NONREPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.3673 OF 2015
M/s Super Label Mfg. Co. .…Appellant(s)
Versus
New India Assurance Company Limited…. Respondent(s)
J U D G M E N T
A.S. Bopanna, J.
1.
The appellant is a registered partnership firm
engaged in the business of printing high technology
labels used as adhesive labels mainly by Drug
Manufacturers and Other Companies on their packing
material. In order to carry on such business, the
appellant had imported highly sophisticated and costly
Signature Not Verified
machinery and had installed the same in their premises.
Digitally signed by R
Natarajan
Date: 2023.05.17
10:44:45 IST
Reason:
1
Among the said machinery that was installed, it also
included the ‘Aquaflex’ brand of machinery from Canada
and ‘GallusArsoma’ from Switzerland, which are
sophisticated printing machinery. In order to insure the
said machinery against any damage and loss, the
appellant had secured a ‘Standard Fire and Special Perils’
Policy from the respondent insurance company. The said
policy was for a total cover of Rs. 3,35,30,000/ (Rupees
Three Crores ThirtyFive Lakhs Thirty Thousand only)
and was valid for the period 15.05.2003 to 30.08.2004.
2.
When this was the position, as per the case of the
appellant, there was a fire mishap in the factory on
28.02.2004 at about 7.50 AM. The fire had damaged and
destroyed certain portions of the factory which included
the plant and machinery, building, raw material and
finished products. The appellant, therefore, invoked the
policy and filed a claim with the respondent insurance
company for a sum of Rs.3,02,75,000/ (Rupees Three
Crores Two Lakh SeventyFive Thousand only). The
appellant had also informed M/s Loss Prevention
2
Association of India Ltd. and requested them to
undertake an investigation.
3. As per procedure the insurance company
appointed a surveyor, M/s Prabha Associates, Mumbai
to assess the loss. The said surveyors were required to
submit a report in not more than six months as per the
regulations under the Insurance Regulatory and
Development Authority. The surveyor conducted the
inspection of the premises several times and, at the
instance of the surveyor, the appellant also called for an
Engineer from the manufacturers in Switzerland to
physically inspect the machine and to tender his opinion.
In this regard, the appellant had also to incur expenses
of about Rs.4,86,665/ (Rupees Four Lakh EightySix
Thousand Six Hundred SixtyFive only). The appellant
contends, though the surveyor admitted the loss to the
tune of Rs.1,81,35,810/ (Rupees One Crore EightyOne
Lakhs ThirtyFive Thousand Eight Hundred Ten only)
and the assessment of loss was enhanced further based
on the letter dated 13.09.2004 and 07.10.2004, on
3
submission of the report the respondents limited the
reimbursement to Rs.16,15,606/ (Rupees Sixteen Lakh
Fifteen Thousand Six Hundred and Six Only) by sending
a voucher dated 16.05.2005. The appellant declined to
accept the same and instead, filed a consumer complaint
before the National Consumer Disputes Redressal
Commission (for short, ‘NCDRC’) claiming a sum of
Rs.5,20,91,724/ (Rupees Five Crores Twenty Lakhs
NinetyOne Thousand Seven Hundred TwentyFour only)
including the amount of Rs.2,26,61,376/ (Rupees Two
Crores TwentySix Lakhs SixtyOne Thousand Three
Hundred SeventySix only) which was the amount
assessed as a loss by the surveyor and also the interest
payable to the various banks.
4. The respondents filed their written statement
disputing the claim put forth by the appellant. According
to the respondent, the amount of Rs.16,15,606/
(Rupees Sixteen Lakhs Fifteen Thousand Six Hundred
and Six only) offered by them was as assessed by the
surveyor, and as such the same would be the full and
4
final settlement of the claim by the appellant. It is alleged
by the respondent that the appellant had not cooperated
with the surveyors at the time of the assessment being
made by the surveyor. It is their case that in respect of
the imported machines, the local representative of the
manufacturers were unable to technically prove the
damage to the machinery since they had no technical
expertise or knowledge to attend to the same. The
engineer of M/s Gallus who visited from abroad declared
the machine to be a total loss based on the photographs
and had not stated categorically that the machine could
not be repaired. The respondents contended that the
Engineer could not explain as to how the damage had
occurred due to fire. In effect, the respondents had
disputed the reports tendered by the experts but had
sought to rely on the report of the surveyor appointed by
them and that of M/s. Material Technology Development
Centre (for short, ‘MTDC’). In that context, they sought to
justify the amount of Rs.16,19,209/ (Rupees Sixteen
Lakhs Nineteen Thousand Two Hundred and Nine only)
5
offered by them. Insofar as the claim and the assessment
of loss to the extent of Rs.2,26,61,376/ (Rupees Two
Crore TwentySix Lakhs SixtyOne Thousand Three
Hundred and SeventySix only) it was contended that it
is unsubstantiated.
5.
In the background of the contentions, the NCDRC
has taken into consideration the surveyor’s report and
based on the same has considered the aspect relating to
the heavy rusting of the machinery and concentrated on
as to whether the rusting within 4 to 5 hours is
technically feasible. In this regard, the NCDRC has
referred to the opinion in the website ‘Wikipedia’ with
regard to corrosion, as explained therein and has based
its decision on the same to arrive at the conclusion that
the rusting to the machinery had taken place over a
number of years and not due to one incident of fire and
the water sprayed for its extinguishment. In that view,
the NCDRC has not given credence to the contention of
the appellant that the surveyor had earlier assessed the
loss at Rs.2,26,61,376/ (Rupees Two Crores TwentySix
6
Lakhs SixtyOne Thousand Three Hundred SeventySix
only) but on the other hand accepted the contention of
the respondents that the appellant is entitled to the sum
of Rs.16,19,209/ (Rupees Sixteen Lakhs Nineteen
Thousand Two Hundred and Nine only) as offered by
them. The NCDRC, therefore, disposed of the complaint
through its order dated 24.02.2015 limiting the relief to
the said sum of Rs.16,19,209/ (Rupees Sixteen Lakhs
Nineteen Thousand Two Hundred and Nine only) with
interest at 12 per cent per annum. The appellant
therefore claiming to be aggrieved is before this Court in
this appeal.
6.
We have elaborately heard Mr. Arunabh
Chowdhury, learned senior advocate for the appellant
and Mr. S.L. Gupta, learned counsel for the respondent
and perused the appeal papers including the order dated
24.02.2015 passed by the NCDRC which is impugned
herein.
7. At the outset, it is necessary to note that insofar as
the respondent having issued the ‘Standard Fire and
7
Special Perils’ Policy which was valid for the period
15.05.2003 to 30.08.2004 covering the damages up to
Rs. 3,35,30,000/ (Rupees Three Crores ThirtyFive
Lakhs Thirty Thousand only) is the accepted position.
The fact that during the validity of the policy, a fire
accident had occurred on 28.02.2004 is also undisputed.
The fire being the cause for having resulted in certain
loss which is covered under the policy for reimbursement
also cannot be disputed. The very fact that the
respondents have quantified the loss and offered to pay
the sum of Rs.16,19,209/ (Rupees Sixteen Lakhs
Nineteen Thousand Two Hundred and Nine only) which
according to them was the loss/damage to the plant and
machinery and other articles would indicate that the
only issue which was to be determined by the NCDRC
and now by this Court is with regard to the extent of
damage caused and the amount of compensation
therefore, to be paid and reimbursed by the respondent
insurance company under the policy, within the amount
of coverage provided therein.
8
8. The report dated 28.03.2005 of M/s Prabha
Associates, the surveyor appointed by the respondent
insurance company shows that on the visit made on
28.02.2004, it records that the fire brigade vehicles had
arrived at 8.15 A.M. and had doused the fire using water
jets till 10.30 A.M. In this regard, it also records that
water was sprayed all over the place which caused
damage to the machineries, than the damage that was
caused by the fire itself. The observation recorded by the
surveyor is that the ‘Aquaflex’ printing press located
below the cables was found affected. Further the ‘Gallus’
Printing Machine, ‘Spengler’ machine and A.V. Flexo
plate counter were all water affected. It was also
observed in the report that the water marks were found
on all the machines and metal rollers on ‘Gallus’ and
‘Aquaflex’ machine which was rusted due to the water
being sprayed. In the report, it was also indicated that
the probable cause of fire is short circuit and it was
extinguished by the fire brigade by spraying water on all
the machines located in the premises. It is observed that,
9
when they visited the premises, all the iron parts were
rusted to varying degrees with regard to the ‘Gallus’
machine and that there was water on mechanical and
electric parts located on the operations side of the
machine. The rear side of the machine was found intact.
It was therefore concluded that the rusting was due to
the water being sprayed.
9. As regards ‘Aquaflex’ machine, it was indicated
that the machine was located very close to the source of
fire and it was found that the plastic knobs had partly
melted; the electrical wirings had burnt and the main
control panel was void of water marks. Pursuant to such
report there was an exchange of correspondence between
the appellant and the surveyor wherein further details
were furnished relating to effort made by the appellant
towards the restoration of the machinery and M/s
Graphic Technology Inc. having informed the appellant
through the communication dated 17.04.2004 that the
cost of repairing the machine will exceed the reasonable
limit and may not be able to guarantee optimum printing
10
quality in spite of repairs as the metal deformation on
the main frame cannot be reverted. The very opening of
the machine requiring additional parts was also
highlighted. It is in that background, having taken note
of this aspect of the matter the surveyor who had on
06.09.2004 made an assessment of Rs.1,81,35,810/
(Rupees One Crores EightyOne Lakhs ThirtyFive
Thousand Eight Hundred Ten only) and had sent for
acceptance of the insured, namely the appellant so as to
finalise the report, on further exchange of
correspondence, the assessment of damage was revised.
10.
The respondent, in that background, also sought
for a report from the Loss Prevention Association of India
Ltd., which on examination by visiting the site on
12.03.2004 along with the Divisional Manager and
Development Officer, apart from suggesting remedial
measures had noted with regard to considering the bill of
damage to the electric cables etc. It was noted that two
printing machines were found partly damaged due to
heat, smoke and fire fighting water. But, observation was
11
however made that heavy rusting was technically not
feasible within the time span of 4 to 5 hours under
conditions of fire and its extinguishment. The respondent
therefore taking into consideration the said reports had
limited the reimbursement to the extent as indicated
above.
11.
While taking note of this aspect, what is also to be
kept in view is the report submitted by M/s
Gallus/Heidelberg India Pvt. Ltd. pursuant to the visit
made on 29.02.2004 within a few hours of the fire
accident. The said report indicated that the machine was
total loss and not repairable with reasonable costs.
Subsequently the Engineer who flew from Switzerland
also visited the site on 05.10.2004. As per the report
dated 06.10.2004, the machine was extensively damaged
as a result of fire and could neither be switched on, nor
be overhauled/repaired at the site. He was also of the
opinion that the machine would have to be dismantled in
order to inspect the damage and if any replacement is
required it would be highly expensive. The said report
12
was no doubt available before the surveyor and surveyor
had raised certain queries with regard to the print
precision and as to why the repairs cannot be carried out
in India. M/s Heidelberg India Pvt. Ltd. submitted its
reply on 05.01.2005 indicating that the premises was
gutted by fire and the medium used to extinguish the fire
was water. As such heavy film of rust had formed over
the heated steel component like plate and impression
cylinders, activation mechanism, machine sliding
surfaces, bearings at various locations throughout the
length and breadth of the press. It was indicated in
technical terms with regard to the machine not being
rectifiable.
12. As noted earlier, the respondent had also secured
reports from MTDC subsequent to the report of M/s
Heidelberg. MTDC vide its report dated 06.01.2005
observed that heavy rusting is not technically feasible
within the time span of 4 to 5 hours under conditions of
fire and its extinguishment. It was indicated, technically
they could not confirm significant amount of rusting
13
within 4 to 5 hours because of fire and its
extinguishment as valid.
13. The appellant on the other hand sought the
assistance of Indian Institute of Technology, Powai to
secure a report in the background of the existing report
including that of MTDC. The IIT, Powai through its report
dated 12.08.2006 observed that the simulation of the
conditions to test the feasibility of rusting within 4 to 5
hours was not proper and cannot be considered as
reliable. The report of MTDC suggesting that rusting
existed prior to break out of fire was commented upon
and was indicated that it was misinterpretation on their
own observations. The Indian Institute of Technology
(IIT), Powai in their report had also indicated that the
seven conditions necessary for rusting and corrosion did
in fact exist. In that light, the report suggested that the
rusting and corrosion of machine occurred on account of
the fire accident. It was suggested that the surveyors
report is not scientific and that it is inconclusive.
14
14. Having noted the various reports that had been
secured at various stages, insofar as the fact that the
assessment by a surveyor is a requirement to arrive at a
conclusion to assess the loss is the accepted position.
However, as against the report of the surveyor appointed
by the insurance company if there is any other material
on record, the same cannot be ignored but is also
required to be noted for the purpose of settlement of
claim. In this regard, learned senior counsel for the
appellant has relied on the decision of this Court in
National Insurance Company Ltd. Vs. Hareshwar
Enterprises (P) Ltd. and Others (2021) SCC Online SC
| “12. | | In the said decision, it is no doubt held that | |
| though the assessment of loss by an approved | | | |
| surveyor is a prerequisite for payment or settlement | | | |
| of the claim, the surveyor report is not the last and | | | |
| final word. It is not that sacrosanct that it cannot be | | | |
| departed from and it is not conclusive. The approved | | | |
| surveyor's report may be the basis or foundation for | | | |
| settlement of a claim by the insurer in respect of loss | | | |
| suffered by insured but such report is neither | | | |
| binding upon the insurer nor insured. On the said | | | |
| proposition, we are certain that there can be no | | | |
| quarrel. The surveyor's report certainly can be taken | | | |
| note as a piece of evidence until more reliable | | | |
| evidence is brought on record to rebut the contents | | | |
| of the surveyor's report.” | | | |
15
15. In that background, in the instant facts where no
oral evidence has been tendered by the parties and
ultimately the consideration is based on the reports
which are available on record, the nature of the reports
and the manner in which the fire accident had occurred
and the situation leading to the claim is to be assessed
in an objective manner by the adjudicatory forum. In
order to buttress his contentions in this regard, the
learned senior counsel has referred to the decision in the
case of
New India Assurance Company Limited Vs.
Zuari Industries Limited and Others (2009) 9 SCC 70
wherein this Court having referred to the earlier decision
has arrived at the conclusion that the chain of events is
to be taken note while considering the claim for
damages. In this regard, it is stated therein as
hereunder:
| “14. | | Apparently there is no direct decision of this | |
|---|
| Court on this point as to the meaning of proximate | | | |
| cause, but there are decisions of foreign courts, and | | | |
| the predominant view appears to be that the | | | |
| proximate cause is not the cause which is nearest in | | | |
| time or place but the active and efficient cause that | | | |
| sets in motion a train or chain of events which brings | | | |
| about the ultimate result without the intervention of | | | |
| any other force working from an independent source. | | | |
16
| 16. | | Thus, in | | Lynn Gas and Electric Co. | | | | v. | | Meriden |
|---|
| Fire Insurance Co. | | | | | t | he Supreme Court of | | | | |
| Massachusetts was concerned with a case where a | | | | | | | | | | |
| fire occurred in the wire tower of the plaintiff's | | | | | | | | | | |
| building, through which the wires of electric lighting | | | | | | | | | | |
| were carried from the building. The fire was speedily | | | | | | | | | | |
| extinguished, without contact with other parts of the | | | | | | | | | | |
| building and contents, and with slight damage to the | | | | | | | | | | |
| tower or its contents. However, in a part of the | | | | | | | | | | |
| building remote from the fire and untouched thereby, | | | | | | | | | | |
| there occurred a disruption by centrifugal force of the | | | | | | | | | | |
| flywheel of the engine and their pulleys connected | | | | | | | | | | |
| therewith, and by this disruption the plaintiff's | | | | | | | | | | |
| building and machinery were damaged to a large | | | | | | | | | | |
| extent | | . | | | | | | | | |
| 17. | | It was held in | | Lynn Gas and Electric Co. | | | that |
|---|
| the proximate cause was not the cause nearest in | | | | | | | |
| time or place, and it may operate through successive | | | | | | | |
| instruments, as an article at the end of a chain may | | | | | | | |
| be moved by a force applied to the other end. The | | | | | | | |
| question always is: was there an unbroken | | | | | | | |
| connection between the wrongful act and the injury, | | | | | | | |
| a continuous operation? In other words, did the facts | | | | | | | |
| constitute a continuous succession of events, so | | | | | | | |
| linked together as to make a natural whole, or there | | | | | | | |
| was some new and independent cause intervening | | | | | | | |
| between the wrong and the injury? | | | | | | | |
| 22. | | In the present case, it is evident from the chain of | | | | |
|---|
| events that the fire was the efficient and active cause | | | | | | |
| of the damage. Had the fire not occurred, the damage | | | | | | |
| also would not have occurred and there was no | | | | | | |
| intervening agency which was an independent source | | | | | | |
| of the damage. Hence we cannot agree with the | | | | | | |
| conclusion of the surveyors that the fire was not the | | | | | | |
| cause of the damage to the machinery of the | | | | | | |
| claimant. Moreover, in | | | | | General Assurance Society | |
| Ltd. | | | v. | Chandmull Jain | it was observed by a | |
| Constitution Bench of this Court that in case of | | | | | | |
| ambiguity in a contract of insurance the ambiguity | | | | | | |
| should be resolved in favour of the claimant and | | | | | | |
| against the insurance company.” | | | | | | |
17
16. In the above backdrop, in the instant case we note
that the entire consideration made by the respondent
before admitting only a portion of the claim and the
ultimate consideration made by the NCDRC appears to
be on the narrow issue with regard to the corrosion of
the machinery and in that regard as to whether the
corrosion can happen within a short duration of 4 to 5
hours. In our opinion, such consideration in the instant
facts was misdirected and therefore resulted in the
wrong conclusion.
17. We note that in the case on hand, the policy in
question is a ‘Standard Fire and Special Perils’ Policy
which is available at Annexures P2 to P5. The policy
includes the coverage in respect of destruction or
damage due to fire, save the exceptions provided therein.
The fact that in the instant case the fire accident had
occurred during the subsistence of the policy and that
such accident was accidental and had caused damage to
the property of the appellants including to the machinery
in question is not in dispute. The photographs relating to
18
the machines along with report of the surveyor would
indicate that there is rusting on the machinery. The fact
that the said machinery is highly sophisticated imported
machinery for precision printing cannot be disputed. In
such situation, when, due to such accidental fire and to
extinguish such fire the assistance of the fire brigade
was called for and even as per the report of the surveyor
the fire brigade had sprayed water and such other fire
extinguishing material over the machinery which was
placed in the room which caught fire and the fire brigade
has made effort between 8.15 am to 10.30 am, the
damage to the machinery has occurred. From the report
of the experts it is indicated that the machinery was
beyond repair keeping in view the precision work to be
performed with the said machinery and there was no
guarantee that even if an attempt is made to repair the
same after opening the machine, it would give good
results.
18. Per contra the fact remains that the respondent
has not tendered any evidence to indicate that the same
19
machinery in fact is being used by the appellants
subsequent to the fire accident either in the same
manner in which it was being used prior to the fire
accident or being used after repairs. Further except for
the MTDC assuming that the corrosion has happened
over a period of time, all other reports suggest that the
corrosion has happened due to the spraying of water to
extinguish the fire. The fact that the appellant was a
going concern as on the date of the fire accident is not in
dispute. Further, the surveyors report in any event does
not suggest that the machineries were not in use as on
the relevant date. On the other hand, the appellants had
contended that the very same machines were being used
for printing the labels immediately prior to the fire
accident and there was no complaint with regard to the
quality of printed labels from its customers. The
respondents have not placed any contrary material to
controvert the said position. In such situation, we are of
the opinion that the emphasis in a fact of the present
nature to arrive at the conclusion as to whether the
20
corrosion could happen within a time period of 4 to 5
hours and in that regard, the NCDRC considering that
aspect based only on the definition of corrosion in
general terms is not justified.
19. In the overall assessment of the instant case, when
the accidental fire on 28.02.2004 is the accepted position
and in the very report of the surveyor dated 28.03.2005
recording the nature of the damage to the machinery is
also the accepted position, a narrow construction as
made by the NCDRC is unacceptable. On the other hand,
the chain of events will lead to the conclusion the fire
accident has caused the damage.
20. If that be the position, the issue would be with
regard to the extent to which the claim of the appellant is
required to be accepted and the respondent be directed
to reimburse the same. In this regard, though the claim
is made by the appellant for the sum of Rs.5,20,91,724/
(Rupees Five Crores Twenty Lakhs NinetyOne Thousand
Seven Hundred TwentyFour only), the learned senior
counsel for the appellant would indicate that the
21
appellant would presently limit the claim to
Rs.2,26,61,376/ (Rupees Two Crores TwentySix Lakhs
SixtyOne Thousand Three Hundred SeventySix only).
In that background, if the nature of assessment made by
the surveyor at the first instance is taken into
consideration, the amount indicated therein was in a
sum of Rs.1,81,35,810/ (Rupees One Crores EightyOne
Lakhs ThirtyFive Thousand Eight Hundred Ten only).
However on the exchange of correspondence between
surveyor and the appellant who brought on record
additional material before the surveyor to indicate that
the machinery cannot be repaired, the amount assessed
was Rs.2,32,02,000/ (Rupees Two Crores Thirty Two
Lakhs Two Thousand only).
21. Therefore, if all these aspects are taken into
consideration, the claim limited by the appellant at this
juncture is the actual loss suffered by the appellant. We
are therefore of the opinion that the appellant would be
entitled to the amount of Rs.2,26,61,376/ (Rupees Two
Crores TwentySix Lakhs SixtyOne Thousand Three
22
Hundred SeventySix only) minus the sum of
Rs.16,19,209/ (Rupees Sixteen Lakhs Nineteen
Thousand Two Hundred and Nine only) which was earlier
offered by the Insurance Company and was received
without prejudice during the pendency of the
proceedings, with interest if any that has been received.
The balance amount of Rs. 2,10,42,167/ (Rupees Two
Crores Ten Lakhs FortyTwo Thousand One Hundred
SixtySeven only) shall be payable by the respondent
with interest at 6 per cent per annum from the date of
the complaint filed before the NCDRC. The same shall be
paid within 8 weeks from the date of receipt of a copy of
this judgment.
22. The appeal is accordingly allowed in part.
23. Pending application, if any, stands disposed of.
…………….…………….J.
(A.S. BOPANNA)
….……………………….J.
(DIPANKAR DATTA)
New Delhi;
May 16, 2023
23