Full Judgment Text
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5584 OF 2012
(Arising out of SLP (C) No. 12334 of 2009)
S. Srinivasa Murthy … Appellant
versus
Karnataka Housing Board … Respondent
J U D G M E N T
G. S. Singhvi, J.
1. This appeal is directed against order dated 14.3.2008 of the National
Consumer Disputes Redressal Commission (for short, ‘the National
JUDGMENT
Commission’) whereby the application filed by the appellant for review of order
dated 9.9.2004 was dismissed.
2. In response to an advertisement issued by Karnataka Housing Board
(respondent), which was published in the Times of India dated 14.7.1993, the
appellant applied for allotment of a HIG flat in Vth Phase, Yelahanka under the
self-financing scheme. He was allotted under S-HIGA Flat No.37, First Floor.
1
Page 1
In the allotment letter issued on 29.11.1993, the tentative cost of the flat was
shown as Rs.3,40,000/-.
| onstruction | of the fla |
|---|
and possession thereof was delivered to the appellant on 19.5.1999.
4. In the meanwhile, the appellant sent letter dated 14.12.1998 to the
Executive Engineer of the respondent with the request that he may be permitted
to change the mode of purchase from lease-cum-sale basis to outright sale basis.
He also conveyed his willingness to pay the balance amount required for that
purpose. That letter reads as under:
“From
S.SRINIVASA MURTHY,
QR 9/TYPE IV, TELECOM QUARTERS,
C.T.O. COMPOUND, JUHU ROAD,
MUMBAI-400054
To
JUDGMENT
The Executive Engineer,
Karnataka Housing Board,
KHB Metro No.1 Dn,
BANGALORE-560064.
Dear Sir,
Sub: Allotment of House at YELAHANKA-5 PHASE-
SHIG-FF
Bangalore Metro Division I
2
Page 2
ALLOTMENT CODE: 210-288-37: Request to
purchase the above under ABSOLUTE SALE
DEED.
| I am willi<br>ose on rec | ng to pay<br>eiving a le |
|---|
I shall await an early action on my request.
Thanking you,
Yours faithfully,
Mumbai,
14-12-98
(S.SRINIVASA MURTHY)”
5. The respondent accepted the request of the appellant and allotted a flat to
him in 3500-Multi-tenaments at Vth Phase, Yelahanka on outright sale basis.
The cost of that flat was shown to be Rs.5,23,232/-.
JUDGMENT
6. Upon receipt of the revised allotment letters dated 22.1.1999 and
25.1.1999, the appellant sent communication dated 15.2.1999 to the Housing
Commissioner of the respondent and protested against the alleged failure of the
concerned authority to take cognizance of the fact that he had already deposited
Rs.3,75,750/-. Thereafter, the respondent issued letter dated 6.4.1999
indicating therein that the appellant is required to pay the balance amount of
3
Page 3
Rs.1,57,482/-. The appellant accepted the revised allotment and deposited the
remaining amount.
| on of the s | ale deed, t |
|---|
Rs.4,31,918/- so that he will be required to pay registration charges on 81% of
the total cost. The appellant conveyed his acceptance vide letters dated
22.8.1998, 27.11.1998 and 15.5.1999. The English translation of the last letter
is reproduced below:
“(TRANSLATION)
KARNATAKA HOUSING BOARD
"CONSENT LETTER"
I have been allotted by the Karnataka Housing Board Flat
No.37-S-HIG 'A' F.F. on full price basis and I have paid the full
value of Rs.533232.00.
JUDGMENT
I am agreeable to the decision of the Board that the registration
value should be 81% of the sale price namely Rs.43198.00 and
the stamp duty should be paid over the said amount.
If the remaining 19% of the value is included in the registration
value the registration charges will be higher. Hence I agree to
have the registration done at 81% of the sale price and I will not
ask for refund of the remaining 19% of the sale price under any
circumstances.
NAME OF THE ALLOTTEE
Sd/-
S.V. Srinivasa Murthy
Date: 15.05.1999”
4
Page 4
8. After taking possession of the flat, the appellant filed complaint under
Section 17 of the Consumer Protection Act, 1986 (for short, ‘the Act’) and
claimed the following reliefs:
“1. Interest on basis cost of Rs.340000/- from 9.2.95
to 18.5.99 310675-00
2. Refund of amount paid on 31.7.95 23840-00
3. Interest on 2 above for the period from 31.7.95
to 18.5.99 19435-00
4. Refund of amount paid on 13.1.96 11910-00
5. Interest on 4 above for the period from 13.7.96 to
18.5.99 7255-00
6. Refund of amount paid on 29.4.99 157482-00
7. Interest on 6 above for the period from 29.4.99 to
18.4.99 1890-00
JUDGMENT
8. Compensation for delay deficiency in specification
and mental tension 50000-00
9. Costs of the complaint 2000-00”
9. In the counter filed on behalf of the respondent, the following pleas were
taken:
5
Page 5
(i) The cost of the flat mentioned in the allotment letter issued on
29.11.1993 was tentative and the same was revised keeping in view the relevant
factors including the cost of construction.
| pped from | questionin |
|---|
because he had accepted the terms and conditions embodied in letter dated
29.11.1993 without any objection and, later on, he voluntarily sought change of
the mode of purchase from lease-cum-sale basis to outright sale basis.
(iii) The time schedule fixed for completion of the flat was also tentative and
possession of the flat was handed over after completion of construction and
ancillary works.
10. The State Commission rejected the appellant’s plea for award of interest
on the amount deposited by him and observed:
JUDGMENT
“Since the amount has been fixed as provisional at the time of
issuing advertisement and subsequently cost has been raised on
account of the escalation and the said amount has been paid by
the complainant, the complainant is not entitled to get interest
on the said amount as claimed in the complaint.”
11. The appellant’s grievance that there were deficiencies in the flat was also
rejected by the State Commission by assigning the following reasons:
“The complainant has contended in his
complaint and in his affidavit and his
6
Page 6
| advoca<br>in so | te Mr.<br>far as |
|---|
12. On the issue of delay in the delivery of possession, the State
Commission partly ruled in favour of the appellant and directed the respondent
JUDGMENT
to pay compensation of Rs.25,000/-. This is evident from paragraph 11 of the
State Commission’s order, which is extracted below:
“ As far as the delay in handing over the possession of
the flat is concerned, the OP has contended that the delay in
handing over the possession is not on account of deficiency in
service, but on account of various acts of nature administration
and various other problems which do not amount to
deficiency in service. The explanation offered by the OP
cannot be easily accepted. According to the original
advertisement and the brochure issued by the Board the flat
will be ready and has to be handed over by the end of 1994
but actually the flat was handed over to the complainant on
7
Page 7
19.5.99. There was no fault on the part of the complainant.
Under those circumstances we are of the opinion that ends of
Justice will be met if we direct the OP to pay a sum of
Rs.25,000/- as compensation to the complainant for the delay in
handing over the flat.”
Commission was dismissed by the National Commission vide order dated
9.9.2004. The National Commission agreed with the State Commission that the
cost indicated in the allotment letter was tentative and the respondent had the
right to revise the same and further that the appellant was not entitled to
complain against the cost mentioned in the revised allotment letters because he
had voluntarily sought change in the mode of purchase. The National
Commission also held that the compensation awarded by the State Commission
was just and proper.
JUDGMENT
14. The application filed by the appellant for review of order dated 9.9.2004
was also dismissed by the National Commission vide order dated 14.3.2008, the
relevant portion of which is extracted below:
“Undisputedly, the tentative cost of the flat booked was
Rs.3,40,000/-. It was enhanced from Rs.3,40,000/- to
4,35,000/- and further to Rs.4,83,000/-. Though the
Petitioner had paid the amount as per allotment letter
dated 6.4.99 a further amount of Rs.1,57,482/- was
demanded which was also paid by him on 29.4.99 and
the sale deed was registered. He took the possession on
8
Page 8
15. The appellant reiterated the grievance made in the complaint and argued
that the demand of additional price by the respondent was only unjustified and
the State Commission and the National Commission committed serious error by
declining to entertain his prayer for award of interest on the amount already
deposited by him and the additional cost. He further argued that the respondent
was not entitled to arbitrarily change the mode of allotment from self-financing
scheme to outright sale scheme and charge higher price without paying interest
on Rs.3,40,000/- deposited by him in furtherance of the initial allotment. He
further argued that the State Commission and the National Commission
JUDGMENT
committed grave error by refusing to direct the respondent to refund the excess
amount of Rs.1,57,482/- with interest. In the end, he argued that the respondent
should be directed to refund Rs.1,01,314/- which was charged in excess of the
cost of the flat mentioned in the sale deed.
16. Learned counsel for the respondent argued that the cost of the flat
mentioned in the allotment letter issued on 29.11.1993 was tentative and was
liable to revision till the completion of construction and the respondent did not
9
Page 9
commit any error by revising the cost from Rs.3,40,000/- to Rs.4,35,360/- and
then to Rs.4,83,000/-. He further argued that the appellant cannot complain
against the demand of total cost of Rs.5,23,232/- because he had voluntarily
| of purcha | se and acc |
|---|
revised allotment letters issued on 22.1.1999 and 25.1.1999. Learned counsel
further argued that the appellant is estopped from questioning the cost of flat
indicated in revised allotment letters because the same cost has been charged
from other allottees of HIG house under the outright sale scheme.
17. We have considered the respective arguments/submissions and carefully
scanned the record. In our view, the appellant cannot make any grievance
against the cost specified in the revised allotment letters issued on 22.1.1999
and 25.1.1999 because he had voluntarily sought change in the mode of
purchase and unequivocally agreed to pay the cost i.e. Rs.5,23,232/-. The
JUDGMENT
appellant’s plea that the cost of the flat cannot be more than what was specified
in the registered sale deed sounds attractive but lacks merit. A careful reading
of letters dated 22.8.1998, 27.11.1998 and 15.5.1999 sent by the appellant to the
respondent makes it clear that he had conveyed his unequivocal willingness for
registration of the sale deed showing the cost of the flat as Rs.4,31,918/-
although the actual cost was Rs.5,23,232/-. Having taken advantage of the offer
made by the Board to get the deed registered at a price less than the actual cost
10
Page 10
of the flat, the appellant cannot turn around and demand refund of
Rs.1,01,314/-.
| lso merits | rejection |
|---|
him was not bona fide.
19. In the result, the appeal is dismissed.
…...……..….………………….…J.
[ G.S. Singhvi]
…………..….………………….…J.
[Sudhansu Jyoti Mukhopadhaya]
New Delhi,
August 22, 2012.
JUDGMENT
11
Page 11