to enhance the
rates. S. 49(3) permits the Board to fix different rates
for the supply of electricity having regard to certain
conditions mentioned therin and ’’any other relevant
factors". It was held that the expression "any other
relevant factors" could not be considered ejusdem generis
because there is no genus of the relevant factors. In New
Central Jute Mills Co. Ltd. v. U.P. State Electricity Board,
(supra) the situation again was similar to the present case.
The argument pressed before the Supreme Court inter alia was
that the Board had no authority to make the demand in excess
of the agreed rate under the agreement. Repelling the
contention, the Court observed in paragraph 4 of the
judgment that the agreement itself did not envision the
supply of electricity in violation of the ban imposed by the
State Government in exercise of its power under s. 22B of
the 1910 Act; nor did the agreement stipulate the rate at
which such supply should be charged if notwithstanding the
ban against the supply a consumer drew electricity in excess
of the permissible quantity. In the circumstances, the Board
was justified in invoking the power under s. 49(3) of the
1948 Act which authorised it to supply electricity by
charging different tariff having regard to certain
conditions and ’ any other relevant factors". S. 49(3) was
interpreted to be wide enough to cover a situation where
electricity in excess of the quantum is drawn in disregard
of the ban imposed under s. 22B of the l9 10 Act. We do not
consider it necessary to multiply the decisions as there
does not appear to be any doubt that either under s. 49(1)
of the 1948 Act read with the agreement or under s. 49(3) or
under both the provisions the respondent Board is fully
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 27 of 28
authorised to levy and to make a demand at a higher rate
than the usual tariff. It is also clear that it is not
essential for the Board to make regulations indicating the
basis for such levy before making the demand. The appellant
has not been able to successfully show before us that the
power by the Board has to be exercised in a particular
manner and by adopting a particular mode. If it is assumed
that a particular formality has to be completed before a
demand can be legitimately raised, the appellant cannot be
allowed to claim now that the same is lacking in the present
case in the absence of a proper pleading in the original
writ petition before the High Court. If the point had been
raised in time, the respondent Board could have placed
relevant materials on the issue. If at the end of the
hearing of the case in the High Court the point was
mentioned in the appellant’s final reply and included in the
PG NO 1015
last instalment of its written argument, it cannot cure the
defect in the pleading specially when the judgment of the
High Court dismissing the writ application does not deal
with the point.
In that view it is not necessary to test the correctness
of the argument of Mr. Kacker that the appellant’s
entitlement to receive the quantum of electricity from the
Board at the normal tariff can be determined only by a
combined reading of the two Orders. We do not, therefore,
consider it necessary to decide as to what would have been
the precisely correct answer if the point had been properly
raised before the High Court at the appropriate stage.
36. We do not find any merit in any of the points urged
on behalf of the appellant. We were informed by the learned
counsel for the parties that the appellant does not accept
the correctness of the calculations in the letter ’P’ series
and the question is being examined by the High Court in a
pending case. The appellant also asserts that even during
the period commencing from November 1979 the Company had
pleaded for emergency supply. The High Court has in the
present case directed the prayer for emergency supply to be
considered on merits. Since these questions are not involved
in the present appeals, arguments relating to these points
have not been addressed before us. We, in the circumstances,
make it clear that any observation made in the present case
shall not be treated to have decided those points which are
the subject matter of a pending case in the High Court.
37. It was also pointed out at the Bar that several
interim orders were issued by this Court during the pendency
of the present appeals and final direction should be given
in regard to them. While granting special leave this Court
by its order dated 5.11.1982 directed the appellant Company
as condition for interim relief of restoration of electric
connection to pay a sum of Rs.50,00,000 within a fortnight
and another sum of Rs. 1,50,00,000 within six months with
interest from l. 1.1983 at the rate of 12% per annum until
payment. The future payment of the electricity bills was
ordered to be made within four weeks from the service of the
bills. The Court also said that the applications made by the
appellants for consideration of emergency supply of the
electricity should be expeditiously disposed of by the Board
on merit, and all payments by the appellants will be subject
to adjustment in the light of the decision on the emergency
applications. By the order dated 24.11.1982 the time for
payment of Rs.50,00,000 was extended to 6.12.1982. With
respect to the payment of Rs. 1,50,00,000 the Court by its
order dated 6.5.1983 permitted the amount to be deposited in
PG NO 1016
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 28 of 28
two equal instalments. The Court also said that if it was
ultimately found that the appellant had paid any amount in
excess of the total liability, the Board shall repay such
excess amount with interest at the rate of 12% per annum. By
a subsequent order dated 23.4.1984 the appellant was
required to pay a sum of Rs. 1,28,00,000 to the Board by the
10th of May, 1984 and to keep the bank guarantee alive till
the final disposal of these appeals as condition for
continuance of the interim order. During the hearing of the
appeal a grievance was made on behalf of the respondent
Board that the bank guarantee had not been effectively
renewed and the learned counsel for the appellant undertook
on behalf of the Company to correct the defect. Subsequently
it was stated at the Bar that proper bank guarantee had been
furnished in accordance with the Court’s direction. In view
of our present decision the respondent Board, besides being
entitled to retain the amount already paid to it in
pursuance of this Court’s direction, is further entitled to
enforce the bank guarantee. The appellant Company,
therefore, must arrange to make the payment withount delay,
failing which the Board shall be entitled to take steps for
enforcement of the bank guarantee. The dispute regarding the
appellant s claim to receive emergency supply is pending
before the High Court. The appellant shall be entitled to
adjustment in the light of the final decision on this point.
38. In the result, the appeals fail and are dismissed
with costs payable to the respondent No. l.
R.S.S. Appeals dismissed