Full Judgment Text
2024 INSC 257
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4626 OF 2024
(@ SPECIAL LEAVE PETITION (C) No.23319 OF 2022)
LEVEL 9 BIZ PVT. LTD. …APPELLANT(S)
VERSUS
HIMACHAL PRADESH HOUSING AND
URBAN DEVELOPMENT AUTHORITY
& ANOTHER …RESPONDENT(S)
J U D G M E N T
BELA M. TRIVEDI, J.
1. Leave granted.
2. The Appellant – Level 9 BIZ Pvt. Ltd., who was not a party to the
proceedings, being Civil Writ Petition No. 1481 of 2021, filed by the
Respondent No.2 – M/s. Vasu Constructions in the High Court of
Signature Not Verified
Himachal Pradesh at Shimla, has challenged the impugned order dated
Digitally signed by
RAVI ARORA
Date: 2024.04.02
17:21:52 IST
Reason:
18.10.2022 passed by the High Court in the said proceedings. The High
1
Court passed the impugned order disposing of the said CWP by merely
accepting the statement made on behalf of the Respondent No.1 –
Himachal Pradesh Housing and Urban Development Authority
(HIMUDA) that it wanted to withdraw the cancellation of initial tendering
process order dated 05.02.2021, and the statement made on behalf of
the Respondent No. 2 that it was ready to execute the project on the
same terms and conditions and the rates as per the initial tender dated
15.11.2018, though the said tender was already withdrawn by the
Respondent no. 1 HIMUDA in view of the irregularities and illegalities
committed by it, as recorded by an independent committee appointed
by the High Court in earlier writ petitions filed by the present appellant
and one Dalip S. Rathore.
3. The broad facts giving rise to the present appeal may be stated as
under: -
| DATES | EVENTS |
|---|---|
| 15/16.11.2018 | Notice Inviting Tender (NIT) was issued by HIMUDA (R-1) for the<br>construction of proposed commercial complex of Vikas Nagar,<br>Shimla, at estimated cost of Rs.45,05,62,074/- |
| 15.12.2018 | Technical Bids were opened and on the same day Financial Bids<br>were also opened. (Appellant & R-2 were the only found to be<br>qualified – But the Appellant was L2) |
| 17.12.2018 | LOI was issued by the R-1 in favour of R-2. |
| 24.12.2018 | One Unsuccessful bidder Dalip S Rathore filed Writ Petition being<br>CWP 3021 of 2018 challenging the technical specifications & |
2
| ineligibility of Respondent No.2, also seeking cancellation of the<br>Tender. The High Court issued notice. | |
|---|---|
| 02.01.2019 | R-1 HIMUDA withdrew the LOI dated 17.12.2018 of R-2 M/S Vasu<br>Constructions stating that the case is pending in the High Court<br>and the work will be awarded only as per the decision of the High<br>Court. |
| 05.01.2019 | R-1 HIMUDA constituted a committee, which reviewed the tender<br>process and concluded that there were many lapses which<br>warranted actions against the erring officials. |
| 07.01.2019 | Another Committee constituted by R-1 submitted a report that<br>Shri Dalip Singh was not qualified and M/s. Vasu Constructions<br>was qualified. |
| 23.02.2019 | Appellant – Level 9 BIZ Pvt. Ltd. filed a writ petition CWP 363 of<br>2019, praying for rejection of Technical Bid and Financial Bid of<br>the R-2 M/s. Vasu Constructions |
| 25.11.2020 | High Court passed a detailed order on 25.11.2020 in CWP No.<br>3021/2018 and 363/2019.<br>In Para 29 High Court observed-<br>“[..] this Court is prima facie of the view that<br>some of the officers manning high positions in<br>HIMUDA have not acted responsibly and in the<br>interest of organization, rather have attempted,<br>directly or indirectly, to give undue benefit to<br>some of the contractors. Having seen the<br>record, this Court is compelled to draw a<br>conclusion that the officers responsible for<br>evaluation of the tender in question, did not<br>scrutinize the documents submitted by the<br>tenderers along with their bids properly and, with<br>a view to ensure ouster of some eligible<br>contractors and awarding the same to their<br>favourites, have made an attempt to justify their<br>action by giving totally implausible reasoning.” |
3
| In para 31, High Court observed-<br>“But, for the reasons, best known to the<br>authority, it still proceeded to award the tender in<br>favour of M/s. Vasu Construction Company.”<br>The High Court therefore to instill confidence in the general public<br>and to ensure transparency in the system, constituted an<br>independent committee to enquire into the tender process in<br>question, and directed the committee to submit its report in a<br>sealed cover to the Court. | |
|---|---|
| 02.01.2021 | Committee constituted by High Court filed its report. |
| 08.01.2021 | High Court disposed of both Petitions being Nos. 3021/2018 and<br>363/19 and directed registry to initiate separate proceedings<br>against erring officials, observing as under: -<br>14. Since the committee, after having perused<br>the records, has arrived at a definite conclusion<br>that on account of shortcomings/irregularities,<br>tender in question requires to be cancelled,<br>nothing much is left for this court to adjudicate in<br>these matters. Leaving everything aside,<br>learned counsel for the petitioners in both the<br>petitions, being satisfied with the findings of<br>enquiry committee as well as suggestions made<br>therein, are not willing to prosecute the cases<br>further and have prayed to dispose of the same<br>as having been rendered infructuous.<br>15. In view of aforesaid, both the petitions are<br>disposed of as infructuous alongwith all pending<br>applications. Interim directions, if any, stand<br>vacated. However, liberty is reserved to the<br>parties to file fresh petition(s), if any, if they still<br>remain aggrieved.<br>16. However, this court, having taken note of the<br>fact that the enquiry committee despite having<br>found officers lacking in discharge of their<br>duties, has failed to fix responsibility and |
4
| recommend action, criminal or departmental,<br>deems it necessary to direct the Registry of this<br>Court to register separate proceedings, enabling<br>this Court to pass appropriate orders so as to<br>ensure strict compliance of recommendations<br>given in the report of enquiry committee and<br>pass appropriate orders with regard to initiation<br>of criminal/ departmental proceedings against<br>the erring officials. Registry is directed to<br>register separate proceedings and list the same<br>on 17.3.2021. The order dated 25.9.2020, this<br>judgment and the enquiry report submitted by<br>the committee constituted by this Court, shall<br>form part of the fresh proceedings. | |
|---|---|
| 05.02.2021 | Respondent No.1 cancelled the Tender in view of the Order dated<br>08.01.2021 passed by the High Court. |
| 03.03.2021 | Respondent No.2 filed a new Writ Petition against Respondent<br>No.1, i.e., CWP 1481 of 2021 challenging order dated<br>05.02.2021.<br>Respondent no. 2 also filed separate two LPAs being LPA No.<br>6/2021 and 12/2021 against the common order dated 08.01.2021<br>passed in CWP No. 3021/2018 and CWP No. 363/2019 by the<br>Single Bench. |
| 17.11.2021 | R-1 HIMUDA issued fresh NIT for the same work. |
| 01.12.2021 | The Division Bench of High Court passed an interim order in LPA<br>No. 6/2021, 12/2021 and CWP No. 1481/2021 staying the NIT<br>dated 17.11.2021 till further orders. |
| 18.10.2022 | The Division Bench disposed of the Writ Petition No. 1481/2021<br>upon statement of the Executive Engineer of Respondent No.1<br>observing as under:<br>7. Learned counsel for the respondent on<br>instructions of Mr. Rajesh Thakur, Executive<br>Engineer, HIMUDA, Division, Shimla-9, has<br>submitted that the competent authority wants to<br>withdraw the cancellation of initial tendering<br>process order dated 5th February, 2021, bearing<br>No. 5806-11, as the public is deprived from the |
5
| facilities, which would have been available to<br>them after completion of the project. The project<br>cost is going to be enhanced due to delay in<br>execution of the project, which will cause<br>additional burden on the public exchequer. The<br>various Government departments/PSUs are<br>facing acute shortage of office accommodation,<br>therefore, in larger public interest, the authority<br>has no objection to go ahead with initial<br>tendering process, in case the petitioner is ready<br>to execute the work at the same rate and terms<br>and conditions as were agreed at the time of<br>finalization of the initial NIT dated 15.11.2018<br>(Annexure P-2). The time period for execution of<br>work will start from date of fresh award letter<br>which will be issued in favour of the petitioner<br>within 15 days.<br>8.Learned Senior counsel for the petitioner, on<br>instructions from the petitioner, has submitted<br>that offer made by the respondent is acceptable<br>to the petitioner and petitioner is ready to<br>execute the project on the same terms and<br>conditions and rates as per initial tender dated<br>15.11.2018 (Annexure P-2). | |
|---|---|
| Nov. 2022 | Contract Agreement was signed between Respondent 1 & 2.<br>Work started. |
| 12.12.2022 | The Appellant filed the SLP challenging the impugned order<br>dated 18.10.2022 and the Court while issuing notice, granted stay<br>of operation of the impugned order dated 18.10.2022. |
4. The question that has been posed before us in the instant appeal is,
whether the High Court could have disposed of the CWP filed by the
respondent no. 2 by simply accepting the statements made on behalf of
the learned advocates for the respondent no. 1 and respondent no. 2,
6
virtually permitting the respondent no.1 HIMUDA to withdraw the
cancellation of initial tendering process order dated 05.02.2021 and
permitting the respondent no. 2 M/s Vasu Constructions to execute the
project on the same terms and conditions and at the rates as per the
initial tender dated 15.11.2018, though the said tender was already
withdrawn by the Respondent No.1 HIMUDA in view of the report made
by the independent Committee constituted by the High Court confirming
gross irregularities and illegalities committed by the officers of HIMUDA
and in view of the order dated 08.01.2021 passed by the Single Bench?
5. As could be seen from the chronology of events, the appellant and the
respondent No. 2 were declared qualified in the Technical Bids opened
on 15.12.2018 and on the same day, the financial bid of the said two
parties were also opened. The respondent no.2 being L-1, the Letter of
Intent dated 17.12.2018 was issued by the Respondent
No.1 in favour of the respondent no.2. Subsequently, an unsuccessful
bidder M/s Dalip Singh Rathore filed a writ petition being No. 3021/2018
in the High Court, alleging irregularities and illegalities in the tender
process and challenging the eligibility of the respondent no. 2, also
seeking cancellation of the Tender. The appellant also filed CWP No.
363/2019 praying for the rejection of the Technical and Financial Bids of
7
the respondent no.2. The respondent no.1 HIMUDA in the meantime
appointed a committee on 01.01.2019 to review the tender process. The
respondent no.1 also vide the letter dated 02.01.2019 withdrew the
Letter of Intent issued in favour of the respondent no.2. Subsequently,
the High Court also appointed an Independent Committee to look into
the alleged illegalities and irregularities vide the order dated 25.11.2020,
in order to instill confidence in the general public and to ensure
transparency in the system.
6. As transpiring from the order dated 08.01.2021, the said Independent
Committee submitted the report, arriving at a definite conclusion that the
officers responsible for evaluation of the tender had not acted
responsibly and fairly, as a consequence of which both M/s Vasu
Constructions Company (respondent no.2 herein) and M/s Level 9 Biz
Pvt. Ltd. (the appellant herein) were wrongly declared eligible in the
Technical Bid. The Committee had concluded that since both the bidders
were not technically qualified as per the terms and conditions of the NIT,
the tender needed to be cancelled. The recommendations made by the
said Committee, except the recommendation for deletion of condition
with regard to NPA, were stated to have been accepted by the Enquiry
Committee of the respondent no. 1 HIMUDA. The High Court recorded
8
the statements of the concerned counsels for the parties and disposed
of the petitions being CWP Nos. 3021/2018 and 363/2019 vide Order
dated 08.01.2021 observing that the petitions had been rendered
infructuous, however reserved a liberty for the parties to file fresh
petition(s), if any, if they still remained aggrieved.
7. Subsequently, the respondent no.1 HIMUDA cancelled the tender on
05.02.2021 in view of the said order dated 08.01.2021 passed by the
High Court. The said action of the respondent no.1 came to be
challenged by the Respondent No.2 M/s Vasu Constructions by filing a
petition being CWP No. 1481/2021. The respondent no. 2 also filed two
LPAs being 6/2021 and 12/2021 being aggrieved by the common Order
dated 08.01.2021 passed by the Single Bench. The Division Bench of
the High Court disposed of the CWP No. 1481/2021 vide the impugned
order dated 18.10.2022 accepting the statements made by the learned
counsels for the respondent nos. 1 and 2 as stated hereinabove.
8. We are at loss to understand as to how the said petition filed by the
respondent no.2 could have been disposed of by the Division Bench by
merely recording and accepting the statements of the learned counsels
for the respondent nos. 1 and 2, when the tender in respect of NIT dated
15.11.2018 was cancelled by the respondent no.1 HIMUDA on account
9
of the gross irregularities and illegalities in the tender process found by
the Independent Committee constituted by the High Court and on
account of the order passed by the High Court on 08.01.2021? We are
also at loss to understand as to how the Executive Engineer of HIMUDA,
could have made the statements before the Division Bench that the
competent authority of the respondent no.1 wanted to withdraw the
cancellation of the initial tendering process order dated 05.02.2021 and
that the respondent no. 1 had no objection to go ahead with the initial
tendering process, in case the respondent no.2 was ready to execute
the work on the same terms and conditions as were agreed at the time
of finalization of NIT dated 15.11.2018, when the respondent no. 1 itself
had decided to cancel and in fact cancelled the initial tendering process
vide its order dated 05.02.2021 accepting the findings of the committee
constituted by the High Court to the effect that there were irregularities
and illegalities committed by the officers of the HIMUDA in processing
the tender and that the respondent no. 2 was not technically qualified?
9. When the common order dated 08.01.2021 was passed in the Writ
Petition No. 3021 of 2018 filed by the petitioner Dalip Singh and Writ
Petition No.363 of 2019 filed by the present appellant, recording the said
findings of the committee appointed by it, pursuant to which order, the
10
respondent no.1 had cancelled the tender on 05.02.2021, and had
issued a fresh NIT on 17.11.2021, it was incumbent on the part of the
respondent no. 2 to implead the said two petitioners as the party
respondents in the new petition filed by it i.e. 1481/2021, and it was also
incumbent on the part of the High Court to give opportunity of hearing
to the said petitioners before passing the impugned order disposing of
the said petition merely recording the statements of the learned
counsels for the respondent nos. 1 and 2, and permitting the respondent
nos. 1 and 2 to go ahead with execution of the work as per the initial
tender which was already cancelled by the respondent no.1.
10. Though it is true that initially an LOI was issued by the respondent no.
1 in favour of the respondent no. 2 on 17.12.2018, but the same was
withdrawn by the respondent no. 1 as per the letter dated 02.01.2019
on account of pending litigations in the High Court. In any case, it hardly
needs to be reiterated that the Letter of Intent is merely an expression
of intention to enter into a contract. It does not create any right in favour
of the party to whom it is issued. There is no binding legal relationship
between the party issuing the LOI and the party to whom such LOI is
issued. A detailed agreement/contract is required to be drawn up
11
between the parties after the LOI is received by the other party more
particularly in case of contract of such a mega scale.
11. Since, there was no right whatsoever created in favour of the
respondent no. 2, and since the respondent no. 1 HIMUDA had already
accepted the recommendations of the Committee appointed by the High
Court and the order dated 08.01.2021 passed by the High Court, and
had cancelled the tender and issued fresh NIT on 17.11.2021, the
respondent no. 1 could not have agreed to allow the respondent no. 2,
who was found to be not technically qualified, to go ahead with the
execution of the project in question and that too without giving the other
two parties any opportunity to negotiate. If the respondent no. 1 was so
keen to provide the facilities to the public without causing any additional
burden on the public exchequer, all the three parties who had
participated in the original tender should have been given the
opportunity to negotiate with it.
12. Having regard to the entire chain of events, and the conduct of the
respondent nos. 1 and 2, we have no hesitation in holding that the
respondent no. 1 in collusion with the respondent no. 2, had taken the
High Court for a ride and misused the process of law for covering up the
irregularities and illegalities committed in the tender process by the
12
officers of the respondent no. 1, and for anyhow awarding the contract
to the respondent no. 2 under the guise of the court’s order. It is a matter
of surprise for us that the High Court also could not notice the ill-intention
of the respondent nos. 1 and 2 and disposed of the petition, permitting
them to go ahead with the original tender, ignoring the reports of the
independent committee and the observations made by the Single Bench
in the Order dated 08.01.2021 with regard to the irregularities and
illegalities committed by the officers of the respondent no. 1 HIMUDA.
13. The impugned order having been passed without proper application of
mind and without assigning any cogent reason for brushing aside the
findings recorded by the Independent Committee and the observations
made by the Single Bench in the order dated 08.01.2021, the same
deserves to be quashed and set aside. Since, we have found that the
respondent no.1 HIMUDA, though ‘State’ within the meaning of Article
12 of the Constitution of India, had acted malafide and in collusion with
the respondent no.2, and had taken the High Court for a ride, the present
appeal deserves to be allowed with heavy cost.
14. In that view of the matter, the impugned order passed by the High Court
is set aside. The appeal is allowed with cost of Rs. 5,00,000/- to be
deposited by the respondent no. 1 HIMUDA with the Supreme Court
13
Advocates-on-Record Association, within two weeks from today.
However, it is clarified that the respondent no.1 shall be at liberty to
initiate a fresh tender process in accordance with law and after following
the due process of law.
……………………………………J.
[BELA M. TRIVEDI]
……………..……………………. J.
[PANKAJ MITHAL]
NEW DELHI;
nd
APRIL 02 , 2024.
14