Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
PETITIONER:
UNION OF INDIA
Vs.
RESPONDENT:
M/S. POPULAR BUILDERS, CALCUTTA
DATE OF JUDGMENT: 17/10/2000
BENCH:
S.N.Phukan, M.B.Shah, G.B.Pattanaik
JUDGMENT:
PATTANAIK,J.
L.....I.........T.......T.......T.......T.......T.......T..J
Leave Granted.
This appeal by the Union of India is directed against
the judgment dated 28th of January, 1999 of the Division
Bench of Calcutta High Court, dismissing the appeal of the
Union of India, arising out of an arbitration proceeding.
The undisputed facts are that the respondent had entered
into an agreement with the appellant for construction of
Annex Building to Telephone Bhawan at Calcutta. The
agreement between the parties contained an arbitration
clause therein. After the completion of work, the final
bill was drawn and was sent to the respondent and he agreed
to accept the final bill and in fact did receive the money
under the final bill without any objection. But thereafter,
he wrote a letter to the concerned Chief Engineer,
indicating several items of claim and additional works which
the respondent had executed pursuant to the directions of
the appropriate authority and the said work had not been
included in the final bill. He, therefore, requested the
Chief Engineer, the authority under Clause 25 of the
agreement to appoint an arbitrator and pursuant to the said
request, the Chief Engineer by his letter dated 25.11.93 did
appoint an arbitrator. Subsequently, the appointed
arbitrator was changed. Pursuant to an order of the High
Court and before the arbitrator, the respondent filed his
claim on different heads. The Union of India-appellant
herein, filed his objection as well as filed a counter claim
before the arbitrator. The learned Arbitrator ultimately
passed an award and that award was filed before the High
Court, for being made a rule of Court under Section 14 of
the Arbitration Act, 1940. The Union of India filed an
objection under Sections 30 and 33 for setting aside the
award. The learned Single Judge considered the objections
filed by the Union of India and rejecting the same, made the
award a rule of Court. Against the aforesaid order of the
learned Single Judge, an appeal was carried to the Division
Bench under Section 39 of the Arbitration Act. The Division
Bench having dismissed the Unions appeal by the impugned
order, the present appeal has been preferred by the Union of
India. From the judgment of the learned Single Judge,
rejecting the objections of the Union of India as well as
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
the impugned judgment of the Division Bench, it appears that
the Union of India had urged the sole point of limitation
and the same had been negatived by the courts below and in
our view rightly.
Mr. A. Subba Rao, the learned counsel for the Union
of India however raised the question that the final bill
having been accepted by the respondent-contractor, without
any objection, there did not subsist any arbitrable dispute
to be referred to arbitration, invoking Clause 25 of the
agreement and, therefore, the impugned award has to be set
aside. In support of this contention, reliance has been
placed on two decisions of this Court M/s. P.K. Ramaiah
and Company vs. Chairman & Managing Director, National
Thermal Power Corpn., 1994 Supp. (3) S.C.C. 126 as well as
a three Judge Bench decision of this Court in Nathani Steels
Ltd. vs. Associated Constructions, 1995 Supp.(3) S.C.C.
324.
Mr. L. Nageswara Rao, appearing for the respondent-
claimant on the other hand contended that this objection had
not specifically been taken in the objection, that was filed
under Sections 30 and 33 of the Arbitration Act, and
therefore, the Union Government should not be permitted to
take up this plea in this forum. He further contended that
pursuant to the request made by the Contractor, the Chief
Engineer himself having appointed an arbitrator on the
ground that dispute subsists for arbitration and in the
arbitration proceeding, the Union Government having fully
participated and further, subsequent to the award, a
rectification application having been filed by the Union
Government and in that application also, only challenge
being made on the quantum and not on the ground of absence
of arbitrable disputes, it would not be appropriate for this
Court to allow the Union Government to take this plea at
this belated stage. He also contended that the two
decisions referred to by the Union Government are prior the
appointment of arbitrator and none of these decisions are
applicable to the case in hand, where an award has been
passed by the appointed arbitrator after due participation
of Union Government in the arbitration proceedings.
Having considered the rival submissions at the Bar and
on careful scrutiny of the objections filed by the Union
Government under Sections 30 and 33 of the Arbitration Act,
though we find sufficient force in the contention of Mr.
Nageswara Rao, but the existence of a dispute being the
condition precedent for appointment of an arbitrator under
Clause 25 and in view of the two decisions of this Court and
that the respondent-claimant did receive the final bill
without any protest, we are not persuaded to outright reject
the contention of Mr. Subba Rao, appearing for the Union
Government. It transpires from the award itself that only
as against claim item No. 2, the Union of India had pleaded
that the said claim cannot be entertained in view of the
receipt of the final bill by the contractor without any
protest, though the arbitrator had rejected the said plea of
the Union of India. It is no doubt true as contended by Mr.
Nageswara Rao that neither the judgment of the learned
Single Judge nor the judgment of the Division Bench, which
is under challenge in this appeal before this Court did
indicate the fact that the Union of India had raised this
contention before the aforesaid two forums below but
notwithstanding the same when the existence of an arbitrable
dispute is the condition precedent for exercise of power for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
appointment of an arbitrator under Clause 25 and since the
final bill that was prepared by the appropriate authority
was accepted by the respondent without any protest as is
apparent from the letter of the claimant-contractor and the
question had been raised before the arbitrator in respect of
the claim item No. 2 by the Union of India, we think it
appropriate to hold that so far as claim item No. 2 is
concerned, the same could not have been a matter of
reference of an arbitrable dispute and as such, the award of
the arbitrator to that extent must be set aside. So far as
the other claim items are concerned, the Union of India not
having taken any objection to the same on the aforesaid
score and that even the objection filed under Sections 30
and 33 of the Arbitration Act not being specific on that
issue, we do not think it appropriate to allow the Union
Government to raise that objection, so far as the other
items of claim are concerned. Accordingly, the impugned
award in respect of claim item No. 2 is set aside and the
rest of the award amount, stand affirmed. The appeal is
allowed in part.