Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
BUNGO STEEL FURNITURE PVT. LTD.
Vs.
RESPONDENT:
UNION OF INDIA
DATE OF JUDGMENT:
30/09/1966
BENCH:
RAMASWAMI, V.
BENCH:
RAMASWAMI, V.
BHARGAVA, VISHISHTHA
DAYAL, RAGHUBAR
CITATION:
1967 AIR 378 1967 SCR (1) 633
CITATOR INFO :
RF 1976 SC 425 (13)
D 1988 SC1166 (7)
R 1990 SC1426 (22)
ACT:
Arbitration-Award-Party contracting to obtain supply of
steel bins-Cancellation of contract after part supply-
Arbitrator awarding damages for wrongful termination-Reasons
or principles not indicated in Award- if could be set aside
on ground of error of law on face of the Award.
HEADNOTE:
The Union of India entered into two contracts in November
1944 and June 1945 with the appellants, which were
subsequently modified in February 1946, for the supply of
4,700 bins at an agreed price inclusive of the cost of
steel. The Government undertook to make available the steel
required for the manufacture of the bins and accordingly,,
supplied to the appellants steel valued at Rs. 2,53,521 for
which amount credit was to be given to the Government.
After 2,172 bins had been manufactured and supplied to the
Union, the latter cancelled the contract for the supply of
the balance 2,528 bins.
Each of the contracts between the parties contained an
arbitration clause and in accordance with this provision,
the dispute arising out of cancellation of the contracts was
referred to an arbitrator. The arbitrator found that the
contract had been wrongfully cancelled; and that at the time
of the cancellation the component parts of the balance 2,528
bins were ready but had not been assembled into finished
bins. By way of compensation for the wrongful termination
of the contract by the Government, the Arbitrator awarded
damages to the company of the amount representing the value
of steel used up in making the component parts for bins
which had not been assembled into completed bins. This
amounted to Rs. 1,65,825.
The Government made an application to the Calcutta High
Court for setting aside the arbitrator’s award on the ground
that there was a mistake of law apparent on the face of the
award in the estimation of damages for wrongful termination
of the contract. A single Judge of the High Court
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
substantially confirmed the arbitrator’s award. The Govern-
ment took the matter in appeal to a Division Bench of the
High Court and the two appeals filed were allowed by that
Bench and the award was set aside.
It was contended on behalf of the appellants that the High
Court could not have interfered with the award of the
arbitrator as there was no error on the face of the award;
that the arbitrator was not bound to give -reasons for
estimating the damages to which the appellant was entitled
and that he had not in fact given any such reasons.
HELD : Allowing the appeal (per Bhargava and Raghubar Dayal,
JJ.). The arbitrator in fixing the amount of compensation
had not proceeded to follow any principles, the valdity of
which could be tested on the basis of laws applicable to
breaches of contract. He awarded the compensation to the
extent that he considered right in his discretion without
indicating his reasons. Such a decision by an Arbitrator
could not be held to be erroneous on the face of the record.
[642 A-B]
634
The consideration that led the arbitrator to consider that
the value of the steel was equal to, and not more or less
than, the amount which he considered it right to award as
compensation, was not indicated by him in his award. This
was, therefore, clearly a case where the arbitrator came to
the conclusion that a certain amount, should be paid by the
Government as compensation for wrongful termination of the
contract, and in his discretion-he laid down that the amount
should be equal to the value of the steel as it existed
after it had been converted into component parts. [641 F-G]
It is now a well settled principle that if an arbitrator, in
deciding a dispute before him, does not record his reasons
and does not indicate the principles of law on which he has
proceeded, the award is not on that account vitiated. It is
only when the arbitrator proceeds to give his reasons or to
lay down principles on which he has arrived at his decisions
that the court is competent to examine whether he has
proceeded contrary to law and is entitled to interfere if
such error in law is apparent on the face of the award
itself. [640 H]
(Per Ramaswami J., dissenting)-In the present case the
arbitrator had estimated the measure of damages as
equivalent to the value of steel used up in making the
component parts. That was the legal proposition upon which
he had based his award and the question was whether that
legal proposition was correct. The arbitrator had found
that the appellant had produced no evidence with regard to
the manufacturing cost of the component parts of the 2,528
unfinished bins; he had therefore failed to prove the
resultant damage on account of the breach of contract. But
if in spite of this finding the arbitrator decided to award
damages to the appellant, the highest amount which he could
award would be Rs. 1,03,066, which is the difference between
the contract price and the value of the steel used up in
manufacturing their component parts. The estimate of
damages at this figure is based, on the assumption that the
appellant had manufactured completely 2,528 bins according
to the terms of the contract. The arbitrator had ignored
the provisions of s. 73 of the Indian Contract Act and had
awarded damages to the appellant on a wrong legal basis.
The award was therefore vitiated by an error of law apparent
on the face of it. [639 C, G, H] .
Champsey Bhara and Co. v. Jivraj Balloo Spinning and Weaving
Co. Ltd. 50 I.A. 324 and James Clark (Brush Materials) Ltd.
v. -Carters (Merchants) Ltd. [1944] 1 K.B. 566,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
distinguished.
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeals Nos. 754 and
755 of 1964.
Appeals from the judgment and order dated August 1, 1962 of
the Calcutta High Court in Appeals Nos. 13 and 131 of 1961
respectively.
A. K. Sen, Uma Mehta, P. K. Chatterjee and P. K. Bose, for
the appellant (in both the appeals).
N. S. Bindra and R. N. Sachthey, for the respondent (in
both he appeals).
The Judgment of BHARGAVA and RAGHUBAR DAYAL J.J was
delivered by BHARGAVA J. RAmAswAmi J. delivered a dissenting
Opinion.
Ramaswamy, J. These appeals are brought by certificate’ from
the judgment of the Calcutta High Court dated August 1, 1962
by which an award of the arbitrator, Sir R. C. Mitter dated
September 2, 1959 was set aside.
The disputes arise out of two contracts being A. T. 1000
dated November 30, 1944 and A. T. 1048 dated June 25, 1945
between the Government of India (hereinafter called the
"Government") and the Bungo Steel Furniture Pvt. Ltd.
(hereinafter called the "appellant"). Both the contracts
contained the usual arbitration clause embodied in cl. 21 of
the general conditions of contract in form no. W.S.B. 133
for reference of any question or dispute arising in
connection with the contract or arising under the condition
thereof. The claims and the counterclaims of the parties
under the two contracts were referred to the arbitration of
Sir R. C. Mitter. The award of the arbitrator is dated
September 2, 1959. The arbitrator found that the contract
no. A. T. 1000 was for the supply of 4700 bins at Rs.
107/2/6 per bin inclusive of the price of steel. In respect
of the supply of bins under this contract the Government
agreed to pay an extra Rs. 4/12/6 per bin for extra
partition. The contract no. A. T. 1048 was for the supply
of 2000 steel bins at Rs. 132/8/- per bin inclusive of the
price of steel. The arbitrator found that on February 20,
1946 the parties agreed to a modification of the contracts
and the agreed modification was that the supply under
contract no A. T. 1000 would be reduced to 1805 bins and the
supply under contract no. A. T. 1048 would be reduced to
367 bins, so that the total supply under the two contracts
would be 4700 bins. The arbitrator further found that only
1805 bins had been manufactured under contract no. 1000 and
367 bins had been manufactured under contract no. 1048 and
that in all 2172 bins were manufactured by the appellant and
were accepted by the Government and the appellant was en-
titled to the price of 2172 bins so supplied inclusive of
the price of steel amounting to Rs. 2,42,044/-. The
arbitrator held that the Government wrongfully cancelled the
contract with respect to the balance 2528 bins and that at
the time of this cancellation the component parts of the
balance 2528 bins had not been assembled into finished bins.
The arbitrator found that the appellant was entitled to a
credit for the sum of Rs. 10,385/- on account of the cost of
supply of the extra partitions for 2172 bins. This finding
of the arbitrator was held to be erroneous by Mallick, J.
who reduced the amount awarded to the appellant by a sum of
Rs. 10,385/-. The finding of Mallick, J. was not challenged
by the appellant before the Division Bench of the High
Court. The arbitrator also found that the appellant was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
entitled to credit for the sum of Rs. 27,969/on account of
payment made by the appellant towards the cost of steel on
M.R.O. and that the Government was entitled to a cross
credit for a sum of Rs. 7,851/- on account of payment made
636
by it to the appellant directly. These two findings of the
arbitrator were not challenged before the Division Bench.
The arbitrator found that the Government was under an
obligation to supply steel for the manufacture of the bins
and that it did supply such steel to the appellant. The
arbitrator disbelieved the appellant’s case that it had
rejected the steel sheets supplied by the Government and had
used the steel sheets from their own stocks and that the
steel sheets supplied by the Government became rusted and
were still lying in their factory grounds as powdered rust.
The arbitrator found : (a) that the price of the total
quantity of steel supplied by the Government to the
appellant at basic rates was Rs. 2,53,521/-, (b) that the
price of the steel used for making 2172 finished bins
amounted to Rs. 87,696/- and the Government was entitled to
credit for this sum of money, and (c) that no surplus steel
was left after manufacture of 2172 finished bins and the
component parts of the unfinished bins. It followed from
this finding that the price of steel used up in making the
component parts of the unfinished bins amounted to Rs.
1,65,825/-.
The arbitrator found that the appellant was entitled to com-
pensation for the wrongful cancellation of the balance 2528
bins. His findings in the award read as follows :-
"I further hold that the cancellation by Government for the
balance was wrongful. There is however no evidence relating
to the manufacturing cost of the aforesaid remaining
component parts. By way of compensation for the wrongful
termination of the contract by Government as aforesaid I
give the company the amount representing the value of the
steel used up in making the said component parts which had
not been assembled into completed bins. I therefore do not
allow the Government credit for the value of the steel used
up in manufacturing those component parts."
The Government made an application to the Calcutta High
Court for setting aside the award of Sir R. C. Mitter on the
ground that the arbitrator had failed to apply his mind and
there was a mistake of law apparent on the face of the award
in the estimation of damages for wrongful termination of
the contract. Mallick, J. made a minor modification in
the award with regard to a sum of Rs. 10,385/- and on July
27, 1960 the learned Judge pronounced his judgment in terms
of the modified award. The Government look the matter in
appeal before the Division Bench of the High Court, appeals
nos. 13 and 131 of 1961. These appeals were allowed by
Bachawat and Laik, JJ. who set a-side the award of the
arbitrator in respect of the two contracts.
637
On behalf of the appellant Mr. A. K. Sen put forward the
argument that there was no error on the face of the award
and the High Court exceeded its jurisdiction in setting
aside the award of the arbitrator. It was contended that
the arbitrator is not bound to give reasons for estimating
the damages to which the appellant was entitled. It was
stated that the estimate of the: arbitrator may be arbitrary
but he was not bound to give reasons for the estimate
reached by him ’and that it is not open to the Court lo
speculate, when no reasons are given by the arbitrator, as
to what impelled the arbitrator to arrive at his conclusion
In support of this argument Counsel for the appellant relied
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
on the following passage from the judgment of Lord Dunedin
in Champasey Bhara and Company v. Jivraj Balloo Spinning and
Weaving Company Ltd.(1):
"An error in law on the face of the award means, in their
Lordships’ view, that you can find in the award or a
document actually incorporated thereto, as for instance a
note appended by the arbitrator stating the reasons for his
judgment, some legal proposition which is the basis of the
award and which you can then say is erroneous. It does not
mean that if in narrative a reference is made to a
contention of one party, that opens the door to, seeing
first what that contention is, and then going to the con-
tract on which the parties’ rights depend to see if that
contention is sound."
It is true that the Court in dealing with an application to
set aside an award has not to consider whether the view of
the arbitrator on the evidence is justified. The
arbitrator’s adjudication is generally considered binding
between the parties, for he is a tribunal elected by the
parties and the power of the Court to set aside the award is
restricted to ’cases set out in s. 30 of the Arbitration
Act.
An award may be set aside by the court on the ground of an
error of law apparent on the face of the award but an award
is not invalid merely because by a process of inference and
argument it may be demonstrated that the arbitrator has
committed some mistake in arriving at his conclusion. Mr.
A. K. Sen on behalf of the appellant also, referred to the
decision of Tucker, J. in James Clark (Brush Materials) Ltd.
v. Carters (Merchants), Ltd. (2) Wherein it is pointed out
that in determining whether the award of an arbitrator
should be remitted or set aside on the ground that there is
an error of law appearing on the face of it, the court is
not entitled to draw any inference as to the finding by the
arbitrator of facts supporting the award, but must take it
at its face
(1) 50 1. A. 324, 331.
(2) [1944] 1 K.B. 566.
638
value. In my opinion,, the principle laid down by the
Judicial Committee in Champsey Bhara and Company v. Jivaraj
Balloo Spinning and Weaving Company Ltd.(’) and by Tucker,
J. in James -Clark (Brush Materials), Ltd. v. Carters
(Merchants), Ltd.(2) has no application in the present case,
for the arbitrator in the present case has expressly stated
the reasons for the estimate of damages -to which the
appellant was entitled for the breach of the contract. The
claim of the appellant is stated by the arbitrator in the
award -as follows :
"the Company claims the price of 2528 bins by way of damages
for the wrongful cancellation of the contract."
Section 73 of the Indian Contract Act provides for the
measure of compensation for loss or damage caused by breach
of the contract. Section 73 states :
"73. When a contract has been broken, the party who suffers
by such breach is entitled to receive, from the party who
has broken the contract, compensation for any loss or damage
caused to him thereby, which naturally arose in the usual
course of things from such breach, or which the parties
knew, when they made the contract, to be likely to result
from the breach of it.
Such compensation is not to be given for any remote and
indirect loss or damage sustained by reason of the breach.
Explanation.-In estimating the loss or damage arising from a
breach of contract, the means which existed of remedying the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
inconvenience caused by the non-performance of the contract
must be taken into account."
Section 55 of the Sale of Goods Act deals with suits for
breach -of the contract where the buyer refuses to pay for
the goods -according to the terms of the contract. Section
55 states :
"55. (1) Where under a contract of sale the property in the
goods has passed to the buyer and the buyer wrongfully
neglects or refuses to pay for the goods according to the
terms of the contract, the seller may sue him for the price
of the goods.
(2)Where under a contract of sale the price is payable on a
day certain irrespective of delivery and the buyer
wrongfully neglects or refuses to pay such price, the seller
may sue him for the price although the property in the goods
has not passed and the goods have not been
appropriated to the contract."
(1) 50 I.A. 324.
(2) [1944] 1. K.B. 566.
639
This section does not apply to the present case because the
bins were not manufactured and the property could not have
passed to the Government. But the appellant was entitled to
claim damages for the wrongful cancellation of the balance
2528 bins by the Government and for non acceptance of the
2528 bins under s. 56 of the Indian Sale of Goods Act which
provides :
"56. Where the buyer wrongfully neglects or refuses to
accept and pay for the goods, the seller may sue him for
damages for non-acceptance."
In the present case, the arbitrator has estimated the
measure of damages as equivalent to the value of the steel
used up in making the component parts. That is the legal
proposition upon which the arbitrator has based his award
and the question is whether that legal proposition is
correct. Now the amount representing the value of the steel
used up in making the component parts of the unfinished 2528
bins could not be the true measure of damages for their non-
acceptance. The normal rule for computing the damages for
non-acceptance of 2528 unfinished bins would be the
difference between the contract price and the market price
of such goods at the time when the contract is broken. If
there is no available market at the place of delivery, the
market price of the nearest place or the price prevailing in
the controlling market may be taken into consideration. It
was argued for the appellant that this rule may not apply
because the bins were not completely fabricated, but, in
that case the measure of damages would be the difference
between the contract price on the one hand, and the cost of
labour and material required for the manufacture of the
component parts of the 2528 unfinished bins on the other.
In this case, the arbitrator found that the appellant
produced no evidence with regard to the manufacturing cost
of the component parts of the 2528 unfinished bins. In
other words, the appellant failed to prove the resultant
damage on account of breach of contract, but if in spite of
this finding the arbitrator decided to award damages to the
appellant the highest amount which he could award for non-
acceptance would be Rs. 1,03,066/- which is the difference
between the contract price at Rs. 107/2/6 per bin including
the price for extra partition amounting to Rs. 2,68,891 /and
the value of the steel used up in manufacturing their compo-
nent parts amounting to Rs. 1,65,825/-. The estimate of
damages at this figure is based on the assumption that the
appellant had manufactured completely 2528 bins according to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
the terms of the contract. It is therefore manifest that on
no conceivable legal basis whatever could the arbitrator
pronounce an award for a sum of Rs. 1,65,825/- which
represents the value of the steel used up in making the
component parts as the compensation to be awarded to the
appellant. In other words, the arbitrator has ignored the
provisions of s. 73 of the Indian Contract Act and has
awarded
640
damages to the appellant on a wrong legal basis. The award
of the arbitrator therefore is vitiated by an error of law
apparent on the face of it.
For these reasons I hold that the judgment of the Division
Bench of the High Court dated August 1, 1962 is right and
these appeals must be dismissed with costs.
Bhargava, J. The facts in these two appeals have been given
in the judgment of Ramaswami, J., and hence, they need not
be repeated by us. The award was set aside by the High
Court, in appeal from the judgment of the learned single
Judge passing a decree on its basis, on the ground that the
award of the Umpire with regard to the compensation for the
wrongful cancellation of the contract was erroneous in law
and the error appeared on the face of the award. In the
award, the arbitrator held that under Contract No. A. T.
1000, only 1805 bins had been manufactured and under the
second Contract No. A. T. 1048, 367 bins had been
manufactured. These bins were accepted and the remaining
component parts had not been assembled into more finished
bins by the time when the contract was cancelled. He
further held that the cancellation by the Government for the
balance was wrongful. There was, however, no evidence
relating to the manufacturing cost of the aforesaid
remaining component parts. Thereupon, he proceeded to
award, by way of compensation for the wrongful termination
of the contract by the Government as aforesaid, to the
company the amount representing the value of the steel used
up in making the said component parts which had not been
assembled into completed bins, and, therefore, he did not
allow the Government credit for the value of the steel used
up in manufacturing those component parts. He further held
that after manufacturing the finished bins and component
parts and unfinished bins, no surplus steel was left.
The High Court, in setting aside the award, was of the view,
that in this part dealing with compensation payable by the
Government to the appellant, the learned Umpire had acted
contrary to the principles recognised in law for assessing
compensation. In our view, considering the principles which
apply to the exercise of the power of a Court to set aside
an award of an arbitrator, this order by the High Court was
not justified.
It is now a well-settled principle that if an arbitrator, in
deciding a dispute before him, does not record his reasons
and does not indicate the principles of law on which he has
proceeded, the award is not on that account vitiated. It is
only when the arbitrator proceeds to give his reasons or to
lay down principles on which he has arrived at his decisions
that the Court is competent to examine
641
whether he has proceeded contrary to law and is entitled to
interfere if such error in law is apparent on the face of
the award itself.
In the present case, the Umpire held that the cancellation
of the contract by the Government for the balance of the
bins was wrongful. He was, therefore, fully entitled to
award compensation for that breach of contract to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
appellant. He, however, found that there was no evidence
relating to the manufacturing cost of the aforesaid.
remaining component parts which, on principles applicable to
breaches of contract, would ordinarily have been the amount
awarded as compensation. Having no such evidence, the
Umpire, it appears, proceeded to use his discretion to
determine the compensation which he thought should be equit-
ably made payable by the Government to the appellant. He
had already arrived at the finding that the steel supplied
by the Government, which had not been used up in completed
bins, had already been consumed in making component parts.
In these circumstances, having decided that compensation
should be paid by the Government to the appellant, he fixed
the amount of compensation at the value represented by the
steel used up in making those component parts. This award
is not to be interpreted as proceeding on any basis that the
value of the steel used up in making the component parts was
held by him on some principle to be the compensation payable
by the Government. What he actually meant was that having
mentally decided on the amount that was to be awarded as
compensation, he came to the view that that amount can
equitably be treated as being equal to the value of the
steel used up in making the component parts. What the value
of that steel in the component parts was at that stage was
not computed by him. May be, the steel had become less
serviceable and deteriorated in value. What was the
consideration that led him to consider that the value of the
steel was equal to, and not more or less than, the amount
which he considered it right to award as compensation, was
not indicated by him in his award. This is, therefore,
clearly a case where the arbitrator came to the conclusion
that a certain amount should be paid by the Government as
compensation for wrongful termination of the contract, and
in his discretion, he laid down that that amount is equal to
the value of the steel as it existed after it had been con-
verted into component parts. He did not hold that the
Government was not entitled to the return of the unused
steel. What he actually held was that the Government being
entitled to the value of the unused steel, no separate
direction in respect of it need be made, because the value
of that steel was equal to the amount of compensation which
he was awarding to the appellant; and thus, the two
liabilities of the appellant to the Government and of the
Government to the appellant were set off against each other.
In the circumstances, it has to be held that the Umpire,
642
in fixing the amount of compensation, had not proceeded to
follow any principles, the validity of which could be tested
on the basis of laws applicable to breaches of contract. He
awarded the compensation to the extent that he considered
right in his discretion without indicating his reasons.
Such a decision by an Umpire or an Arbitrator cannot be held
to be erroneous on the face of the record. We, therefore,
allow the appeals with .costs, set aside the appellant order
of the High Court, and restore that of the learned single
Judge.
ORDER
In view of the majority Judgment, the appeals are allowed
with ,costs, the appellate order of the High Court is set
aside and that -of the learned single Judge, is restored.
R.K.P.S.