Full Judgment Text
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 04.12.2018
Date of Decision :28.02.2019
+ O.M.P. (COMM) 196/2018 & I.A. Nos.6150/2018, 9997-98/2018
NOBLE CHARTERING INC ..... Petitioner
Through: Mr.V.K. Ramabhadran, Sr. Adv.
with Mr.Jayesh Ashar, Mr.Bomi
Patel, Mr.Dhaval Mehrotra and
Mr.Sudhanshu Sikka, Advs.
versus
STEEL AUTHORITY OF INDIA LTD. ..... Respondent
Through: Mr.Sandeep Sethi, Sr. Adv. with
Mr.Santosh Kumar, Mr.Manav
Gill and Ms.Bhabna Das, Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
1. The present petition has been filed by the petitioner challenging the
Arbitral Award dated 27.12.2017 passed by the Sole Arbitrator in Case
No. 2 adjudicating the disputes that had arisen between the parties in
relation to the Contract of Affreightment dated 27.07.2010 executed
between the parties.
2. The Sole Arbitrator by way of the Impugned Award, while
rejecting the claims filed by the petitioner, has allowed the Counter
Claim of the respondent for a sum of USD 862,500.00 with interest at the
rate of 3% from the date of the payment of the freight by the respondent
for the two shipments where the petitioner was found in default and till
the date of the Award. The Sole Arbitrator has further directed that incase
the petitioner fails to make the payment of the awarded amount within a
O.M.P. (COMM) No. 196/2018 Page 1
period of three months from the date of the Award, the petitioner shall
pay interest at the rate of 9% per annum on the amount awarded together
with interest.
3. As stated above, the disputes between the parties arose in relation
to the Contract for Affreightment dated 27.07.2010 (hereinafter referred
to as the „COA‟). In terms of Clause 1(a) of the COA, the respondent, as
charterers, had agreed to ship 10,00,000 MT 5% more or less at
Charterers‟ option of coking coal. The shipment period was agreed as
two years from October, 2010 to September 2012, extendable by three
months at charterer‟s option which was to be declared latest by
30.06.2012. The shipment was to be evenly spread throughout the period
on pro-rata basis.
4. The respondent had declared a total of fourteen Stems / shipments
to the petitioner, the details whereof are mentioned hereinbelow:-
| SI. | Vessel Name / Not<br>nominated by<br>Noble | Laydays | Quantity<br>Declared | Sailing<br>Date |
|---|---|---|---|---|
| 1. | AVOCA Substitute<br>/ OF MILAGRO | 20-30 Oct<br>2010 | 75,000 MT | 26 Oct 2010 |
| 2. | MAHATIS S/O<br>AOM MILENA | 20-30 Dec<br>2010 | 75,000 MT | 31 Dec<br>2010 |
| 3. | S NICOLE S/O | 18-28 Feb | 75,000 MT | 16 Feb |
O.M.P. (COMM) No. 196/2018 Page 2
| GH FORTUNE | 2011 | 2011 | ||
|---|---|---|---|---|
| 4. | MEDI SENTOSA<br>S/O BELMONTE | 10-20 April<br>2011 | 75,000 MT | 17 Apr 2011 |
| 5. | AMALIA S/O<br>BELMONTE | 10-20 June<br>2011 | 75,000 MT | 08 Jul 2011 |
| 6. | KM HONG KONG<br>S/O HONG DIA | 20-30 Oct<br>2011 | 75,000 MT | 24 Oct 2011 |
| 7. | Not Nominate by<br>Claimant | 10-20 Nov<br>2011 | 75,000 MT | No sailing |
| 8. | Not Nominated by<br>Claimant | 5-14 Dec<br>2011 | 75,000 MT | No sailing |
| 9. | Not Nominated by<br>Claimant | 1-10 Feb<br>2012 | 75,000 MT | No sailing |
| 10. | Not Nominated by<br>Claimant | 1-10 Mar<br>2012 | 75,000 MT | No sailing |
| 11. | DIAMANTINA | 30-9 May<br>2012 | 75,000 MT | 2 May 2012 |
| 12. | KEA S/O<br>PINNACLE BLISS | 15-25 June<br>2012 | 75,000 MT | 24 Jun 2012 |
| 13. | BELLEMAR S/O<br>HONG SHENG | 15-25 July<br>2012 | 75,000 MT | 29 Jul 2012 |
O.M.P. (COMM) No. 196/2018 Page 3
| 14. | NAVIOS MARCO<br>POLO S/O KEA | 10-20 Sep<br>2012 | 75,000 MT | 20 Sep 2012 |
|---|
5. The above table would show that six Stems had been declared by
the respondent between the periods October 2010 to October 2011. There
is no dispute between the parties in relation thereto. Between the periods
November, 2011 to March, 2012 the respondent declared another four
Stems, however, the same were not performed by the petitioner. From
May, 2012 to September, 2012 the respondent declared another four
Stems that were also duly performed by the petitioner.
6. By the e-mail dated 25.09.2012, the respondent sought to terminate
the COA relying upon the “Default Clause”, that is, Clause 62 of the
COA. This e-mail is of some relevance to the disputes raised between the
parties and is therefore reproduced hereinbelow:-
“From: Jasmina SAIL
Sent: Tuesday, September 25, 2012 5:31 PM
To: Sh. T.R Krishnan
Cc: CCC Transchart; col@hub.nic.in; MANAS; PRC SAIL
Subject: Noble - SAIL COA dtd. 27/7/2010
To Transchart
Subject: Agreement dated 27.7.2010 (Contract of
Affreightment) (COA) for transportation/shipping of Imported
Coal from USA during October 2010 to September, 2012
through TRANSCHART.
Please refer to the Subject COA and various correspondence
and discussions with regard to the continuation or to deal
O.M.P. (COMM) No. 196/2018 Page 4
otherwise with the said COA and declaration of stems there
under.
Reference may be made to different events and circumstances
adversely affecting the subject agreement which does –not need
any further elaboration.
The M/S Noble Chartering Inc. vide their correspondence and
actions defaulted in performing their obligations under the
subject agreement stated imposing extraneous demands and
conditions which were all beyond the scope of the subject
agreement. SAIL in the compelling circumstances of
transporting the material from the Load Port and avoid delays
therein accommodated the unreasonable demands on a few..
asions but the said firm tried to impose unreasonable and
impracticable conditions which all were beyond the subject.
Notwithstanding the above facts, the subject agreement
continued to be honoured on account of SAILS positive
approach of cooperation. However, as it may not be out of
place to mention, during the performance under the above COA
on various occasions, the provisions of the COA, were
breached, which inter-alia include substitution of vessels,
refusal to give nomination of vessels etc. All these caused
substantial harassment and problems to SAIL besides losses
which it had to suffer.
Going by the above facts, it leaves no doubt about the positive
intentions of the SAIL as charterer which led to continuation of
the COA under the aegis of TRANSCHART, in spite of hostile
conditions and attitude on Owners part.
Finally therefore please be informed that, SAIL is left with no
option but to state that the subject agreement yd terminated
under the 'Default Clause' and the subject COA stood
terminated.
Therefore there is no alternative but to treat the contract as
rescinded. However, reserving our right to claim compensation
/ damages caused for the breach committed by Owners.
O.M.P. (COMM) No. 196/2018 Page 5
For Steel Authority of India Ltd.
(Jasmina Maiti
Copy to M/S
Noble through
their brokers for
information.”
7. The petitioner, by its e-mail dated 28.09.2012 disputed that the
petitioner was in breach of the COA, while also claiming that various
general allegations of breach had been made in the said e-mail against the
petitioner without giving full details thereof. The contents of the e-mail
are relevant and are reproduced hereinbelow:-
“We refer to your e-mail of 25th September, 5:31 p.m.
regarding the COA dated 27th July 2010.
In your e-mail, you have made various general allegations
against Noble Chartering Inc. in respect of their Conformance
under the COA. You have alleged that Noble are in breach of
their obligations under the COA and as a result of these alleged
breaches, you are purporting to terminate the COA.
Noble do not accept that they have acted in breach of the above
COA at any time, and the allegations made by SAIL in their e-
mail of 25th September are denied in the strongest terms. Noble
call on SAIL to provide gull details of the alleged breaches by
Noble under the COA.
It is Noble's position that it is SAIL who are in breach of their
obligations under the COA in that SAIL have failed to declare
three outstanding stems which would ensure that the
contractual quantity under the COA was performed.
Noble are not prepared to accept any purported termination of
the COA by SAIL. Noble insist that SAIL perform their
obligations under the COA by nominating the outstanding three
O.M.P. (COMM) No. 196/2018 Page 6
stems so that the COA can be fully performed. Noble require
SAIL to respond by return.
It is clear to Noble that the only reason that SAIL have failed to
perform the remaining stems under the COA is because the
charter market has fallen and, in breach of their contractual
obligations, SAIL have chosen to charter in alternative cheaper
tonnage to meet their requirements rather than comply with
their COA obligations.
Noble wish to make it clear that, if SAIL do not comply with
their contractual obligations under the COA and if SAIL do not
respond constructively to this message, Noble will be entitled to
treat SAIL as being in repudiatory breach of the COA in which
event, Noble will accept SAIL's repudiatory breach and claim
damages in accordance with the terms of the COA. The amount
of such claim would clearly be substantial, and Noble will also
seek a full recovery in respect of interest and legal costs. Aside
from commencing arbitration as per COA, Noble will also take
appropriate legal action against SAIL's assets in order to
obtain security.
Noble look forward to receiving SAIL's prompt response.
Meantime all Noble's rights are fully reserved.”
8. The respondent did not respond to the above e-mail.
9. The petitioner, through their solicitors addressed further e-mails
dated 26.10.2012, 13.11.2012 and 07.12.2012 calling upon the
respondent to withdraw the termination notice. Again there was no
response from the respondent.
10. Finally, by the e-mail/fax dated 12.12.2012 the petitioner
terminated the COA contending as under:-
“We refer to our fax/email to you, the Steel Authority of India
Ltd ("SAIL"), of 7 December 2012, calling on you to withdraw
your wrongful termination of the COA dated 27 July 2010 (the
O.M.P. (COMM) No. 196/2018 Page 7
"CON'), and to confirm that you would comply with your
obligations under the COA by 5.00pm Indian time on Tuesday
11 December 2012. You have failed to respond, whether to us
or to our clients.
To recap, on 25 September 2012 you wrote to our clients, Noble
Chartering Inc ("Noble"), purporting to terminate the COA on
the grounds that Noble were in breach of the COA. You did not
specify with any particularity how Noble were said to be in
breach of the COA and such allegations as were made were so
vague as to disclose no identifiable allegation of breach. There
was in fact no basis for asserting that Noble were in breach of
the COA and Noble deny that they were in any way in breach.
The reason relied on by you for terminating the COA was
therefore without substance, and the purported termination on
the basis of that incorrect assertion was therefore wrongful.
Noble responded to your purported notice of termination on 28
September 2012, and we have written to you on Noble's behalf
on three further occasions: 26 October 2012, 13 November
2012 and 7 December 2012. In each of these messages, it has
been explained to you that your purported termination was
wrongful and you have been invited to perform the COA. You
have therefore been provided with ample opportunity to
withdraw your wrongful termination.
You have failed to respond to any of those messages and have
failed to take any steps towards performance of the COA.
Your wrongful termination of the COA, your failure to take any
steps towards performance of the COA despite demands that
you comply with your obligations, and your conduct since you
sent your message of 25 September 2012, each separately and
cumulatively constitutes a repudiatory breach/renunciation of
the COA. Noble hereby accepts your repudiation/renunciation
of the COA, bringing the COA to an end.
As a result of Noble's termination of the COA, you are liable to
Noble for any and all losses they have suffered as a result of
your repudiation/renunciation. Details of these losses will be
O.M.P. (COMM) No. 196/2018 Page 8
provided to you shortly along with a demand for payment of the
sums due. If you fail to pay following this demand, Noble will
commence arbitration to recover the sums due to them without
delay, and reserve the right to take all/any steps necessary in
any appropriate jurisdiction to secure and/or recover the sums
due, including interest and legal costs, without further notice.”
11. The petitioner thereafter invoked Arbitration Agreement claiming
damages from the respondent based on the alleged outstanding balance
cargo of 238,803 MT under the COA alleging that the termination of the
Agreement by the respondent vide its e-mail dated 25.09.2012 was
illegal.
12. The respondent, on the other hand, while refuting the claim of the
petitioner, raised a Counter Claim alleging that the petitioner was in
default of performing four Stems between the period November, 2011 to
March, 2012; out of which it was liable to pay damages for Stems
declared with laycan of 10-20 November, 2011 and 5-14 December 2011,
as spot rates for these stems were more than the COA rates.
13. The Arbitral Tribunal by its Impugned Award has rejected the
submission of the respondent that the COA was not a binding Agreement
between the parties. The Sole Arbitrator has further held that the
respondent was not entitled to terminate the Agreement under Clause 62
of the COA, however, at the same time has held that the termination of
the Agreement by the respondent was valid inasmuch as the petitioner
was in default of performance of four Stems declared by the respondent
and thereby committed repudiatory breach of the Agreement. The Sole
Arbitrator, therefore, awarded damages in favour of the respondent and
against the petitioner for the two laycans mentioned hereinabove.
O.M.P. (COMM) No. 196/2018 Page 9
14. The Arbitrator also rejected the claim of the petitioner that the
period of the Agreement, based on an oral understanding between the
parties and as recorded by the petitioner in its e-mail dated 05.01.2012,
had been extended till September, 2013. The Arbitrator further held that
the Stems were not declared by the respondent on a „Fairly Evenly
Spread‟ basis but at the same time, the petitioner having accepted those
Stems, cannot make a grievance of respondent‟s declaration of Stems.
15. As noted above, the Sole Arbitrator has held that the respondent
was not entitled to terminate the Agreement under Clause 62 of the COA.
In reaching this conclusion, the Sole Arbitrator has held that if Clause 62
is to be read as providing for termination for convenience or without
cause, the same would be vulnerable to being declared void under
Section 23, 28 and 73 of the Indian Contract Act, 1872. The Arbitrator,
thereafter, held that Clause 62 is intended to enable the respondent to
declare the contract to be at an end when it is helpless in performing the
contract.
16. Though the respondent has not challenged the above finding, I
must note that by a separate order passed today in OMP(COMM)
225/2018 Steel Authority of India Ltd. v. Nobel Chartering Inc ., I have
held that the above finding of the Arbitrator in relation to another
similarly worded clause in another Contract between the same parties,
cannot be sustained and is liable to be set aside.
17. The Arbitrator has thereafter considered whether the petitioner was
in breach of the Agreement in refusing to nominate vessel(s) in respect of
four stems declared by the respondent between November, 2011 to
O.M.P. (COMM) No. 196/2018 Page 10
March, 2012 and if so, to what effect. The Arbitrator has answered this
issue in the affirmative and against the petitioner.
18. The Arbitrator has held that the real reason for the petitioner for
not accepting the four stems was because the petitioner wanted to compel
and coerce the respondent to provide shipment under the COA dated
20.08.2008. In reaching the said conclusion, the Arbitrator has placed
reliance on the answers given by Mr.Jagmeet Makkar (CW-1) in his
cross-examination as also certain e-mails exchanged between the parties.
19. The learned senior counsel for the petitioner has challenged the
above finding by placing reliance on the e-mail dated 05.10.2011 by
which the respondent declared the stems with laycan 10-20 November,
2011. The petitioner by its reply dated 07.10.2011 had called upon the
respondent to adhere to the “Fairly Evenly Spread” principle while
declaring the laycan under the COA. The respondent by its e-mail dated
01.11.2011 declared the stems afresh with laycan 05-14 December, 2011.
The same was duly accepted by the petitioner by its return mail dated
01.11.2011. The learned senior counsel for the petitioner submits that,
therefore, the petitioner could not have been held to be in default in
relation to this particular Stem. The above submission of the petitioner is
also relevant as the Arbitrator has also awarded damages for the said
stems in favour of the respondent.
20. The learned senior counsel for the petitioner further submits that
the plea of the petitioner that the respondent must also declare Stems
under the COA dated 20.08.2008 had been found to be genuine by the
respondent and, infact, the parties entered into an Addendum laying
down schedule for the further declaration of Stems under the COA(s).
O.M.P. (COMM) No. 196/2018 Page 11
Therefore, the petitioner has been wrongly held by the Arbitrator to be in
breach of COA dated 27.07.2010.
21. The learned senior counsel for the respondent, on the other hand
submits that the Arbitrator has rightly concluded that the real reason for
the petitioner not nominating the vessels was its insistence that the
respondent should declare the stems under COA dated 20.08.2008. This
being a finding on fact, cannot be interfered with by this Court in
exercise of its power under Section 34 of the Act.
22. While I appreciate the limitation on the power of this Court under
Section 34 of the Act, at the same time a reading of the e-mail dated
01.11.2011 addressed by the respondent to the petitioner would show that
the respondent agreed to the refusal of the petitioner to nominate a vessel
for the laycan 10-20 November, 2011 on the ground of the same not
being in accordance with the principle of Fairly Evenly Spread. I may
only quote the said e-mail as under:
“From: aco2
To: westward@vsnl.com
Cc: S Chandrasekaran ; V K Sharma
Sent: Tuesday, November 01, 2011 4:32 PM
Subject: RE: NOBLE/SAIL COA DTD 27.07.10 – EX-USEC
CHOPTION US GULF – RQST FOR NOMINATION
To M/S WESTWARD – MR SURENDER VERMA
FM TR KRISHNAN TRANSCHART NEW DELHI
RE: NOBLE/SAIL COA DTD 27.07.210 – EX-USEC
CHOPTION US GULF
REF ABV COA. THIS CONNECTION REF OWNRS LAST MSG
WHEN THEY EXPRESSED THEIR INABILITY TO
NOMINATE A VSL IN NOV’11 ANGAINST THE DECLARED
STEM 10-2011.2011 AS ACCORDING TO THEM, IT IS DUE
O.M.P. (COMM) No. 196/2018 Page 12
ONLY DURING DEC’11. ACCORDINGLY RQST TAKE UP
WITH OWNERS TO NOMINATE A SUITABLE P’MAX VSL
FOR A QTY OF 75 TMT 5% MOLOO 5LK C. COAL IN
TH
LAYCAN 05-14 DEC., 2011 EX-NEWPORT NEWS (DTA
ST
COAL TRMNL) LATEST BY COB 1 HRS ON 03.11.11. PLS
INTIMATE OWNERS TO ENSURE THE NOMINATION IS
MADE IN THE ABV ORIGINAL CONRIMED STEM LAYCAN
ONLY AND NOT IN DEFERRED LAYCAN AND ALSO TO
AVOID FREQUENT CHANGE OF PERFORMING VSL.
MATTER MOST URGENT. RGDS
TRANSCHART
T.R. KRISHNAN”
(Emphasis Supplied)
23. The respondent, therefore having accepted the contention of the
petitioner that the stem with laycan 10-20 November, 2011 was not in
conformity with the “Fairly Evenly Spread” principle and having
declared a fresh laycan of 5-14 December, 2011, cannot thereafter be
heard to claim that the petitioner had committed a default/breach of the
COA by not nominating the vessel for laycan 10-20 November, 2011.
The Arbitrator in the Impugned Award has not considered the above e-
mail.
24. In Associate Builders v. DDA , (2015) 3 SCC 49, the Supreme
Court while cautioning the Courts exercising powers under Section 34 of
the Act, has held as under:
“ 29. It is clear that the juristic principle of a “judicial
approach” demands that a decision be fair, reasonable and
objective. On the obverse side, anything arbitrary and
whimsical would obviously not be a determination which would
either be fair, reasonable or objective.
xxxxx
O.M.P. (COMM) No. 196/2018 Page 13
| 31. The third juristic principle is that a decision which is<br>perverse or so irrational that no reasonable person would have<br>arrived at the same is important and requires some degree of<br>explanation. It is settled law that where:<br>(i) a finding is based on no evidence, or<br>(ii) an Arbitral Tribunal takes into account something<br>irrelevant to the decision which it arrives at; or<br>(iii) ignores vital evidence in arriving at its decision, such<br>decision would necessarily be perverse. | 31. The third juristic principle is that a decision which is | ||
|---|---|---|---|
| perverse or so irrational that no reasonable person would have | |||
| arrived at the same is important and requires some degree of | |||
| explanation. It is settled law that where: | |||
| (i) a finding is based on no evidence, or | |||
| (ii) an Arbitral Tribunal takes into account something | |||
| irrelevant to the decision which it arrives at; or | |||
| (iii) ignores vital evidence in arriving at its decision, such | |||
| decision would necessarily be perverse. | |||
| xxxxxx | |||
| 34. It is with this very important caveat that the two | |||
| fundamental principles which form part of the fundamental | |||
| policy of Indian law (that the arbitrator must have a judicial | |||
| approach and that he must not act perversely) are to be | |||
| understood.” |
25. The above finding, however, may not have been sufficient to set
aside the Award that has held that the petitioner was in breach of the
COA by not nominating vessels for another three stems, but for other
peculiar factors in the case.
26. While no quarrel can be found to the finding of the Sole Arbitrator
that the COA(s) dated 20.08.2008 and 27.07.2010 cannot be confused or
interlinked with each other and merely because the respondent is
allegedly in breach of COA dated 20.08.2008, it would not be justified
for the petitioner to deliberately act in breach of COA dated 27.07.2010,
at the same time, in my view, such breach by the petitioner cannot justify
the termination of the Agreement by the respondent.
27. As noted above, the petitioner has been held in breach of the
Agreement for refusing to nominate vessel(s) in respect of four stems
O.M.P. (COMM) No. 196/2018 Page 14
declared by the respondent between November 2011 to March 2012.
Admittedly, after these four stems, the respondent declared another four
stems in April-May, 2012, June, 2012, July, 2012 and September, 2012.
If the petitioner was already in breach of the Agreement, which the
respondent thought would entitle the respondent to terminate the
Agreement, it was for the respondent to show why it continued with the
Agreement and declared these four stems after the alleged breach of the
Agreement by the petitioner, especially when there is no allegation of
breach in relation to these subsequently declared stems.
28. Further, Clause 1(d) of the COA provides for the consequence of
the petitioner‟s failure to nominate a vessel in the required laydays.
Clause 1(d) of the COA is reproduced hereinunder:
“ 1. CARGO/QUANTITY:
xxxxxx
(d) COA shall be quantity based and Owners to complete their
quantity within the shipment, period as per stems declared by
charterers. In case owners are unable to nominate vessel in the
required laydays the quantity may be covered by charterers on
spot loss and the difference in it, if any, including any other
cost/consequences shall be to the account of Owners.”
29. The respondent neither gave a notice claiming such damages from
the petitioner nor terminated the Agreement relying upon the
abovementioned alleged breach of the COA by the petitioner, instead, the
respondent declared four further stems after the date of the alleged
breach. The Arbitrator in his Impugned Award has failed to consider this
conduct of the respondent.
O.M.P. (COMM) No. 196/2018 Page 15
30. On the other hand, the Arbitrator has held that even Clause 1(d) of
COA would not apply to the facts of the case as there was a deliberate
refusal by the petitioner to perform the Agreement with the petitioner
demanding that the respondent must declare stems under the COA dated
20.08.2008.
31. Though, it may be correct that in case of repeated breach by the
contracting party, the innocent party may not only claim damages for the
said breach, but may also terminate the Agreement, at the same time, in
the facts of the present case, the respondent had clearly not exercised this
right. On the other hand, the fact of declaring four further stems,
subsequent to the breach, would show that the respondent had signified
its acquiescence in the continuation of the Agreement.
32. In any case, the effect of declaration of the four subsequent stems
was a relevant factor to be considered by the Arbitrator and the Arbitrator
having not considered the same, the Award cannot be sustained.
33. It is further important to note that while the petitioner was claiming
that the respondent should declare stems under the COA dated
20.08.2008, the petitioner by its e-mail dated 05.01.2012 had also
asserted that the parties had entered into an addendum whereby not only
the period of the COA(s) had been extended till 30.09.2013 but also the
manner of declaration of further stems had been agreed to between the
parties. Though, the Arbitrator has held that the parties did not proceed
on the basis of said addendum, the correspondence in this regard would
show that the respondent was, in fact, favourably considering the plea of
the petitioner that the declaration of further stems should be made
keeping in mind the COA dated 20.08.2008 as well. This is evident from
O.M.P. (COMM) No. 196/2018 Page 16
email dated 12.01.2012 addressed by Mr. P Ray Chaudhury of the
respondent to the petitioner, which has been quoted by the Arbitrator as
under:
“The proposal for extension of the COAs is being processed for
seeking internal approvals in line with the discussions held with
Noble. This may take some more time and we seek owners
understanding in the matter”.
34. Though, no fault can be found with the finding of the Arbitrator
that merely because of exchange of email dated 05.01.2012, a binding
addendum between the parties cannot be said to have come into existence
and, in fact, the parties continued to perform their respective obligations
thereafter based on the original COA(s), at the same time, the above
exchange of emails would also show that the respondent did not
terminate the Agreement due to breach of the petitioner in nominating
vessels for the four stems between the period November, 2011 to March,
2012. This again is a vital piece of evidence, which the Arbitrator failed
to appreciate.
35. I may here note that though the learned senior counsel for the
petitioner has vehemently argued that an addendum as recorded in the
email dated 05.01.2012 addressed by the petitioner to the respondent was
in fact arrived at between the parties, I am unable to agree with the said
submission.
36. The e-mail dated 05.01.2012 addressed by Mr.Jagmeet Makkar to
Mr. P Ray Chaudhury of the respondent itself seeks a confirmation from
the respondent to the alleged agreed terms. The relevant extract from the
e-mail is as under:
O.M.P. (COMM) No. 196/2018 Page 17
nd
“We refer to our pleasant meeting on 22 December in your
office in Kolkata followed by further discussions between SAIL
th
and us in Delhi on the 29 December. In view of our long term
association and good cooperation between the Steel Authority
of India and Noble Chartering, we have agreed to your request
for an extension to the duration of the COAs in line with our
discussions. We are pleased to recapitulate the agreement in the
form of an addendum, as follows, for your confirmation.”
(emphasis supplied)
37. Mr. P Ray Chaudhury in his e-mail dated 12.01.2012 as
reproduced hereinabove, had clearly stated that the addendum as alleged
by the petitioner was merely a proposal which required internal
approvals. The Arbitrator has also relied upon other contemporaneous
correspondence exchanged between the parties and also answers given by
Mr. Makkar during his cross examination to conclude that no binding
addendum came into existence by the above exchange of e-mails. I do
not find any reason to disagree with the said finding.
38. Returning to the question of termination of the Agreement, the e-
mail dated 25.09.2012 by which the respondent sought to terminate the
Agreement, has been reproduced hereinabove. A reading of the e-mail
would show that while the respondent has alleged breach of the COA by
the petitioner, it sought to terminate the Agreement by relying upon the
“Default Clause”, that is, Clause 62 of the Agreement which reads as
under:
“62. Default
Should Suppliers/Charterers fail to provide materials for
shipment or to ship the materials by the time or times agreed
upon or should Suppliers/Charterers in any manner or
otherwise, fail to perform the contract or should a Receiver be
appointed on its assets or make or enter into any arrangements
O.M.P. (COMM) No. 196/2018 Page 18
or composition with creditors or suspend payments (or being a
company should enter into liquidation either compulsory or
voluntary), the Suppliers/Charterers shall be entitled to declare
the contract as at an end without any liabilities on either side.”
39. The petitioner by its e-mail dated 28.09.2012 not only denied and
disputed that they were in breach of the COA, but also called upon the
respondent to give particulars of such breach. The respondent, however,
chose not to respond to the e-mail.
40. The petitioner again, through their solicitor addressed e-mails
dated 26.10.2012, 13.11.2012 and 07.12.2012, reiterating petitioner‟s
contention and called upon the respondent to withdraw the termination
notice. These e-mails were necessary to be considered by the Arbitrator
as the respondent never responded to the said emails or even alleged that
it had terminated the Agreement because the petitioner had failed to
perform the four stems mentioned hereinabove. The Arbitrator failed to
consider the said e-mails and upheld the termination of the COA by the
respondent by holding as under:
“161. The aforesaid answers given by Mr. Jagmeet Makkar
(CW1) and the emails noted above, leave no manner of doubt
that the Claimant deliberately failed to provide the vessels for
the stems to be declared by the Respondent. This clearly left the
Respondent in a helpless situation. Therefore, in my opinion,
the Respondent was fully justified in terminating the COA
through email dated 25.09.2012. It is true that under Clause 1
(d) the Respondent would be entitled to cover the laydays by
chartering the vessels in the Spot Market and the difference in
freight, if any, including any other cost/consequences shall be
to the account of Owners. However, the aforesaid Clause would
apply in cases where the Owner is unable to nominate the
vessel for bonafide reasons and not in a case of deliberate
refusal. The circumstances in which the Claimant has refused to
O.M.P. (COMM) No. 196/2018 Page 19
nominate the vessels would clearly constitute deliberate breach
of the COA. Therefore Issue No. 7 is answered accordingly.
162. Whilst it is true that Claimant and the Respondent have
entered into numerous contracts for transport of Coal from
different countries to India, the COA no. 1 dated 20.08.2008
and COA no. 2 dated 27.07.2010 cannot be confused or
interlinked with each other. Merely, because the Respondent is
allegedly in breach of COA no. 1 dated 28.08.2008, it would not
justify the Claimant to deliberately act in breach of COA no. 2
dated 27.07.2010. It must be remembered that rights and
responsibilities of both the parties under both the contracts are
not co-extensive. The Claimant cannot be permitted to claim a
breach by the Respondent whilst justifying the same breach
committed by itself. I therefore have no hesitation in concluding
that the termination of the COA by the Respondent by the email
dated 25.09.2012 is legal and valid, and the Claimant was not
justified in refusing to nominate a vessel in respect of 4 stems
declared by the Respondent between November, 2010 to March,
2012. Issue no.8 is decided accordingly.
163. In view of my observations and conclusion on Issue No.7 it
follows that the repudiatory breach communicated by the
Claimant to the Respondent is ineffective, having no legal
consequences. Issue no.9 is decided accordingly."
41. The Arbitrator in reaching the above conclusion has failed to
consider a vital piece of evidence in form of conduct of the parties,
especially of the respondent, thereby rendering the Award liable to be set
aside on this ground alone.
42. The Arbitrator having held that the Agreement was validly
terminated by the respondent, has further awarded damages in favour of
the respondent for the failure of the petitioner to nominate vessels for the
two laycans, that is, the laycan of 10-20 November, 2011 and 5-14
December, 2011. As discussed hereinabove, the laycan of 10-20
O.M.P. (COMM) No. 196/2018 Page 20
November, 2011 had been shifted to 5-14 December, 2011 and therefore,
it could not be said that the petitioner was in breach of the COA in not
nominating a vessel for this laycan.
43. The learned senior counsel for the petitioner has submitted that
though the respondent had produced two Agreements dated 20.10.2011
and 14.11.2011 executed by the respondent with a third party in support
of its claim of damages, the same could not have been relied upon as the
freight mentioned therein was subject to be reduced by a certain amount
depending upon the load rate. Even the quantity to be shipped could be
reduced at Owner‟s option by 5%. He submits that in absence of the Bill
of Lading and the proof of actual payment being made by the respondent,
such claim could not have been granted in favour of the respondent.
44. On the other hand, the learned senior counsel for the respondent
submits that the petitioner had taken no such plea in its defence to the
Counter Claim. In the reply filed to the Counter Claim before the
Arbitrator, the only plea taken by the petitioner was in the following
words:-
“(3) Further and in any event, it is denied that the Respondent
has correctly quantified its loss. In particular:
(i) It is denied that the spot market freight rate (net of
commission) was US$44 or US$41.5 per mt as alleged.
The Respondent is put to proof as to the correct market
freight rate.
(ii) It is denied that the Claimant would have lifted
75,000 mt of cargo as alleged. Given the market
conditions prevailing at the dates of the alleged breaches,
the Claimant would have exercised its option to lift 95%
O.M.P. (COMM) No. 196/2018 Page 21
of 75,000 mt, i.e. 71,250 mt. The Respondent's damages
should be calculated accordingly.”
45. The Arbitrator has discussed the quantification of such damages
and has held as under:
“171. In view of the provisions contained in Clause 1 (d) of the
Case 2 Agreement, on the deliberate refusal of the Claimant to
nominate the vessels for the stems declared, the Respondent is
entitled to charter the vessels on spot basis. The Respondent
would therefore, be entitled to recover the difference in freight,
if any, including any other cost/ consequences from the owners.
In view of the aforesaid clear provision, it would not be
necessary for the Respondent to establish its entitlement to the
damages caused by the refusal of the Claimant to nominate the
vessels. It is a matter of record that Claimant refused to
th
nominate the vessels in respect of the stems declared on 5
st
October, 2011 and 1 November, 2011. The Respondent,
therefore, had to make alternative arrangements for
transporting the shipments from Australia to India, at a rate
higher than the rate agreed in the Case 2 Agreement. The
details of the expenses incurred by the Respondents are as
under:
"(a) USD 525,000 towards the shipment of 75,00 MT
through spot market @ USD 44 per MT as against the
agreement rate of USD 37 per MT (75,00 MT X USD 7)
on the refusal by the Claimant to nominate the shipment
th
for the laycan 10-20 November, 2011 with interest of
7% p.a. from the date of payment of the freight by SAIL
until payment by Claimant.
(b) USD 337,500 towards the shipment of 75,000 MT
through spot market @ USD 41.5 per MT as against the
agreement rate of USD 37 per MT (75,000 MT X USD
4.5) on the refusal by the Claimant to nominate the
th
shipment for the laycan 5-14 December, 2011 with
interest @ 7% p.a. from the date of payment of freight by
SAIL until payment by Claimant."
O.M.P. (COMM) No. 196/2018 Page 22
172. As regard, the rate at which the Respondent had shipped
the cargo, the rate of 44/ MT and 41.5/ MT is evident from the
contracts executed with the Owners, which were produced with
the evidence of Ms. Jasmina Maiti as Ex. RW-1 and Ex. RW-2.
It is therefore not possible to accept the submission of the
Claimant that the Respondent has not proved the freight rate.
xxxxxx
175. I am also not able to accept the submission of the Claimant
that the Respondent has not proved the quantum of its Counter-
Claim. Ms. Jasmina Maiti in cross-examination has clarified all
the questions raised by the Claimant with regard to the
quantum of Counter-Claim; with respect to non-raising of the
Counter-Claim earlier, proof of payment, the variation on
account of quantity, port of discharge, commission etc. She has
clearly stated that the calculations have been made on the base
rate basis. Therefore I am of the opinion that factors such as the
port of discharge, commissions etc. would have no impact on
the Counter-Claim (see answers to questions 367, 368, 371).
176. With regard to proof of payment it is to be noted that in the
Reply to the Counter-Claim, the Claimant had not disputed the
same. However, Ms. Jasmina Maiti was exhaustively cross-
examined. In answers to questions no. 354 to 366, she has
clarified the entire issue. Similar is the position with regards to
the objections regarding port of discharge (see answers to
questions 360, 361, 383 and 384). With regard to commission
again it is to be noted that the issue was not raised in the Reply
to the Counter-Claim. However in the cross-examination the
issue was raised and answered (see answers to questions 390 &
391). Similarly, with regard to quantity in the Reply to the
Counter-Claim, the Claimant has stated that it would have
exercised its option to lift 5% less of 75,000 MT i.e. 71,500 MT
and therefore computation of loss has to be assessed on that
basis. However, the issue was again clarified by Ms. Jasmina
Maiti in answers to questions no. 392, 396 and 398.”
O.M.P. (COMM) No. 196/2018 Page 23
46. A reading of the above finding of the Arbitrator would show that
the Arbitrator has extensively relied upon the answers given by Ms.
Jasmina Maiti, witness of the respondent, in her cross-examination
specially to question Nos. 354, 368, 371, 383, 384, 390, 391, 392, 396
and 398.
47. The above being a matter of appreciation of evidence, cannot be
interfered with by this Court as if sitting as a Court of appeal. Therefore,
the quantification of damages by the Arbitrator insofar as the second
declaration with laycan 05-14 December 2011 cannot be faulted.
48. The learned senior counsel for the petitioner further submits that
the respondent had terminated the COA relying upon Clause 62 of the
same; Clause 62 states that the Contract shall come to an end without any
liabilities on either side. He submits that, therefore, respondent cannot
claim any damages for any alleged default prior to the termination.
49. I am unable to accept the submission of the learned senior counsel
for the petitioner. Clause 62 merely absolves parties of liability to pay
damages as a consequence of termination. It, however, is not intended to
absolve the parties of any liabilities previously incurred by the parties due
to their default.
50. Even otherwise, it was the own case of the petitioner that the
respondent could not have terminated the Agreement relying upon Clause
62 of the COA. This plea has been accepted by the Sole Arbitrator.
Therefore, the petitioner cannot now be heard to say that the termination
being under Clause 62, it was discharged of its liabilities to pay damages
for breach committed prior to such termination.
O.M.P. (COMM) No. 196/2018 Page 24
51. The learned senior counsel for the petitioner further contends that
the respondent having not raised any claim for damages prior to their
termination notice, is deemed to have waived its right to claim such
damages. He places reliance on the judgment of the Supreme Court in P.
Dasa Muni Reddy vs P. Appa Rao, (1974) 2 SCC 725.
52. I do not find any merit in the above submission. The petitioner has
been unable to point out any document from which it can even remotely
be implied that the respondent had waived its right to claim damages for
the breach of the COA by the petitioner in not nominating the vessels. On
the other hand, the termination letter dated 25.09.2012 specifically stated
that the respondent reserves its right to claim compensation/damages for
the breach committed by the petitioner.
53. In P. Dasa Muni Reddy (Supra), the Supreme Court has held that
waiver is an intentional relinquishment of a known right or advantage
which, except for such waiver, the party would have enjoyed. It is a
voluntary surrender of a right. Waiver is consensual in nature. The
essential element of waiver is that there must be voluntary and intentional
relinquishment of a right. Judged by any of these parameters, I do not
find any waiver of the right of the respondent to claim damages for the
refusal of the petitioner to nominate vessel for 05-14 December, 2011
stem.
54. The learned senior counsel for the petitioner has further challenged
the award of interest by the Arbitrator in favour of the respondent. He
submits that as the respondent had failed to produce any document
establishing the date of payment of freight, there is no reference date with
respect to interest.
O.M.P. (COMM) No. 196/2018 Page 25
55. The Arbitrator in his Impugned Award has directed the payment of
interest as under :
“(i) The Claimant shall pay to the Respondent a sum of USD
862,500.00 with interest @ 3% from the date of payment of the
freight by the Respondent for the 2 shipments till the date of
Award, within a period of three months from the date of the
Award. In the event of default the amount awarded together
with interest shall be paid @of 9% p.a. from the date of the
award, till payment.”
56. The Arbitrator has not specified the date of payment of the freight
by the respondent to the third party. In fact, the said date could not be
ascertained from the submission of the learned senior counsel for the
respondent before this Court as well. The Arbitrator has, however,
directed that if the petitioner fails to make the payment alongwith interest
at the rate of 3% „from the date of payment of freight by the respondent
for the two shipments till the date of Award, within a period of three
months‟ it shall pay the awarded sum together with interest at the rate of
9% per annum from the date of the Award till payment. Therefore, there
is differential rate of interest awarded by the Arbitrator, with the
enhanced rate of interest being payable by the petitioner on default.
57. As the date of payment of freight by the respondent to the third
party is unknown, the petitioner would not be able to calculate the
interest payable for the pre and pendente lite period. It would necessarily
have to depend on a confirmation of the same by the respondent. It may
even want to dispute the date of such payment. Therefore, in the peculiar
facts of the present case, the direction to pay interest at a higher rate post
award cannot be sustained.
O.M.P. (COMM) No. 196/2018 Page 26
58. In view of the above, the Award insofar as it dismisses the claim of
the petitioner and awards damages to the respondent of USD 525,000.00
alongwith interest is set aside. Award of interest at the rate of 9% per
annum from the date of the Award till payment is also set aside. The
challenge to the Award insofar as damages of USD 337,500.00 with
respect to the laycan 5-14 December, 2011 along with interest at the rate
of 3% per annum from the date of payment of freight by the respondent
for the said laycan till the date of payment by the petitioner is rejected.
59. The petition is partially allowed in the above terms, with no order
as to cost.
NAVIN CHAWLA, J
FEBRUARY 28, 2019/ rv/vp
O.M.P. (COMM) No. 196/2018 Page 27