Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
PETITIONER:
BRID CORPN. OF ORISSA LTD.
Vs.
RESPONDENT:
M/S INDIAN CHARGE CHROME LTD.
DATE OF JUDGMENT: 13/05/1998
BENCH:
G.T. NANAVATI, S.P. KURDUKAR
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
S.P. KURDUKAR, J.
Leave granted.
(2) These appeals are directed against a common Judgment
and order dated 10.2.98 passed by the Learned Chief Justice
of Orissa High Court, Cuttack in Miscellaneous Appeal Nos.
599/97, 600/97 and MJC No. 229/97. All these appeals are
being disposed of by this Judgment.
The brief facts leading to the present controversy may
be summarised as under:-
(3) The GRID Corporation of Orissa Ltd., (for short ’the
GRIDCO’) is the appellant in all these appeals whereas M/S
Indian charge Chrome ltd., (for short ’ICCL’) is the
respondent. GRIDCO was the appellant in Miscellaneous Appeal
Nos. 599/97 -600/97 whereas ICCL was the petitioner in MJC
No. 229/97 before the Orissa High Court.
(4) The GRIDCO became the successor of the Orissa State
Electricity Board (hereinafter referred to as ’OSEB’) w.e.f.
1.4.1996 and was engaged in the business of transmission,
distribution and supply of electricity to various consumers
in the State of Orissa. Indian metals and Ferro Alloys
Company (for short ’IMFA’) is a sister concern of ICCL. ICCL
sometime in 1984 corresponded with the Government of Orissa
seeking permission to generate power. Accordingly after
completing the formalities ICCL sometimes in 1989 set up
the Captive Power Plant to generate power in the State of
Orissa at Choudwar. Power generated at Choudwar was to be
wheeled to The Indian Metals and Ferro Alloys Company (IMFA)
at Therubali a sister concern of ICCL and PPL and the
surplus power was to be sold to OSEB. For the purposes of
administrative convenience ICCL was incorporated.
Accordingly, an agreement dated February 14, 1989 was
entered into between OSEB and ICCL and under the said
agreement the power generated by ICCL at Choudwar was fed to
the GRID of OSEB for further transmission to the Charge
Chrome Manufacturing Plant of IMFA at Therubali. The
arrangement between OSEB and ICCL continued until a
Memorandum of Understanding dated 15.11.1994 was arrived at
and signed by ICCL and OSEB and thereafter followed by an
agreement dated 4.3.1995 w.e.f. 1.12.94. Under this MOU of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
1994 power supplied by ICCL to OSEB was charged at 77 paise
per unit; wheeling of power by OSEB (from ICCL) was charged
@ 15%, (known as wheeling charges). ICCL was permitted to
draw power from OSEB for supply to PPL/IMFA/PPT on payment
of Rs. 2.31/- per unit (back- up power); ICCL guaranteed
supply of power to OSEB at least 10 MW per day. Although
this agreement was valid for six months, however the
exchange of power on both sides continued even thereafter.
OSEB used to raise the monthly bills as per the readings
recorded on TOD meters with 30 minutes’ recording time.
GRIDCO who became the successor of DSEB w.e.f. 1.4.96,
called upon ICCL to pay outstanding dues for the period
December, 1994 to December, 1996 amounting to Rs. 24.8281
crores. ICCL failed to make the payment. During this period
the OSEB and thereafter GRIDCO had been wheeling/supplying
electricity to ICCL in terms of MOU dated 15.11.1994.
(5) On 25.2.1997 ICCL filed an application before the
Regulatory Commission constituted under the Orissa
Electricity Reform Act, 1955 (for Short "Reform Act’)
raising a dispute as regards bill amounts and its liability
to pay to GRIDCO. On 7.4.1997 GRIDCO informed ICCL that
unless the arrears of Rs. 24.8281 crore are paid on or
before 22.4.97, it will be compelled to discontinue the
power supply in accordance with law. On 8.4.97 ICCL filed
another petition before Regulatory Commission alleging that
the claim of the GRIDCO for the arrears for the period from
December, 1994 to December, 1996 is untenable inasmuch as
the same is contrary to the MOU and the agreement. ICCL then
alleged that because of variation of frequency in the GRID,
the power generated by its Captive Power Plant could not be
inducted into the GRID. It was an obligation of GRIDCO to
check variation of frequency in the GRID and because of its
negligence its captive power plant got damaged. The billing
done by GRIDCO on the basis of half hourly reading was
totally unjustified. The GRIDCO in this reply denied the
allegations and stated that variations of frequency in the
GRID was maintained by using proper electric system. The
frequency was maintained as prescribed under the Indian
Electricity Rules. The power was wheeled according to the
MOU dated 15.11.1994 and the agreement dated 4.3.1995. As
regards the maintenance of frequency it was stated that it
depends upon all operators in the GIRD Which is coordinated
by the Eastern Regional Load Despatch Centre. The GRIDCO
used to receive power from various sources. The claim set up
by ICCL as regards the damage to their Captive Power Plant
is untenable. As regards the billing it was stated tat it is
established practice for all heavy industrial consumers that
though billing is done on a monthly basis, but for billing
purposes exchange of energy/power supplied to the consumers
is measured on the basis of consumption for each 30 minutes
block separately. To facilitate this TOD meters are
installed at the supply point. Clause 16(2) of the Agreement
dated 4.3.95 provides for such billing.
(6) Despite the notice no payment was made by ICCL and
therefore, vide notice dated 24.4.97 under Section 24(1) of
the Indian Electricity ACT the ICCL was called upon to pay
the arrears within seven days, in default power supply will
be discontinued.
(7) The ICCL did not make any payment. But on the contrary
on 30.4.97 ICCL filed a petition under Section 9 of the
Arbitration and Conciliation Act, 1996 (for short
’Arbitration Act’) in the Court of District Judge, Puri
which was numbered as Arbitration Case No. 195/97 for relief
of injunction. The District Judge on 30.4.97 granted ex-
parte injunction restraining GRIDCO from disconnecting back
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
up power supply to ICCL, IMFA and PPL. GRIDCO aggrieved by
this order filed appeal before the Orissa High Court on
15.5.97. The High Court Stayed the operation of the order of
the District Judge dated 30.4.97. on 16.5.97 ICCL appeared
before the High Court and prayed for recall of the order of
stay dated 15.5.97. The High Court recalled its order and
directed to restore the electric supply which was
disconnected, subject to deposit of Rs.5 crores by ICCL as
against the arrears of Rs. 24.8281 crores. Aggrieved by this
order dated 16.5.1997 ICCL filed SLP in this Court which
came to be disposed of on 27.5.97 confirming the direction
of payment of Rs. 5 crore but, however, this Court granted
facility to make payment in two instalments. As regards the
recurring charges the Court observed as under:-
" We are not passing any order with
regard to recurring charges. The
matter is left open. The appeals
are disposed of accordingly".
(8) In the meantime the Regulatory Commission on 21.5.97
asked ICCL to clarify as to how its petition could be
treated as Reference under Section 37(1) of the Reform Act
since it is not a licensee under the said Act. On 2.6.97
ICCL filed another application before the Regulatory
Commission stating that the same may be treated as a
Reference under Section 37(1) of the Reform Act. On 9.6.97
GRIDCO filed its reply and took a preliminary objection to
the maintainability of the application of Reference under
Section 37(1) of the Reform Act. The Regulatory Commission
adjourned the matter to 19.7.97 for hearing on the question
of maintainability.
(9) On payment of rupees five crores by ICCL in pursuance
of the order of this Court the GRIDCO restored power supply
to ICCL. Again for the period of January, 1997 to May, 1997
the ICCL failed to pay the bills amounting to Rs.
5,12,45,546.06 and, therefore, on 19.6.97/20.6.97 the GRIDCO
issued a notice to ICCL to pay the said amount within seven
days in default power supply will be disconnected. The ICCL
approached the Additional District judge Challenging the
said notice and the Court on 27.6.1997 granted interim order
staying the operation of the notice dated 19/20.6.97 of
disconnection without imposing any condition. On 14.7.97 the
ICCL filed a petition before the Orissa High Court under
Section 11 of the Arbitration Act being MJC No. 229/97 for
appointment of an Arbitrator. In the meantime the Additional
District Judge who was seized of the two applications
disposed of the same by two separate orders dated 26.7.97
restraining GRIDCO from disconnecting power supply to
ICCL/IMFA till disposal of Case No. 15/97 pending before the
Regulatory Commission. Both these orders did not impose any
condition for payment of arrears or current charges except
stating therein that in the event ICCL failed to comply with
the order of the Supreme Court, GRIDCO may take appropriate
action.
(10) Aggrieved by the tow orders dated 26.7.97 passed by the
additional District Judge the Gridco on 14.8.97 filed two
appeals before the Orissa High Court being M.A. Nos. 599-600
of 1997 challenging the legality and correctness of the said
orders.
(11) In view of the blanket stay order dated 26.7.97, ICCL
did not make any payment for the amounts due from June, 1997
to September, 1997 in the aggregate sum of Rs. 13,18,88000/-
. On 7.11.1997 GRIDCO, therefore, issued a notice of
disconnection for non payment of the dues of Rs.
13,18,88000/-. On 7.11.1997 GRIDCO, therefore, issued a
notice of disconnection for non payment of the dues of Rs.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
13,18,88000/-. On receipt of this notice ICCL on 10.11.1997
filed an application before the High court praying for stay
of the notice dated 7.11.97 of disconnection and the High
Court on 11.11.1997 granted the interim relief.
(12) The Learned Chief Justice of Orissa High Court took up
for final disposal Miscellaneous appeal Nos. 599/600 of 1997
filled by GRIDCO and MJC No. 229 of 1997 filled by ICCL. The
High Court by its order dated 10.298 held that there was a
dispute between ICCL and the GRIDCO which is arbitrable
falling within the jurisdiction of the Regulatory Commission
under Section 37 of t he Reform Act and also arbitrable
under Section 3 read with Schedule of Electricity Act. The
High Court further held that since the Regulatory Commission
failed to arbitrate in the matter and/or failed to appoint
an Arbitrator, nominated a Retired Chief Justice of India as
the sole Arbitrator. The High court further directed that
stay of disconnection shall continue. From the return filed
on behalf of ICCL it appears that ICCL without loss of any
time, on 25.2.98 filed statement of claim on its behalf
before the sole arbitrator.
(13) The GRIDCO aggrieved by the common judgment and order
passed by the High Court filed these three appeals
challenging the legality and correctness thereof.
(14) We have gone through the judgment of the High Court and
in our considered view it had exceeded the jurisdiction
while entertaining the application of ICCL under Section 11
of the Arbitration and Conciliation Act, 1996. The High
Court erroneously assumed that the Regulatory Commission had
failed to arbitrate under Section 37(1) of the Reform Act.
this finding is factually incorrect because vide application
dated 19.797 ICCL asked the Regulatory Commission to adjourn
the proceedings pending before it on the ground that it had
filed MJC No. 229/97 in the High Court . In view of this
application the Regulatory Commission did not proceed in the
matter. If this be so the High Court in our opinion was
wrong in holding that there was failure on the part of
Regulatory Commission to arbitrate and consequently the
application made by ICCL under Section 11 of Arbitration Act
is maintainable. In our considered view the application made
by ICCL under Section 11 of the Arbitration Act, 1996 (MJC
No. 229/97) was premature and the High Court could not have
entertained the same and granted desired relief to ICCL.
(15) Another question which was seriously contested on
behalf of GRIDCO before the Regulatory Commission as well as
before the High Court was that ICCL is not a licensee within
the meaning of Section 2(h) of Indian Electricity Act, 1910
and also under Section 2(e) and (f) of the Reform Act, 1995.
The High Court recorded a finding that ICCL is a licensee
under the Indian Electricity Act, 1910 and it continued to
be a licensee even after Reform Act, 1995 came into force.
The High Court placed reliance on Section 14(1) of the
Reform Act and held that ICCL is authorised by the State
Authority in the business of supplying the electricity. It
was thus concluded that ICCL in view of Section 14 of the
Reform Act, 1995 shall continue to be a licensee. In view of
this finding the High Court held that the dispute is
arbitrable under Section 37(1) read with Section 33 of the
Reform Act, 1995. It is not seriously disputed that ICCL
after a long drawn correspondence with the Orissa Government
had received no objection to put up the captive power plant
at Choudwar to generate power. Accordingly in 1989 the
Captive power plant started generating power which was
supplied to the OSEB. This arrangement continued till 1994
When MOU and agreement were entered into between ICCL and
OSEB. The GRIDCO being a successor of OSEB naturally the MOU
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
of 1994 and agreement of 1995 will be binding upon the
GRIDCO in the absence of any material to the contrary. It is
not the contention of the GRIDCO that ICCL did not supply
any power at all during the period for which the bills were
raised on ICCL. Despite this factual position it appears
that no formal licence was issued under Section 2(h) of
Indian Electricity Act, 1910 or under the Reform Act, 1995.
It cannot be ignored that the investment of ICCL in putting
up a Captive power Plant at choudwar is running into few
hundred crores. Section 2(e) and (f) of the Reform Act read
as under:
" (e) "licence" means a licence
granted under Chapter VI;
(f) "licence" or "licence holder"
means a person licensed under
Chapter VI to transmit or supply
energy including Gridco".
CHAPTER VI DEALS WITH LICENSING OF
TRANSMISSION AND SUPPLY
Section 14(1) reads as under:
No person, other than those
authorised to do so by licence or
by virtue of exemption under this
Act or authorised or exempted by
any other authority under the
Electricity (Supply) Act, 1948
shall engage in the State in the
business of
(a) transmitting; or
(b) supplying electricity.
From the facts noted hereinabove and in view of Section
14(1) of the Reform Act it is quite clear that ICCL was/is
authorised and engaged in supplying the electricity to OSEB
and thereafter to GRIDCO and if this be so the dispute
between the GRIDCO and ICCL could be arbitrable under
Section 37(1) read with Section 33 of the Reform Act, 1995.
(16) Mr. F.S. Nariman, Learned Senior Counsel in support of
these appeals urged that not only the District Judge but
even the High Court had totally ignored a well settled rule
while injuncting the GRIDCO from performing its statutory
function of disconnection of power supply to ICCL for non
payment of arrears of electricity bills without imposing any
condition as regards payment of arrears and recurring
charges and consequently the GRIDCO is obliged to continue
power supply. The order passed by the High Court is neither
just nor fair and is opposed to the rule of balance of
convenience. As regards the amount of arrears of Rs. 24
crore recoverable pursuant to the first demand/disconnection
notice for the period December, 1994 to December, 1996 at
the moment it is covered by the interim order of this Court.
His grievance is as regards the subsequent arrears from
January, 1997 to March, 1998 come to Rs. 46.193 crores
(approximately) on monthly settlement basis. On half hourly
settlement basis the amount payable would come to Rs. 62.52
crores including delayed payment surcharge @2% per month.
Demand/disconnection notices have already been served but in
view of various orders passed by the courts the GRIDCO is
unable to recover arrears and in addition it has been
injuncted from disconnecting power supply. The only
equitable order in such circumstances ought to be to call
upon ICCL to pay all the arrears since ICCL had availed
facility of power/energy to run its plants IMF and PPL. He
urged that no reasons whatsoever re given by the Courts
below while granting unconditional interim orders in favour
of ICCL.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
(17) Mr. K.K. Venugopal, Learned Senior Counsel while
countering these submissions urged that ICCL was neither in
arrears nor it neglected to pay the bill amount. According
to him the bills served on ICCL were patently wrong because
billing was done on the basis of half hourly consumption
recorded on TOD meter. ICCL was not obliged to honour such
bills. He also urged that ICCL was generating power but it
was because of high frequency in the GRID it could not
absorb power generated by ICCL and as a result thereof its
Captive Plant and boilers were required to be shut down. At
times the boilers were closed down for several hours. Though
the high rise frequency was intermittent but once the
boilers were shut down they used to take more than two hours
to produce the steam which is supplied to the turbines to
generate power. The GRID high frequency had caused damage to
the blades of the turbines costing about couple of crores in
replacing the same. Mr. Venugopal then urged that in fact
the GRIDCO owed certain amounts to ICCL and had received Rs.
10 crores and for the balance the matter is pending before
the high power Committee set up by Government of Orissa. As
regards the wheeling charges counsel disputed any liability
thereof and urged that there was no question of paying any
wheeling charges when power was not wheeled by GRIDCO by
reason of time to time shutting down to turbines and boilors
of ICCL. It was, therefore, urged that the GRIDCO had no
claim whatsoever against the ICCL and therefore the courts
below were right in staying the disconnection notices
without imposing any condition.
(18) In our considered view the spacious claim pressed
before us on behalf of ICCL cannot be accepted at this
interlocutory stage. it is not denied by ICCL that back up
power was available to its sister concern IMF and PPL and
the manufacturing process was continuing. At this
interlocutory stage what the courts are required to bear in
mind is as to whether a prima facie case for recovery of
arrears of energy charges is made out and on whose side the
balance of convenience lies. In the facts and circumstances
of the case whether interim order should be passed by
imposing certain conditions or without any condition. The
net result of the impugned order is that the GRIDCO is
required o maintain back up power to the constituents of
ICCL but for such supply latter was not required to make any
payment for power consumed. It also needs to be mentioned
that under the MOU dated 15.11.94 and agreement dated
4.3.95 ICCL is required to pay for consumption of energy @
Rs. 2.31 per unit which is far less than the rate at which
power is supplied to other commercial units. It is true that
ICCL when supplies power to GRIDCO the latter pays at the
rate of 77 paise per unit to former. Some dispute is also
raised as regards interpretation of MOU and agreement but we
do not think it appropriate to deal with these contentions
at his point of time.
(19) Mr. Venugopal also disputed the recording of
consumption of power on half hourly basis. It was according
to learned counsel wholly illegal and as a result thereof
the amounts in the bills stood inflated, and consequently
ICCL is not liable to honour such bills. On the other hand
Mr. Nariman urged that it is not open to ICCL to challenge
the half hourly recording because it was specifically agreed
upon between the parties under MOU and the agreement. We do
not propose to deal with these rival contentions at this
interlocutory stage and, therefore, they are kept open.
(20) Mr. Nariman alternatively urged that at any rate on the
basis of monthly billing, the amounts payable by ICCL to
GRIDCO would come to Rs. 46.193 crores and, therefore, at
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
this interlocutory stage without touching the controversy as
regards half hourly recording is right or wrong, ICCL must
make the full payment of this amount. Another dispute also
relates to wheeling charges @ 15%. According the GRIDCO
power was in fact wheeled but according to Mr. Venugopal
when the turbines were shut down though intermittantly there
was no question of wheeling the power. This issue again
needs further investigation in depth and at this
interlocutory stage it would not be proper to conclude one
way or the other. We, therefore, proceed on the assumption
that the amount reflected on the basis of monthly bills
payable to the GRIDCO by ICCL would be Rs. 46.193 crores
less 15% wheeling charges which would come Rs. 6.92 crores
approximately. At this interlocutory stage even if we give
benefit of this amount of Rs. 6.92 crores payable by ICCL to
GRIDCO under the various bills still the outstanding arrears
payable by ICCL to GRIDCO would come to Rs. 39.273 crores.
(21) Now the question is what could be the fair and just
order as regards the payment of these arrears. Mr. Venugopal
although expressed the financial constraints of ICCL to make
any payment but that cannot be a ground to allow ICCL to use
power without any charges. We, therefore, feel that the fair
and proper order to meet the ends of justice at this
interim stage would be to direct ICCL to pay Rs. 39.273
crores in seven equal instalments of Rs. 5 crores payable on
or before 10th of each month to GRIDCO and the 8th
instalment of Rs.5 crores will be payable in the month of
June, 1998. The Regulatory Commission while making the
award, will pass appropriate orders as regards interest on
the amount if found refundable to ICCL or recoverable by
GRIDCO on their respective claims in accordance with law. In
the event of any two defaults, facility of payment by
instalment to stand vacated. Disconnection notices will
revive and Gridco will be at liberty to take such steps as
permissible in law. As regards the recurring charges if ICCL
wants to use power it will have to make payment of such
bills as and when served upon them. ICCL may raise a dispute
before the Regulatory Commission. If there be any Occasion
to consider such application the Regulatory Commission will
pass interim orders in accordance with law. These
calculations and directions are without prejudice to the
rights and contentions of the parties.
(22) For the conclusions recorded hereinabove all the three
appeals are allowed. The judgment and order dated 10.2.98
passed by the High Court is set aside and resultantly the
appointment of the Arbitrator stands quashed. The ICCL is
directed to make the payment of arrears as indicated above.
The application made by ICCL to the Regulatory Commission
will dispose of the matter in accordance with law. In the
facts and circumstances of the case the parties are directed
to bear their own costs.